Spring Supplementary Estimate 2008-09 - Defence Committee Contents


Report



Spring Supplementary Estimate: an overview

1. The Spring Supplementary Estimates (SSE) for Financial Year 2008-09 were laid before the House of Commons on 12 February 2009.[1] The Ministry of Defence is seeking a net increase in resources and capital of £1,297 million—in cash terms a net increase of £627 million.[2] This is the additional sum of money required by the MoD to fund its activity over and above the sums already voted in the Main and Winter Supplementary Estimates. Table 1 provides a breakdown of this requested increase in expenditure.

Table 1: Change in Resource and Capital Expenditure sought in the Spring Supplementary Estimate

Resource Expenditure £million
Provision of Defence Capability (RfR1) 226.313
Operations and Peace Keeping (RfR2) 741.766
Total Net Request for Resources 768.079
Capital Expenditure
Net Provision of Defence Capability (RfR1) 264.000
Operations and Peace Keeping (RfR2) 65.000
Total Net Request for Capital 329.000
TOTAL CHANGE IN CAPITAL AND RESOURCE 1,297.079

Source: Ministry of Defence[3]

2. The requested Resource and Capital increase of £490 million in Request for Resources (Provision of Defence Capability)—RfR1—is explained in the Department's Estimate memorandum.[4] The increase is mainly due, on the Resource side, to a drawdown of £45 million End-of-Year Flexibility (EYF) from £105 million available which is to be allocated to Defence Equipment and Support (DE&S) in order to alleviate resource pressures, and to £170 million added by the Treasury to the non-budget part of the MoD's Estimate because of impairments which reflect the downturn in the market prices for fixed assets held by Defence Estates and a revised lower forecast of asset values for DE&S.[5] On the Capital side, the increase in RfR1 is due to the drawdown of £214 million in EYF (the full Capital EYF sum available for 2008-09) which it is proposed will be allocated to compensate Defence Estates for loss of non-operating receipts, which are lower than previously forecasted,[6] and to an increase in the MoD's Captial budget of £50 million in anticipation of some of the receipts from the sale of the MoD's holding in electro-magnetic wavelength bandwidth, or "Spectrum".[7]

3. We expect the Ministry of Defence, in its response to this Report, to set out in more detail the nature of the resource pressures within Defence Equipment and Support, and the reasons for that organisation's revised lower forecast. We would also be grateful for a note setting out the nature of the losses from Defence Estates for which these additional requests compensate, and an explanation of whether these losses are expected to recur in the next Financial Year.

4. All but £5 million of the requested £807 million increase in RfR2 (Operations and Peace Keeping) of £802 million is to fund the additional costs of conducting operations in Iraq and Afghanistan. This comprises a Resource request of £737 million and a Capital request of £65 million. Details of what comprises these sums is available in Table 2. The largest single sum within these additional requests is £455 million in Indirect Resource costs as a contingency to cover possible costs of the drawdown in Iraq.[8] The total of £802 million is additional to the £3,715 million sought at the time of the Winter Supplementary Estimates in November and voted by the House of Commons in the following month.[9] In total, the MoD will have sought an extra £4,517 million for operations in 2008-09, far beyond the estimate of "at least £2 billion" set out in the Main Estimates at the beginning of the Financial Year.

5. In our Report on the Spring Supplementary Estimate 2007-08 we expressed concern at the very short time which departmental select committees have to consider the Supplementary Estimates thoroughly and to report to the House in time for the debate and decision on those estimates.[10] On this occasion there is more than the minimum fourteen days set down by the Standing Orders of the House of Commons for this scrutiny. However, the time allotted is still insufficient for us to analyse the Estimate and its accompanying memorandum, one week of this time falling in recess and another when we are away in Russia, Estonia and Georgia in connection with one of our current inquiries. We understand that the MoD's hands are tied in terms of this difficult time-table which, beyond the stipulation of the minimum number of days given in Standing Orders, is the responsibility of the Treasury. We also understand that the process of gathering information for the Supplementary Estimates and then of their internal approval prior to publication is complex and time-consuming, and that improvements may be made to process and output as a result of the Treasury-led Alignment Project. However, we reiterate our belief that the amount of time committees currently have to analyse the Supplementary Estimates properly, to seek further information where necessary on any areas of particular interest, concern or uncertainty, and then to consider a draft Report, agree it and publish it before the debate and decision on those Estimates in the House is insufficient.

