2 Governance, resourcing and risk
management
6. Planning and governance was one of the weaker
areas in the contracts assessed by the National Audit Office,
with six of the eight contracts rated as amber or worse, a finding
consistent with the results of the Office of Government Commerce's
own Procurement Capability Reviews. The National Audit Office
also found, however, examples of excellent senior level engagement,
for example, by the Permanent Secretary at the Department for
Work and Pensions, who is actively involved in the management
of major suppliers. In the Office of Government Commerce's view,
Permanent Secretaries increasingly understood the importance of
getting contract management right and of having proper governance,
and most were personally involved in some aspects of procurement
and in commercial matters more generally in their departments.[7]
7. It is also helpful for there to be a single point
within a department for contract management policy, practice and
capability, although fewer than half the organisations (43%) surveyed
by the National Audit Office had an individual with overall responsibility
for contract management across the organisation. In addition,
there was no documented plan for managing 28% of contracts. The
Office of Government Commerce considers that it should be standard
to have a documented plan for managing major contracts and it
would make this clearer in future guidance.[8]
8. In 2007-08, central government spent the equivalent
of 2% of annual contract expenditure (an estimated £240 million)
on managing service contracts. Having sufficient people with the
right experience and skills is essential to effective contract
management, but no commercial director/head of procurement rated
the level of resources allocated to the management of their major
service contracts as 'good'. In addition, 22% of the contract
managers surveyed considered they did not have time to perform
their responsibilities well. Resources were stretched, for example,
at the Ministry of Justice, where the manager of the contract
for court security, worth £29 million a year, also managed
two other major contracts.[9]
9. The Office of Government Commerce does not consider
it is possible to specify what percentage of the contract value
should be spent on contract management as this will depend on
the level of risk, the value for money opportunities, and the
importance of the contract to the organisation. It would, however,
review whether it could provide more advice on resourcing as part
of future guidance on contract management.[10]
10. Over three-quarters of the contract managers
surveyed had three or more years experience of managing major
contracts, with 14% having one year's experience or less. Most
contract managers had no formal commercial qualification but had
undertaken some relevant training, although 60% of organisations
did not provide a structured training programme for their staff.
There was also a lack of established contract management 'communities'
where contract managers could discuss issues and share good practice.[11]
11. The Office of Government Commerce considers that
ensuring that contract managers receive the right training and
development, and that they are part of a community so they can
exchange best practice, is more important than professional qualifications.
The Office of Government Commerce is taking action to bring contract
managers into the fold of the procurement profession, which in
the past has often not been seen as including contract managers.
It is identifying contract managers across government, and at
the time of our hearing Permanent Secretaries had just approved
plans for career development, talent management, and learning
and development across the government procurement profession,
together with a reward strategy.[12]
12. Most service contracts are critical to the delivery
of an organisation's business objectives and carry significant
risk if the supplier fails. Despite this, many of the contracts
in the National Audit Office's survey did not have in place some
or all elements of good practice risk management (Figure 1).
For example, 37% did not have a risk register and 56% did not
have a contingency plan in case of supplier failure. The Office
of Government Commerce accepts that there is more to be done on
risk management, particularly given the prevailing economic circumstances.
Though guidance is available, risk management is not embedded
in all contracts.[13]
Figure 1: Risk management processes in place across
central government service contracts

Source: Comptroller and Auditor General's Report,
Figure 13
13. Two-thirds of the contracts in the National Audit
Office's survey involved suppliers dealing with personal or security
information, but even 30% of these contracts did not have a risk
register. The Driving Standards Agency, for example, did not have
a specific risk register for its contract for driving theory tests
prior to the supplier losing a computer hard disk drive containing
personal information about test applicants. The Office of Government
Commerce pointed to the amount of work that was underway across
government on data security. The Government had made clear to
its largest suppliers their obligations in respect of handling
sensitive and personal data, and there would be mandatory security
clauses in future contracts to that effect. For example, suppliers'
staff should be trained in areas such as the secure transfer and
disposal of data.[14]
7 Qq 21, 33-36; C&AG's Report, para 2.3; Figure
9 Back
8
Qq 15-16, 54; C&AG's Report, paras 2.4-2.5 Back
9
C&AG's Report, paras 2.6-2.8 Back
10
Qq 55-58 Back
11
C&AG's Report, para 2.10 Back
12
Qq 8-9, 38-39 Back
13
Qq 2-4; C&AG's Report, paras 1.5, 2.21; Figure 13 Back
14
Q 23; C&AG's Report, paras 2.21-2.23; Ev 12 Back
|