Supplementary memorandum by the Environmental
Change Institute
I would like to thank the Committee for providing
the opportunity to discuss our research and submission in person.
This memorandum summarises the evidence submitted to the enquiry,
and clarifies or expands on some of the responses given to the
Committee on 11 February 2004.
A PORTFOLIO OF
INTERMITTENT ELECTRICITY
GENERATION
A strategic approach to the evolution of the
intermittent generating infrastructure in the UK will result in
a robust, reliable, low-intermittency solution to renewable energy
development. This research can identify the "next best"
development option for intermittent technologies, whether that
be identifying the next best offshore wind site that will deliver
the most reliable wind electricity supply, or the next best intermittent
technology that will provide system benefits including lower backup
and load following requirements (see below), lower grid capacity
requirements, etc. Furthermore:
This research considers only intermittent
generatorsour scenarios do not include electricity generated
from waste, landfill gas, hydro-electricity or bio-mass, as these
are essentially dispatchable power supplies.
Marine resources (wave and tidal
current) have yet to be included. Preliminary work on a geographically
diverse tidal power system suggests that the combined output of
a diversified tidal generating system would not drop below 50
per cent of peak system output, resulting in a renewable electricity
supply capable of supplying baseload demand, with output above
the 50 per cent level being intermittent but predictable.
The installation of domestic combined
heat and power (dCHP) contributes substantially to the stability
of the system during the crucial winter peakdCHP should
be considered integral to a successful low-intermittency electricity
supply, irrespective of whether dCHP itself is considered a renewable
source of electricity or not.
The initial policy should be to install
around 175 dCHP units (8kW heat output) and 225 solar roofs (32m2
@ 15 per cent efficiency) per MW of installed wind capacity.
BACKUP AND
LOAD FOLLOWING
REQUIREMENTS
Using a portfolio of wind power, solar power
and domestic combined heat and power systems would result in the
lowest requirement for conventional backup capacity and the lowest
need for additional load following. Backup and load following
requirements under this scenario are given belowit should
be noted that further geographic expansion of offshore wind power
(ie to Scotland) and additional intermittent generating technologies
(eg tidal stream power) will further reduce the need for additional
backup capacity.
BACKUP REQUIREMENT
FOR 10 PER
CENT SUPPLY
The amount of additional backup generating
capacity required when 10 per cent of annual electricity demand
met by intermittent sources is 400MW.
This figure does not include the
contribution that the existing backup capacity operating on the
transmission network would make to balance intermittency (typically
around 20 per cent of operating generating capacity).
Backup would be required on average
one hour in every five yearsfor four out of every five
years no additional backup would be required.
BACKUP REQUIREMENT
FOR 20 PER
CENT INTERMITTENT
SUPPLY
The amount of additional backup generating
capacity required when 20 per cent of annual electricity demand
met by intermittent sources is around 2,000MW.
Again, this figure does not include
the contribution that the existing backup capacity operating on
the transmission network would make to balancing intermittency,
which would be expected to significantly reduce this figure.
Backup would be required on average
one hour each year.
LOAD FOLLOWING
With a diversified intermittent generating
portfolio meeting 10 per cent of annual electricity demand, there
is very little change in the load following requirement for the
conventional generating capacity on the network.
The average hourly load following
requirement is virtually unchanged from that currently experienced
due to variation in hourly demand.
The peak load following requirement
increases from 7,600MW currently to 8,700MW, however load following
in excess of the existing peak will occur on average only one
hour in each year.
INTERMITTENCY AND
COST
A focus solely on the cost of providing the
electricity to the grid as cheaply as possible will not provide
the lowest cost solution for the whole supply system. Through
a strategic approach to the location, type and amount of intermittent
generation:
The costs of back-up capacity, its
running time and the amount of cycling (and thus wear and tear)
will all be reduced.
Lower carbon emissions will be achieved,
as less backup plant and less load following (from existing conventional
plant) will be required for the same overall contribution of intermittent
electricity.
EMBODIED ENERGY
Lord Winston asked a question regarding the
energy payback times, or embodied energy component, of renewable
energy systems. This is not dealt with directly by our research,
however previous work has shown that:
Wind turbines have an energy payback
time of around three months (ie they generate the same amount
of energy in their first three months of operation as was used
in their manufacture and construction).
Solar photovoltaic panels have an
energy payback time of around three to five years, depending on
manufacturing process and roof mounting system.
GOVERNMENT POLICY
AND SUPPORT
A question was raised regarding government support
for renewable energy targets. In this context is important to
note that:
If given an informed choice and no
price differential, 80 per cent of householders and small medium-sized
enterprises (in Europe and in the UK) would choose electricity
with a "low impact on climate change and no nuclear waste"
(Boardman and Palmer 2003)[4].
This choice will be available under
the EU Directive 2003/54/EC on liberalisation of the European
electricity market to be implemented by the British Government
after July 2004.
As a result, it is important that
the Directive is implemented in the most effective way possible,
providing consumers with the information and choice they are seeking.
17 February 2004
4 Boardman, B, Palmer, J, et al (2003) 4CE-Consumer
choice and carbon consciousness: Electricity disclosure in Europe. Back
|