UNCORRECTED TRANSCRIPT OF ORAL EVIDENCE To be
published as HC 26-i
House of COMMONS
MINUTES OF EVIDENCE
TAKEN BEFORE
WELSH AFFAIRS COMMITTEE
Enlarged by the enterprise
and learning committee, NATIONAL assembly for wales
Cross-border public services for wales:
follow-up
Monday 23 November 2009
MIKE BAGSHAW RON DAVIES, MARK HOPWOOD, JEFF JAMES, ANTHONY
O'SULLIVAN, JOHN POCKETT, GARETH ROBERTS, TREVOR ROBERTS, MICHAEL VAUGHAN RON
DAVIES, MICHAEL WHITTAKER, TREVOR ROBERTS, GARETH ROBERTS, RICHARD WORKMAN, JEFF
JAMES, ANTHONY O'SULLIVAN
Evidence heard in Public Questions 1 - 65
USE OF THE TRANSCRIPT
|
1.
|
This is an uncorrected transcript of
evidence taken in public and reported to the House. The transcript has been
placed on the internet on the authority of the Committee, and copies have
been made available by the Vote Office for the use of Members and others.
|
|
2.
|
Any public use of, or reference to, the
contents should make clear that neither witnesses nor Members have had the
opportunity to correct the record. The transcript is not yet an approved
formal record of these proceedings.
|
|
3.
|
Members who receive this for the purpose of correcting questions
addressed by them to witnesses are asked to send corrections to the Committee
Assistant.
|
|
4.
|
Prospective
witnesses may receive this in preparation for any
written or oral evidence they may in due course give to the Committee.
|
Oral Evidence
Taken before the Welsh Affairs Committee (enlarged
by the Enterprise and Learning Committee,
National Assembly for Wales)
on Monday 23 November 2009
Members present
Dr Hywel
Francis MP, in the Chair
Nia
Griffith MP
Siān James
MP
Alun
Michael MP
Hywel
Williams MP
The following members of the Enterprise and
Learning Committee, National Assembly for Wales also attended, in accordance
with Standing Order Number 137A(3):
Christine
Chapman AM
Jeff
Cuthbert AM
Paul
Davies AM
Nerys
Evans AM
Gareth
Jones AM
David
Melding AM
Jenny
Randerson AM
Witnesses: Mike Bagshaw, Commercial Director, Michael Vaughan, Head of Franchise and Stakeholder Management,
Arriva Trains Wales, Mark Hopwood,
Managing Director, John Pockett,
Manager for Wales, First Great Western gave evidence.
Q1 Chairman: (Through an interpreter)
The Committee looks forward to collaborating on this inquiry. We want to ensure
that we carry out our work well and appropriately. In the past, we have
collaborated very successfully with a number of committees of the Assembly, and
I am sure that this inquiry will also be a success.
Q2 Gareth Jones: (Through an interpreter) We extend a warm welcome to you and we are pleased to have the
opportunity to collaborate like this. There is so much talk about House of
Commons committees in Assembly committees, but it is special that we can come
together with the most important people in the field and have an opportunity to
scrutinise jointly. We should do a lot more of it, but time will tell. To turn
to our scrutiny session, we extend a warm welcome to the representatives of the
train companies. On behalf of Arriva Trains Wales, we have Mike Bagshaw, the
commercial director, and Michael Vaughan, the head of franchise and stakeholder
management. Here to represent First Great Western are Mark Hopwood, the
managing director, and John Pockett, the manager for Wales. On behalf of all Members,
from Parliament and the Assembly, I thank you for your written evidence.
Contrary to normal practice, there is no time for us to hear a presentation,
but I emphasise that we are grateful for the written evidence that we have
received. I am sure that, through questioning, we will get more details and
information. I am looking forward to this discussion.
Q3 Chairman: (Through an interpreter) I have a relatively simple question to begin with. How do you work with
the Assembly Government, the Department for Transport and Network Rail to
ensure that the network is successful and appropriate? In addition, do you work
with the Regional Minister for the South West in England?
Mr Pockett: (Through an interpreter) We have a cross-border franchise and First Great Western provides
services from south Wales to
London, in addition to the services from Cardiff to Taunton and to Portsmouth. We meet
regularly with officials from the transport department of the Government here
in Cardiff, and my colleagues meet with
Department for Transport officials in London.
Over the past two years, the working arrangements between us and the Government
in Cardiff have
improved immensely. We meet regularly to discuss whatever needs to be
discussed. No-one is afraid of picking up the phone or of raising issues with
me, Russell or Mark's office. I hope that that answer is of some assistance to
you.
Mr Bagshaw: I echo those points. At Arriva Trains Wales, we work closely with
the Welsh Assembly Government and the Department for Transport. We meet with
the Assembly Government on an almost weekly basis to discuss the various
transport plans in Wales,
and we discuss capacity provision, looking to the longer term. We also meet
regularly with the Department for Transport. There is a cross-border forum at
which representatives from the Welsh Assembly Government, the Department for
Transport and other stakeholders meet to discuss cross-border services, at
which issues of capacity and timetabling are relevant to both Governments. So,
we have a very close working relationship. We are planning carefully how we
cater for the ongoing growth that we are seeing in passenger numbers across Wales
and on the English borders. We are currently in discussions with the Department
for Transport and the Welsh Assembly Government about how we can provide more
capacity, where funding is available and develop the policies in the national
transport plan.
Q4 Alun
Michael: (Through
an interpreter) Thank you. It is a pleasure to be here in the constituency on
a Monday like this. Can we cut to the heart of the issue on the First Great
Western service between Cardiff or Swansea and London?
When will the experience of travellers between Cardiff
or Swansea and London improve? When are we going to be able
to depend on trains arriving at advertised times? How will you increase
capacity? I say this against the background of what I consider to be a real
problem with the measures of performance and a degree of complacency. It comes
as a shock when you travel to places like Yorkshire
or the north-east and discover that longer journeys can be simple, pleasant and
on time. The north-west service used to be as bad as the south Wales service,
but it has greatly improved, although ours has not. When can we expect to see
the dependable improvements that other parts of the country have experienced?
Mr Hopwood: There has been a substantial improvement in
punctuality on the London to south Wales
services. There is more work to be done, but we are now running more services
punctually on that key route than before. A key part of the First Great Western
franchise was to bring in additional capacity, and the five-coach trains that
had been introduced into traffic at the end of the last decade have been taken
out of the franchise and replaced by longer high-speed trains. So, if you look
at our current high-speed train fleet, you will see that it now has 54 train
sets, whereas for most of the period since those trains were brought into
traffic many years ago, the Great Western route operated with just over 30. So,
there has been a substantial increase in capacity. As far as working with
Network Rail is concerned, there are many things that we are doing to carry on
driving improvements in performance. Our high-speed train fleet is delivering
the best levels of reliability in terms of the rolling stock that we have ever
seen. That is significantly helped by the new engines in the high-speed train
fleet, and they have all been refitted over the past three or four years. There
is more work to be done, particularly at the London end of the route, where it is most
congested. The development of Reading station, with the four additional
mainline platforms, will make a substantial difference to capacity and
performance. We are working with Network Rail on other smaller-scale schemes,
such as ensuring that high-speed trains from south Wales get more priority than they
currently get against the Heathrow Express trains coming out of the airport.
There are many other smaller schemes of that nature that will help to improve
performance. Our customers are telling us that they have seen a difference in
performance; the number of complaints is substantially lower and our national
passenger survey results have improved. So, there is evidence of improvement,
and our punctuality has often been as good, and sometimes better, than the
punctuality of the services on the London-to-Yorkshire
inter-city operation.
Q5 Alun
Michael: I must be singularly fortunate when I travel to the
north-east and singularly unfortunate when I use your services. I have some
sympathy for current management, because I acknowledge that things have moved
from the singularly awful to the poor and unpredictable, and that, in itself,
is an improvement. Do you accept that there is still a long way to go before we
have the dependable service that there is in other parts of the country? Do you
also accept that weekend services, particularly on Sundays, are often
particularly poor, and that you end up with an additional hour of travelling
and then being late on top of that? We have seen south Wales services being merged with
west country services, which means that the trains are vastly overcrowded, but
it is presumably a saving to the company. Things are still not at an acceptable
level, are they?
Mr Hopwood: The punctuality of First Great Western services is now
better on the whole than the national average. On whether there is more to be
done, I have already acknowledged a few times that we accept that there is more
work to be done and that we are getting on with doing that. As far as weekend
engineering work is concerned, there is a lot of work being done between train
operators and Network Rail, which is also facilitated by the Department for
Transport. Lord Adonis, as Secretary of State for Transport, has shown a
personal interest in the work as regards reducing the amount of disruptive
engineering work at weekends, and to try to ensure that we can operate the
normal advertised services on a greater number of weekends. As many Committee members will be aware, the Severn tunnel closures
that we have had-and there was one this weekend, for example-led to our London to south Wales
service diverting via Gloucester.
A key constraint in those diversions is the single-track railway between
Swindon and Kemble, which means that we have to combine our London
to Cheltenham service with the London to south Wales
service; that is not to save money, but for capacity reasons. First, that
deprives Cheltenham of a through service to London,
but it also slows down the south Wales service. A lot of positive
progress has been made over the last nine months or so, after the
disappointment of the double-tracking scheme not being included in the periodic
settlement for the railway industry over the next five years, and local
authorities are diverting funds from road schemes to progress double-tracking
further. Many of us in the industry are confident that, despite the initial
disappointment, we may well see that scheme completed. We have two targets on
this: first, to avoid the need for the diversions, which Network Rail is making
progress on; and secondly, when they do occur, to make them less disruptive.
Q6 Jeff Cuthbert: I endorse the
comments welcoming this excellent opportunity to meet with our colleagues from
the Welsh Affairs Select Committee for joint scrutiny. My main question is to
you both, but I suggest that First Great Western answers it first in order to
give Arriva Trains Wales an opportunity to consider its response. I will also
ask my supplementary question now in order to save time, Chair. The main
question is: to what extent is the planning for new railway infrastructure
adequately integrated with the provision of rolling stock? My supplementary is
directed very much at Arriva Trains Wales, because my particular concern is the
Valleys lines, which are well-used for commuter travel into Cardiff, and specifically the Rhymney valley
line. Many millions of pounds of public money has been invested over the last
few years to lengthen platforms, and improve signalling and infrastructure on
these lines, all with the intention of allowing you to run trains of up to six
cars at peak times. That has not happened. Some of those platforms have been
lengthened for more than two years, so the infrastructure is in place, but my
constituents complain to me regularly that they are packed in like sardines at
peak times. When we will see six-car trains on the Valleys lines, particularly
in the Rhymney valley, and especially at peak times? To conclude, Chair, when I
travel back from London
I often entertain myself by buying a copy of Private Eye. In an article from the edition of 13-27 November,
under the heading 'Signal Failures, with Dr B. Ching'-I will not use his
colourful language, because this is on the record and I do not want to cause
offence-it says that Arriva Trains Wales has 60 of Britain's 'poorest'
carriages, shall we say? Private Eye
uses a different word, and goes on to say that Arriva will not provide any new
trains by the time its 15-year franchise ends in 2018. The article then
criticises the Association of Train Operating Companies. Is this true? I assume
that it is referring to pacer trains, but it links to my supplementary question
on rolling stock, and I would be grateful for an answer on that.
