Examination of Witnesses (Questions 200-219)
11 FEBRUARY 2004
Mr Alan Moore, Mr Chris Shears, Mr Rob Hastings and
Mr Alan Mortimer
Q200 Lord Young of Graffham: In addition
to the problem of sight, of course, a real obstacle to achieving
a ten per cent, let alone a 20 per cent market is finance, finding
institutions which are prepared to invest or help to fund the
investment. Have you noticed any change in the attitude of institutions,
in particular the 2015 target for Renewable Obligations, has
that helped?
Mr Moore: Yes. Perhaps I could take that one.
As I said in my first answer, I think the 2015 Obligation was
extremely useful, not only as a signal in terms of the Government's
intentions. Whether I am talking to my in-house investors or outside
banks and equity players, political risk is always the one risk
that is quite difficult to mitigate. The 2015 target was a powerful
signal about political intent but also, as I was explaining earlier,
it gives us the ability to do our economic spread sheets over
a period where we can make our own predictions about Renewables
Obligations Certificate values. Whilst we were looking at a short
period that was not so easy. I think it is fair to say, and I
am not being in any way rude, it takes finance houses a couple
of years after any major change to get comfortable with the risks
that are involved. I am told, although I was not involved at the
time, that was the case when the old fashioned NFFO contracts
came into place in the early 1990s. I think we have seen that
in the last couple of years since the RO was first announced.
What I can say is my own company announced only last week the
closure of a £400 million financing deal involving private
equity and a consortium of 13 banks. I think that is a very good
sign that the finance houses in the city are getting comfortable
with the risks. Inevitably there will be tension between who takes
the risk on the off-take contract, on the long term contract for
the electricity and the Renewables Obligation Certificates. There
are some pretty interesting negotiations going on between the
electricity supply companies, who have the Obligation, and the
finance houses about who takes that long term risk. I think that
is a debate which is going on right now and I think there will
be a compromise somewhere in the middle with both sides taking
some of that risk. Very powerful signs are that in only the last
few weeks things are moving on that front.
Q201 Lord Young of Graffham: Obviously your
company has made progress but are you aware of other potential
investors who cannot get finance or will be looking to finance?
Mr Moore: Certainly if you went and talked to
some of our colleagues in the industry they would say they have
been having problems, but equally I am aware that what I would
like to think of as a bit of a pioneering deal that we have done,
I already know that others are riding on the wave of that.
Q202 Lord Tombs: Could you give us a ballpark
figure of the capital cost of six gigawatts of wind power?
Mr Moore: If you take onshore and offshore as
a mixture
Q203 Lord Tombs: 50/50 you said.
Mr Moore: It is around £900 a kilowatt
at today's prices.
Q204 Lord Tombs: £900?
Mr Moore: Yes, £900 a kilowatt, £900,000
a megawatt.
Q205 Lord Tombs: That is rather a lot of
money, is it not?
Mr Moore: It is quite a lot of money but the
running costs are very low once you have built it.
Q206 Lord Tombs: I am thinking about capital
resources. It makes your £400 million deal look quite small.
Mr Moore: Yes, it will deliver something like
approximately 400 megawatts and a lot of money has to be raised.
Q207 Lord Tombs: I have two questions on
your press release which I found very interesting. It is to finance
your existing 13 wind farms and new development. What is the split
between that?
Mr Moore: There are about 150 megawatts of existing
wind farms.
Q208 Lord Tombs: How much of the £400
million is taken up financing those?
Mr Moore: That is commercially confidential,
if you do not mind me not answering that.
Q209 Lord Tombs: I can do my sums.
Mr Moore: There are about 150 megawatts of existing
wind farms and the total fund will be for about 430 megawatts.
Q210 Lord Tombs: You said in that same statement
that the principal aim was to get the existing wind farms off
your balance sheet to allow breathing space. I can understand
that. Is that a situation widely existing in the industry? You
are a big operator.
Mr Hastings: Maybe I could come in? The way
in which financing is approached in the projects is it is maybe
driven in some cases by a corporate target. We have a return on
equity investment hurdles to reach. It can be that you can structure
a capital investment with financing which can improve some of
your returns on equity and so it really depends on what sort of
corporate targets we have. Yes, going for structured project finance
which may be non recourse and, therefore, off balance sheet, can
be beneficial to the economic performance of the project when
it is consolidated within the corporate targets.
Q211 Lord Tombs: It is a bit of a problem
essentially because of the size of operators?
Mr Hastings: Yes.
Q212 Chairman: If we turn to the specifics
of offshore briefly at the moment. What do you see as the main
risks associated with offshore development? There are questions
of health and safety associated with the maintenance of offshore
turbines. There is the question of reliability of turbines working
for long periods in very hostile environments. There is the question
of appropriate foundation structures to stop these things falling
over. The first one which falls over will be quite a blow for
the confidence in the industry. Comments, please?
