Government response
Overview of targets
1. In view of the central role played by the Treasury
and the OGC in the delivery of the overall efficiency programme
across Government, we would have expected the Government to set
stretching efficiency targets for the Chancellor's own departments.
The process by which final targets were set for HMRC, the ONS,
the Treasury itself and other offices and departments was internal
to the Government, and the reasons for the differences between
the individual departments are not readily apparent. The ONS was
set the most ambitious efficiency targets, including a substantial
emphasis on relocation, combined with reductions in its overall
budget between 200506 and 200708. The targets for
HMRC as well as the ONS placed a strong emphasis on headcount
reductions as a source of efficiency savings. Across Government
as a whole, savings based on headcount reductions have emerged
more slowly than savings derived from procurement. (Paragraph 19)
Departmental targets for efficiency gains and headcount
reduction were agreed as part of the SR04 Spending Review.
Sir Peter Gershonwho led the Government's
independent review into public sector efficiencyagreed
stretching headcount reduction and efficiency targets with every
department, including the Chancellor's departments, as part of
his work. Relocation targets were agreed as part of the independent
review of public sector relocation, led by Sir Michael Lyons.
Agreed efficiency, workforce reduction and relocation
targets reflect the forward business plans and positions of the
departments.
HMRC is a large civil service employer with a relatively
small programme (as opposed to administration) budget. As a result,
efficiency savings were agreed to be found primarily in reforming
and reducing HMRC's workforce. ONS agreed that substantial relocation
alongside other efficiencies was an important component in restructuring
of the department in line with its business planning to 2010.
Overview of reporting and monitoring
2. In view of the welcome availability of information
on the classification of efficiency savings across central and
local government as a whole as final, interim or preliminary,
we regret that information about the classification of savings
by the Chancellor's departments on the same basis is not publicly
available. We welcome the co-operation between the OGC and the
NAO on classification issues. In future, we trust that co-operation
between the Treasurywhich is now assuming the monitoring
role hitherto performed by the OGCand the NAO will be constructive
and productive. We were concerned to hear the Permanent Secretary
to the Treasury wonder whether the NAO has adopted an "excessively
purist" approach to measurement issues. It is important that
any assessment of efficiencies achieved is underpinned by agreement
between the Treasury and its Permanent Secretary, on the one hand,
and the NAO, on the other, about how these achievements are measured.
(Paragraph 26)
HMT and OGC have put forward their approach to measuring
efficiency gains in the guidance available on the HMT website,
building on the principles set out by Sir Peter Gershon in his
review.
HMT, OGC and NAO have worked closely in the implementation
of the SR04 Efficiency Programme and this has been both productive
and constructive. NAO have been consulted on the drawing up of
both efficiency measurement guidance and in the drafting of departmental
Efficiency Technical Notes. NAO have provided useful review in
their two reports into the Efficiency Programme.
HM Treasury has published since Budget 2007 a breakdown
of the Efficiency Programme's progress by department and by classification
of gains (into the categories of 'preliminary', 'interim', and
'final'. This information is available on the HM Treasury website.
Departments are responsible for explaining the progress of their
individual efficiency reforms, including the classification of
gains reported. The Chancellor's Departments will be including
such a breakdown in future Departmental and Autumn Performance
Reports.
3. At the heart of the Gershon efficiency programme
lies the notion that efficiency gains can be achieved without
an adverse effect on quality of service, and that monetary savings
will therefore not be reported as efficiency savings unless quality
of service is maintained. Witnesses raised concerns about the
general adequacy of measurement of quality of service, the involvement
of customer experience in such measurement, the extent of publicly
available information about such measures, the rigour of validation
of such measures within government and the possible role for external
validation of such measures. Given these concerns, we urge the
Government to reconsider its decision to reject our earlier recommendation
that the Treasury undertake research into the quality of measures
in place within departments to provide assurance that efficiency
savings have not led to a reduction in the quality of services
delivered or products provided, and that it publish the outcome
of such research. In the absence of such research, we remain to
be convinced that the current framework for measuring quality
of service is adequate. Our concerns about the existing framework
inform the following recommendations in this Report, which relate
to particular departments. (Paragraph 33)
Measures of quality of service are already in place
across the programmeevery efficiency initiative is required
to have in place measures of service quality. These are monitored
as part of the programme to ensure that there is no decline in
service quality attributable to efficiency programme reforms.
