CHAPTER 5: PUBLIC
ACCEPTABILITY
THE NEED FOR PUBLIC ACCEPTABILITY
5.1 The importance of public acceptability is widely
recognised: many witnesses told us that, however well founded
the safety case in the view of experts, no progress would be made
without public acceptability (e.g. the Environment Agency p123,
Gosforth Parish (Cumbria) Action Group pp143-144). Nirex told
us (p 319) the chief requirement is for a proposal which is "in
a form which is workable and wins public acceptance".
5.2 Overseas the need for public acceptance has been
widely recognised. Sir John Knill highlighted the relative success
in Finland and Sweden where work had been undertaken on public
acceptability and "an atmosphere was created within which
there has been real achievements" (p 195, Q 1005).
The Committee visited the US, Canada, Sweden and France, where
public acceptability has also been addressed. In Canada in 1978
the Federal and Ontario Provincial Governments set up a programme
to find a permanent repository for nuclear fuel waste. It was
agreed that the selection of the site of the repository would
not begin until after a formal public review. That review[42]
concluded that broad public support is necessary to ensure acceptability
of a concept, and "safety is a key part, but only one part,
of acceptability. Safety must be viewed from two complementary
perspectives: technical and social". Applying these criteria
the Canadian review panel concluded that while safety had been
adequately demonstrated from a technical perspective, from a social
perspective it had not.
5.3 The technical problems in Canada are very different
from our own. There is no legacy of weapons manufacture and they
have elected not to reprocess spent fuel. Therefore Canada does
not have the intermediate level wastes associated with reprocessing,
nor the problem of managing separated plutonium. But Canada has
over twenty nuclear reactors in service, has historic wastes associated
with the long term operations of radium and uranium refining,
and has to deal with uranium mine and mill tailings (about 200
million tonnes of these tailings have been generated since the
mid 1950s). Despite the technical differences, much of the Canadian
analysis has parallels in the United Kingdom. The Canadian conclusion
was that work should not proceed until what the panel called "the
social issues" had been further addressed. Exactly what criteria
should be used to define acceptance were not specified in the
report.
5.4 In the United States a good level of acceptance
has been established locally at the proposed Waste Isolation Pilot
Plant (WIPP) site at Carlsbad in New Mexico. Here it is proposed
to dispose of "transuranic waste", primarily plutonium
contaminated materials. But a lack of widespread national acceptance
of waste management plans has given rise to difficulties over
the transportation of the waste to the site. The Yucca Mountain
project in Nevada, an evaluation of a potential repository site
for spent nuclear fuel and other forms of high level radioactive
waste, is considerably less advanced. The decision to embark on
this work was primarily at the direction of the US Congress and
has been subjected to intense opposition from the local community.
There are also objections at the federal level from agencies responsible
for health, safety and environmental standards. A lack of public
acceptance is a major stumbling block at Yucca Mountain, where
there are also outstanding technical issues.
5.5 France, which like the UK has a legacy of nuclear
waste from both civil and defence programmes, has, unlike the
UK, nearly 80 per cent of its electricity generated by nuclear
power. The same spectrum of views about nuclear matters exists
but, perhaps because of the greater dependence on nuclear power,
there is less controversy about nuclear facilities and there seems
a greater recognition by the public of the need to deal with waste
management issues. The French government also has programmes established
specifically to improve the public acceptability of waste facilities
(see para 5.37).
5.6 Sweden has had an underground repository at Forsmark
for short-lived low and intermediate waste in operation since
1988. By any standard this is a significant achievement, although
the Swedish waste disposal problem is inherently more straightforward
than our own. The Swedish Government had no weapons programme
and has elected not to reprocess spent fuel and therefore Sweden
does not have the intermediate level waste associated with reprocessing,
nor the problem of managing separated plutonium. The public has
confidence in the regulators, which may stem in part from the
existence of freedom of information laws: allegations of secrecy
rarely seem to be levelled at the Swedish nuclear industry and
even less frequently at the regulators.
5.7 But even with the history of public confidence
in the regulators, the absence of a nuclear waste legacy from
past military programmes, a more straightforward waste management
programme with the absence of reprocessing, and ten years' operational
experience with an underground repository, Sweden has not yet
gained public acceptance for a deep geological disposal facility
for spent fuel.