SPECTRUM CHARGING

6. The MoD's Estimate memorandum notes £50 million extra capital budget from the Treasury as a contribution from the sale of the Department's electro-magnetic spectrum.[11] Evidence received from the MoD in relation to our inquiry into the Department's Annual Report and Accounts 2007-08 stated that the MoD "is permitted to retain up to £500 million of Spectrum receipts over the CSR period."[12] It is not clear whether this £50 million receipt from the Treasury in this Financial Year is the first in a series of such receipts, and if so, whether or not the Department expects to receive its permitted total of £500 million for its spectrum, with the Treasury perhaps receiving further receipts in excess of that limit. We request a note from the Ministry of Defence setting out the exact position with regard to the likely eventual benefit for the MoD budget.

Operations and Peace Keeping: Iraq and Afghanistan

7. We are fully aware of the volatility of operational costs for both Iraq and Afghanistan and appreciate the MoD's efforts in providing the House of Commons and ourselves with as accurate a forecast of such costs as it can. We also acknowledge that in the 2009-10 Main Estimate, published in a couple of months' time, greater detail of forecast operational costs for the new Financial Year will be provided than was possible in the Main Estimate at the outset of this current Financial Year: the MoD has previously assured us that the forthcoming Main Estimate will include, for the first time, provision of Iraq and Afghanistan operational costs.[13] Given that the MoD, when its Spring Supplementary Estimate goes before the House of Commons for approval, will have sought over twice the amount it set down as a likely minimum for operational costs at the time of the last Main Estimate, we hope that the next forecast in 2009-10 will prove more robust an assessment of operational costs and closer to the eventual out-turn.

8. As the MoD Estimates memorandum points out with regard to costs within RfR2, the major indirect cost increase is for costs in anticipation of the drawdown in Iraq. Despite lower than anticipated equipment depreciation, a sum of £455 million has been "prudently set aside" in this Estimate as a contingency to cover "potential non-cash costs of depreciation, write-offs and gifting of equipment and other capital assets" in Iraq.[14] The prudent setting aside of such significant extra resource in anticipation of the drawdown was not considered at the time of the Winter Supplementary Estimate: at that time, the figure for such depreciation and associated costs was forecast to be only £170 million.[15] Moreover, in response to a recommendation in our Report on the Winter Supplementary Estimate, the MoD submitted to us just over a week before the Spring Supplementary Estimate was laid a note setting out its forecast of operational costs at that time. This note, dated 4 February 2009, also did not include the large contingency for the drawdown in Iraq, although it explained that some further provision was expected to be included at the time of the Spring Supplementary Estimate: presumably the scale of the contingency had yet to be agreed.[16]

9. We are currently engaged in an inquiry into readiness and recuperation. As part of that inquiry we are looking at the likely costs of the recuperation of the Armed Forces following the drawdown from Iraq. We are aware that the initial phase of drawdown would be costly in terms of logistic support and in terms of possible equipment losses. We expect in response to this Report a note setting out in detail what the very substantial contingency in the Spring Supplementary Estimate for the Iraq drawdown is particularly intended or expected to cover.

10. In the Government's response to our Report on the Winter Supplementary Estimate (appended to this Report), the MoD explains that remaining military tasks in Iraq will have been completed by 31 May 2009 at the latest, and all but around 400 UK troops (of a current 4,100) will have been withdrawn by the end of July.[17] We would expect the response to this Report to set out the extent to which the cost of the drawdown (as opposed to the cost of the continued, albeit reduced, presence in Iraq) will continue into Financial Year 2009-10, and what the magnitude of any continuing cost of drawdown will be in that new Financial Year.

11. Aside from the additional £455 million cost within RfR2 as a contingency for indirect resource costs in Iraq arising from the drawdown, there are some other less substantial but still significant changes in forecast costs for Iraq and Afghanistan visible in the Spring Supplementary Estimate when compared to the costs set out in the Winter Supplementary Estimate. The increase is stock consumption costs, of 23.1% in Iraq and 37.5% in Afghanistan since the forecast in the Winter Supplementary Estimate, represent increased fuel and ammunition consumption, particularly in the case of Afghanistan. Other increases, in infrastructure and equipment support (26.1% and 7.2% in Iraq and 13.6% and 9.6% in Afghanistan respectively), are due to "higher than expected equipment repair costs, the inclusion of some recently approved urgent operational requirements and sterling's adverse exchange rate variation".[18] Life support equipment costs have risen for Afghanistan on account of the construction of Camp Bastion and Gereshk.[19]