The recent NAO report found no conclusive evidence
of service quality decline in their detailed survey of the programme
and in fact noted that in many instances public services had improved
significantly. Relating to HMRC specifically, the NAO noted that,
according to the indicators agreed to monitor the impact of the
Programme on quality of service in areas where headcount reductions
are being made, performance had not been adversely affected during
the period of headcount reductions. In some areas, performance
had risen substantially, as shown in the latest 200607 results
in the areas covered by the NAO report:
- the percentage of tax returns
processed correctly first time has risen from 72 per cent (200304)
to 78 per cent (200607);
- the percentage of calls handled correctly has
risen from 80 per cent (200304) to 95 per cent (200607);
- the percentage of formal complaints handled within
15 days has risen from 88 per cent (200304) to 95 per cent
(200607);
- additional VAT payments secured by HMRC staff
have increased from £1,401m (200304) to £1,469m
(200607).
The efficiency programme in the Office for National
Statistics
4. We are concerned by the evidence we have received
about the process by which targets for relocation within the ONS
were arrived at and plans for meeting those targets developed.
Official assessments about the costs and value of particular numbers
of posts at particular sites appear to have been undertaken after
targets were set and to have changed on at least two occasions.
Targets up to 2010 had been offered by the ONS itself and then
set by the middle of 2004, although the ONS has now admitted that
relocation plans for the period from 2008 to 2010 were undertaken
during 2006. Communication with staff and stakeholders about the
relocation programme in its various phases and its rationale appears
to have been haphazard and inadequate. We are also concerned about
the apparent weakness of the human resources planning for the
relocation, as well as weaknesses in the implementation of a consistent
human resources strategy. These weaknesses in the planning process
may have contributed to concerns about the effects of relocation
on quality of service, an issue which we examine later in this
Report. (Paragraph 42)
The work to consider the relocation of ONS posts
which led to the submission to the Lyons review demonstrated clear
financial savings as a result of moving work out of central London.
The detailed relocation planning carried out during
the early part of 2004 identified the business areas which would
relocate in the period up to April 2008. This reflected the 2008
target set in the 2004 Spending Review and was based on the Centres
of Excellence site strategies announced alongside the plans in
September 2004. The plans did not focus beyond this date given
the uncertainties about the shape of the Office and new work it
would be undertaking. Relocation and efficiency planning within
ONS has needed to evolve to reflect the outcomes of its corporate
and statistical modernisation programme. The re-engineering of
the statistical and corporate systems has provided opportunities
for changes in working procedures and the overall structure of
the teams delivering the statistical outputs and providing corporate
support services. This has been essential in delivering business
efficiencies.
ONS has learned lessons from the early phases of
the relocation programme and has improved its strategy. The announcement
of the subsequent strategy for delivering relocation made in September
2004 was well received and has been supplemented with regular
corporate updates from the relocation programme team. At the lower
level, development of the more detailed plans and their delivery
has been managed through business specific project teams with
an overarching Relocation Programme Board overseeing and assuring
the integration of plans to ensure the delivery of relocation
while minimising risk to ONS' statistical outputs. Communication
plans within these teams have focused on the needs of individual
members of staff and have facilitated close working with the HR
support teams.
The overall monitoring of organisational change is
undertaken by a workforce change team which integrates business
planning for relocation, efficiencies and headcount reduction.
Its role is to ensure adherence to, and monitor progress towards,
corporate targets. Importantly the team seeks to promptly address
the resulting people issues, such as effective and successful
redeployment activity, union consultation, recruitment and supporting
staff moving to the new location.
5. We recommend that, in its response to this
Report, the Government set out the total efficiency savings originally
expected to be achieved as a result of the ONS's online registration
project, the costs associated with the delays to online registration,
the latest timetable for successful completion of the project
and the latest estimate for the effect of savings and costs associated
with the project on the overall monetary efficiency savings to
be reported by the ONS to the end of 200708. (Paragraph 46)
The Registration Online project (RON) aims to update
and greatly improve the registration process. It is a necessary
project to bring the Registration side of ONS business into the
current age of computers and the internet, in order to offer the
services that customers now expect. As such, the project was necessary
in its own right, and was never expected to deliver significant
efficiency savings in ONS. There will be significant benefits
from faster access to data and provision of data (where law provides)
including for Other Government Departments and Local Authorities
(LAs).
