Memorandum by the British Wind Energy
Association (BWEA)
The British Wind Energy Association welcomes
the opportunity to participate in the House of Lords' Science
and Technology Committee's inquiry on the Practicalities of Renewable
Energy.
The BWEA was established in 1978 and is the
representative body for companies active in the UK wind energy
market. Its membership has grown rapidly in recent years and now
consists of 281 companies including all grid-connected wind energy
and every company with a lease to develop offshore.
Wind energy is widely recognized as an abundant
energy resource indigenous to the UK. Most commentators accept
that wind is likely to represent at the very least half of the
Government's "10 per cent by 2010" target because of
the maturity and low cost of wind powered generation relative
to other forms of renewable electricity generation technologies.
Continued growth of installed wind energy generation capacity
beyond this 10 per cent 2010 baseline is almost guaranteed. In
representing the industry BWEA is therefore in a unique position
to comment on the measures necessary to ensure that "UK Plc"
is able to deliver the requisite number of MW of installed wind
and other renewables capacity by 2010.
In a letter of 18 July 2003 the Committee noted
the challenging set of targets contained within the White Paper
and requested information on the practical steps that will be
needed to ensure that these demanding targets for renewable energy
production are met. In answering this question we have been guided
by the Committee's particular interest in the following four areas.
The cost effective technologies available
now for the generation of renewable energy.
The number of sites potentially available
for such technologies and the obstacles to taking these up.
The logistics of providing stand-by
capacity for times when intermittent sources are not available.
The intermediate milestones that
should be set on the way to achieving the White Paper's aims.
In answering these questions we have clearly
focussed on wind-related issues; in addition we have not, where
we believe that there are additional points of relevance, confined
ourselves solely to the above four areas.
BWEA believes that the White Paper has laid
out a bold vision for renewables. In creating a 10 per cent renewable
energy target for 2010 and a 20 per cent aspiration by 2020 it
would be fair to say that the UK is now a world leader in creating
stable incentives to encourage the development of an efficient
and effective renewables industry. Nonetheless BWEA would also
note that political and financial commitments alone are not enough.
INTRODUCTION
BWEA notes that there has been a significant
increase in developer interest in wind farm projects since April
2002. BWEA firmly believes that this increased interest is directly
attributable to the stimulus provided by the Renewables Obligation
(RO). The following table clearly indicates the growth in planning
submissions since the RO was introduced.

* Full year 2003 numbers are an estimate
and, as Figure 2 demonstrates, there are clearly
sufficient numbers of MWs getting through planning.

* Full year 2003 numbers are an estimate
The numbers speak for themselves. However the
rate at which consented projects are being built is a different
story as illustrated below.

* Full year 2003 numbers are an estimate
Today there is about 1,400MW of wind capacity
in the UK which has received planning permission but which is
not being built. The remainder of this document seeks to provide
the Committee with a summary of the views of the wind industry
regarding matters affecting the speed with which wind farms are
being constructed and the possible reasons for delays in wind
farm construction.
In this regard we would note that the barriers
to further development of the UK's vast wind resource are institutional
and not technical. As such solutions to them are, while not simple,
entirely within government influence. We are concerned with institutional
hurdles in three broad areas: Finance, Grid and Planning, and
will address each in turn.
1. FINANCE
1.1 Government track record in energy markets
This Government has a very poor track record
of regulatory intervention in the energy markets. As a result
the private sector has had its "fingers burned" on a
number of occasions; the most notable of these relates to investments
in the 1990s in both CCGT and British Energy. The introduction
of NETA and the subsequent collapse in wholesale prices, has severely
damaged these investments such that there is now in the region
of £10-15 billion of distressed assets in UK power generation.
Given this background and continued generation capacity overhang,
it should come as no surprise that the private sector does not
appear to be rushing to invest a further £10 billion in building
10,000MW of renewable generation plant by 2010.
The nature of the RO means that an investment
in renewables today is affected by changes to the RO over the
next 10-15 years. Consequently the value of the Renewable Obligation
Certificates (ROCs) is highly susceptible to political interference.
In some European countries, where the government has established
a favourable track record with the financial and energy communities,
such a high degree of regulatory risk would not be an issue. Unfortunately,
as mentioned, the UK Government has a poor record in the energy
markets. It will therefore take some time for the financial community
to get sufficiently comfortable with the RO. Only once they have
this level of comfort will they be prepared to make significant
long-term investments in renewables.