12. While personnel costs, military and civilian, have remained more or less the same as forecast towards the end of last calendar year for Iraq, there is a significant reduction in military personnel costs for Afghanistan (of £33 million, which represents a 31% cut) which more than offsets a 20% increase (at £2 million) in civilian personnel costs in that theatre.[20] The Estimate memorandum fails to explain this reduction in military personnel costs. However, we noted the original significant increase in military personnel costs for Afghanistan in our Report on the Winter Supplementary Estimate, and the Government response to that Report explains that the reduction in these costs in the Spring Supplementary Estimates represents the rectification of an over-forecast, identified following the restructuring of cost-gathering responsibilities for operational allowances.[21]

Urgent Operational Requirements

13. The MoD's Estimate memorandum states that the additional RfR2 Capital request of £65 million is mainly for Urgent Operational Requirements (UORs) in Iraq and Afghanistan. It further explains that examples of UORs which have been recently ordered are: "force protection (e.g. tactical support vehicles and protection for engineering plant); and specific modifications to military equipment so that they can operate in the operational environment (e.g adaptations to Merlin and Lynx helicopters, and Tornado aircraft)".[22] The memorandum also notes that the MoD has requested £45 million Indirect Resource DEL from the Treasury Reserve "to cover costs of capital, depreciation and impairment charges associated with fixed assets purchased under Urgent Operational Requirement arrangements".[23]

14. The MoD in its Main Estimates memorandum said that the agreed limit for UOR spend in 2008-09 was £1.065 billion.[24] In our Report on the Main Estimates we asked the MoD to explain the implications of such UOR expenditure on the Department's future capital and resource budgets. The MoD explained that "the UOR expenditure will be scored against peace keeping and operations (RfR2) and claimed against the Treasury Reserve as usual". It added that there will be "no impact on the Department's core (RfR1) budget for 2008-09". If the figure of £1.065 billion were exceeded, the Defence budget would "bear half the cost of the excess in 2010-11 under the arrangements agreed in the 2007 Comprehensive Spending Review".[25]

15. In our Report on the Winter Supplementary Estimates we noted that the MoD had already estimated a total spend of £1.063 billion for 2008-09 on UORs, only £2 million short of the agreed limit for that Financial Year. We asked the MoD whether that limit was going to be breached and for an explanation of how any breach in that limit would impact upon the Department's 2010-11 budget. In its response,[26] (appended to this Report) the MoD points out that it now expects UOR expenditure to be no more than £1.054 billion in this Financial Year, £9 million less than expected at the time of the Winter Supplementary Estimate and £11 million short of the limit agreed with the Treasury. Consequently, the MoD does not "anticipate any impact on the MoD's 2010-11 budget or equipment programme" from expenditure on UORs in this Financial Year. We welcome this reassurance. However, it is unclear to us how the new, additional, request for £65 million capital resources, largely to cover the cost of UORs, fits within this figure if UORs are now expected to cost less than was the case at the time of the Winter Supplementary Estimate. We would welcome clarification from the MoD as to the exact make-up of the £1.054 billion UOR cost figure and how the forecast cost has reduced at the same time that another £65 million is sought.

16. On account of the importance of UORs to the current deployment of UK forces in Afghanistan, and the likely continuing need for UORs as the deployment there persists, we would welcome a categorical restatement that any cost in excess of the limit agreed for UORs between the Department and the Treasury will fall in part on the MoD in Financial Year 2010-11 and not before, the Department bearing half of the excess cost. We would also welcome some indication of expected UOR costs in 2009-10, notification of the agreed UOR limit for that year, and an explanation of how the cost of the Protected Mobility Package announced on 29 October 2008 falls within this year's and next year's UOR limit. We remain concerned about the potential impact in the future of UORs on the MoD's core budget and we will return to this subject in an inquiry later this year.

Table 2: Operations in Iraq and Afghanistan—changes in anticipated additional costs since Winter Supplementary Estimates (from RfR2)

Cost Type Iraq Forecast £m 2008-09 (as at Winter Supp Est) Iraq Forecast £m 2008-09 (now ) % change

[£m change]

Afghan Forecast

£m

2008-09

(as at Winter Supp Est)

Afghan Forecast

£m

2008-09

(now)

% change

[£m change]

DIRECT RESOURCE
Military personnel 116116 --- 10673 -31.1%

[-33]

Civilian personnel 1718 +5.9%

[+1]

1012 +20%

[+2]

Stock/other consumption 195240 +23.1% [+45] 379521 +37.5% [+142]
Infrastructure costs 119150 +26.1% [+31] 147167 +13.6% [+20]
Equipment support costs 332356 +7.2%

[+24]

185220 +18.9%
Other costs and services 194175 -9.8%

[-19]

311305 -1.9%

[-6]