It has been estimated that the whole RON project
will contribute £200k efficiency savings per annum within
ONS.
When the project was rolled out to the Local Authorities
there were some teething problems, leading to delays in getting
all LAs on to the new systems. It is estimated that resolution
activities will cost in the region of £1m, so taking into
account the £200k annual efficiency savings the net effect
over 2007/8 is estimated to be costs of £800k.
Currently about half of Local Authorities are using
RON to register Births & Deaths. ONS is aiming to rollout
to 95% by March 08 but anticipate that it may take longer to resolve
the technical issues with a few LAs. RON is being successfully
used by all LAs to register Civil Partnerships.
6. The ONS has reported having achieved 90% of
its monetary efficiency targets, while remaining little more than
a third of the way towards its headcount reduction target, which
was planned to account for around 72% of the ONS's efficiency
savings. This indicates that the ONS's efficiency programme has
not gone as planned. We recommend that, in its response to this
Report, the Government:
- give an account of each
revision of the ONS headcount baseline since the inception of
the efficiency programme, explaining the rationale in each case;
- provide its latest estimate of the total monetary
savings expected to accrue from reductions in ONS headcount over
the period of the Gershon efficiency programme; and
- explain the reasons for continued adherence
to the initial headcount reduction target or any subsequent revision
of it in the light of the overall progress by the ONS towards
its monetary savings targets. (Paragraph 49)
ONS's efficiency target of £25m is made up of
£12.5m cash savings and £12.5m non-cash savings. As
of December 2006 ONS had achieved £10.2m savings towards
the cash target. 237 full time equivalent (FTE) staff had been
released bringing a saving of £6m. Procurement savings contributed
£2m towards the target, the rest being saved on general administrative
expenditure including rationalisation of ONS's estate.
ONS's FTE baseline as of 1 April 2004 was 4,310.
Changes to the baseline are shown in Table 1.
| TABLE 1: ONS Baseline adjustments
| FTE posts
|
| 2004 Baseline | 4,310
|
Maternity Leave adjustment
(baseline mistakenly did not include staff on maternity leave as advised by the Cabinet Office guidelines)
| + 32 |
| Machinery of Government Changes
Government Actuaries Dept for ONS Centre for Demography
Cabinet Office for Civil Services Statistics
Government Actuaries Dept for Occupational Pensions Survey
|
+ 5
+ 7
+ 2
|
| |
| |
| |
| Controlled Expansions for new burdens
Extra posts for repayment work, migration task force and other new work
|
+ 45.5 |
| Revised Baseline | 4,401.5
|
Headcount reductions will contribute a large share
towards ONS's efficiency programme. However, many of the headcount
reductions will arise from efficiencies delivered towards the
end of the period of the Gershon efficiency programme so will
contribute little by way of cash savings within this period. Nevertheless,
they will generate savings in subsequent years that will release
resources for enhancing the statistical and registration work
programmes.
7. Evidence received by the Sub-Committee clearly
indicates that the ONS is an organisation under intense pressure.
That pressure arises from the combined effect of budgetary restraint,
the requirement to meet stretching efficiency targets for monetary
savings, headcount reductions and relocation, the ambitious modernisation
programme including re-engineering of the National Accounts, the
need to prepare for the 2011 Census and the preparations for legislative
change, including the creation of a new Statistics Board. (Paragraph 61)
8. The overall quality of staff of the ONS and
their commitment to maintaining the highest statistical standards
are not in doubt, but the combination of demands creates an exceptional
burden. The Treasury should therefore review the implementation
of the efficiency programme in the ONS or the resources allocated
to the department to achieve that implementation. (Paragraph 62)
The Government's response to these recommendations
also includes the response to Recommendations 10 and 25.
ONS welcomes the recognition of the challenges it
is facing. Many of these are challenges ONS has already been dealing
with for a number of years, or has faced in the past. It is important
that ONS meets these challenges while still focussing on its key
priority: that of producing official statistics. Over the past
year ONS published 100 per cent of market sensitive publications
on time and 99 per cent of other releases.