Mr Hopwood:
As requested, I will answer first. As far as First Great Western is concerned,
and particularly looking at our services into Wales, there has been good
co-operation on rolling stock provision and network capacity. For us, things
are perhaps more straightforward than for other operators-we already operate
quite long trains into Wales on the high-speed network, with eight vehicles and
the two power cars giving a total of 10. Generally, where capacity is capable
of accommodating those trains, it is capable of accommodating all the smaller
trains as well. That works in our favour. Away from this part of the world,
there are examples where we have had to work on infrastructure upgrades to
provide for the longer trains that we need, and we have been able to do that as
well. As far as the future is concerned, the infrastructure is generally in
place for us to provide more capacity on local services into Wales. The next
key event for us in looking at where infrastructure provision and trains come
together in the context of capacity will be the replacement of our high-speed
train fleet. It is proposed that the replacement trains, which will be called
the super-express trains and which have been ordered by the Department for
Transport from Hitachi,
will have 26-metre vehicles. Currently, we use 23-metre vehicles. So, they will
be longer at their maximum length than our current trains. There is already a
stream of work, which we are co-operating with but that is led by Network Rail
and the Department for Transport, to ensure that the infrastructure in south Wales and England is capable of accommodating
those trains. That work has started, although the trains will not enter
passenger service until 2016.
Mr Bagshaw: I
will respond on the points about capacity, but it might be worth first putting
this in the context of the franchise that Arriva Trains Wales operates. The Wales and
borders franchise was let in 2003 by the Strategic Rail Authority. It was let
on a minimal basis. There was no real investment, it made little provision for
passenger growth, and there was no provision for new trains-very little
investment was envisaged in the franchise. That was the policy at the time.
Thankfully, the reality has been very different. There has been investment by
the Welsh Assembly Government and Arriva in the franchise. There has been
additional rolling stock, longer trains on some routes and investment in
stations. We are continuing to work with the Welsh Assembly Government to
deliver its national transport plan and the growth in passenger numbers we are
seeing in Wales.
You raised the issue of our trains being relatively old. The average age of our
fleet is 16 years. Yes, it is an old fleet, which was known when the franchise
was let. Although they are old trains, we have spent some money on making them
a lot more reliable. We are now one of the most reliable train operators in the
UK.
We are the fourth most punctual train service in the UK. So, despite the fact that the
trains are old, a lot of effort is being made to ensure that the trains are
reliable for the passengers. You raised a specific point about the Rhymney
valley line and the six-car platforms. The decision on whether to run longer
trains in the Valleys will be made by the Welsh Assembly Government. Funding
would be needed to operate longer trains on those services to provide that
extra capacity. We are working very closely with the Welsh Assembly Government
on delivering all its aspirations in the national transport plan. We are
discussing with it the funding and the timing of funding for those
developments, but the actual decision as to when longer trains will operate
will be one for the Welsh Assembly Government.
Q7 Jeff Cuthbert: So, Arriva Trains is
just waiting on a decision from the Welsh Assembly Government. Is that what you
are telling us? I have heard that the extra rolling stock exists, but is being
used elsewhere on the network. Is that the case?
Mr Bagshaw: All
the rolling stock we have available to us now is being used. Going forward, we
obviously need to talk to the Welsh Assembly Government about how the rolling
stock is deployed and what the aspirations are for running more services and
more frequent services.
Q8 Jenny Randerson: My question is
specifically to representatives from Arriva Trains, but representatives from
First Great Western might wish to comment from their perspective. In your
evidence, you say: 'we believe a root and branch review is required to ensure
that future development and investment in railway infrastructure is based on
sound strategies which address actual need and provide the best value for
money.' You have just indicated the basis on which the current franchise was
let. That comes as no surprise to me. However, do you think that it was let on
a worse basis than any other franchise across the country? The franchises were
let at much the same time, and the Strategic Rail Authority was clearly working
to a different agenda at the time. Can you tell us what you mean by that rather
coded comment on the need for a root-and-branch review? Is that a comment on
the Assembly Government's transport planning, or is it a reference to the origins of the current franchise?
Mr Bagshaw:
We are keen that the agenda is moved on. There is an appetite for investment in
rail infrastructure and for developing rail, and that is a positive thing. We,
like everyone else, are keen to ensure that investment is made in the right
places, that it delivers the best value for money, and that it encourages
passenger growth. That requires close dialogue between the train companies,
Network Rail and the Welsh Assembly Government.
Q9 Jenny Randerson: You refer to 'a
root and branch review'. Are you suggesting that the Assembly Government's
transport strategy, which was produced very recently, is not the result of good
thought and planning?
Mr Bagshaw:
No, that is not what we are implying at all.
Q10 Jenny Randerson:
Your comment refers to the rubbish franchise that was let in 2003.
Mr Bagshaw:
The franchise in 2003 was let at the minimum cost, which was the agenda at the
time. Today, thankfully, the reality is very different. We are now setting out
to see how we, in conjunction with Network Rail, can best deliver the
aspirations that the Welsh Assembly Government has set out in its national
transport plan. That is what we mean by 'a root and branch review', which we
will do in order to develop those aspirations.
Q11 Jenny Randerson:
Your evidence refers to the question of whether the Assembly Government will
get additional powers over infrastructure, and you say that that needs to be
done in tandem with better planning. Would it help or hinder you if the
Assembly Government had additional powers over infrastructure? For the benefit
of colleagues who were not here last week, we heard evidence at the last
meeting from Transport Scotland,
which said that cross-border issues were not an issue in Scotland at all
because of the way in which it runs the system.
Mr Bagshaw:
We have a number of lines that go across borders, indeed far more than in Scotland, so it
is a key issue. On the development of the infrastructure, we know that the
Welsh Assembly Government has a close working relationship with Network Rail,
as it does with us, and we work very closely together. We do not have a strong
view as to how that may change in the future, but the important issue is that
all parties work together to deliver the right thing for the travelling public.
Q12 Jenny Randerson: Does First Great Western want to comment on any of those issues?
Mr Hopwood:
You referred to Transport Scotland.
From the perspective of the railways and the train operating companies, Wales's geography is quite different from that
of Scotland.
We at First Great Western believe, based on the numbers that we have produced,
that we carry just under 25 per cent of the passengers travelling into Cardiff in the morning and out of Cardiff during the evening peak period. To
compare that with Scotland,
Virgin Trains, for example, on the west coast or east coast lines, is an
important provider of long-distance services, but it provides a much smaller
number of seats for travel-to-work journeys into and out of Glasgow and
Edinburgh. Our experience is slightly different, as there was quite a large
investment in our franchise in respect of rolling stock and stations. As
Members will be aware, we do not have a role in managing stations in Wales; all the
stations that we call at are maintained and operated by Arriva Trains Wales. We
have been able to have constructive dialogue about the future of our services
in a way with which we feel comfortable. The main structural issue with our
franchise is the provision of capacity and the specification of local services
in Bristol, south Wales
and the west of England.
However, I am pleased to say that we have had some positive discussions with
the Department for Transport, in which the Welsh Assembly Government has been involved
and of which it is well aware.
Q13 Nia Griffith: I would like to explore
your views about using Network Rail's current forecast for future growth as a guide for
future investment and whether the currently planned infrastructure improvements
will meet demand. To put this in context, we have an increased number of
passengers, which is great news, but we have also had steep hikes in ticket
prices. Therefore, people feel that you are getting a lot of extra income, but
they want to see fully-staffed stations; they want to see places like Kidwelly
getting a more regular service with more trains stopping at the station and not
just passing through; and they also want to see an improved Sunday service. If
you want to go to see a match from Llanelli, or if you are trying to get to Cardiff or London
for a big event, it is no good because the first train does not run until 11.30
a.m. Do those forecasts match up to what you believe needs to be done? What
additional things might you be able to do?
Mr Bagshaw: I will respond to that. We are working closely with Network Rail. You
mentioned some specific examples in west Wales,
where currently the infrastructure is limited, with single sections of line
between Swansea
and Llanelli. There are plans for that section of line to be doubled.
Q14 Nia Griffith: That work is starting today, is it not?
Mr Bagshaw: I believe that some of the preparation work is starting today. The
project will take a little longer. I cannot recall the exact timescales. The
positive aspect is that that will release a key bottleneck on our network that
constrains a lot of the timetable. This will give us a lot more flexibility to
run the train services at different times or to better cater for passenger
needs. That is a positive step forward. We will work with the Welsh Assembly
Government to look at service provision in the future. You mentioned Sunday
services. We are planning to revise the service on Sunday in west Wales this
December to ensure better connections with the rest of the rail network and a better
spread of services to provide better journey opportunities. That will come into
play from the December timetable change. In addition to that, we are working
closely with Network Rail to try to reduce the amount of disruption that we see
because of engineering works so that we can run more services on Sunday
mornings so that we reduce the number of occasions where passengers are
required to travel on buses. Engineering work is essential and, inevitably,
there will need to be some disruption at certain times. We are seeking to hold
Network Rail to account, particularly on its commitment to a seven-day railway,
so that we can make Sunday a day on which people can make journeys easily by
rail.
Mr Hopwood: I would support a lot of what Mike has said. We work closely with
Network Rail, and we support its rail utilisation studies, in relation to both
the work that goes into them and some of the outputs. As I said earlier, the
track capacity provision will allow us to grow the business quite substantially
with regard to what is in place in south Wales. In relation to providing a
service from south Wales to London, the key challenge is very much at the east end of
the route, as the London and Thames
valley area is very much at capacity. In the very long term, if we are to
provide the service that many people in south Wales quite rightly aspire to, we
will need to split the current train service into two so that there is an
express service to south Wales and that places like Reading, Didcot and Swindon
have a separate service. That is a long-term aspiration and there is certainly
no capacity to provide for that at the moment. That is one of the challenges in
the long term for the rail industry to look at. A seven-day railway is
important. It is true to say that Network Rail's engineering activity has not
caught up with people's travelling habits on a Sunday. Network Rail now
understands that and we will see engineering work being moved away from
weekends into weekday nights and there will be a rapid acceleration of some of
the technological improvements that will allow one railway line to be renewed
while the other is kept open. Currently, they are both closed. You will see the
benefit of that in the next few years when the train service will be allowed to
continue to run, whereas it might not be able to do that at the moment. As is
the case with Mike at Arriva Trains Wales, we are pushing Network Rail quite
hard to achieve that as quickly as possible.