5.8 For the last six years the Swedish Government
has had in place a well-developed government programme, financed
by the industry, to gain public acceptance at a local level for
its nuclear waste plans. Moreover, any proposal in Sweden is subject
to local referendum, which gives the local community the right
of veto. On the last occasion that a local referendum was taken
the proposal was lost only narrowly. It seems likely that the
public confidence necessary to win approval for a proposal to
build a deep repository on another site will be forthcoming in
the not too distant future.
PUBLIC
ACCEPTANCE
5.9 Finding publically acceptable solutions to complex
technical issues is not straightforward. One witness observed
that on most things the public does not think anything until it
is forced to do so (Hawkes Q1488). Another witness said that "
.the
public should not be expected to have an opinion. There are many
things for which quite legitimately the public looks to Government
to make up the mind of 56 million people. Nuclear energy is a
matter that is largely in Government hands and is a matter for
Government decision" (Fishlock Q1489). These witnesses were
clear that it is the job of those in power to take the decisions
necessary for the sound management of nuclear waste. If those
people are trusted by the public they will be allowed to get on
with the job. Government is seeking acceptance by the majority,
recognising that there may still be vocal opposition from minorities.
Acceptance by the public does not imply one hundred percent endorsement.
NATIONAL
AND LOCAL ISSUES
5.10 It is quite frequently the case that people
will support the construction of a large facility, a major airport
or large out of town shopping centre, for example, whilst also
arguing that it should not be placed in a certain location e.g.
"not in my back yard". The disposal of nuclear waste
confronts both sets of issues: securing general acceptance of
the principles underpinning an approach to the management of nuclear
waste and securing local acceptance to the selection of disposal
sites. Many people will go along with the concept as a general
principle but object when it affects them directly.
5.11 At present it is not clear that the first prerequisite
has been achieved and we discuss in the following sections some
of the elements necessary to build up public confidence in a policy
for nuclear waste management. These are necessary but not sufficient
conditions for securing agreement at a local level: the generality
must be translated into local acceptability somewhere.
TRUST
5.12 The public will accept the decisions of Government
and institutions if it feels confident in placing its trust in
the individuals, the organisations and all the parts of the process
that lead to those decisions. The organisational structure must
be one in which the public can see that its interests are well
protected, and all the elements of that structure must be seen
to be operating fairly. Establishing such trust is difficult and
takes time: if it is lost, regaining it is likely to be even harder
and to take much longer.
5.13 Surveys of public opinion about environmental
issues show that the public in Britain has less trust in government
scientists than in those working for environmental organisations.
A MORI poll in 1997 on environmental attitudes showed that the
proportion of the public expressing "a great deal" or
a "fair amount" of confidence in scientists working
for Government was 44%, whilst the corresponding figure was 47%
for scientists working in industry and 83% for scientists working
for environmental groups.[43]
5.14 In 1998, the Royal Commission on Environmental
Pollution's 21st report[44]
commented that "there is nevertheless much evidence that
trust has been eroded. When major and widely-publicised issues
arrive (such as
the disposal of waste from the nuclear
industry), public opinion about the nature and extent of the risks
they pose may turn out to be at sharp variance with the assessments
that have been made by those with official responsibility for
environment protection". In general, the public has a propensity
to believe statements from environmental organisations that there
are significant risks and to disbelieve Government statements
that risks are negligible. Professor Wynne (University of Lancaster)
told us that expert bodies had not taken the institutional trust
dimension seriously enough (P 411).
PERCEPTION
OF RISKS
5.15 Dr Pidgeon from the University of Wales explained
that disposal of nuclear wastes has almost all the negative characteristics
as far as its perceived risks are concerned. The risks are not
voluntarily accepted at the level of the individual; the benefits
and the costs are not seen clearly alongside each other; the nature
of some of the risks (e.g. cancer) have a particular dread factor;
and the degree of risk is subject to uncertainty, to which the
public has a particular aversion (Q 872).
5.16 Although it is a relatively new field of study,
there has been considerable academic debate recently over public
tolerance or acceptance of different types of risk. Some of this
general discussion was rehearsed in the evidence we received,
although most comments focused on the specific issues raised by
the long time scales involved. The UKAEA told us that there was
substantial agreement on the standard of safety acceptable, and
that safety now and in the future can be defined quantitatively
in terms of risk (p 315). However, the BGS (p 32) said that it
is unreasonable to expect that an assessment of risk made now
will remain unchanged.