It is natural for those who rely on ONS outputs to
have concerns about the future and to voice those concerns, but
the fact of the matter is that there has been no drop in quality
of outputs. ONS still attracts praise for the quality of its work,
and is regarded throughout the world as an example of a quality
statistical office. Of course there will always be some problems:
statistics are estimates based on available information and there
is always scope for improvement. This is not an indication of
poor quality, but rather of the need to prioritise.
It is simply not possible to meet all demand for
statistics. The CSR provides a sound basis for ONS operations
but nevertheless it will be vital to set priorities, and cuts
to the programme have and probably will arise as a result of this
prioritisation. ONS is currently carrying out an extensive 3-phase
consultation exercise with external stakeholders in order to assess
priorities for its work programme over the period 2008-2012.
ONS is in the process of strengthening senior management
in Newport, recruiting two Directors General to support the National
Statistician, enabling her to take a full role in governance following
independence. The Statistics Board will inherit an organisation
that consistently meets its publication targets; is recognised
throughout the world as a producer of high quality outputs; is
responsive to the challenges it faces; and is well-placed to continue
delivering.
9. We have based our conclusions on the principle
that efficiency targets, and the budgetary provisions that partially
underpin them, should be open to revision in order to ensure the
maintenance of quality of service. (Paragraph 63)
HMT maintains regular dialogue with all departments
on their budgetary position and their delivery of key outputs
and outcomes. Departments are expected to live within the budget
allocated to them at the time of the relevant spending review
and to deliver the performance and reform targets they agree to,
including efficiency and relocation targets.
Where genuinely unforeseen and unexpected spending
pressures arise, there is the possibility of budgets being adjusted
in response. This is part of regular ongoing public spending management.
Similarly, where specific performance and delivery targets no
longer make sense (for example if there are significant Machinery
of Government changes to departments) then these can also be reviewed.
No department has had its efficiency and relocation
targets altered, other than to reflect Machinery of Government
changes, where there is no net effect on Government's overall
targets. Changes to departmental budget allocations, including
access to the reserve, are explained in Budget and Pre-Budget
Reports.
10. There is a disparity between progress by the
ONS towards its overall monetary target set as part of the efficiency
programme, in relation to which the ONS has reported significant
advances, and progress towards the relocation and headcount reduction
targets, which are far from being achieved. There is considerable
evidence that the relocation programme in particular poses risks
to the quality of statistics provided by the ONS. In addition,
we note admissions from the ONS and the Treasury that there have
been some shortfalls in the quality of the statistics produced
by the ONS. The Minister denied any direct linkage between the
problems with certain statistical series and the efficiency programme,
but one of the lessons of our inquiry has been the difficulty
of distinguishing the effects of the various factors exerting
pressure on the performance of the ONS. (Paragraph 64)
The Government's response to this recommendation
is included with the response to Recommendations 7 and 8 above.
11. Concerns about the programme for relocation
from London to Newport lie at the heart of worries within and
outside the ONS about its current and future operations. We have
already argued that the relocation programme was inadequately
planned. We recommend that, as a matter of urgency, the Treasury
review the case for, and the consequences of, the current relocation
programme of the ONS and the relationship between this and the
wider efficiency saving targets. To facilitate that review, we
further recommend that the business plans and cost-benefit analyses
prepared as part of the relocation programme be made available
to trade unions representing staff in the ONS to assist those
unions in making an informed contribution to the review. We would
also expect these documents to be made available to us. (Paragraph 65)
The relocation is well under way and recruitment
in Newport is going well. ONS has attracted many good-quality
senior staff from other Government Departments and the private
sector to Newport. ONS is in the process of strengthening senior
management in Newport, recruiting two Directors General to enable
the National Statistician to take a full role in governance following
independence.
Stopping the relocation programme midway, with work
areas split between sites and staff leaving London as planned,
would create uncertainty for staff, customers and the business
and would give rise to greater risks to quality of service.
ONS has engaged fully with both staff and unions
and shared information as its restructuring plans have been developed.