Q15 Nia Griffith: Is
there a commitment to keep staff at the stations that are currently staffed
because that is important in terms of people's safety and comfort when
travelling?
Mr Bagshaw: The answer is, yes.
Q16 David Melding: I
would like to probe on the issue of franchises, if that is the correct plural.
Obviously, when your companies bid for them, you responded to the terms of the
franchises that were advertised and there was competition, and that is what you
do. So, in a sense, you must feel slightly frustrated about some of our
questions on what we may see as inadequacies in the franchise system. However,
we are trying to make recommendations that will improve public services and
value for the public pound, so, in general, should the length of the franchise
be related to the level of investment? I specifically want to ask Arriva Trains
Wales if it was surprised about a 15-year franchise with essentially a 'do
nothing' commitment on investment. You rightly pointed out that you had
invested, but that that had taken you beyond the strict terms of the franchise.
Should not investment fit a bit more into the terms of the franchise? Surely,
in any future rounds, should we not be more aware of likely passenger growth
and how that would affect the franchise system? Perhaps we could start with
Arriva and the fact that it has a 15-year 'do nothing' franchise.
Mr Bagshaw: As I said before,
although it was let as a 'do nothing' franchise, there has been investment from
both sides. Arriva has invested because over that 15 years, we can get a
payback, whereas, with a shorter franchise, we may not have been able to make
that investment. Some of the things that we invested in included a new depot at
Machynlleth, improved customer information screens, better security, ticket
gates and many other initiatives on which we would probably not have received
the same level of payback with a shorter franchise. Long franchises provide a
greater opportunity to invest, which is positive.
Q17 David Melding: The
First Great Western franchise is significantly shorter, so has that had an
effect on investment decisions? For example, the current engines are being
refurbished, but the new engines will not be here until after this franchise
period runs out.
Mr Hopwood: That is right. Ours is a
seven-year franchise, with the opportunity to earn a three-year extension. We
committed at the start of the franchise to a large amount of investment, which
was built into the franchise. Some of that investment was specifically asked
for, but all bidders were required to produce proposals on some of it. Unique
to FirstGroup plc was the fact that we said that we would make additional
investment. That has been committed to in the franchise. There is always a
slight dilemma about this subject. For example, having a long-term franchise
gives you that opportunity to invest more and to recover that investment over a
longer time, but clearly the longer the franchise, the more uncertainty there
is about things like passenger income and about what the requirements of
customers and stakeholders will be at the end of the franchise. All of us can
look around the UK
at the moment and reflect on how things have changed in quite a short period of
time. There are a number of things about our franchise-which most people
thought were sensible when the original specification was written in 2005-that we
would now have done differently. That is a challenge. In fairness to the
Department for Transport, we have been able to accommodate changes that have
happened with some degree of flexibility, so we are talking to the Department
for Transport about provision of additional capacity, which was never part of
our original franchise. We are also managing the considerable changes to the
infrastructure that will happen on our patch, even though they were not part of
the original franchise specification. That is our position.
Q18 David Melding: I
would like to ask both witnesses if they think that the franchise that they
secured in 2003 and 2006 respectively-if I have got those dates right-was
technically fit for purpose at the time.
Mr Bagshaw: At the time, there was
no vision of investment in the franchise and it was let on a low-cost basis.
Obviously, Arriva bid for the franchise on that basis. Thankfully-
Q19 David Melding: I
must say that these are technical questions and you should not infer from what
I am saying that I think that you are to blame. We are looking at the technical
nature of the franchise that was let to you and why the passenger-growth
assumptions in particular, which are now common currency, were not anticipated
in any way.
Mr Bagshaw: Obviously, we are now
looking at this with the benefit of hindsight. We have seen some spectacular
growth, which clearly was not envisaged at the time and we are now responding
to that by looking forward and planning how we are going to allocate rolling
stock. With a good working relationship with the Welsh Assembly Government, we
are able to do that and we are able to plan, even though the original franchise
was fairly pessimistic in its outlook for rail travel. Clearly, the increased
popularity of rail travel that we are now seeing was not envisaged, but,
thankfully, we now have policies in place that seek to address that trend going
forward.
Mr Hopwood: As far as First Great
Western is concerned, I would concur with a lot of that. One of the challenges
has been that of growth, particularly outside London, where commuting fares generally are
much lower. We are very often faced with the challenge that the times when we
need additional rolling stock are quite limited, so there is not a commercial
case for having a vehicle that, very often, will only work one loaded journey
in the morning and one in the evening. So, it becomes a question on which the
Government has to work with us to address. Certainly on our local services in
this area, particularly into Bristol, where
there is quite a lot of commuting from south Wales,
as well as from other parts of England,
there are phenomenally high levels of growth, which is providing an interesting
challenge for us
Q20 Hywel Williams:
(Through an interpreter) I have a
question to First Great Western specifically about the electrification of the
south Wales
main line. What do you foresee will be the effects of that? Will there be
problems? Will there be any disruption to the service while the work is
undertaken, and, if so, how will you deal with that?
Mr Hopwood: I think that we have to
be realistic and say that there will be some disruption, but Network Rail is
currently developing its plans for how it will electrify the route. Certainly,
if one looks back over the last 20 to 25 years at electrification in the UK, at routes
such as the east coast main line and other electrification schemes, a very
large amount of that work took place without disrupting train services because
masts and so on were installed overnight and existing engineering blockades
were used. However, there will be some disruption. The challenge for us is to
make sure that Network Rail uses the technology that it has available to it as
effectively as possible and keeps disruption to a minimum. We have other work
planned with Network Rail on the route and one of the challenges is to make
sure that we make best use of the planned engineering possessions. If you take
Reading, for example, in an earlier answer I talked about some of the upgrade
work at Reading and one of the things that the project team at Reading is doing
is building some of the electrification work into its projects so that you will
not have two separate disruptive events at Reading. By taking that approach, we
will minimise disruption. We have some diversionary routes available. That will
lead to some extension of journey times, but, by and large, it will keep
customers on trains and customers tell us that if they are going to have some
disruption, they would much rather stay on the train, even if it means that they
are diverted, than get off and get on a bus. So, we will certainly try to
follow that approach.
Q21 Hywel Williams: (Through an interpreter) I also asked you
what the likely impact of the electrification of the line would be. Is there
any good news?
Mr Hopwood: Sorry, I thought that
you meant the impact of the works. The overall impact of electrification
clearly will be very positive. When you combine the electrification of the
infrastructure with the delivery of the new super-express trains, you are going
to see some reductions in journey times. It looks likely that those reductions
will be in the region of 20 minutes on the fastest trains from Swansea
to London. As I
said earlier, the trains will themselves have more capacity. They will be able
to accelerate more rapidly away from stations and attain 125 mph more
effectively. An area for discussion that we have already kicked off with the
Welsh Assembly Government is how we can exploit the high-speed capability of
the trains on the existing infrastructure to greater effect. Many of you may
know that once our high-speed trains get into Wales, we do not use their 125 mph
capability, so we will want to look at whether we can change that. Each
individual thing that we do is unlikely to add more than one or two minutes,
but if you do several of those things between Paddington and Swansea, you will deliver worthwhile
improvements.
Q22 Hywel Williams: (Through an interpreter) My supplementary is perhaps a layman's
question. Since electrification brings all sorts of economic gains, will it be
implemented at the same time along the length of the line, or will you start at
the London end or the Maidenhead end, or will
you start at the Swansea
end? I am sure that there is some value in starting at the Swansea end or the Maidenhead end if the work
does not take place along the whole line at the same time.
Mr Hopwood: That is probably a
question that we will have to ask Network Rail to answer. I think that not even
Network Rail has decided on the detailed plan for electrification, but it is
worth pointing out that our current fleet of trains does not have any
capability to operate under the electrified network. In reality, therefore, the
infrastructure is only a part of the equation, and we will not be able to use
the electrified infrastructure until the new train fleet has arrived. Some of
the new trains will be electric trains that are designed only to operate on the
electric network, while others will be bi-mode, and they will be capable of
operating away from the electrified network. Our through service to Carmarthen and our summer services to Pembroke Dock would
use bi-mode trains, which would be capable of using the electrified
infrastructure even if the whole route is not electrified.
Q23 Nia Griffiths: I
think that you have answered my question. As the line is electrified, the use
of those bi-mode trains will mean that people will not have to change trains,
but will be able to stay on the same train from London
right through to west Wales.
Is that correct?
Mr Hopwood: Yes, that is correct.
Q24 Nia Griffiths:
Will you be using those bi-mode trains from the beginning of the
electrification process, from when the very first bit is done from London to Reading,
for example?
Mr Hopwood: Your questions are very
interesting, and, if I am honest, the industry has not yet reached that
detailed stage of planning. However, the intention is to have a mixture of
solely electric trains and bi-mode trains. If we get to a position where the
bi-mode trains have arrived and are available for use, and some, but not all,
of the route, is electrified, I would expect us to take advantage of the
electrified network wherever possible, because, in performance terms, it is
better and more environmentally friendly, so we would be keen to use it.
Q25 Nerys Evans: (Through an interpreter) With regard to your priorities for the
electrification of other lines in Wales, we heard evidence from the Deputy First
Minister that he wants to see every line into and out of Wales, as well as
every line within Wales, electrified. What is your response to that? Arriva
Trains Wales, you say in your evidence that there are benefits to be had from
electrifying Valleys lines, but Network Rail doubts that there is an economic
case for doing that. Why is there a difference of opinion on that?
Mr Pockett: (Through an interpreter) I believe that which lines are electrified
is a matter for the Government. Our interest, and a cause of great joy for us,
is that the decision was taken in London to
electrify the entire line between London and Swansea, and we welcome
that. For other lines, however, I believe that it is a matter for Government,
whether here or in London.
Mr Bagshaw: I would echo the point
that it is a matter for Government, but Arriva Trains Wales will certainly work
closely to look at opportunities for further electrification in Wales, such as
diversionary routes on the south Wales mainline, the Valleys line and the
Wrexham to Bidston line. This is a decision for Government, but we would
support any investment in electrification on our network.
Q26 Nerys Evans: (Through
an interpreter) So, you are not working on any long-term plan where
electrification is a major factor in the network in Wales-you are only working
according to the basis of your current contract.
Mr Bagshaw: That is correct-there is
no assumption that there will be further electrification of our network at the
moment.
