PRELIMINARY DRAFT BUDGET (PDB) OF THE
EUROPEAN COMMUNITIES 2008
Letter from the Chairman to Ed Balls MP,
Economic Secretary, HM Treasury
Thank you for your Explanatory Memorandum dated
6 June 2007.
Sub-Committee A discussed the procedure for
scrutiny of the 2008 Preliminary Draft Budget at their meeting
on 12 June. They have asked me to express our regret that prolonged
contact at Official level has suggested that you are unable to
give evidence to the Committee this month. The scrutiny of the
Preliminary Draft Budget has become a mainstay of Sub-Committee
A's annual work programme and is an issue that the Select Committee
takes most seriously. The scrutiny of this item, alongside that
of the Commission Annual Work Programme and Annual Policy Strategy,
is a crucial part of the Select Committee's work examining cross-cutting
European issues as they are being developed. We consider it would
be inappropriate if there was an override of the scrutiny reserve
on this item.
The Sub-Committee would be happy to accommodate
an evidence session with you on any sitting day this month. Should
this not be possible then the Sub-Committee would wish to insist
on an evidence session in the first week of July.
The Sub-Committee also noted that it would help
their deliberations if the Explanatory Memorandum could be submitted
in a more timely manner in future years. They would also find
it helpful if a Minister or Officials were able to give oral evidence
between the First Reading of the Budget and its final agreement,
to update the Committee on the period of negotiations.
13 June 2007
Letter from the Chairman to Kitty Ussher
MP, Economic Secretary, HM Treasury
Thank you for your Ministry's Explanatory Memorandum
dated 6 June and for meeting with Sub-Committee A on 5 July. The
Sub-Committee have now considered the Preliminary Draft Budget
and have cleared the item from scrutiny. As is usual practice,
the Committee plans to publish a Report on the Budget in due course.
We broadly agree with the Government's position
and endorse your priorities. We fully support the Government's
efforts to ensure that the principles of affordability, efficiency
and value for money underpin all proposed expenditure to the EC
budget. The Sub-Committee were also pleased to hear that the Government
is still minded to focus the Regional Development and Social Funds
where they are most needed. In giving evidence, you discussed
hoped-for improvements in the draft budget to be agreed on 13
July. We would be grateful if you would write to the Committee
after 13 July to update us on progress at Budget ECOFIN.
As the Sub-Committee discussed with you at the
meeting last week, the Committee has particular concerns relating
to the form and transparency of the funding of the Galileo Project.
We support your stance to refuse to raise the Financial Perspective
ceilings to fund the Project. However, we remain concerned that
other Member states will not support your position and that the
Government's views may not prevail at Transport Council. The Sub-Committee
would appreciate regular updates on the progress of this dossier.
The Sub-Committee also noted that there appear
to be a variety of opinions on the form and purpose of the European
Institute of Technology. The Sub-Committee strongly opposes the
dedication of a contingency fund towards any purpose other than
as a reserve for an urgent situation, and so does not support
the Commission's planned use of this as a funding mechanism for
the European Institute of Technology. We support your stance that
funding for the European Institute of Technology should be found
by transparent means within the existing Financial Perspective
headings, and also urge the Government to work with all stakeholders
to agree on the purpose of the Institute.
The lack of transparency surrounding the funding
of the Commission's Agencies remains a concern, and is a subject
which we may choose to return to in the future. We would welcome
news of any steps you are able to take in Budget ECOFIN to improve
monitoring of their management, budgets and output.
You agreed to write to the Committee with more
information regarding the External Borders Funds, which appears
to have had its budget frozen; to give more information on the
purpose of the "mobility" line of the administration
budget and the reason for its significant increase. The Sub-Committee
also noted your aim to negotiate a lower number of additional
staff for the Commission.