12. Our task in assessing the overall impact of
the efficiency programme in the ONS in the face of contested and
incompatible evidence has been rendered more difficult by the
absence of broadly supported and readily understood measurements
of quality of service. It seems ironic that the body charged with
maintaining the standard of national statistics is unable to satisfy
its users about its capacity to measure the quality of its own
products. We recommend that the ONS undertake consultations about
the formulation of agreed measurements of quality of outputs,
based wherever possible on existing Service Level Agreements,
which reflect the views and experience of users of those outputs,
with the aim of establishing measurements to serve as a baseline
for quality of service when new governance arrangements for statistics
are put in place in Spring 2008. (Paragraph 66)
While there are significant risks to the quality
of outputs, ONS has managed the risks effectively so far and,
as a result, its outputs have been delivered on time with no drop
in quality, and in some cases quality has increased. ONS regularly
monitors the quality of its outputs. As well as seeking feedback
from users, it provides quality analyses of its statistical releasesfor
example, all economic First Releases include general, generic
quality statements and analysis of revisions. ONS also monitors
the internal coherence of the national accounts estimates, their
coherence with other data sets and with external surveys and plans
to publish material on the quality of specific National Accounts
data sets early next year.
Some users have the perception that quality might
decrease in the future because of relocation. That perception
is seemingly based on the prospect of ONS losing the expertise
of staff who would not be relocating. The Government is confident
that ONS will deal with this loss of expertise through effective
management strategies, which will be adapted to changing circumstances.
Recruitment policy is particularly important, with, for example,
the relocation of National Accounts being phased over a longer
time-scale than other areas and retention allowances being offered
to National Accounts staff. This will allow time for expertise
to be built-up in the Newport office.
The Statistics Board will want to take up the question
of monitoring the quality of outputs, and ONS will continue to
work towards implementing improvements.
The efficiency programme in HMRC
13. In terms of the numbers reported, HMRC appears
to have made substantial progress towards its headcount target.
However, it is noted that HMRC has discounted, for the purposes
of its returns of headcount reductions, certain staff increases
which, in the opinion of the NAO, are integral to the efficiency
programme, and second, it has used a definition of "front-line"
posts of which the NAO is not fully persuaded, calls into question
the robustness of the figures. (Paragraph 73)
The Government is committed to robustness and transparency
in reporting progress of the Efficiency Programmea detailed
breakdown of progress was published alongside the Budget 2007,
and each department publishes information on all efficiency measures
in their Spring Reports and Autumn Performance Reports. The Government
notes that the NAO recognised that HMRC's reported headcount reductions
are robust in overall terms, but does not share the NAO's specific
concerns about the reporting of headcount reductions.
CONTROLLED EXPANSIONS FOR NEW POLICY BURDENS
The NAO expressed concern that the additional 1,325
staff recruited by HMRC to work in Contact Centres handling tax
credit claims should not have been treated as a new policy burden,
and excluded from the baseline for measuring headcount reductions.
The NAO considered that the recruitment of staff to work in Contact
Centres was a key part of the efficiency programme and was therefore
related to an existing policy.
The Government does not accept the NAO's view that
it was inappropriate to treat the controlled expansion of staff
in its Contact Centres as a new policy burden, nor that this means
that the headcount reductions reported by HMRC have been overstated.
As explained in HM Treasury's supplementary note
to the Committee in June 2007, Sir Peter Gershon's report in July
2004 recognised that the efficiency savings available from the
integration of Inland Revenue and HM Customs and Excise, along
with existing plans and proposed efficiency reforms, were on the
basis of existing policy commitments and spend to save packages.
In 2006, the Government agreedfollowing an
announcement of changes to the Government's policy on tax credits
in the 2005 Pre-Budget Reportthat HMRC should expand its
Contact Centre capacity by 1,325 posts to provide the improved
level of customer service required to meet this new policy burden.
These posts are effectively ring-fenced from the delivery and
calculation of efficiency gains, and are outside the scope of
HMRC's target to reduce net full-time equivalent staff in post
by 12,500 by 31 March 2008. (Indeed, the whole area of tax credit
work is not affected by staff reductions in HMRC.) To achieve
its target HMRC therefore has to reduce by a net 12,500 full-time
posts from other parts of the department. HMRC expects to exceed
this target.
