APPENDIX 8: NOTE FROM THE PROMOTER
TO THE COMMITTEE ON CLAUSES 40 AND 41 OF THE BILL
On Tuesday 29 April the Committee asked for a note
from the Promoter explaining clauses 40 and 41 of the Bill.
Clause 40 is based on a provision contained in the
Channel Tunnel Rail Link Act 1996, and deals with co-operation
between the controllers of railway assets with which Crossrail
construction, maintenance or operation interact and the Nominated
Undertaker. Either party can require the other party to enter
into an agreement. The object is to ensure that neither the Nominated
Undertaker nor the controller can act unreasonably in dealing
with a problem relating to the interaction of the Crossrail works
with overland or underground railway assets.
If the parties cannot reach agreement under clause
40, the matter is referred to arbitration. The Secretary of State
may then, under clause 41(3), specify the results to be achieved
by arbitration, and then the arbitrator determines the fair termssuch
as compensationby which those results are achieved. This
is to avoid the possibility that the result of the arbitration
frustrates the ability of the Nominated Undertaker to deliver
essential Crossrail works, which have been authorised by Parliament.
The asset controllers in question include London
Underground and the Public Private Partnerships, BAA, and Network
Rail. Clauses 40 and 41 are only intended to be used in circumstances
where the matter is not within the Office of Rail Regulation's
normal jurisdiction, or a solution cannot be reached by normal
agreement.
It follows, therefore, that the Promoter does not
intend that clauses 40 and 41 will apply to railway operators
on the Network Rail network, as clause 40 should not supplant
or override the allocation of access rights under the Railways
Act 1993, the taking of possessions under the Network Code as
overseen by the ORR, nor, indeed, the Department's stated intention
to work within normal industry processes as far as possible in
connection with the Crossrail project. If clause 40 is not applied
in circumstances where the matter may be referred to the ORR for
determination in accordance with its statutory duties or functions,
then clause 41 does not apply in these circumstances either.
Indeed, it is unclear how these clauses could be
used to supplant or override the ORR's decisions under the Railways
Act 1993 with regard to access rights, as the provisions that
would have allowed intervention in the allocation of access rights
are intended to be removed in accordance with the Minister's recent
statements (made on 11 and 18 April) and clauses 40 and 41 do
not directly empower the Secretary of State in making a direction
to modify any access arrangements directed by the ORR under the
Railways Act 1993. It would therefore be an abuse of power, and
thus judicially reviewable, for the Secretary of State to use
clause 41(3) to seek to modify any decisions made by the ORR under
the access regime of the Railways Act 1993.
Whilst, therefore, clause 41(3) is not to be used
to direct the ORR in discharging its statutory duties or functions,
there are other circumstances where clauses 40 and 41 might apply.
For example, the Crossrail works at Farringdon station will involve
a complex interface with other works, such as Thameslink, and
non-regulated asset controllers, such as London Underground. It
is therefore recognised that this complexity requires managing
in order to ensure the successful delivery of the Crossrail project
at this location, particularly as it may be necessary for the
Secretary of State to ensure that the terms of a London Underground
or PPP contract (which is not regulated by the Railways Act 1993
or within the ORR's jurisdiction) do not unreasonably prevent
something that is critical to the delivery of the Crossrail project
that has been defined as part of the Bill process.
Nevertheless, clauses 40 and 41 remain fall-back
provisions in these circumstances, as it is also recognised that,
in this example, London Underground, as a key delivery partner
to the project, will have a direct interest in integrating Crossrail
works successfully with its own existing assets.
The Promoter is considering whether it is appropriate
to, during later stages of the Bill process, make it explicit
that clauses 40 or 41 should not be invoked by either party where
the matter may be referred to the ORR for determination in accordance
with its statutory duties or functionsin effect, where
a solution can be reached under the aegis of the normal regulatory
processes.
Notwithstanding that, the Promoter is clear that
it does not intend that clauses 40 and 41 will apply to railway
operators on the Network Rail network. The provisions would instead
remain in reserve to deal with such complex circumstances as outlined
above, although the Promoter will specifically review clause 41(3)
following comments that the Select Committee has made.
|