The Sub-Committee have asked me to emphasise
the conclusions of their Report Financial Management and Fraud
in the EU. [7]Although
this is not directly related to the matter at hand, the Committee
noted that some progress has been made in this field. Given the
orders of magnitude involved, the Sub-Cominittee urge the Government
to show real determination in energising other Member States to
scrutinise actively their own expenditure of EU funds.
Finally, Baroness Cohen and the Sub-Committee's
Members have asked me to thank you for giving evidence so promptly
after taking up your new post. We look forward to working with
you both on this issue and on other dossiers in the future.
11 July 2007
Letter from Kitty Ussher MP to the Chairman
Thank you for your letter of 11 July clearing
the Preliminary Draft Budget from scrutiny and also expressing
the Committee's broad endorsement of the Government's position
and priorities. I should also thank Baroness Cohen and the Sub-Committee
for their thorough questioning and scrutiny. I am pleased to update
you on the progress made at Budget ECOFIN on 13 July.
The Council of the European Union formally agreed
the 2008 Draft Budget (DB) of the European Communities at the
ECOFIN (Budget) Council on 13 July, following conciliation with
the European Parliament. The DB was agreed by Council unanimously
and was based on a package put together by the Portuguese Presidency
following discussions of the Commission's 2008 Preliminary Draft
Budget (PDB) in the Council's Budget Committee.
My Explanatory Memorandum of 6 June 2007 set
out the PDB proposals in detail. The DB documents will be published
in the autumn and discussed further at the Council's second reading
in November, following amendments and modifications proposed by
the European Parliament in its first reading in October. The main
features of the DB are set out below.
The DB proposes a total of 128,401.2
million in commitment appropriations, and 119,410.3 million
in payment appropriations.[8]
This represents a reduction of 717 million (or 0.5%) for
commitments and 2,122.8 million (or 1.7%) for payments compared
to the Commission's PDB. These figures are well within the ceilings
set by the multi-annual Financial Perspective (FP), leaving an
increased margin of 3,902.0 million under the FP ceiling
for commitments. The reductions are made up of targeted reductions
to the proposed increases for specific programmes reflecting the
Council's estimate of actual financing needs for 2008, across-the-board
reductions to increases for Heading 1a, 1b and 2 taking into account
implementation trends, and reductions to increases in budgets
of decentralised agencies to ensure these are subject to the same
budget discipline as other institutions.
UNDER
HEADING 1A
(COMPETITIVENESS FOR
GROWTH AND
EMPLOYMENT), commitment appropriations
were reduced by 266.4 million and payment appropriations
by 548.4 million compared to the PDB, leaving a margin of
343 million below the FP ceiling for commitments. These
overall reductions consist of:
across-the-board reductions to
commitments of 250 million;
reductions to the subsidies for
decentralised agencies of 16.4 million;
a transfer of commitment appropriations
for Galileo into the Reserve, pending a decision on the issue;
and
similar across-the-board reductions
for payments.
UNDER
HEADING 1B
(COHESION FOR
GROWTH AND
EMPLOYMENT), commitment appropriations
were not reduced, leaving a margin of 11.1 million. The
PDB's proposed increase in payment appropriations was reduced
by 498.0 million, consisting of:
reductions to budget lines relating
to the completion of 2000-2006 programmes, particularly the European
regional Development Fund, of 298.8 million; and
reductions to 2007-2013 programmes,
taking into account completion and implementation rates, of 199.2
million.
UNDER
HEADING 2 (PRESERVATION
AND MANAGEMENT
OF NATURAL
RESOURCES), commitment and payment
appropriations for agricultural expenditure were reduced by 553.2
million respectively compared to the PDB, leaving a margin of
3,077.3 million below the FP ceiling for commitments. Rural
Development spending has not been affected by these reductions,
which come from:
an across-the-board commitments
and payments reduction of 350 million for interventions
in agricultural markets, except for budget lines relating to food
programmes, the free distribution of fruit and vegetables and
school milk;
a targeted commitments and payments
reduction of 200 million to the budget line relating to
the clearance of accounts; and
reductions to the subsidies for
decentralised agencies of 3.2 million.