1.2 BWEA commissioned financing study
In June of 2003 BWEA commissioned an independent
report into the efficacy of the RO. In September BWEA released
the findings of this analysis and these findings are publicly
available through our web-site or by contacting BWEA direct. BWEA
is now consulting with its members and will not take an official
position before this consultation is complete. We currently expect
to have developed a view by the end of November and will share
our findings with Government at that time.
While it would seem clear from this study that
the problems of the RO run deeper than the lack of a post 2010
target, BWEA would nonetheless note that the absence of such a
target does not help. We are concerned that as the industry moves
closer to 2010 without a clear decision being made on renewable
energy targets beyond that date, the current interest in developing
and building wind farms, both on and offshore, will fall off rapidly.
Notwithstanding the above we re-iterate our
view that we do not believe that a simple extension of the existing
2010 targets will necessarily provide financiers with sufficient
comfort to cause them to invest capital in renewables to the degree
required.
1.3 Co-firing
On Friday 29 August 2003 the DTI opened "The
Renewables Obligations (Amendment) Order 2003 Statutory Consultation".
This consultation outlines a number of changes that DTI is proposing
to make with effect from April 2004. Most are minor technical
alterations that will have minimal impacts on the RO mechanism.
However the most significant relates to an extension of the existing
co-firing rules.
BWEA would remind this Committee that the RO
was created to support renewable generation and in this regard
notes that the only apparent support for the co-firing changes
as proposed comes from the thermal generatorsspecifically
the coal lobby. Hardly anyone from the renewables industry believes
that the measures as proposed will support renewables. On the
contrary the view of the overwhelming majority is that the proposals
will do great harm to the credibility of the RO and to the development
of renewables.
BWEA sympathises with the concerns of the Government
that the RO in its present form is not encouraging sufficient
amounts of investment in renewable generation plant. Nonetheless
BWEA does not believe that the solution to this problem lies in
a co-firing "quick fix". Such a "quick fix"
would only benefit coal fired generators and would ensure that
targets for renewables are met (even if not with renewable generation!).
However it would NOT assist the development of the British biomass
industry and would significantly damage confidence in the RO and
hence the nascent renewables industry.
There are real solutions to the current problems
with the RO and BWEA has been investigating these for some months
now. We are currently consulting internally and with other trade
associations and would encourage Government to work with us to
find a real solution to this complex problem.
2. GRID
2.1 Licence obligations
BWEA notes that, at its most fundamental, the
problems that developers face in securing Grid connections can
be distilled down to the simple fact that the primary licence
obligations of the Transmission System Operators (TSOs) and Distribution
Network Operators (DNOs) as well as the industry regulator (Ofgem)
are to ensure a safe, secure and economical supply of electricity.
In all instances, environmental considerations are secondary (or
less) obligations. BWEA believes that the licences for all of
the above institutions should include, as a primary obligation,
a requirement to encourage the connection of;
(1) renewable generation technologies
(2) technologies which, while they may not
comply with existing Grid and Distribution code technical specifications,
are moving toward compliance and are not present in sufficient
amounts to threaten grid stability.
BWEA recognises the efforts that are being made
by TSOs and DNOs to connect renewables, but nonetheless notes
that these entities must be mindful, in the first instance, of
their licence obligations. Consequently, until such time as the
licence conditions are amended to address this problem, BWEA believes
that Grid related problems will persist.
2.2 Nature of the Grid Codes
The England & Wales as well as the Scottish
Grid Codes today are functional specifications of existing, relatively
mature, large centralised synchronous generation sets. Likewise
the Distribution Code has been written for networks that are designed
to supply customer demand with power sourced from a high voltage
transmission network and subsequently delivered to demand loads
which reduce with distance from that transmission network.
Wind generation turns these traditional models
upside down. At a transmission level, BWEA notes that wind turbine
generators (WTGs) most commonly employ asynchronous generation
technology and that this technology is relatively immature and
rapidly evolving. At a Distribution level, WTGs are generally
located in areas with low population and load densities and hence
connecting them fundamentally alters the operation of distribution
networks. BWEA therefore wonders whether a fundamental review
of the Grid and Distribution Code might be more appropriate than
the "tinkering" that is currently taking place.