Mr Hopwood: As far as First Great
Western is concerned, once the electrification of the main line has been
completed, it would allow us to operate the vast majority of our London services with
electric trains. We have started explorative discussions with the Department
for Transport about the changes we might want to make to our local train
network to exploit electrification to enable as many of those routes as
possible to operate electric trains. It is worth reflecting on the fact that if
you take the Cardiff to Portsmouth
service, for example, once the current electrification plans are delivered,
although those trains will be diesel trains, a large chunk of the mileage that
they will operate on will be under overhead electrification or the third rail
system in the Portsmouth and Southampton
area. So, one is inevitably led to the conclusion that if we were to work with
Network Rail to fill in the small amounts of track that are left we could
convert further services to electric operation, with obvious benefits. Those
are discussions that we have already started.
Q27 Paul Davies: My
question is for Arriva Trains Wales, and it is to do with the north-south
route. In your written evidence to us, you say that from an operational,
customer service point of view, you feel strongly that improvements in line
speeds on the Marches
line should be pursued as soon as possible. What speeds and journey times from
north to south will be possible after the planned line-speed improvements?
Mr Bagshaw: This subject is
currently being reviewed by us, the Welsh Assembly Government and Network Rail.
It is a key aspiration for the Welsh Assembly Government to reduce travel times
between north and south Wales,
and we are currently exploring the best ways to do that. The issues are about
the type of rolling stock, the line speeds, the signalling capability and
bottlenecks such as those between Wrexham and Chester, where there is only a single section
of track. Currently, we have a mixture of trains on that route; some of them
have a top speed of 90 mph, and some have a top speed of 100 mph. The maximum
line speed is 90 mph, and given that many of our trains have 100 mph
capability, there is an opportunity to improve the journey time if line speeds
are improved. However, that needs to be looked at along with signalling and the
timetabling of other services. It needs to be looked at as part of a package,
and we are working on that very closely with the Assembly Government and
Network Rail, because it is a key aspiration of the Welsh Assembly Government
to bring north and south Wales
closer together in terms of journey time.
Q28 Paul Davies: When
do you envisage these improvements taking place.
Mr Bagshaw: The infrastructure work
may take some time, because it would require investment; I know that Network
Rail is carrying out quite a detailed review of what needs to be done to
achieve the aspirations. We are looking at aspirations to improve the rolling
stock and the journey times on that corridor as well. So, we are looking at a
range of measures-some of them will be in the shorter term and some will be in
the longer term.
Q29 Paul Davies: So,
it could be five years before the improvements take place?
Mr Bagshaw: It is likely to be a
staged approach-there might be things that we can do as early as next December
if we are able to prune the timetable to bring some type of journey time
improvements. However, investment in the infrastructure is likely to take
longer than that. So, I think that we will see gradual, year on year,
improvements in the service between north and south Wales, but it will be a phased
approach rather than everything happening in one go.
Q30 Christine
Chapman: I have a specific question about light
rail. What role do you see for light rail schemes in Wales, and how should these be
integrated with investment in heavy rail?
Mr Bagshaw: It
is not something that Arriva Trains Wales has looked at closely, but light rail
could have a role in urban transport. If there is a case where light rail could
provide a better solution to existing heavy rail services, we would be
supportive in developing those options and in looking at the best overall
solution. However, we have not been involved in any detailed study on light
rail at this stage.
Q31 Christine Chapman: May I pursue that? In its paper, Arriva Trains Wales talks about
workable options being presented when available, so I am not quite clear who
would be proactive in this-would it be the Government or you? How would it come
together?
Mr Bagshaw: It
is more likely to be the Government. Any investment in light rail would be
significant, so it is something that would be led by Government, but as a train
operator we would happily participate in those discussions and look at the best
solution overall to the transport needs in that area.
Q32 Christine Chapman: What are the advantages and disadvantages of converting the Valleys
lines, for example, and local services to light rail?
Mr Bagshaw: There
are some advantages in light rail, particularly in urban areas where better
frequency can be achieved at a more affordable cost. Heavy rail plays a more
important role in longer journeys, particularly in reducing journey times. So,
it needs to be looked at as part of a package, recognising the needs of people
making short journeys who want a frequent and convenient service, as opposed to
those making slightly longer journeys, where journey time is perhaps more
important.
Q33 Siān James: (Through an interpreter) Good afternoon
and welcome. Which passengers would benefit the most if the Swindon
to Kemble line was re-doubled?
Mr Hopwood: I
will answer that question. As to who would benefit the most, it is most likely
to be the local customers and the longer-distance, regular customers of that
route. However, as we discussed earlier, the route is also important as a
strategic diversionary route when the Severn tunnel is not available, or when
any of the infrastructure between Bristol and Newport is not available.
So, there are much wider benefits than just to the immediate, regular customers
of that service. If we had a double track on that route, one of the immediate
benefits is that it would allow us to operate a faster service to south Wales because we could operate a local service
at the same time that we were diverting the south Wales express services.
Q34 Siān James: There
has been a lot of evidence about the dependency on the Severn
tunnel, which is in a good state of repair, as I am reassured continually by
Network Rail. However, we are very dependent on that tunnel remaining open and
remaining in useful life. What are your views on the need for a second Severn rail crossing?
Mr Hopwood: As
for whether it is justified entirely by the condition of the Severn tunnel, I
do not believe that there is a need for a second Severn
crossing in the short to medium-term. If you opened the question to wider
issues around capacity and journey time, and you were to provide a second Severn rail crossing as part of a substantial increase in
capacity through investment, then it would play a part. One of the things that
we mentioned briefly in our evidence was a new high-speed line, and although
there is no immediate prospect that that will happen, it is an aspiration of
many people, which we share. You would almost certainly want to provide a
second rail crossing at the time that you were providing that infrastructure.
Q35 Siān James: So,
you are providing a much more long-term future for rail in that way. In the
Welsh Affairs Committee, we looked at the situation up to 2025 and 2030, and we
were thinking in the much longer term. In your opinion, how important is the
electrification of the Severn tunnel
diversionary route?
Mr Hopwood:
As you probably know, there is currently no proposal to divert that route. That
means that we will have to allocate our rolling stock carefully so that, in the
future, when engineering works are carried out, bi-mode trains are allocated to
south Wales
services. There is a potential issue in that if we have to deal with emergency
engineering work or an unforeseen short-term closure, we would either have to
terminate the train or provide a diesel locomotive to drag the electric train
along the route via Gloucester.
From an operational perspective, it would be much more desirable to have the
diversionary route electrified as well. That is not just an issue for that
route-it is also an issue for the route via Newbury, which is also,
occasionally, used as a diversionary route for south Wales. In due course, we would want
to explore that. It is difficult to justify electrifying a railway purely for
diversionary capability. One has to look at the day-to-day use of a railway
line. If you were to combine the diversionary use with daily use, in due
course, you may well find that it is something that could be done during future
stages of the electrification process. It is right that you raise that issue,
as it is one that will have to be explored in more detail between now and the
introduction of the new trains.
Q36 Nerys Evans: (Through an interpreter) The Committee has heard evidence about a
concern with regard to problems as the number of people using trains increases
and due to an increase in the amount of freight being transported by rail. How
are you planning to prevent those problems from arising?
Mr Bagshaw:
That is a key area. Track capacity on many routes is limited, and there are
parts of our network that are very congested, which limits the opportunities to
run more passenger and freight services. It is something that Network Rail has
picked up in its rail utilisation strategies, identifying areas where capacity
is critical, and there are plans to invest in the infrastructure at some
locations. We talked earlier about the links between north and south Wales, via Newport
and Shrewsbury.
That is one route on which the signalling is limited, and with further
increases in freight and passenger services, we may find that capacity is
insufficient, and we may need to look at improving the signalling and making
other improvements to the infrastructure. I mentioned the single section of
track between Chester
and Wrexham that is also a bottleneck. Network Rail is aware of that. Again, we
are looking at where growth across the network will happen, and with Network
Rail, we are looking at where investment is needed to provide better
infrastructure.
Mr Hopwood:
I echo what Mike has said. Trying to run 125 mph passenger trains on the same
railway as 60 mph freight trains is not always a great combination, but a lot
of work has been done to add capacity-the route from Didcot to Swindon, for example, now has additional loops for
freight trains compared to some years ago. The work with Network Rail will
continue, and in the very long term, the issue that you raised in your question
will be one of the factors that will be driving us towards dedicated,
high-speed lines. That is some time away, so we have to use the infrastructure
that we have as effectively as possible.
Q37 Gareth Jones:
(Through an interpreter) You may be glad
to know that that was the last question in this part of the scrutiny session.
On behalf of both committees, which have had the opportunity to ask searching,
and sometimes difficult, questions, thank you very much for your response. The
information that you have shared with us will be fed in to the reports and
further reviews of the House of Commons and the National Assembly. We had
invited one other company, but it was not able to attend this morning. Thank
you for your attendance, and we wish you well in your very important work that
you undertake from day to day. Thank you very much.
Witnesses: Councillor Ron Davies, Chair, Michael Whittaker, Executive Officer, TAITH, Councillor Trevor Roberts, Chair, Christopher Wilson Co-ordinator, Gareth Roberts, Ceredigion County
Council, Christopher Wilson, Co-ordinator, TraCC, Richard
Workman Lead Chief Officer, SWWITCH, Councillor
Jeff James, Vale of
Glamorgan Council, Anthony
O'Sullivan, Caerphilly County Borough Council, Chair SEWTA Directorate, SEWTA
Q38 Gareth Jones:
(Through an interpreter) We will move on
to the second part of item 2, the evidence session on the future railway
infrastructure in Wales.
We extend a warm welcome to representatives from the regional transport
consortia who have joined us. You know the background to this. This is a
special joint meeting between the Welsh Affairs Committee of the House of
Commons and the National Assembly for Wales. Before I refer to the
representatives who have joined us, I would like to thank you for your detailed
written evidence, which we have had the opportunity to read. There will be no
introduction; we will move directly to the questions. I apologise that we are
running a little late. On behalf of both committees, I extend a warm welcome to
representatives from Taith, Councillor Ron Davies, the chair of Taith, and
Michael Whittaker, its executive officer. From the mid Wales transport
consortium, TraCC, we are joined by Councillor Trevor Roberts, the chair, and
Christopher Wilson, the co-ordinator for TraCC. A warm welcome to you. From the
South-West Wales Integrated Transport Consortium, SWWITCH, we welcome Richard
Workman, its lead chief officer. From the South-East Wales Transport Alliance,
we are joined by its chair, Councillor Jeff James from the Vale of Glamorgan
Council, and Anthony O'Sullivan from Caerphilly County Borough Council, the
chair of the SEWTA directorate. I welcome you on behalf of both committees.
Thank you for the evidence that you have submitted to us. I now turn to Jenny
Randerson, who has the first question.