UNDER
HEADING 3A
(FREEDOM, SECURITY
AND JUSTICE),
commitment appropriations were reduced by 4.3 million and
payment appropriations by 18.3 million compared to the PDB,
leaving a total margin of 60.3 million under the FP ceiling
for commitments. These overall reductions were achieved through:
a targeted reduction to commitments
for the Prince programme of 1 million;
a targeted reduction to payments
for budget lines relating to the European fund for the integration
of third country nationals, the European return fund, Fundamental
rights and citizenship, and Fight against violence (Daphne) or
15 million in line with absorption capacities and past implementation
rates; and
reductions to the subsidies for
decentralised agencies of 3.3 million.
UNDER
HEADING 3B
(CITIZENSHIP), commitment appropriations
were reduced by 14.6 million and payment appropriations
by 44.6 million compared to the PDB, leaving a total margin
of 31.1 million under the FP ceiling for commitments. This
represents:
targeted reductions to commitments
and payments for the budget lines, Multimedia actions, Information
for the media and specific actions under the "Going Local"
communication article of 5 million;
targeted reductions to payments
for the budget lines Media 2007, Culture 2007-2013, and Youth
in action of 30 million; and
reductions to the subsidies for
decentralised agencies of 9.6 million.
UNDER
HEADING 4 (THE
EU AS A
GLOBAL PARTNER),
commitment appropriations were increased by 217.6 million
and payment appropriations reduced by 364.2 million (including
a reduction of 239.2 million to the Emergency Aid Reserve)
compared to the PDB, leaving a total margin of 1l2.2 million
below the FP ceiling for commitments. This allows for increases
in commitment appropriations of 80 million for assistance
to Palestine and of 180 million for assistance to Kosovo,
both of which are entered in the Reserve. The reductions were
mainly achieved through:
targeted reductions to commitments
for the Instrument for pre-accession (18.5 million), the
evaluation of results, the co-ordination and promotion of awareness
and the Prince programme (10.5 million) and regional and
horizontal programmes (13.4 million) taking into account
absorption capacities and past implementation rates;
targeted reductions to payments
for the same budget lines and those relating to transition and
institution-building, and the completion of former co-operation
with Turkey, taking into account absorption capacities and past
implementation rates totalling 125 million; and
a reduction of 239.2 million
in payments to the Emergency Aid Reserve.
UNDER
HEADING 5 (ADMINISTRATION),
the large increase in commitment and payment appropriations proposed
by the PDB was reduced by 96.2 million, leaving a total
margin of 266.8 million below the FP ceiling for commitments.
The approach taken by Council was to set an appropriate level
for the administrative budget of each institution taking into
account their own specificities and their real and justified needs
while accepting all new posts relating to the 2004 and 2007 enlargements.
In particular, the reductions were achieved through:
limiting the global increase
of the Council's own budget to 0.2%;
applying for other institutions
a 2% reduction taking into account efficiency gains and the impact
of inter-institutional co-operation;
retaining specific decreases
on individual budget lines for some institutions taking into account
real needs;
increasing the standard flat
rate abatement on salaries for some institutions, taking into
account their current vacancy rate;
accepting only a few new posts
for new tasks on the basis of justified needs.
There were no changes to the PDB
proposal for HEADING 6 (COMPENSATIONS).
Tables summarising the changes between the PDB and DB are set
out in Annex 1 to this letter.
During a conciliation meeting between the Council
and the European Parliament, five Joint Statements relating to
the budget were agreed. These concerned: Structural and Cohesion
Funds and Rural Development 2007-2013 programmes; Recruitment
in Relation to the 2004 and 2007 Enlargement; Decentralised Agencies;
Executive Agencies; and Assigned Revenues. The Government is supportive
of these statements, which call for a greater degree of transparency,
sound financial management and budget discipline in the areas
they concern.