2.3 Development of ancillary markets
We return to the point made in 2.2 above that
the Grid Code is little more than a functional specification of
existing technology. In this regard BWEA is concerned that current
markets for reactive power and frequency response rely on all
generators having the capabilities necessary to compete in those
markets. What this means is that prices in these ancillary markets
are being driven down perhaps to the point where generators choose
not to bid. The result of this is that the cost of providing ancillary
services is then, by default, being passed on in the MWh price,
thereby forcing up the cost of generation.
BWEA feels it would be more appropriate to have
a system wide review which identified the needs of the system
in respect of ancillary services and examined the differing properties
of synchronous and non-synchronous generation such that the benefits
of each can be recognized and the ancillary services market adjusted
accordingly to enable the system to obtain optimum economic and
technical benefit from each. The result would be a stable grid
system which would not, as is the case now, involve excessive
cost for electricity consumers.
2.4 Regulatory monitoring
The renewable energy industry generally and
the wind industry specifically has, relative to existing generators
and established market participants, extremely limited resource
with which to be able to monitor and respond to the very many
consultations and grid issues that are currently underway. The
significance of this should not be underestimated and should be
addressed as a matter of priority.
2.5 Intermittency
We note that the Committee has specifically
requested information on the logistics of providing stand-by capacity
for periods when intermittent sources (such as wind) are not available.
In this regard we would refer you to the response submitted by
David Milborrow on Friday 10 October. David Milborrow is a BWEA
Board member and also acts as BWEA's technical consultant. Consequently
his response, which focuses specifically on Intermittency, covers
all the points that BWEA would wish to make on this subject and
should therefore be considered as an integral part of this formal
BWEA submission.
3. PLANNING
3.1 PPS22
The wind industry is anxious for the ODPM to
put in place the revised PPS22 Planning Guidance for Renewables
in England. We flagged this as a concern to PRASEG in May of this
year; nonetheless we note that the program continues to run behind
schedule. Progress on TAN 8 for Wales will also be critical to
achieving increased progress in planning. BWEA notes that similar
guidance in Scotland, as well as strong support from the Scottish
Executive, was published much more rapidly and has already proved
beneficial in promoting planning consents.
3.2 Site constraints
Planning authorities should recognize that planning
is only one of many areas that a wind developer needs to consider
when assessing a potential site. Industry therefore requests that
planning authorities do not attempt to zone or identify sites
for wind farms but instead provide clear, criteria based policies
to inform and guide developers as to the planning considerations
in their plan area.
3.3 Aviation
3.3.1 Low flying and Tactical Training Areas
(TTAs)
Defence Estates (DE) continues to object to
all wind farm applications within TTAs. Nonetheless BWEA believes
that TTAs can co-exist with wind farms as with other forms of
development and transport infrastructure. DE should therefore
be encouraged to cater for some wind developments in TTAs as these
regions provide otherwise appropriate siting areas for wind turbines.
3.3.2 Radar
Civil and military aviation stakeholders continue
to object to wind farms which are in the "line of sight"
of radar; these objections cover a very significant portion of
the UK land and sea area that has wind development potential.
BWEA notes that there has been no equivalent problem between wind
turbines and radar in other parts of Europe. The most attractive
solution developed to date has been the AMS Advanced Digital Tracker
(ADT) which is currently being trialled at two sites in Scotland
and is a software based filter which removes turbines from the
radar display without blocking the entire area of the wind farm.
It is vital that this technology is supported and developed and
BWEA feels that the House of Lords may have a significant role
to play in progressing this issue.
3.4 Telecommunications
The ways in which telecom operators deal with
wind turbines and their effects on remote telecoms links is inconsistent.
While the Radio Communications Agency (RCA) is sympathetic, they
would appear to have no control over objections raised by individual
operators. BWEA believes that the solution to this should include
a universally agreed set of data and distance requirements which
would be available to wind developers and network operators alike
and which should become accepted as best practice guidelines by
all concerned. While BWEA continues to work closely with RCA on
this, any support which this Committee can provide would be welcome.
In conclusion, the various hurdles that the
British wind industry has to overcome in order to build wind farms
are many, varied and complex. Given the intended audience, BWEA
has endeavoured to summarise these issues and in doing so we have
endeavoured to ensure that none of the salient facts are omitted.
Nonetheless please be assured that BWEA remains ready to give
additional evidence and provide any further clarification as and
when it may be required.
October 2003
|