Q39 Jenny Randerson:
Good morning. In your written evidence, you have all expressed support in
principle for the idea of the Assembly gaining additional powers over the
railways. Could you explain what would be the main advantages from a regional
transport planning point of view of the Assembly having direct responsibilities
for specifying the outputs required of Network Rail and having the additional
funding required to do that?
Gareth Jones: You do not need to touch the microphones.
Mr Whittaker: I just want to come
back on the point about the transport plans. We have a public transport group
that meets regularly with Arriva Trains Wales and Virgin West Coast. There
would be advantages in the strategic planning of the regional transport plans,
the national transport plan and the commitments in 'One Wales' so as to co-ordinate investment. It is one thing for the
Committee to look into infrastructure in Wales, but people still have to get
to and from the train station, and that is within the purview of the consortia
and their constituent local authorities in delivering the regional transport
plan. Unlike our colleagues over the border in England,
where there are four transport consortia, Wales has the opportunity to
achieve that close integration. The Committee will be able to make
recommendations on that.
Mr Wilson: From TraCC's point of
view-although everyone will probably give the same answer-it is the logistics
of it all. The Assembly Government has additional powers and has a big role to
play on rail, as well as in other areas, and just having that ability to talk
to the integrated transport unit, in this case, would be a big help to us. It
would make handling the various relationships with the various partners a lot
easier. TraCC has a regional rail partnership that is attended by Assembly
Government officials, Network Rail and Arriva, for example. We try to deal with
the issues in that forum. It brings people together, and so that would be the
real benefit.
Q40 Jenny Randerson:
That is interesting. We heard evidence from Transport Scotland to the
effect that cross-border issues were not of concern and the rail networks were
perfectly integrated. However, the Assembly Government chose not to seek
additional powers under the Railways Act 2005 because it felt that cross-border
issues were a factor. There are more trains running between Wales and England
than there are between Scotland
and England,
but are there any legitimate cross-border issues, and is it possible to plan
effectively across borders?
Mr Davies: May I come in here? In
north Wales, we already have
the Mersey-Dee alliance, which covers north-east Wales, and we discuss our work with
them. In fact, it is one of our aims to create a new link to the airports at
Liverpool and Manchester, which also serve north
Wales,
and we work across the border to achieve that.
Mr Whittaker: Our chair has just
written to the chair of the Office of Rail Regulation in connection with the
proposals that you heard about in evidence from Arriva Trains Wales-that is,
their application to run additional services through to Manchester airport from Manchester Piccadilly
from the December 2009 timetable. Unfortunately, I understand that there is
some resistance to that. Given the equipment that the Assembly Government
provides through the franchise, and the considerable revenue payment, it would
make sense for the service to run to the airport and back-and not just a couple
of times in the morning and again late at night, but right around the clock.
That would make sense at a Wales
and a UK level as an
effective use of assets, as well as providing an improved service from the
airport to north Wales.
Mr G. Roberts: Over the years since
the rail Bill was introduced, we have found that border locations such as Shrewsbury are
fundamental to the rail network because so many trains meet there. Unless there
is Welsh input to investment decisions, there is some evidence to suggest that
Network Rail has a tendency to view the Welsh network as peripheral to its core
business. That is very much contrary to what we find on the ground from
consultation through the consortia. A Welsh network should develop trains that
can connect mid Wales
especially to the rest of the UK.
Unless we or the Assembly Government has a greater say in investment, and guide
Network Rail on what is needed at locations such as Shrewsbury,
Newport and so
forth, where we can connect into the main network, there are cross-border
issues that are fundamental to how we are looking at rail at present.
Q41 Siān James:
(Through an interpreter) A warm welcome to friends old and new. As key
stakeholders-and I know this from first-hand experience-you have a key role in
driving forward rail development in your regions. What role do you think the
regional transport consortia and regional transport plans play in the future
planning and delivery of railway infrastructure schemes in Wales?
Mr Workman: The consortia play a
vital role in identifying which improvements are necessary from the ground
level up, in the context of a whole-network approach. It is important not only
that there is a business case but also that the case is developed with the
public generally. The SWWITCH area, for instance, covers a large geographical
area in which 650,000 people live. We have to assist in how we deliver rail
services across the region to residents and businesses through identifying
local constraints on how the infrastructure could be improved. That clearly
needs to be in the context of what is happening across Wales and across the UK, taking a whole-network
approach. Our businesses tell us that. The local consortia are ideally placed
to identify those local issues within the context of what is happening in Wales
overall.
Mr James: To support that, I think
that the consortia are unique in having a three-way partnership, including the
Welsh Assembly Government and councils. It is a great strength to have councils
working together and with the Welsh Assembly Government, and there have been
great examples of that. I cannot take credit for it as I have been a member of
SEWTA for only a year, but I have seen the programmes that have been delivered
in my area and in others, and I have also seen the ambition that the consortia
have for improvements and investment. I would say that the national and
regional transport plans reflect that ambition. It is an exciting opportunity
to have that three-way working happen.
Q42 Siān James: In TAITH's
evidence, you talk about the formalisation of that. Do you see that perhaps the
Welsh Assembly Government should formalise its relationship with you as regional
transport consortia?
Mr James: It is difficult to say
whether it should be formalised because it works very well at the moment to
some extent because of the degree of flexibility in it. It depends on what
formalising would mean in reality, rather than just the concept.
Q43 Siān James: I
will give you a quick example. When organisations such as FirstGroup plc have a
formal consultation, are we certain that information comes to you and that you
are formally consulted every time? I am not necessarily convinced that you are.
Mr James: I totally agree with you.
Siān James: Good.
Mr O'Sullivan: We would certainly
welcome a degree of formalisation-perhaps councillor James is being a bit too
modest-and I think that that is also the case with our members. The key with
the development of SEWTA is the increasing role that members have taken.
Members wish to drive the agenda and they would certainly welcome an interface
with you on a biannual basis, or whatever is appropriate, so that you could
sensibly discuss the issues that affect you all. That is a forum that is
currently missing. On the role of the consortia in delivering the
infrastructure that you asked about earlier, it is a great feather in the
Assembly Government's cap and in SEWTA's cap that the Ebbw valley railway has
been delivered. It is the first new railway in the UK in 40 years. Recently, it
carried its millionth passenger. So, on the basis of 'If we build it, they will
come', that will happen. The consortium had a key role to play in that. The
Ebbw valley railway runs through several different local authority areas, and
there is integration with park-and-ride facilities, as a key part of the
strategy to get people onto rail. SEWTA has been able to deliver park-and-ride
sites around all the stations, it has an interface with local communities, it
has popular local support, and that has driven the whole thing. It has been
very pleasing to see it. It was not without its teething problems, but if you
are treading new ground after 40 years, you will experience that, but an awful
lot was learned in the process that can be sensibly built upon.
Mr T. Roberts: Thanks very much for
the opportunity to come here. On the formalisation, I understand that the Assembly
Government is carrying out a review at the moment. We have an officer who has
been having discussions with the consortia.
Mr Whittaker: I hope that that will
be taken into account, because the consortia have made reference to the working
relationship with the train operating companies, the Welsh Assembly Government
and Network Rail. The consultation on the national transport plan has just
closed, and it and the regional transport plan are now before the Government,
having been submitted in September. Together with the Committee's work, they
provide an opportunity, as councillor Jeffrey James said, for a tripartite
arrangement from planning through to delivery. Examples of the delivery of rail
projects have been quoted and, in the case of north Wales, there was the introduction
of real-time information screens for customers. It is a testament to the
strength of the constituent authorities, but we need the methods that Andrew
Davies referred to recently at the North Wales Economic Forum to do with smart
collaboration. Wales
is not a big country, but we can play to the strengths of our key individuals.
You have a lot of them around this end of the table this morning to do that. It
is a chance that should not be missed because it does not come around too
often.
Q44 Gareth Jones: Just
to be clear, Trevor, there is an ongoing consultation, is there?
Mr T. Roberts: Yes, there is a
review going on at the moment. The officer from the Assembly Government is
coming to us on 4 December. The Government is in discussion with our officer at
the moment.
Q45 Chairman:
(Through an interpreter) Good afternoon. My question is about forecasting. We
all know how difficult it is to forecast future growth and to make such forecasts
robust. What are your views on Network Rail's forecasts for growth, as a guide
to future investment?
Mr G. Roberts: What we have seen so
far from the forecasts of Network Rail, particularly for rural lines, is that
it takes a low-growth view. However, when opportunities are given to people to
travel, we find that the forecasts are exceeded by quite a lot. That has been demonstrated
by the Ebbw valley line, where the original forecasts were exceeded. The
Network Rail forecasting system tends to play down the extent to which rail and
other factors can change the country rapidly; it is not taken into
consideration. It is a very slow, ponderous system, and many investment
decisions are made on the basis of these forecasts. If they had been more
accurate, infrastructure and service provision would have been delivered far
earlier. The case for better provision in Wales would have been made.
Gareth Jones: Thank you for those general thoughts.
Mr James: I would say that it is a
classic case of the point made earlier about the methodology used to arrive at
these predictions not satisfying the ambitions of the consortia. There is an opportunity
to explore how Network Rail arrived at that position. Was it being cautious in
its business case, looking at the risk? The consortia are looking to be
ambitious for Wales
and for transport. So, there is an issue to do with better understanding and
communication between the two sides.
Q46 Chairman: Do you
have the opportunity to challenge these predictions and the methodology?
Mr James: I would not say that we
have an opportunity to challenge them. We have meetings to which Network Rail
is invited where we ask questions, but the methodology is never really
discussed.
Mr Whittaker: I would like to add to
that, when the route utilisation programme and the rail planning assessment
came forward, the consortia was not on the core reference group, although we
were part of the wider stakeholder group. That would support the points that my
colleagues, the chairs of the other consortia, have made. Again, that is
something that would reflect the data and the experience of local authorities'
economic development departments and data from the Assembly Government, that we
are all members of our respective spatial plan areas in Wales.
Mr Workman: There is also the point
that the role of the regional consortia is to promote sustainable travel within
and throughout Wales.
In consortia such as SWWITCH, at the moment, only 1% of total journeys are made
by rail, which is considerably below the national average. As I said, there are
large populations, and the consortia must play a role in promoting
opportunities. Obviously, that must be on the basis of a proper business case,
but there are opportunities out there that the consortia can help to drive
forward. There are examples in our area, such as the Fishguard line, where a
lot of work has been done to demonstrate that there is an economic case. So,
occasionally, those statistics need not necessarily to be challenged, but to be
bolstered by other, aspirational views, while recognising that each case has to
have a fully thought out business case.
Q47 Gareth Jones:
Those are well-made points.