The Government believes the Council's 2008 DB
goes a considerable way to meeting its key objectives for the
negotiations. In particular the DB maintains budget discipline:
it significantly reduces the level of payment appropriations in
Headings 1 and 2, to bring the budget closer to the likely implementation
rate and to reduce the likelihood of another large surplus. It
also protects allocations for Afghanistan and Iraq and other UK
priority areas (Adjustment Support for Sugar Protocol Countries,
Cooperation with Developing Countries in Asia, Humanitarian Aid
and CFSP) and it takes a rigorous approach to expenditure in Headings
3 and 5, delivering savings and increased flexibility.
In addition, the 2008 DB remains fully consistent
with the financial settlement agreed in December 2005 and continues
to cater for the needs of enlargement in a budget-disciplined
fashion. Whilst the Government would have welcomed a more ambitious
reduction to administrative expenditure, the DB represents a balanced
overall package to put to the European Parliament, and the Government
will continue to pursue its key objectives in the subsequent stages
of the 2008 budget process.
25 July 2007
Annex A
Table 1
SUMMARY OF
2008 PDB AND DRAFT
EC BUDGETEUR MILLION
Heading
| Financial
Framework
Ceiling
| 2008 PDB
CA (2)PA (3)
| 2008 DB Council 1st ReadingCAPA
| Difference DB/PDB CAPA
|
| 1. Sustainable Growth | 56,736
| 57,148 | 50,161
| 56,882 | 49,115
| -266 | -1,046 |
| 1a. Competitiveness for Growth and Employment
| 9,847 | 10,270 | 9,539
| 10,004 | 8,990 | -266
| -549 |
| Margin[9]
| | 76.6
| | 343.0
| | 266 |
|
| 1b. Cohesion for Growth and Management |
46,889 | 46,878 | 40.623
| 46,878 | 40,125 | 0
| -498 |
| Margin |
| 11.1 |
| 11.1 |
| 0 | |
2. Preservation and Management of Natural Resources
| 58,800 | 56,276
| 54,770 | 55,723
| 54,217 | -553 |
-553 |
| Margin |
| 2,524.2 |
| 3,077.3 |
| 553 | |
3. Citizenship, Freedom, Security and Justice
| 1,362 | 1,288 |
1,190 | 1,271 | 1,128
| -17 | -62 |
| 3a. Freedom, Security and Justice
| 747 | 691 | 496
| 687 | 478 | -4
| -18 |
| Margin |
| 56.0 |
| 60.3 |
| 4.3 | |
| 3b. Citizenship | 615
| 597 | 693 | 584
| 650 | -13 | -43
|
| Margin |
| 17.7 |
| 31.1 |
| 13 | |
4. European Union as a Global Partner[10]
| 7,002 | 6,911 |
7,917 | 7,129 | 7,553
| 218 | -364 |
| Margin |
| 329.8 |
| 112.2 |
| -218 |
|
5. Administration |
7,380 | 7,336 | 7,336
| 7,190 | 7,190 |
-146 | -146 |
| Margin |
| 121.2 |
| 266.8 |
| 146 | |
6. Compensation |
207 | 207 | 207
| 207 | 0 | 0
| 0 |
| Margin |
| 363.7 |
| 363.7 |
| 0 | |
TOTAL (4) | 131,487
| 129,166 | 121,581
| 128,401 | 119,410
| -765 | -2,171
|
| Margin |
| 3,137 |
| 3,902 |
| 765 | |
| Appropriations for payment as % of GNI
| | | 0.97%
| | 0.95% |
| |
NOTES
(2) CA = commitment appropriations.
(3) PA = payment appropriations.