Mr Hastings: If we are taking risks in general
of course you have to get the project in the first case so there
is a consenting risk. There is a process you have to get it through
in terms of converting an idea into something which is operating
so that is one part of it. Of course there is a lot of work going
on at that stage to identify what is appropriate and that is appropriate
in the sense of the environment it is working in and that can
be an extended period of time, typically something in the region
of maybe three years. There is an awful lot of work going into
identifying what the actual environmental considerations are and
the issues like we mentioned in terms of the suitability of the
foundation designed for the location would be worked through extensively
and effectively what will be delivered will work in terms of the
engineers' design. There are other risks. There is the financial
risk of making this thing perform financially and return for the
investors and there are other risks like making sure you have
a distribution system which is going to operate. If I may pick
up specifically on the points you raised which are the safety
related risks. Is the asset going to be safe? Once we have constructed
it will it stay there, will it operate and will it function as
it was intended to function? I think inevitably as you go through
the process of making a decision to invest, for example, £500
million in building an offshore wind farm, clearly there is a
rigorous process of investigation which goes on to determine whether
it is an appropriate design and whether it will operate appropriately
for its application. If you look at who is doing this work I think
typically these are large household name engineering type companies
who are doing the design. For example, if you take specifically
foundation design, there is a wealth of experience in terms of
constructing offshore foundations and that largely comes from
the oil and gas industry.
Q213 Chairman: Can you tell me what industry
has experience of building structures in situ in which wind farms
are placed because I believe very little of the oil and gas industry
experience is relevant?
Mr Hastings: I am not sure that is the case.
I think there is a lot of work that has gone on in marine engineering,
marine structural engineering, if you like, which is applicable.
For example, the environmental loading conditions which are encountered
in these locations are quite similar. There are slightly different
parameters you may have, because of the shallower water conditions
there may be slightly different parameters that they have to design
to. Effectively the engineering models that are used, the design
concepts which are used and applied, for example piled foundations,
are in effect very similar to what you find in an offshore area.
Q214 Lord Flowers: At first sight an oil
rig is one thing, a wind turbine is a very different proposition.
Mr Hastings: It is relatively easy to design
for a wind turbine compared with an offshore oil and gas structure.
If you imagine the difference in scale, offshore oil and gas structure
could weigh something in the region of 10,000 tonnes. A wind turbine
could weigh something like maybe 200 tonnes, a large offshore
wind turbine. It is an order of magnitude of difference in terms
of weight. The dynamic loadings are probably different but, again,
in terms of relative loadings a wind turbine, even a large wind
turbine, maybe a three or four megawatt wind turbine, which would
be applied offshore, still does not approach anything like the
kind of loadings you would encounter on an oil and gas structure.
Q215 Chairman: Has anybody, for example,
modelled the effects of the vibrationswhich we have been
discussing alreadyassociated with the operation of the
turbine and unconsolidated sound? These vibrations would be transmitted
down the structure.
Mr Hastings: There has been quite a lot of research
done on this already. Probably going back over the last maybe
five or six years, there was a lot of research undertaken by,
strangely, the Danish engineering organisations and universities
and, in fact, some of the Germans have been doing that as well.
Q216 Lord Sutherland of Houndwood: May I
ask an additional question? This is on the ScottishPower piece.
I was looking particularly at the paragraphs dealing with the
predicted price rises to end users and then you have a very significant
paragraph seven in which you say there is a real concern when
Government actually come to face these they will be tempted tomeddle
is the word I would useintervene is the word you use. Have
you drawn this very clearly to the attention of the relevant departments
and has it registered? This will clearly have an impact on the
long term planning?
Mr Mortimer: In terms of prices?
Q217 Lord Sutherland of Houndwood: Yes.
Is Government aware that these are your predictions and are they
nonetheless giving you encouraging noises to go ahead?
Mr Mortimer: Yes, I think they are. We have
made it clear, certainly in our responses to various consultations,
that there will be implications for consumer prices and that it
is in our interest to be up front and honest about what they are
and recognise that is the cost of a lower carbon economy.
Q218 Baroness Platt of Writtle: I am struck
by the difference in David Milborrow's papers, on intermittency
from Scottish Power's views. Has he seen the paper that we have
had from ScottishPower which is very much more doubtful about
the practicality of their being able to operate in a sensible,
efficient, economic, secure way? We have had this paper and ScottishPower
seems extremely doubtful.
Mr Mortimer: Certainly we are flagging up some
issues which do need to be tackled in the early term. There are
some particularly Scottish issues as well which are maybe driving
that concern.
Q219 Baroness Platt of Writtle: Yes, but
that is going to be a major source, is it not?
Mr Mortimer: It could be and it should be. It
should be a substantial contribution towards the national targets.
We can see, for example, that the grid could become a significant
constraint. It is already a constraint, I know, to areas, for
example the North West of Scotland and South West Scotland where
there just is not any grid capacity at the moment. That has been
recognised and studies have been done to show how it can be expanded
to deliver the capacity but that will take time. To take new grid
infrastructure through the planning process and invest in it and
construct it will take time and our experience, for example, with
the Northern Ireland interconnector was that it took seven years
to go through that process. Now when you bear in mind that by
2010 the achievement of targets could start to be compromised
by lack of grid then really we need to be acting now. Work is
underway on environmental aspects, environmental assessment of
new grid lines in Scotland, and that is good, but as yet there
is no agreement on a funding mechanism which will allow investment
in this grid infrastructure to go ahead. That is very urgently
required and Ofgem are working on it but it is not in place yet.
|