5.17 The National Radiological Protection Board (NRPB)
advocates a risk "constraint" of one in a hundred thousand
per year for any individual who could be exposed to radiation
from a closed waste disposal facility. The risk referred to is
that of the individual incurring fatal cancer or passing on to
his or her children a serious hereditary defect. NRPB considers
that 1 in 100,000 is the maximum risk which should be tolerated
from a waste repository and further recommends the use of a risk
target of one in a million per year in repository design. "The
(1 in a 1,000,000) design target represents a level of individual
risk which is widely regarded as acceptable" (NRPB p218).
RWMAC (p 258), Nirex (p 325), BNFL (p 38), UKAEA (p 315),
the DETR (Q 56), and others in the nuclear industry all defended
the one in a million (10-6 ) risk level.
5.18 Most of those who supported the 10-6
criterion argued that it would continue to be acceptable. Some
witnesses, however, argued that a change of attitude may well
occur if current trends continue. "As the hazards of life
have diminished in industrialised society, reflected by increasing
life spans, the tolerance of risk, particularly risk associated
with technology, has diminished" (The Royal Society, P367).
Dr Loomes made a similar point (Q 878). Greenpeace said that we
know nothing about the view that future generations might take;
"all we do know is that the levels of radioactivity which
are deemed to be acceptable during the lifetime of the nuclear
industry have progressively declined" (Q 434).
5.19 We received much evidence on the public's view
of risk and the need to put figures in perspective. For example
Gosforth (Cumbria) Parish Council noted that a rational assessment
of risk by the public would be difficult when the Government accepted
smoking (1 in 200 risk of death from smoking related disease),
but legislated against selling beef on the bone (p 149) (where
the risks of contracting CJD are likely to be much less than 1
in 500,000 but are less well characterised).
5.20 QuantiSci (pp 245-246), the Health and Safety
Executive (p 162) and Golder Associates (p 141) said that
numerical estimates should form only part of the risk evaluation
and should be treated with caution because very few people have
sufficient understanding of what the numbers represent. Similarly,
the DETR said that risk estimates should form only part of the
safety case, although they were useful in shaping engineering
concepts (Q 55). Dr Couples warned that lumping performance parameters
together could obscure the significance of a single element which
might be critical "and would not be recognised by someone
who did not have a complete grasp of the entire model
and
who would?"(pp 98-99). Professor Wynne argued that abstract
figures of risks like these are not meaningful to the public.
Cumbria County Council and others said that risk assessments of
storage or disposal will need to be more effectively explained
and made accessible to a lay audience (e.g. pp104, 113).
5.21 Some of the characteristics that affect public
perception are easier to change than others, but the idea that
"there is a public perception out there" that can be
easily changed "by providing information or a publicity campaign,
just does not work" (Pidgeon Q 864). Indeed according to
Dr Loomes from the University of Newcastle "were the Government
to find the right way of putting across
the truth about these
things" there would still be a difficulty because "in
many of these sorts of areas there is no obvious and uncontested
truth" (Loomes Q864). Nonetheless perceptions can change:
"we observe that people's perceptions change very rapidly
in relation to events such as media stories" (Dr Pidgeon
Q865).
5.22 Dr Loomes told us how the public attitude to
nuclear risk tended towards the catastrophic: "I think many
members of the public suspect that there is a very substantial
possibility of human error, negligence or something of the kind
which may be left out
. The other possibility is that members
of the public may just have very different values about the nature
of the losses that are involved" (Q 851). Dr Loomes
said that public misconceptions should be identified and genuine
public values should be taken into account when framing policy,
but admitted that this was extremely difficult to do (Q 851).
OPENNESS
AND TRANSPARENCY
5.23 A key requirement in any programme intended
to increase public trust is openness. Many witnesses expressed
the need for openness on regulatory matters; for example the Scottish
Environment Protection Agency (SEPA) was cited by the National
Steering Committee of Nuclear Free Local Authorities as a good
example of openness (Q 403-404). SEPA thought that its present
structure, where most meetings are held as open fora, allowed
open, transparent decision making and enabled the public to "participate
meaningfully in this process"(p 276). The Environment Agency
told us that most of its regional and local area committees were
open to the public and, although its main board was not, a summary
of its business was published on the Agency's Web pages (Q 615).
The Health and Safety Executive told us that the public was involved
in all of its major inquiries into nuclear sites, and inspectors
report regularly to representatives of the public at local liaison
committees (Q 694-696).
