Memorandum by Mr Chris Bolt, Arbiter for
London Underground PPP Agreements
INTRODUCTION
1. The role of statutory Arbiter for the
London Underground Public-Private Partnership Agreements was created
by the Greater London Authority Act 1999. I was appointed as the
first PPP Arbiter in December 2002. Annex 1 gives a brief
summary of the PPP Agreements, and Annex 2 outlines my functions
and duties.
2. The London Underground PPP covers the
maintenance, renewal and upgrading of the infrastructuretrack,
trains, signalling and stations. The PPP Agreements are 30 year
commercial contracts, with reviews of scope and pricing every
7½ years. My role is concerned principally with assessing
the efficient level of costs and pricing at Periodic Review (and
at the Extraordinary Reviews which may take place between Periodic
Reviews).
3. Based on my experience to date, I set
out below my views on some of the questions covered by the call
for evidence. I do not respond on questions which are outside
the scope of my role as PPP Arbiter.
Q1: Assessment of value for money
4. The PPP deals were subject to a value
for money assessment before they were finalised, comparing bids
with a public sector comparator. The National Audit Office reported
on those assessments[1].
NAO also took the view that creation of the role of Arbiter was
important in protecting value for money. Specifically, one of
its recommendations was as follows:
"Departments should negotiate commercial
terms that are broadly neutral in respect of unforeseen and unforeseeable
asset condition because seeking to transfer too much risk is likely
to over-compensate the private sector on grounds of uncertainty.
Steps were taken to think through and reduce such risks in this
case. Specifically, the provisions for decision by an independent
Arbiter mitigate the risk that thresholds for price review are
too easily reached. In larger deals, Departments should consider
similar arrangements."
5. The PPP Agreements establish the concept
of the Notional Infraco as a basis for judging efficient delivery:
this is defined as the entity which has the same contractual obligations
and financing as the actual Infraco, but which carries out its
activities in an "overall efficient and economic manner and
in accordance with Good Industry Practice". The contract
identifies some characteristics of Good Industry Practice, but
it is for me as Arbiter to judge what is efficient and economic
and to assess the costs and revenues of the Notional Infraco when
disputes about price are referred to me.
6. In assessing the characteristics of the
Notional Infraco, the approach I have adopted, following consultation
with the PPP Parties and others with a relevant interest, has
involved a number of elements:
review of actual Infraco performance
and plans;
"internal" benchmarking between
the three Infracos;
"external;" benchmarking with
other relevant metros and railways; and
expert technical advice.
7. In order to ensure that the Arbiter has
adequate access to information, the GLA Act gives me powers to
obtain information from the PPP Parties and their associates.
I have also published the results of benchmarking work which I
have commissioned, although technical advice drawing on actual
performance and plans is generally confidential to the Parties.
Q2: Comparison with traditional procurement
8. As indicated above, the London Underground
PPP bids were compared with a public sector comparator before
the contracts were signed.
9. Subsequent performance of the infracos
can be assessed against alternative procurement models through
the external benchmarking. The Metronet infracos have been transferred
back to TfL ownership, following their entering administration
in July 2007, and integrated with London Underground. However,
it is too early to make a robust assessment of the comparative
performance of infracos under the different regimes. There are
three main reasons for this:
transitional changes designed to remove
inefficiencies are still not fully complete;
financial systems are being integrated
with London Underground in order to produce robust cost information;
and
Metronet costs have not yet been subject
to any detailed independent review.[2]
Q3: Risk transfer
10. Under the terms of the London Underground
PPP Agreements, Infracos are protected against changes in costs
(or loss of performance revenue) subject to three conditions:
the protection only applies to the extent
that the Notional Infraco would also have faced increased costs:
cost increases due to inefficiency are therefore borne by the
shareholders;
Infracos have to absorb the first £50 million
of additional efficient costs in each Review Period,[3]
although this risk is reflected in pricing; and
decisions on what cost increases are
allowable are taken by the independent Arbiter, if not agreed
with London Underground, which introduces a (limited) measure
of "regulatory risk".
11. Where cost changes arise within a 7½
year Review Period, an Infraco can make a reference to me for
Extraordinary Review. I then judge how far the cost changes reflect
those of the Notional Infraco, and determine the change in the
ISC payable by London Underground to cover the allowed cost increase
which is in excess of the Materiality Threshold.