REALLOCATIONS TO THE "FRONT-LINE"
The Treasury Sub-Committee reflected two concerns
expressed by the NAO about the robustness of the figures reported
by HMRC on reallocations, or redeployments, to the "front-line":
that "the reallocations reported by HMRC do not always reflect
actual staff in post"; and that "the reallocation data
includes projections of staff numbers rather than the actual number
employed in reallocated roles.
The Government believes that the NAO had misunderstood
HMRC's planning and reporting of reallocations. Departmental plans
project the number of reallocations into business areas as an
integral part of the overall planning process. These may not match
the final and actual staff-in-post figures, but it is only the
actual staff-in-post figure that is scored as a reallocation.
HMRC believes that overall they have the evidence, through activity
monitoring, to support this contention.
The NAO was also not persuaded of HMRC's definition
of a "front-line" post, though it is noted that the
NAO had pointed out to the Treasury Sub-Committee that "there
is no overall agreed definition of what constitutes a "front-line"
role".
Sir Peter Gershon's Report and HMRC's Spending Review
2004 settlement made it clear that the reallocation of posts is
designed to improve front-line services. Each department has been
required to determine a definition of reallocations appropriate
to its own business activities and circumstances, and HMRC agreed
with HM Treasury a programme of reallocations to front-line areas
covering clearly identified business strategies and initiatives.
These include: VAT Compliance Strategy; Spend-to-Raise; Project
Cyclamen (a counter terrorist initiative to detect and deter the
illicit importation of radioactive materials entering the UK);
Construction Industry Scheme; and other strategies, for example,
to combat smuggling.
In its written evidence to the Treasury Sub-Committee,
the NAO drew comparison between the Department for Work and Pensions'
definition of the front line, as constituting certain customer-facing
positions, and HMRC defining its front line with reference to
certain business units. The NAO also noted that HMRC's practice
on reallocations differed from DWP by including managers, administrative
support and IT staff.
The Government considers that the best way for HMRC
to conduct its wide ranging business portfolio is to continue
to better target and focus resources, including greater reliance
on improved intelligence and risk assessments to, for example,
ensure the right amount of tax is collected. Posts reallocated
into such activities will invariably not have direct contact with
its customers, but provide an essential ingredient in developing
a modernised tax collection system to help ensure society's financial
wellbeing. Reallocations made include some managers, analysts,
risk and intelligence officers, administrative support and IT
staff, working directly on agreed initiatives, whose work is necessary
to make best use of deploying limited resources and to increase
HMRC's front-line effectiveness.
14. Not all of the information provided to the
Sub-Committee in the course of its inquiry about the overall monetary
savings by HMRC and the contribution of headcount reductions to
those savings is clear. The Sub-Committee's work was made more
difficult by the provision of substantive information after it
had concluded taking oral evidence. We recommend that, in its
response to this Report, the Government provide coherent and comprehensible
answers to the following questions
i. Are any of the financial savings from headcount
reductions in 200405 being counted towards achievement of
the overall monetary target of £507 million, and what is
the rationale for the statistical treatment?
ii. Are the 1,982 post reductions taking place
in 200405 which it was not originally assumed would be taking
place in that financial year treated differently for the purposes
of calculating performance against the monetary savings target
from the 1,610 posts that were planned to be saved in 200405
and, if so, for what reason?
In its Spending Review 2004 settlement, HMRC was
set an efficiency target to reduce by 16,000 full-time equivalent
posts over the 4 years 1 April 2004 to 31 March 2008, and to redeploy
3,500 of these to additional front-line posts.
HMRC was also set an SR04 financial savings target
to be in a position to deliver at least £507 million in annual
efficiencies, of which at least half must be cash releasing, on
the basis of gross staffing reductions and non headcount savings
measured over the 3 years 1 April 2005 to 31 March 2008.
Therefore, none of the financial savings from the
3,592 gross headcount reductions in 2004-05 count towards achievement
of HMRC's overall monetary target of £507 million, although
in practice HMRC will have benefited from any savings made in
that year.
iii. Are HMRC's new plans to achieve a gross
reduction of more than 16,000 posts by the end of 2007-08 related
to the treatment of headcount figures for the purposes of calculating
performance against the monetary efficiency target?
HMRC's revised workforce plans are not required in
order to achieve the financial target. On current forecasts the
Government expects HMRC to exceed its £507 million financial
savings target through increased financial savings from non-headcount
sources, in particular procurement.