Chairman: It almost sounds as though you are implying that we ought to have
municipal or public ownership of our transport system. [Laughter.] That is a
rhetorical question.
Mr Workman: As an officer, I would
not say that. [Laughter.]
Gareth Jones: It was a rhetorical question, apparently, so we can move on
quickly.
Q48 Nia Griffith: To
turn to the issue of priorities, you have listed in the documents that you have
given us what you see as the main priorities for development. Are there any
particular ones that you want to emphasise or any that you feel have not been
given sufficient attention? In other words, is your voice being heard regarding
the list that we have? The issue of frequency is very important in terms of
uptake and I note that, particularly in the SWWITCH document, if there are to
be any additional trains that only stop at main stations, they should be in
addition to the ones that stop at the smaller stations, because if you are to
increase the 1%, it is the frequency of trains that stop at the smaller
stations that will matter. So, in your comments on those priorities, you do not
need to go through the whole list again, but can you say in which areas you
need to push extra hard and whether you are getting the response that you want?
Mr G. Roberts: One of the issues
coming through loud and clear when we try to look at problems around stations,
is the bureaucracy that you have to deal with in Network Rail and the way that,
over a number of years, strips of land had been sold off. When we move forward
to bring in park-and-ride schemes and interchanges, it is difficult to get a
speedy response or a solution, even without financial finality. It is a
question of knocking heads, at times, and of who you should speak to to get a
decision. In rural areas, it is about bringing together rural stations and
communities to feed into the network. The network is a wonderful asset, but it
is difficult to feed into it at certain locations. One of the issues that we
have raised with the electrification that will hopefully come to Swansea is
that, from mid and west Wales, you can feed into that investment, because most
people-we have to be pragmatic-will have to travel either by car or bus to a
railhead somewhere, but unless you have facilities so that you can easily
interchange at that railhead, it will be difficult. The bureaucracy that is
still enshrined in Network Rail is getting better, but it needs to be broken
down, as a priority, to move things forward.
Mr O'Sullivan: Of all the agencies
that we deal with, Network Rail is probably the most difficult. Why that should
be is not obvious or apparent, because there is very much a fraternity-I think
that you can see that the relationship between the transport consortia is very
good-and people get on well. It seems that, regrettably, Network Rail is not
quite able to grasp that ethos. We stretch out the hand of welcome, and we will
continue to do so. The way in which the transport grant is currently
administered in Wales
is frustrating, in that you get an allocation for a year. If you are looking to
acquire a piece of land from Network Rail, or conclude a financial deal with
it, but you are unable to do it within the financial year, you then lose the
money and you must bid again. There is no continuity. There have been several
fairly high-profile examples of that. There have been great difficulties in
delivering high-profile things that put transport and the Assembly on a proper
footing, and that put the consortia in a proper light. Another area where we
feel that we could be listened to a little better is in improving the rolling
stock, and that must be the case. There will be capacity issues, and we are
going to need to press for that. I mentioned the Ebbw valley line, which was
hopelessly oversubscribed when Wales
played an international rugby match on a Friday evening 10 days ago. We need
more rolling stock and more capacity. We have demonstrated where the need lies,
and we will keep asking very politely. Those are the issues that will be
recurrent.
Mr T. Roberts: There have been
several incidents in the Network Rail saga. We have a pure partnership within
the TraCC consortium, which has been working well. Network Rail is hardly
turning up at all, and, with all due respect, we do not have any one from the
hierarchy present. A classic example is Dyfi Junction, where there is a
national coastal footpath and where everything is held up at the moment. There
are moneys available for the next few years to create a pathway, but Network
Rail will not give any information about any infrastructure work to be carried
out there, which would help-a new footbridge or a cycle bridge. We just cannot
get Network Rail representatives to sit around the table at the moment. Mr
Williams sat in a meeting with me a week last Friday, and it was a battle just
to get Network Rail to the table. The Assembly has just opened its office in
Aberystwyth; road vehicle parking is hopeless there and there is scope for a
park and ride facility in the Machynlleth area. You just cannot get Network Rail
to the table. On Mrs Randerson's first question on additional powers, that is
perhaps something on which the Assembly should be looking to bring Network Rail
on board. It is still operating out of Swindon, and, being very parochial, I
believe that it should be operating within Wales.
Q49 Nia Griffith:
Yes, on the Sunday services. It seems that, very often, trains are very
overcrowded because there are so few of them, and that people are humping
suitcases on and off coaches and so forth. Would better dialogue with Network
Rail help you to improve existing services? What prioritisation would you give
to increasing services, because it is certainly frustrating not being able to
leave Llanelli before ll.30 a.m. on a Sunday if you want to get anywhere?
Mr G. Roberts: On service provision,
in the mid Wales
context, we very much want the hourly service, and that is one of our top
priorities. Unfortunately, I experienced difficulties last Friday coming back
from Leeds, when, having missed the connection in Manchester,
I had to sit for an hour and 50 minutes at Shrewsbury station waiting for the two-hourly
service, and I did not get home until 9.30 p.m.. They do not appreciate in Manchester how difficult it is to get to the west coast of
Wales
if you miss your train connection. So, we definitely want a minimum of an
hourly service in mid Wales.
In this day and age, I do not think that that is too much to ask if you are
trying to promote a modern railway system.
Mr Whittaker: I will just build on
that from a north Wales
perspective and on our short-term service strategy, which was outlined in our
paper. There has been considerable growth in Sunday services, for tourism and
leisure, in terms of access, for example, to Chester, and to Liverpool and
Manchester airports, and inbound to Bangor and Llandudno in the summer. It is
critical that we have earlier services starting on a Sunday, and that we
realise our aspirations for the key Wrexham to Bidston line, which was
mentioned by Arriva Trains Wales
in its evidence to you earlier this morning, the extension to Manchester
airport, as I mentioned, and to accelerate services to Manchester, which are presently quite slow. We
would also be concerned that north Wales might be cut off from discussions on
the prospects for electrification, which I mentioned in my paper, and the
discussions that I hope are going on between the Deputy First Minister and Lord
Adonis in connection with the demands for High Speed 2 to ensure that north
Wales-and, for that matter, mid Wales-are not disadvantaged regarding
connections. We would not want to undo the good work over a number of years of TAITH's
predecessor, the north Wales
economic forum, in supporting the key Holyhead to London service.
Mr Workman: I just have one further
point, Chair, based on the weekend service and improving services in general.
We in SWWITCH would argue that a number of infrastructure constraints have led
to relatively poor services west of Swansea.
Hopefully, we are now heading towards the major infrastructure constraint being
removed by 2012, with the doubling of the section over the Loughor. That will
enable greatly improved services to the west, because it will remove that
capacity issue, and we therefore hope to see service improvements. However,
bearing in mind the previous discussion about other agencies, all parties
should ensure that there is a clear link between infrastructure investment and
service improvements-the two should come together, so that we are joining up
our thinking on this.
Q50 Paul Davies: I
want to explore additional capacity further with you, and ask a brief question
about train services west of Carmarthen. I
specifically want to ask about improvements to services to Fishguard, which
Richard has already touched upon. I recently had the privilege of accepting a
petition from two 15-year-olds, calling on the Welsh Assembly Government to
fund an additional five trains per day to Fishguard, which SWWITCH has already
identified as necessary. The petition has attracted over 1,300 signatures, and
has been passed on to the Assembly's Petitions Committee for consideration. It
is a credit to those young people that they have organised such a petition. My
question is therefore for Richard. Why do you support the case for additional
services to Fishguard, and what benefits would they bring?
Mr Workman: By way of introduction, the point about youngsters was important,
and the more that we can get youngsters used to using rail services, it is a
habit that they will continue with rather than looking at less sustainable
modes of travel. There is a tremendous benefit there. As part of the work that
we have done, we have developed a robust business case to demonstrate that
improved services to Fishguard would increase both commuting opportunities and
the wider use of rail. Along with the infrastructure improvements that I
mentioned-the doubling of the Loughor section-it would also improve
connectivity across the network, so that is an example of service improvements
coming together with infrastructure improvements. Fishguard would benefit in
its own right, but the major benefits would be driven out when it can connect
better to the rest of the network.
Q51 Paul Davies:
Could you confirm whether these additional services could be provided prior to
the doubling of the track west of Swansea?
Would the cost be fairly modest?
Mr Workman: Unfortunately, I cannot
share the cost at this public meeting, because the work was done for a
confidential report. However, if Members are interested, I can share that
information with you on a confidential basis via the secretariat. It is
certainly cost-beneficial to undertake the services by themselves, but as I
have said, the benefits are far greater alongside the other infrastructure
works.
Q52 Christine Chapman: I would like to ask about the franchise arrangements. I know that
we could all recount good and bad experiences under the franchised network, but
how fit for purpose are the current franchise arrangements for rail services in
Wales, particularly in light of the continuing growth in demand, which we have
just discussed?
Mr G. Roberts: As you suggested in the question, experience suggests that the
no-growth franchise is certainly not fit for purpose given the way that we see
the network developing in Wales.
That is not just for the provision of rolling stock and services for
passengers-although in the end, the passenger is paramount-but whenever you ask
a train operating company for any form of improvement, its response is guarded
and limited, and usually amounts to asking for funding from the Assembly Government
in one form or another. It has just been proven that growth is happening but
without a mechanism for addressing it. Even the ability to make improvements to
stations is limited unless an outside pot of funding is available. In essence,
the franchise is stifling the commercialised entrepreneurship of the companies.
As for whether Arriva is hiding behind that in some instances, that might be
another way of looking at it. As far as we are concerned, this franchise is not
best suited to Wales
getting an improved service.
Mr O'Sullivan: We concur with that view. Looking back to some of the earlier
questions, it was unfortunate that Wales did not go for additional
powers, because we really wanted to influence some cross-border issues. For
example, with the 15:15 train from Paddington, we were not able to punch our
weight or make a point with the franchise holder on that, which was First Great
Western in that case. We have also seen the spectacular collapse of another
franchise recently on the east coast main line, which has strengthened the hand
of the franchise holders here. They can now say that we must be cautious
because of what has happened elsewhere. Clearly, they are not philanthropists
and are doing quite well out of it. Regrettably, the odds seem to be stacked in
their favour. Although we enjoy good personal relationships and try to press
matters as far as we can, you can take goodwill only so far. We do not have the
mechanisms to enable us to say that we want to make changes and ask where there
is scope for more negotiation. It does not exist. They are sitting pretty at
the moment, regrettably.
Q53 Gareth Jones: On
that specific point, my understanding from last week's session is that we can
renegotiate, but there must be money on the table. So, there is scope, but we
will look into that specific point. It is vital, because it is a part of the
problem that we have with upgrading the franchise and the service. I agree with
the comments that you have made, but there is another aspect that we need to
get to grips with, to find out more about how this can be improved upon.
