1 The Department's performance
1. Each year UK passengers make more than one
billion journeys on rail services, run by the private sector.
In 2006-07, passengers paid about £4.8 billion out of a total
cost of £9 billion for these critical public services. The
Department for Transport (the Department) provided around £3.1
billion as grants to Network Rail, £0.8 billion directly
to train operators and £0.3 billion to local bodies.
2. In 2005, the Department took over responsibility
for letting and managing rail franchises from the Strategic Rail
Authority. Following the hand-over, it completed the letting of
four franchises in 2005-06, including the InterCity East Coast
franchise awarded to GNER. The Department specified and let the
South Western franchise in 2006-07, and a further four franchises
in 2007-08. Throughout planning and procurement, the Department
has specified services that reflect its objectives to control
costs and live within the public funding available. The Department
is not, however, always well informed about the likely impact
of its rail franchising decisions on passengers and, therefore,
on its wider transport objectives.[2]
3. The Department's specification for each franchise
is based on a cost-benefit test: services with higher benefits
than costs are generally included in the specification. Some exceptions
are permitted on safety grounds.[3]
Train operators are allowed to put forward innovative proposals,
but the selection of winning bidders for each franchise is largely
based on bids for the base specifications.[4]
4. Local bodies may also elect to pay for services
to meet local needs and which need additional subsidy. Most train
operators, however, admitted that they do not put much effort
into working up the optional part of their bids. And, because
the Department does not involve the local bodies in evaluating
and negotiating the actual bids, local awareness of shortcomings
in bid options might be overlooked.[5]
As a result, the crucial local voice in securing suitable train
services may be lost.
5. Overall, the Department has been successful
in stimulating competition and letting franchises to planned timetables.
There has been keen competition with three or more bidders on
seven out of the eight franchises, although overseas companies
showed little interest because of the strength of the established
UK bidders.[6]
6. Varying levels of activity make direct cost
comparisons with the Strategic Rail Authority difficult. The Department's
costs are generally lower, although for most bids the Department
still spends over £2 million on consultants. Train operators
have complained about their own costs of up to £5 million
for each bid. The Department cannot influence the total cost incurred
by bidders, which includes the bidders' own choices on success
fees and bonuses, but it has reduced the document length and the
number of detailed plans required in an effort to reduce bidders'
costs.[7]
7. The Department has operated with fewer staff
than the Strategic Rail Authority, bringing the cost of managing
franchises down from £7.3 million in 2004-05 to £5.7
million in 2007-08. Some 30% of staff had departed within two
years of the change in responsibility. The Department expects
people to move on every two or three years and many Strategic
Rail Authority staff had been in post for some time. The Department's
rail service delivery team does not normally recruit from the
wider civil service. It recruits largely from the railway industry
itself instead, and has difficulty in attracting and retaining
staff because it pays salaries towards the bottom quartile of
that industry.[8]
8. The Department's arrangements for identifying
and managing risks, including handling the failure of a train
operator, follow good practice. For example, the parent company
of GNER, which operated the InterCity East Coast line, was unable
to support GNER through a period of financial difficulty. The
Department negotiated a management contract with GNER to operate
the service until the franchise was re-let competitively. The
passenger experience on this line has, however, continued to be
much the same after re-letting the franchise to National Express
in 2006-07.[9] National
Express has committed in the franchise agreement that it will
bring in a number of specified improvements in accordance with
the timetable set out in the Department's note to the Committee.[10]
2 Qq 94, 114, 122, 131-133, 159-161 Back
3
Qq 116-117 Back
4
C&AG's Report, paras 1.10, 13; Appendix 4 Back
5
Qq 118-120 Back
6
Q 115 Back
7
Q 121 Back
8
Q 99 Back
9
Qq 15-16 Back
10
Ev 18-21 Back
|