5.24 Various witnesses said that the nuclear industry
is not open enough, despite improvements in recent years. Copeland
Borough Council described how they had been unable to obtain some
information on the Nirex proposal until it reached the RCF Public
Inquiry. Others described to us the need to ensure scientific
papers are published and subject to peer review (eg Greenpeace
Q 497). Nirex acknowledged that it had been severely criticised
in the past and that their aim in future was to be seen as not
secretive (Nirex Q1396). There were criticisms of the Nuclear
Installations Act, which contains no provisions for HSE to consult
the public on variations of nuclear site licences (eg pp221-222),
and of the Health and Safety at Work Act, which only allows HSE
to release information when an industry organisation gives its
permission. An example of the restrictions under the latter Act
was when UKAEA felt that an HSE inspector's report would be commercially
damaging and HSE could not make the report public until many months
after it had been written[45].
There was considerable criticism of the secrecy of MoD on nuclear
waste matters (eg CND, pp53-55)
5.25 We were told in Sweden that their tradition
of freedom of information, dating back to 1766, had established
a basis of trust whereby the public understood that it could always
obtain the relevant information if needed. In practice this meant
that rarely did members of the public seek information themselves;
they placed their trust in their elected representatives and regulators
to do what was necessary on their behalf. Freedom of information
is a broader subject than we wish to address here but it is clear
that where people are concerned about risks, secrecy can be counterproductive.
5.26 There should be a general presumption of disclosure,
openness and transparency. This is a necessary condition for achieving
public trust. The RCEP[46]
concluded that "bodies setting environmental standards must
operate in an open and transparent way. There must be full publicity
for their existence, their terms of reference, the decisions they
take and the reasons for them. There must be adequate opportunities
for those outside an institution, especially those with a particular
interest in the given decision, to contribute fully to the decision
making procedure".
5.27 Openness is not without cost. In matters such
as the selection of a prospective site for storage or disposal
of nuclear waste we were told that the fundamental problem underlying
a commitment to an open, honest and transparent process is planning
blight (Grant Q1276). This difficulty cannot be avoided: it is
part of the price of openness (see paragraphs 5.36 and 5.43).
THE MEDIA
AND THE SILENT MAJORITY
5.28 We briefly examined the influence that the media
has in providing information and influencing public opinion. Where
people have no personal experience, for example of radioactivity,
undoubtedly the media can play a role in forming public opinion
(Hawkes Q1465). Normally the newspapers and television are the
first places where people learn about these issues, and the way
in which the stories are couched can set the development of public
attitudes.
5.29 Nuclear waste was the subject of some considerable
media attention during the course of our enquiry. There was reporting
on clean up plans for the Dounreay waste shaft and an incident
leading to the closure of the reprocessing facility there; on
Britain's acceptance of a small amount of nuclear waste from Georgia
in the former Soviet Union; and on pigeons that have spread radioactive
material from the Sellafield site. None of these stories showed
the nuclear industry in a favourable light. The Royal Society
commented that the media tend to give a story a sensational angle
(Q 910, Q 912), but witnesses who spoke to us about risks said
that the media were only part of the process through which public
perceptions become formed (Pidgeon Q 865). One witness considered
that, on many issues where there really is no public opinion,
the reporter's tendency is to take the views of a small number
of people who are talking loudly as representing a large number
of people with more moderate opinions (Hawkes Q1464). Mr Hawkes
explained that a pressure group that specialises in a particular
subject has a well-formed opinion that is generally quite well
argued with supporting data (Q 1645).
SOME
WAYS OF BUILDING PUBLIC TRUST
5.30 We examined one area where the public perception
of risk and the action that should be taken seemed at odds with
the scientific assessment: the experience of Shell in the disposal
of its Brent Spar oil rig in the North Sea. The conclusion of
both the company and Government experts was that the preferred
option for decommissioning the rig was deep-sea disposal. But
a campaign by Greenpeace and others in the United Kingdom, Denmark,
the Netherlands and Germany led to the abandonment of this policy
in favour of an alternative use.[47]
5.31 Following the abandonment of its original proposal
(still considered by many to represent the best environmental
option), Shell established a process whereby the company could
open up a discussion with interested parties. Mr Faulds, from
Shell, observed that the "traditional decide, announce, defend"
process had now changed to "show me" (Q 1298), where
explanation and discussion of the options preceded the decision.