Mr James: I can see that everyone is
reflecting the frustration that people feel that the ambition that we all have
for improved services and better rolling stock does not seem to be shared by
the franchise holder. Then again, it rests with you to examine what constraints
are on Arriva in operating the franchise. From our point of view, as Anthony
rightly said, I am sure that we all engage with it. We invite its
representatives to our meetings; in fact, we invite them to make presentations.
That engagement happens, but what is frustrating is that you have to ask what
is holding them back from doing what they want to do. If they keep saying that
it is due to a lack of money, that would be disingenuous to some extent,
because we need to know how the franchise operates, how it can be made to
operate better, and how we can get more value for your money from it. If we can
help in any way with that, perhaps with a round-table partnership to improve
how the franchise operates, we would be willing to offer that help.
Q54 Gareth Jones: We
appreciate those comments. It is an aspect that we need to look at, because it
is an important issue. I was surprised to learn that there is this possibility
or option to improve the services and the franchise and so on, and we will need
to look into that carefully.
Q55 Alun Michael:
Those of you who are interested in history might like to reflect that it was
the general election of 1979 that led to British Rail's headquarters staying in
Swindon instead of moving to Brunel House in Cardiff. That would have made all our lives
much easier. The comments about the need to challenge methodology and look for
change and improvement are very interesting. I wanted to ask about one particular
aspect of improvement. In the 1980s, the old Mid and South Glamorgan councils
worked with British Rail and put a lot of money and effort into opening up new
stations that improved matters in the Valleys and the Vale of Glamorgan, which
was good for the whole of the network. Are you doing any serious work on
opening up additional stations and services? If I were to give one example, it
would be the St Mellons area of Cardiff,
because a station there would open up real opportunities for the greater Rumney
area. There is a total lack of stations there, simply because of how Cardiff grew. There is an
enormous amount of congestion on the eastern side of Cardiff that a service of that sort would
help to obviate. That aspiration has been around since 1973 when I first stood
as a councillor, so there has been plenty of time to think about it. Are you
examining examples like that-and I am sure that there are others in other parts
of Wales-to put those improvements to services and opportunities on the map at
least, even if it takes some time to get there?
Mr Davies: I refer you to the
regional transport plan prepared by TAITH, in which there is a list of six
stations that we are looking into. They are scattered across north Wales, on the coastline and also on the line
from Chester to Cardiff
at Rosset and Johnstown.
The accessibility of some of the stations is also worrying us, as you cannot
park a car there or get a bus to the station. It is that modal aspect that we
need to look at carefully to ensure that you can make the journey to the
station, either by car or bus, to catch your train to go a further distance.
Mr Whittaker: As part of that,
integration is critical to get to and from any station, either by bus, walking
or cycling, as has been referred to in the national transport plan. We have a
specific package for non-car station access to do that, but we still come up
against some of the issues with Network Rail. There is also the TrawsCambria
service, which I do not think has had a great deal of airing in this Committee.
It has been referred to in the national transport plan to buy rail-equivalent
services in key inland locations that are not currently on the rail network,
although perhaps they were, historically. It is critical that its services are
brought into that, because, at the end of the day, the end user does not really
mind how they get to their destination, whether via Arriva or Virgin, a trunk
road or a county road, or a tendered bus service. The integration issues are
critical to meet that, particularly on the public transport side to provide a
totally seamless journey as well as information. There is no point in just
putting in investment, as we need capital. Are we able to take advantage of the
present powers and guidance being brought forward to provide end-to-end
journeys, to increase the 1% that Richard referred to in the SWWITCH figure,
particularly given the Assembly Government's commitment to carbon reduction?
Mr T. Roberts: TraCC has
commissioned a feasibility study, which will report at the end of February. It
is looking at the reopening of Carno, Dyfi junction, the park-and-ride
facility, and Bow Street.
The money has been spent, and we are waiting for the final report on that,
which will be out at the end of February. That is the way to go and it will
happen. We must look at that and at the difficulties around the Aberystwyth
area, as I mentioned. So, there is a need for it. We have been lucky, because
our officers managed to find money from somewhere for that feasibility
study-sorry, it has just been pointed out to me that it was the Assembly
Government's money. [Laughter.] However, at least we are halfway down that road
now.
Mr James: SEWTA is looking for new
stations at Brackla, Llanwern, Coedkernew and St Mellons.
Mr Workman: We are looking to reopen
two stations: Goodwick, which is part of the Fishguard line, and Gowerton,
which is dependent on the Loughor doubling. In both those instances, because
they form part of a wider package, we have avoided increasing journey times,
because, occasionally, the problem with reopening stations is that you increase
the journey time. May I also say that we should not forget the national station
improvement programme? A lot of our stations are in need of a lot of
investment-that is, the existing ones.
Mr G. Roberts: One issue in this
context is that, quite often when you come to propose a station opening, it is
defined in the business case and, when you start dealing with Network Rail, it
quite often views the business case in the light of how it looks at stations in
south-east England.
Wales
has to get away from that initial rejection because a proposal does not fit
with the model that it has had for x number of years. In the Welsh context, we
have to look at new business cases and at what those stations are for.
Q56 Alun Michael:
So, it is back to the methodology again.
Mr G. Roberts: Yes.
Q57 Nerys Evans:
(Through an interpreter) I want to ask
about freight. What needs to be done to develop freight transport facilities in
Wales
to prevent any possible conflict in future between the transportation of people
and of freight?
Mr Davies: We have a perfect example
of this in north Wales.
We have the A55 road that runs right along the coast, alongside a railway that
is underused. If you have had the misfortune of travelling on the A55, you will
have seen all the heavy lorries that travel from Holyhead right across north Wales through to England. In fact, next week, some
of us are going to Brussels on behalf of TAITH to
lobby Europe for some help-mainly in the form
of money-to provide for the electrification of that railway line, as that would
provide a better infrastructure, enabling containers to go on the railway
rather than along the A55.
Mr Workman: Echoing the comments
just made, in south Wales,
we have the M4, which runs virtually parallel to a heavy rail link, serving the
ports at Milford Haven and Pembroke Dock particularly, which account for a huge
amount of the freight that comes into the country. We need to ensure that we future-proof
the current infrastructure and infrastructure improvements to make sure that we
do not reduce the capability of the network to take future freight
enhancements. The improvements that I have already talked about would help to
do that.
Mr James: To support what the others
have said, SEWTA is focusing on freight. I hold the view that we need to be
engaging the people who generate the freight. We need to start looking not only
at the people who run the heavy-goods-vehicle fleets, but also at those who put
the goods in them. There is a job of work for the consortia in engaging with
that process. It is very difficult to encourage the private sector to use rail
unless it suits its purposes, on business and costs. If we want that to happen,
to see that shift, it is incumbent on us to engage with the private sector in
the freight business.
Q58 Gareth Jones: I totally agree. From the evidence that we have received, it is
not quite as simple as there being a straightforward transfer onto rail-once
the rail is there, that is. It is far more complicated than that.
Mr Whittaker: Some elements of the TAITH
rail strategy would apply to the comments that Richard made. As you will be
aware, the amount of rail freight on the north Wales coast is currently declining,
unfortunately, with the tragic loss of Anglesey Aluminium traffic and the variable
amount that is moved out of Penmaenmawr quarry. The TAITH management office is
at Flint
station and I know when the freight trains go past because the whole building
shakes. As part of that, a report has found indicative signs of good commercial
demand for the reintroduction of a land-bridge service from northern Europe to Holyhead. If you have driven along the A55, you
will know that a great number of vehicles belonging to the same manufacturers
and haulage firms travel along that road carrying freight that could be moved
on the special wagons. That has been mentioned a number of times. The
longer-term aspiration of electrification would give W10 clearance, as Robin
Smith from the Rail Freight Group mentioned to you in evidence during an
earlier session. The same is true of the consolidation park at Deeside. To pick
up the point that Jeff James of SEWTA made, we also identified that a rail
freight awareness campaign would have an extremely high benefit-cost ratio. The
consortia, of which we are members, were collectively involved with the
production of the Wales
freight strategy and sit on the Wales
freight group. There is an opportunity for us to use that forum to take that
forward.
Q59 David Melding:
How important is it that Wales
gets on the high-speed rail network?
Mr G. Roberts: In Wales, unless High Speed Two has a connectable
interchange around Birmingham so that you can
connect to north and mid Wales,
it will not be of much use to us. By the same token, if any high-speed line
comes to south Wales,
it must have adequate connectivity so that existing road or rail services allow
you to interchange very quickly. We support the initiatives but it must have
adequate connectivity at sensible locations.
Mr Whittaker: I echo that. We are
very concerned that north and mid Wales do not become disconnected
from the network by forced changes. As Stuart Cole indicated, in France the TGV
can run on the classic lines, which is another case for electrification of the
main lines and the station. As I understand from the High Speed Two report
published earlier, Warrington station would not
be adjacent to the line from Chester to Manchester, for example, so at a stroke, it would be
disconnected, whereas I think that there may be an alternative site at Crewe, which would be much better in terms of the
connectivity. If you are going to spend that amount of money, it is important,
as was set out in the Wales
Transport Strategy, that we have good international connectivity. In fact, I
would go further and say that the connection from High Speed Two to Europe
might be a physical connection rather than having to change trains in London, as presently
happens if you go on the French TGV network. You do not have to change at Paris as there are trains that go around Paris. I do not think that we should lose
sight of that. I would go even further and say that the Irish are quite
critical in this. The southern corridor through SEWTA and SWWITCH, and the
north Wales corridor to Dublin are priority access routes on the European network
and are among the top 30 in Europe. We need to
make more of that and bring them in to do that strategically. In the Department
for Transport's Delivering Sustainable
Transport document, the arrows stop at the boundary between England and Wales. The Committee might want to
take a view on that.
Mr Workman: I just want to reflect
on the point that high-speed rail is important for areas where peripherality,
particularly among the economic community, is seen as a key issue. We have to
make sure that wherever the high-speed rail link finishes-at present, it is
proposed to be Swansea-the
benefits are then apparent to the rest of the network.
Q60 David Melding:
Are there any doubters? We have heard some evidence that electrification is important
but high-speed rail comes at one heck of an infrastructure cost, which could be
used elsewhere. Your primary aim is to promote modal shift on public transport.
Should we be trying to spend money elsewhere or would you give high-speed rail
the sort of priority that the British Government seems to want to give it at
the moment?
Mr Whittaker: I think that we would
support it-[Inaudible.]-on the west coast main line, the present projections
are that it will run out of capacity by 2015, but it is not just a matter of
passenger growth; we are also considering the needs of freight. I would like to
make the case for freight as part of that. It is not always the most popular
option. Nonetheless, if we are to move towards more sustainable transport,
stuff that we eat goes by freight, and so there would be a release in capacity
on conventional lines, and why not have high-speed freight lines for parcels
and high-value goods as an alternative to air freight?