(4) Due to rounding, the sum of the lines may not equal the total.
| | | |
| | | |
Table 2
2008 PDB AND DRAFT
EC BUDGETGBP MILLION
Heading | Financial
Framework
Ceiling
| 2008 PDB
CA (2)PA (3)
| 2008 DB Council 1st ReadingCAPA
| Difference DB/PDB CAPA
|
| 1. Sustainable Growth | 38,240.1
| 38,517.8 | 33,808.5
| 38,338.5 | 33,103.5
| -179.3 | -705.0
|
| 1a. Competitiveness for Growth and Employment
| 6,636.9 | 6,922.0 | 6,429.3
| 6,742.7 | 6,059.3 | -179.3
| -370.0 |
| Margin[11]
| | 51.6
| | 231.2
| | 179.3
| |
| lb. Cohesion for Growth and Management |
31,603.2 | 31,595.8 | 27,380.0
| 31,595.8 | 27,044.3 | 0
| -335.7 |
| Margin |
| 7.2 | |
7.2 | | 0
| |
2. Preservation and Management of Natural Resources
| 39,631.2 | 37,930.0
| 36,915.0 | 37,557.3
| 36,542.3 | -372.7
| -372.7 |
| Margin |
| 1,701.3 |
| 2,074.1 |
| 372.7 |
|
3. Citizenship, Freedom, Security and Justice
| 918.0 | 868.1 |
802.1 | 856.7 | 760.3
| -11.5 | -41.8 |
| 3a. Freedom, Security and Justice
| 503.3 | 465.7 | 334.3
| 463.0 | 322.2 | -2.7
| -12.1 |
| Margin |
| 37.7 |
| 40.6 |
| 2.9 | |
| 3b. Citizenship | 414.5
| 402.4 | 467.1 | 393.6
| 438.1 | -8.8 | -29.0
|
| Margin |
| 11.9 |
| 21.0 |
| 8.8 | |
4. European Union as a Global Partner[12]
| 4,719.3 | 4,658.0
| 5,336.1 | 4,804.9
| 5,090.7 | 146.9
| -245.3 |
| Margin |
| 222.3 |
| 75.6 |
| -146.9 |
|
5. Administration |
4,974.1 | 4,944.5 |
4,944.5 | 4,846.1 |
4,846.1 | -98.4 |
-98.4 |
| Margin |
| 81.7 |
| 179.8 |
| 98.4 |
|
6. Compensation |
139.5 | 139.5 | 139.5
| 139.5 | 139.5 |
0 | 0 |
| Margin |
| 245.1 |
| 245.1 |
| 0 | |
TOTAL (4) | 88,622.2
| 87,057.9 | 81,945.6
| 86,542.3 | 80,482.3
| -515.6 | -1,463.3
|
| Margin |
| 2,114.3 |
| 2,629.9 |
| 515.6 |
|
| Appropriations for payment as % of GNI
| | | 0.97%
| | 0.95% |
| |
| | |
| | | |
|
Notes
(2) CA = commitment appropriations.
(3) PA = payment appropriations.
(4) Due to rounding, the sum of the lines may not equal the total
Sterling figures converted the exchange rate on 29 June 2007: 1= £0.674.
Excludes 234.5m from the Emergency Aid Reserve.
| | | |
| | | |
Letter from the Chairman to Kitty Ussher MP
Thank you for your letter dated 25 July 2007 regarding the
2008 Draft Budget. This was considered by Sub-Committee A at their
meeting on 9 October. The Sub-Committee are grateful for this
update, and look forward to receiving details of progress in due
course.
10 October 2007
7 15th Report of Session 2005-06, HL Paper 270. Back
8
For Sterling equivalents of key figures quoted, please refer to
the tables in Annex 1.
Back
9
The margin for Heading 1 (sub-heading 1a) does not take into account
the appropriations related to the European Globalisation Adjustment
Fund (500m). Back
10
Excludes 234.5m from the Emergency Aid Reserve. Back
11
The margin for Heading 1 (sub-heading 1a) does not take into account
the appropriations related to the European Globalisation Adjustment
Fund (500m). Back
12 Excludes 234.5m from the Emergency Aid Reserve.
Back
|