Income generated/ (foregone) (2)(1) +50%

[+1]

(7)(15) -114.3%

[-8]

INDIRECT RESOURCE 170625 +267.6% [+455] 180225 +25%

[+45]

Total Resource DEL 11411679 +47.2% [+538] 15111710 +13.2% [+199]
Capital Additions 256279 +9%

[+23]

807849 +5.2%

[+42]

Total 13971958 +51.7% [+561] 23182559 +10.4% [+241]
Total (excluding Indirect Resource costs) 12271333 +8.6% [+106]2138 2334+9.2% [+196]

OPERATIONAL FORECASTS

17. We have in the past had occasion to criticise the MoD for the very significant increases between the Winter and Spring Supplementary Estimates.[27] Although these Estimates are founded upon forecasts of costs drawn up some time apart from each other, within volatile operational theatres, we considered the often very great increases to be a symptom of poor forecasting skills, or of departmental over-optimism. Table 3 below sets out these changes in two previous Financial Years. While there has been an increase in operational costs for Iraq between Supplementary Estimates this Financial Year of 40.2% (only 10.4% for Afghanistan), the magnitude of this increase is in very large part down to the increase in Indirect Resource costs. Without those costs, the increase amounts only to 8.6% which compares very favourably with 51.7% in the last Financial Year.[28] We are pleased to note that, setting aside the extra £500 million in Indirect Resource costs, over 90% of which is for the drawdown in Iraq, the margin of change between the Winter and Spring Supplementary Estimates has not been as great as it has been in the past. We commend the MoD for undertaking what is clearly an increasingly robust analysis of forecast costs throughout the Financial Year.

Table 3: Changes in forecasts for operational costs between WSE and SSE in 2006-07 and 2007-08

WSE
2006-07
SSE
2006-07
% change WSE
2007-08
SSE
2007-08
% change
Iraq 8601002 + 16.5 %955 1449 + 51.7 %
Afghanistan 540770 + 42.6 %964 1424 + 47.7 %
TOTAL 1400 1772 + 26.6 % 1919 2873+ 49.7 %

Note: Does not include indirect resource costs

CONCLUSION

18. We recommend that the House of Commons approve the request for resources set out in the MoD's Spring Supplementary Estimate. The £1,297 million, in large part requested to meet the forecast additional cost of operations in Iraq and Afghanistan during this Financial Year (including contingency provision for drawdown in the former theatre), represents a significant sum of public money, but we believe that the task our Armed Forces are carrying out is one that requires such a significant resource—especially in terms of new equipment and force protection, both so essential to their mission abroad.


1   HM Treasury, Central Government Supply Estimates 2008-09 Spring Supplementary Estimates, HC 265, February 2009 Back

2   Ev 2 Back

3   ibid, Table 1 Back

4   Ev 2-11 Back

5   Ev 6, para 4.5 Back

6   Ev 5, para 4.2 Back

7   Ev 5, para 4.3 Back

8   Ev 6, para 5 Back

9   Defence Committee, First Report of Session 2008-09, Winter Supplementary Estimates 2008-09, HC 52 Back

10   Defence Committee, Eighth Report of Session 2008-09, Operational costs in Afghanistan and Iraq: Spring Supplementary Estimate 2008-09, HC 400, para 3 Back

11   Ev 5, para 4.3 Back

12   Defence Committee, written evidence, ARA 02, MoD Annual Report and Accounts 2007-08 inquiry, available at www.parliament.uk/defcom Back

13   Defence Committee, Ninth Special Report of Session 2007-08, Ministry of Defence Main Estimates 2008-09: Government response to the Committee's Eleventh Report of Session 2007-08, HC 1072, response to recommendation 8 Back

14   Ev 6, para 5.3 Back

15   HC (2008-09) 52, Ev 6, Table 6 Back

16   Ev 1, para 1 and Table 2 Back

17   Ev 13, response to recommendation 14 Back

18   Ev 6, para 5.1 Back

19   Ev 13, response to recommendation 14 Back

20   See Table 2 Back

21   See Table 2 Back

22   Ev 2, para 2.1b and Ev 6, para 5.2 Back

23   Ev 7, para 5.5 Back

24   Defence Committee, Eleventh Report of Session 2007-08, Ministry of Defence Main Estimates 2008-09, HC 885, Ev 4, para 4.6 Back

25   HC (2007-08) 1072, response to recommendation 7 Back

26   Ev 13, response to recommendation 16 Back

27   See, for example, HC (2008-09) 52, paras 10-12 Back

28   See Table 2 Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2009
Prepared 9 March 2009