Mr O'Sullivan: I do not think that
the doubt is about HS2. Perhaps HS3 is a different argument for somewhere
further down the line. If High Speed Two delivers a connection from Swansea all
the way to Paddington, and reduces the time out of Cardiff to an hour and 40
minutes, that is probably where we want to be. If we are talking about £15
billion to take another 10 or 15 minutes off that journey, that might be where
we would come in and say, 'We are doubtful about that; the money could be
better spent elsewhere', but we are fully behind the principle of HS2.
Mr T. Roberts: Could I quickly
mention David Rowlands, who is heading this high-speed HS2 project with the
Government? They are about to publish their report at the end of this year.
David Rowlands spoke to the Assembly Government around three months ago. I also
had a meeting with him. So, we should not lose sight of the fact that
electrification is a major step forward at the moment, which should be grasped
with both hands; we should push on with it.
Mr James: I just wanted to say that
we do not yet have electrification and we are already talking about what will
come after it. So, to some extent, I think: let us get electrification first.
The infrastructure costs that will arise out of that will no doubt be
challenging. However, issues such as the Severn
tunnel junction and introducing additional capacity are key issues on which we
should be working now. We still have the ambition and the wish to see the
connections through to Europe and so on.
However, we need to consolidate what is available to us and look to make the
most use of that and have an eye on the future, but we have to be realistic
because someone else holds the purse strings in terms of those big
infrastructure costs.
Q61 Jeff Cuthbert: I
have experienced first hand the benefits of light-rail systems in cities like Manchester and Sheffield.
You refer to it in your submission, but could you say more about to what extent
you see the value of light-rail schemes in Wales and how they can integrate
with heavy rail? To SEWTA in particular, do you think that the Valley lines
could integrate with the light-rail systems towards Cardiff?
Mr O'Sullivan: From a SEWTA point of
view, the traffic on the Valley lines has increased significantly; they are
very popular now. We have capacity issues there, but it is encouraging that we
have achieved a modal split, which fits in with park-and-ride policies and so
on. The balance that we need to achieve with light-rail is, effectively, down
to how long people are willing to stand. It is a rapid-transit, high-frequency
system, which carries 85 passengers with 15 or 20 standing. People will
tolerate standing for around 20 minutes. The systems that you mentioned in Manchester and Sheffield
are very good. Nottingham is a more recent
example where the capacity or capability of these new vehicles to climb
significant gradients is a big departure from the past. That fits in with our
Valleys terrain. There needs to be integration, but quite where it starts and
finishes, I am not sure. Cardiff Council has a draft light-rail strategy, which
is still being considered internally, but there will be nodes and points at
which heavy and light rail will interact. If we are to get the full benefits,
as we say in the evidence, the system must run on city streets and it has to
move away from heavy rail. That is a discussion for us to have and the study
that Cardiff Council has undertaken will ascertain whether that is viable.
Clearly, that is very expensive in initial capital costs, but the benefits are
there for all to see. We have aspirations for Wales
to be a modern European country and for Cardiff
to be a modern European city. The leading cities have these systems in place-it
is the way to get people around and we want to be a part of that. We could
apply the Nottingham example in particular; I was disappointed that Manchester and Liverpool
failed to get an extension, but that was to do with costs, so we need to get
the right balance. So, do we like it? 'Yes, we do'. Does it have applications?
'Yes, it does', but I am not sure whether we can afford it just yet.
Q62 Alun Michael: I
think that you have answered part of my question because I was going to ask
about priorities for electrification and we just talked about the mainline
electrification being the priority. However, the Deputy First Minister, in his
evidence to the Assembly's Enterprise and
Learning Committee said that he wanted to see all lines-to, from and within Wales-electrified.
What would be your priorities within Wales and what would be the
realistic timescale for that?
Mr G. Roberts: Looking at the whole
of Wales
and speaking from a rural perspective, it is quite often put forward in the
rail industry that rural lines should not be electrified, but if you take the
model used on the continent, most rural lines are electrified. Making quite a
leap of faith and going forward 30 years into the future, the environment is
paramount and the climate change debate has been taken on board, so we should
not rule out looking at rural lines because there are so many benefits in terms
of noise reduction, lower maintenance costs on the rolling stock and a better
ability to sell rail as a clean form of transport. When it comes to priorities,
we cannot argue with the fact that the Valleys lines and the south Wales lines
need to be electrified, but not at the expense of ruling out doing so to
possible rural lines in the long term.
Mr James: Again, I do not disagree
with anything that has been said, but this is about being realistic about what
is achievable. Clearly, we all welcome the mainline electrification through to Swansea. I know that we
would like it to go beyond Swansea
and into other areas that have been mentioned, for example, the Valleys lines
and so on. However, we have to make the best of what is available and the
electrification of the main line will be a fantastic improvement. I suspect
that any further investment will be done on a cost-benefit analysis, based on
the likely increase in flow of traffic, whether that be passenger traffic or
freight traffic. Again, because the infrastructure costs are so great,
extending that to rural areas would probably take around 30 years, which is a
good guess, but it may take longer. The amount of investment required is so big
that any Government would have to weigh that against all the other transport
challenges that it faces.
Mr Workman: I would not disagree
with what colleagues have already said, but clearly it is a given that
electrification, as far as Swansea
is concerned, is necessary. Beyond Swansea, from
the SWWITCH perspective, bearing in mind the question about our aspirations and
where we would like to see it, we would like the line to be linked to the ports
and be part of the trans-European network-making that journey across Europe
seamless and delivering what Europe can
potentially deliver for the international traveller.
Mr O'Sullivan: SWWITCH's aspirations
are clearly set out in the paper, but the one point I would bring to your
attention is that we would hope that any major signalling works being
undertaken in the coming years are future proofed to the degree that they would
be able to accommodate electrification, should it occur, and that would be part
of our continuing healthy dialogue with our good friends, Network Rail.
Q63 Gareth Jones: I
can see that there will be a lot of healthy dialogue.
In the absence of the Chairman, Hywel Williams took the Chair
Q64 Hywel Williams: (Through
an interpreter) There has been much discussion recently about developing and
improving services. For someone like me, who is committed to the railways, that
is very promising and is contrary to how things were in the past. We have heard
about the possibilities of improving the line from south to north between
Wrexham and Bidston and the Severn barrage that could be used for a new
crossing thereby doubling the line between Swindon
and Kemble. There are all those possibilities. Sometimes it is illustrated in
the press as a question of whether we should concentrate on going from west to
east or from south to north. I do not know whether that is a fair question.
What do you think is most important: south to north or west to east? You might
not want to answer that question or perhaps you are ready for your lunch.
[Laughter.]
Mr G. Roberts: (Through an
interpreter) Both are important, but in terms of going from the north to the
south, we have to be realistic in the long term about that journey. We should
not lose sight of the fact that, as communities in Wales
change, we need to look at how people travel throughout Wales and to make improvements to the railways
to bring some towns closer together, particularly in west Wales. We often
talk about the marches line, and it is important that the standard of that line
is improved so that it can handle not only passengers, but freight. Until that
is done, we cannot ask for more money to be spent on something else. However,
we sometimes have to look at off-the-wall ideas in order to see what could be
done in Wales
to connect the railway lines that we have. At the moment, the railway network
in Wales is in the form of a
reversed 'E'-if you travel from north to south Wales
you have to go out of Wales
and then come back in. It will be expensive, but we should not lose sight of
what could be achieved in the future.
Mr James: I am representing SEWTA,
which is located in south-east Wales.
You would probably expect me to say that I would not prioritise a north-south
route, but, as someone who travels to north Wales and back, as I am sure many
of you do, it is an incredible challenge. I can go to London more quickly than I can go to
Llandudno. We all have to accept that there are geographical and geological
problems to be faced. In the SEWTA region, we are seeing a lot of investment in
the Valleys lines, and they are benefiting from that. That is the best that I
can do with regard to north-south lines.
Hywel Williams: That is slightly to the north.
Mr Davies: To add to what Jeff said,
we feel that it is important that there should be a link between south and
north Wales.
Michael and I came down this morning on the train from north Wales, but there is no equivalent train from
south Wales to north Wales, which we
think is important. Being realistic, I represent areas in north-east Wales, and it is important to us that we have
that east Wales
link. I mentioned the electrification of the north Wales line; it is important that
that continues. It is a continuation of the English electrification. I have
also mentioned the link to the airports in the north-west of England, which are desperately important to
Wrexham and to north Wales
generally.
Mr Wilson: To add to what Gareth
said about the missing link in Wales,
with regard to the priorities, we are currently torn between north-south and
east-west links, especially in mid Wales. Most freight and so on goes
from east to west, so, in the shorter term, we have to look at what we can do
to strengthen the east-west links. Having said that, the north-south link is
vital, especially if we can get something in mid Wales. To join the north-south
route from Aberystwyth you have to travel to England and onto the marches line.
So, in the shorter term, there is an issue as to whether we focus on east-west
or north-south links. In the longer term, we should be looking at north-south
links, which will include having something within Wales.
Q65 Gareth Jones: We
have to leave things there. As someone who travels every week for four hours,
and sometimes for four and a half hours, from Llandudno to Cardiff, I am glad to hear that the will does
exist. There is an old saying in Welsh-'diallu pob diewyllys'; I am not sure
how the interpreters will convey it-which means that if there is no will, there
is no way. However, where there is a will, there is a way-and we will get
something in the future. Before I close the meeting, I would like to thank the Enterprise and Learning
Committee members and members of the Welsh Affairs
Committee. This joint meeting has been interesting and
special. I hope that you have enjoyed being here. We have certainly enjoyed
your company and the opportunity to ask questions. We are extremely grateful to
the witnesses. We have already thanked the train operators, but we appreciate
the consortia's work. Your answers have shown where the frustration lies in all
of this and that there needs to be more co-ordination if we want to see a
bright future for our railways and transport more generally in Wales. Thank you
again for joining us. I know that time has been scarce this morning, but I
assure you that your answers do count. They will certainly inform the follow-up
review to be undertaken at the House of Commons, through the Welsh Affairs Committee, and they will be of benefit
to us in our work of scrutinising the railway infrastructure in Wales for the
future. I greatly hope that you feel that the welcome you received is much
warmer than the temperature of this room. I apologise for that; regardless of
what is happening in this iconic building, it is cold. Thank you for making the
effort to join us. We appreciate your written evidence and what we heard this
morning, and we wish you all the best. I assure you that we are more than
willing to work with you, given that we are all moving in the same direction.
Thank you to all of you. That brings our meeting to a close.
|