He explained that it is not practical to consult directly with
the public in a wide sense on a complex technical issue (Q 1305),
but a means had to be found to assess views. Shell brought together
balanced audiences which were not dominated by industry, green
or other groups: they included political interests, unions, the
church, academic interests etc, with no one group dominant (Q
1319). Shell was not seeking to establish a consensus (Q 1309)
but was asking the group what criteria it would use in making
a judgement on the relative priority of the issues put before
it. The company's role was to listen; it still had to make its
own decision. "We do not think that either industry or Government
can abdicate its responsibilities for making decisions" (Mr
Faulds, Q1306). The process described by Mr Faulds, which was
put in place after Shell had been forced to abandon its original
plans for Brent Spar, is an example of attempts to build an understanding
of the issues with key sections of the public.
5.32 The technique used by Shell is only one of those
now being tried. The Cabinet Office has formed a "Peoples'
Panel"[48],
there has been one consensus conference and another is planned,
and other countries have used citizens' juries and deliberative
polls. As the RCEP point out in their 21st report[49],
when judgements are made about environmental issues "decisions
must be informed by an understanding of people's values".
None of the new techniques is a means of achieving compromises
between extremes or of taking decisions. They enable constituencies
of opinion formers to be built which have a deeper understanding
of the issues, and provide decision-makers with valuable information.
National issues, such as the management of nuclear waste, must
remain matters for Government decision.
THE PLANNING
SYSTEM
5.33 We discussed in paragraphs 5.10-5.11 the distinction
between national and local issues. If handled with sensitivity,
enough confidence in Government's chosen policy for nuclear waste
management may, over time, be established at the national level.
Such national acquiescence in the overall policy is a necessary
condition to proceed but agreement must also be reached locally
on specific site proposals.
5.34 Many witnesses hoped that the technique for
building public trust could establish a consensus which would
overcome local planning difficulties. The RWMAC agreed with the
findings in the POST report that the Town and Country Planning
procedures created great difficulty for repository development
(p 251). The BGS (p 31), the UKAEA (QQ 244-251), the Environment
Agency (Q 548) and other witnesses told us that the site selection
process must seek a consensus view by involving the public, regulatory
and advisory bodies, academia and relevant learned societies.
5.35 But in essence the planning system is designed
as a process of dispute resolution. At its heart it is almost
inevitably adversarial when dealing with local issues on which
there are genuine differences of opinion amongst industry, Government,
local authorities, pressure groups and local residents. For the
local planning process to function well, a clearly stated and
broadly accepted Government policy must be in place at the outset.
It is certainly not appropriate, as Professor Grant said, for
a planning inquiry inspector to try to make national policy for
Government or Parliament in the light of the evidence given at
a local public inquiry (Grant, Q1233). That does not mean that
the inspector should stifle all debate. As Professor Grant pointed
out, participants at local inquiries feel cheated if they are
unable to question some of the fundamental assumptions on which
the proposal is premised (Q 1234).
5.36 We discuss in chapter 6 the improvements to
the planning system described by the DETR (Q 58)[50]
which include key points designed to improve the planning procedures
for major infrastructure projects. These policies, when implemented,
have the potential to achieve significant improvements. Nevertheless,
the planning inquiry will remain the point of local assessment,
and cannot be confined to details of policy implementation. The
final decision on a site will rest with the Secretary of State
based on the Inspector's report.
ASSOCIATING
RISKS AND BENEFITS
5.37 We discussed earlier the steps needed to build
trust and establish agreement to - or acquiescence in - a national
policy. To achieve local agreement more is required. Many witnesses,
and in particular those representing people close to the proposed
Nirex site near Sellafield, argued that compensation should have
been given so as to offset the fall in land and house prices described
as "nuclear blight". The Gosforth Parish Action group
described the nuclear blight in their area: new industry was reluctant
to set up nearby and one food firm had to close because customers
elsewhere in the UK refused to buy products coming from near Sellafield
(p 145). From the evidence of Copeland Council (p 93) we conclude
that, while the local community there stood to gain indirect benefits
from accepting a waste facility, for example in increased employment
opportunities and in the provision of services to the contractors,
much of the local electorate would have seen little direct benefit.
There is little motive for them to support any proposal to site
a repository in their locality.