12. Although, therefore, the PPP is intended
to transfer the risk of inefficient delivery to the private sector,
the effectiveness of this transfer depends on the ability of equity
holders to absorb this risk. This is turn depends on early identification
of inefficiency, enabling the Infraco to take early corrective
action. In the case of the two Metronet Infracos, the scale of
inefficiency was identified too late to allow for such corrective
action, and the interim increase in ISC which I proposed to allow
in my draft direction of 16 July 2007 was insufficient
to maintain their viability. My decision reflected my assessment
that the bulk of the cost increase being experienced by Metronet
was the result of inefficiency. As a consequence, the Infracos
went into PPP Administration on 18 July 2007. The resulting
cost to the taxpayer was identified in a recent NAO report.[4]
13. One lesson from the failure of Metronet
which is relevant to the issue of risk allocation is that Metronet
and London Underground appeared to have different views of what
risks each party was taking. Given the definition of the Notional
Infraco, for example, costs omitted from Metronet's bid were still
a risk for London Underground if efficiently incurred, although
London Underground originally argued that such omissions were
a Metronet risk. This difference of understanding contributed
to the delay in addressing cost overruns beyond the point where
corrective action could be taken.[5]
Q4: Monitoring performance and quality
14. As Arbiter, I have no role in respect
of regular monitoring of performance and quality, other than in
one respect. The Metronet PPP Agreements provided for an annual
reference to me for guidance on whether the infracos had performed
its activities in the period since transfer in an overall efficient
and economic manner and in accordance with Good Industry Practice
or not. In preparation for the 2005 report, which was deferred
by agreement between Metronet and its lenders and London Underground,
I developed a format for variance analysis which had not previously
existed. I have expressed the view[6]
that the problems experienced by Metronet could have been addressed
earlier had I been allowed to prepare the annual report in 2005.
15. In preparing for the Periodic Review
of Tube Lines' PPP Agreement, and in particular in developing
the framework for internal benchmarking, I was concerned that
information from the three infracos was not in a consistent format.
I therefore developed, in consultation with Metronet, Tube Lines
and London Underground, a Data Breakdown Structure which London
Underground and Tube Lines subsequently agreed to adopt for their
Periodic Review submissions. Again, this is a matter which would
ideally be addressed at the start of a contract rather than having
to be developed subsequently.
Q5: Changing requirements
16. The PPP Agreements provide for a Periodic
Review to take place every 7½ years (ie there are three reviews
during the 30-year contract term). London Underground is only
able to make changes to its requirements at Periodic Review (or
for affordability reasons at Extraordinary Reviews). As part of
the current Periodic Review of Tube Lines' PPP Agreement, London
Underground has introduced changes in its requirements, and also
proposed modification of other contractual terms (for example
in relation to asset management systems). However, Tube Lines
has contended that some of these changes go beyond the scope of
changes which can be made under the contract.
17. The PPP Agreements provide that some
of the contentions made in the context of a Periodic Review must
be referred to me, and that others must be referred to an adjudicator.
This potentially creates unhelpful timing issues, and potentially
a conflict of jurisdictions. Similarly, the fact that some cost
changes are subject to a contractual claims process and could
in principle also be part of an Extraordinary Review highlights
the difficulties of running two different change and appeal mechanisms
in parallel.
Annex 1
THE LONDON UNDERGROUND PPP
1. London Underground Limited entered into
three separate Public Private Partnership (PPP) Agreements, with
Tube Lines in December 2002 and with Metronet (two separate
agreements) in April 2003. Under these Agreements, which cover
a 30 year period, three separate companies ("Infracos")
are responsible for the maintenance, renewal and upgrading of
specific parts of London Underground's infrastructure. London
Underground, which is an operating subsidiary of Transport for
London, retains responsibility for delivering services to customers.
2. Responsibility for the different lines
was as follows:
Metronet Rail BCV Ltd: Bakerloo, Central, Victoria
and Waterloo & City
Metronet Rail SSL Ltd: Metropolitan, Circle,
Hammersmith & City and District (the Sub-Surface Lines)
Tube Lines Ltd: Jubilee, Northern and Piccadilly.
3. On 18 July 2007, Metronet Rail BCV
Limited and Metronet Rail SSL Limited entered PPP Administration,
exiting on 27 May 2008. Ownership was transferred to two
new companies within Transport for London. The two Metronet PPP
Agreements remain in place pending agreement of a permanent structure
for the Metronet Infracos.
4. The PPP Agreements provide for a Periodic
Review of obligations and pricing every 7½ years. The Periodic
Review for Tube Lines' Agreement is now under way. London Underground
issued its Restated Terms and Affordability Constraints on 8 December
2008, and Tube Lines submitted its formal Response to Restated
Terms on 30 June 2009. Between 1 July 2009 and
30 June 2010, the Parties will seek to negotiate agreement
on revised terms, and failing that make a reference to the PPP
Arbiter. Any required additional finance will also need to be
in place for the start of the second Review Period on 1 July
2010.
Annex 2
THE FUNCTIONS AND DUTIES OF THE PPP ARBITER
1. The role of the PPP Arbiter was established
by the Greater London Authority Act 1999 (GLA Act). Under
the terms of the GLA Act, the Arbiter is independent of Government
and of the PPP Parties and can only be dismissed by the Secretary
of State on grounds of incapacity or misbehaviour, or for unreasonable
delay in the discharge of his functions.
2. The Arbiter is a corporation sole. I
was appointed as the first Arbiter on 31 December 2002, and
my appointment now runs to 30 December 2010. I am supported
by a small permanent staff. As I am appointed as an individual,
and am personally responsible for the exercise of my statutory
functions, I have also appointed an Advisory Board to provide
independent and expert challenge to my decisions and procedures.