5.38 Dr Loomes said that members of the public were
more likely to be comfortable with risks if they were familiar
with them and if they could also see direct benefit from taking
them (Q 851). QuantiSci called for community financial trusts,
infrastructure improvements, local and regional development preferences
and local tax deductions (p 245). Sir John Knill described the
benefits that could be made available to a community that agreed
to host a site (Q 1031). In France the Committee was told the
French Government offered the equivalent of £0.5 million
per year during the investigation period to communities that volunteered
to host a nuclear waste repository and that £6 million was
available per annum until the year 2006 for the communities actually
chosen. Other witnesses (including Nirex, p324, Sir Richard Morris,
p210, and RWMAC, p254) expressed support for measures in countries
such as Sweden, Hungary, France and Canada where communities are
asked to volunteer as possible sites for a waste repository. Some
were given some form of financial inducement.
5.39 With a transparent and open system for decisions
on the location of facilities it is inevitable that blight will
occur. Changes underway to the planning system will speed up the
process and will minimise blight[51],
but it will nonetheless occur. Government should do more to create
a linkage between the costs that a local community might have
to bear and benefits that it can receive from any nuclear waste
management activity. These benefits might be in the form of specific
measures to improve the local infrastructure, to compensate for
increased road traffic or loss of other business, or it might
take the form of more direct assistance in the form of community
services.
CONCLUSIONS
ON PUBLIC ACCEPTABILITY
5.40 Public acceptability of a national plan for
the management of nuclear waste is essential, but achieving it
will be difficult. The potential risks to human health and the
environment are not easily expressed in ordinary terms and the
benefits of managing waste are not clearly related to these risks
either at national or local level. Within many groups in society
there is an aversion to the uncertainty inherent in long-term
risks and a lack of trust in some of the organisations involved
in regulating such risks. Some groups have a single minded adherence
to their own viewpoint such that they will not accept a contrary
conclusion, however democratically arrived at (Greenpeace Q470).
Because of these differences in attitude the establishment of
broad public trust in all aspects of the process is vital.
5.41 Social science research has provided some insights
into how people perceive risks. It has shown that there is no
one "public perception" or public opinion, and that
perceptions and opinions do change with time. But there is no
simple means of changing them by, for example, providing information
in different ways or through different media.
5.42 Much emphasis is placed in the evidence given
to us upon openness and transparency in decision making. These
are seen as essential to the task of seeking to gain public acquiescence,
acceptance and, possibly, even support for a national programme
on nuclear waste management: where there are concerns about risks
secrecy is counterproductive. We concluded that it is necessary
to be open and transparent but further mechanisms are needed to
include the public, or rather the various groups within it, in
decision making. Some new methods are currently being tried which
do not give undue preference to minorities at the expense of the
"silent majority".
5.43 The steps outlined above, based upon the recognition
that the attitude of the public is vital, have been lacking in
previous attempts to develop policies for the long-term management
of nuclear waste in the United Kingdom. There has been an over
reliance on the nuclear industry to establish or change public
views, to formulate its preferred policy and to gain public acceptance
of it. Past approaches, which could be characterised as "decide,
announce, defend", have not worked. Local planning inquiries
have become the focus of major public debate on the nation's policy
for nuclear waste disposal, a role for which they are singularly
ill suited. A national policy must be established with which the
public is broadly content. This should be demonstrated and underpinned
by parliamentary endorsement, as we will discuss in the next chapter.
5.44 With a national policy in place, there still
remains the even more difficult task of ensuring that those most
affected must have confidence in the integrity of the planning
inquiry. They must also be reassured that they will not be the
losers, in economic terms, from the selection of a local site.
Supporting measures might include regional infrastructure improvements,
support for local authority services, or other measures specifically
to address the difficulties of individuals selling property.
42 Report of the Nuclear Fuel Waste Management and
Disposal Concept, February 1998, Canadian Environmental Assessment
Agency. Back
43
Market and Opinion Research International (MORI) 1997, Business
and the Environment 1997. Attitudes and Behaviour of the General
Public. August 1997. Back
44
Royal Commission on Environmental Pollution 21st Report
"Setting Environmental Standards" October 1998. Back
45
HSE Inspector's Report on the fuel cycle area at Dounreay, released
15 June 1998. Back
46
Royal Commission on Environmental Pollution 21st Report
"Setting Environmental Standards" October 1998. Back
47
Decommissioning of oil and gas installations, February 1996. Back
48
The People's Panel; The Service First Unit, Cabinet Office. Back
49
Royal Commission on Environmental Pollution 21st Report
"Setting Environmental Standards" October 1998. Back
50
Modernising Planning 15 January 1998. Back
51
DETR, January 1998, Modernising Planning. Back
|