Although I am not required by statute to do so, I have published
each year a Business Plan and my Annual Report and Accounts setting
out the work programme of my Office and the resources used.
3. As PPP Arbiter, I have two principal
statutory functions:
to give directions on matters specified
in the PPP Agreements, when asked to do so by one of the Parties
to a PPP Agreement; and
to give guidance on any matter relating
to a PPP Agreement, when asked to do so by either (or both) of
the Parties to a PPP Agreement.
4. When the Arbiter is asked for guidance
by one Party only, the Act gives me discretion about whether to
give guidance. Where I am asked for directions, or am asked for
guidance by both Parties to an Agreement, I am required to give
directions or such guidance as I consider appropriate.
5. Although the Arbiter can be asked for
guidance or directions at any time, it was expected that he would
exercise formal functions in three main circumstances:
in giving an annual "definitive
statement" on the performance of the two Metronet infracos;
at the Periodic Review of the Agreements
which takes place every 7½ years; and
at an Extraordinary Review of the terms
of a PPP Agreement if there were material changes in costs and
revenues within a Review Period.
6. In addition, the Act gives the PPP Arbiter
further powers "for the purposes of the proper discharge
of the functions" conferred on him by the GLA Act. For example
the PPP Arbiter may do "all such things as he considers appropriate
for or in connection with the giving of a direction or guidance
and
do such other things as he considers necessary or expedient
for purposes preparatory or ancillary to the giving of directions
or guidance generally
notwithstanding that there is no matter
in relation to which a direction or guidance is required".
7. The PPP Arbiter's function in respect
of directions is limited by the terms of the PPP Agreements: if
there is no specific provision in a PPP Agreement for the PPP
Arbiter's involvement then disputes are dealt with through contractual
dispute resolution. Even on matters within his remit, he is only
brought in if one of the Parties seek a direction from him. The
PPP Arbiter therefore has no unilateral power to change, or propose
to change, provisions in the PPP Agreements. Even where he has
made a direction on a disputed matter within his remit, the Parties
may, under the provisions of the GLA Act, jointly agree to set
it aside.
8. In exercising his functions, the Arbiter
is under a statutory duty to act in the way he considers is best
calculated to achieve four objectives:
to ensure that London Underground has
the opportunity to revise its requirements under the PPP Agreements
if the proper price exceeds the resources available;
to promote efficiency and economy in
the provision, construction, renewal, or improvement and maintenance
of the railway infrastructure;
to ensure that if a rate of return is
incorporated in a PPP Agreement, and taking into account matters
specified in the Agreement, a company which is efficient and economic
in its performance of the requirements in that PPP Agreement would
earn that return; and
to enable the Infracos to plan the future
performance of the PPP Agreements with reasonable certainty.
The Arbiter is also under a duty to take account
of any factors which are notified to him by both Parties to an
Agreement, or are specified in the relevant PPP Agreement, as
ones to which he must have regard.
9. For the purposes of assessing costs at a
Periodic Review or Extraordinary Review, the PPP Agreement establishes
the concept of the Notional Infraco. This is defined as the entity
which has the same obligations as Infraco, which carries out its
activities in an overall efficient and economic manner and in
accordance with Good Industry Practice, and has certain other
specified characteristics. A key part of the Arbiter's role is
therefore to assess what constitutes Good Industry Practice and
the level of performance and cost which would be efficient and
economic.
1 London Underground PPP: Were they good deals? 17 June
2004, HC: 645 2003-04 Back
2
Although the PPP Agreements remain in place, London Underground
has made it clear that it does not intend to refer matters relating
to Metronet activities to me for review. However, I intend to
ask the independent reporters appointed by me (currently KPMG
and Lloyds Register Rail) to review Metronet's Asset Management
Plan for the next Review Period when available to assess its robustness
as a comparator for Tube Lines. Back
3
This Materiality Threshold was £200m for Tube Lines in the
first Review Period only. A £50 million Materiality
Threshold represents about 1% of the contract value. Back
4
The Department for Transport: The failure of Metronet, 5 June
2009, HC: 512 2008-09 Back
5
"It also seems clear that there have been differences of
understanding between Metronet and London Underground about the
allocation of different risks under the contract. In particular,
the cost consequences of increases in the scope of work required
to deliver obligations are mostly borne by London Underground;
only the (low) Materiality Threshold and the cost consequences
of delivering inefficiently are borne by Metronet. Thus, even
where sums were omitted from the original bid, or disputes about
contractual requirements have been won by London Underground (such
as whether Low Loss Conductor Rail for the Victoria Line was an
original obligation or not), London Underground still has to bear
the efficient increase in costs." (Extract from my written
evidence to the House of Commons Transport Committee, The London
Underground and the Public-Private Partnership Agreements, Second
Report of Session 2007-08, HC45.) Back
6
In my evidence to the Transport Select Committee (op cit). Back
|