However, HMRC's planning round 200708 identified
opportunities to go beyond the SR04 12,500 net post savings by
the end of 200708 through efficiency savings created by
the Departmental Transformation Programme. This will put HMRC
in a good position to meet the challenges of CSR07.
The additional posts to be saved in 200708
will form part of HMRC's announced CSR07 plans to save a further
12,500 posts by 31 March 2011 in addition to the original 12,500
target for SR04 (i.e. around 25,000 total net posts by 31 March
2011).
iv. Does the methodology used for calculating
the monetary value of headcount reductions for the purpose of
measuring progress against the monetary efficiency target in the
case of HMRC differ from that used in the case of any other departments
and, if so, why?
Departments are using different methods to calculate
efficiency savings from headcount reductions, depending on their
circumstances. Where HR systems allow, a post-by-post calculation
is made based on actual pay. Where workforce reductions are too
numerous and complex to make this practical (as in the case of
HMRC) they are done on a weighted average cost. This average is
subjected to monitoring and review to ensure that it is a robust
reflection of actual costs.
v. What is the Government's latest estimate
of the net monetary value of headcount reductions in HMRC (a)
at the end of December 2006, (b) at the end of March 2007, (c)
at the end of March 2008, and (d) at the conclusion of the efficiency
programme, for the purposes of calculating performance against
the monetary efficiency target?
HMRC has counted its efficiency savings in gross
terms in accordance with the basis on which targets were set in
SR04. Table 2 provides gross financial savings associated with
headcount reductions and also provides the non-headcount financial
savings. This shows that the Department expects to exceed its
£507 million monetary efficiency target.
| Table 2: Monetary value of headcount and non headcount reductions in HMRC
|
| | 31 Dec 2006
| 31 Mar 2007
| 31 Mar 2008
(estimated)
| Estimated full year 2008-09 value of savings towards SR04 £507m total monetary savings target
|
| Monetary Value of headcount reductions in HMRC
| £156,041,279 | £194,437,930
| £359,998,587 | £394,914,058
|
| Monetary Value of non headcount savings in HMRC
| £99,133,197 | £116,145,825
| £200,556,833 | £208,450,294
|
| TOTAL | £255,174,476
| £310,583,755 | £560,555,420
| £603,364,352 |
15. We recommend that the Government, in its response
to this Report, indicate the extent of income received by HMRC
as a result of sub-letting and clarify whether such income can
be scored as efficiency savings for the purposes of the Gershon
programme. We further recommend that the Government state in its
response whether it is satisfied that the STEPS PFI contract has
not acted as a constraint upon the capacity of HMRC to obtain
savings through estates rationalisation. (Paragraph 83)
Approximately 9.5 per cent of the HMRC estate not
required by the Department is occupied by other Government Departments
(OGDs), who pay estates running costs on a pro rata basis. The
income received from existing OGD sub-let agreements, known as
MOTOs (Memorandum of Terms of Occupancy), is not included in the
estates contribution to HMRC efficiency targets. As part of the
Estate Consolidation Programme and in support of the wider Government
agenda on property management, HMRC is seeking new opportunities
for OGDs to backfill additional space no longer needed by the
Department. Where agreement is reached and new MOTOs are signed,
the income received will qualify for scoring as efficiency savings
as set out in the following example:
- HMRC occupies a three-storey
office at a cost of £1.2 million per annum. An OGD occupies
another building in the same town at £0.5 million per
annum. The lease on this building is about to expire. Total Exchequer
cost = £1.7 million per annum.
- HMRC does not fully utilise its office as a result
of staff efficiencies and agrees to consolidate its activities
on two floors of its office in order that the top floor can be
sub-let to the OGD at a pro rata cost of £0.4 million
per annum.
- The OGD moves into the HMRC office and ceases
to pay for its former building. The HMRC net liability for its
office is now £0.8 million per annum as it is receiving
£0.4 million from the OGD.
- The overall Exchequer cost has reduced from £1.7 million
to £1.2 million per annum, saving £0.5 million.
The saving is scored as £0.4 million by HMRC and £0.1 million
by the OGD in keeping with the change to their respective estate
outgoings.
In the event that agreement with an OGD cannot be
reached or there is no OGD interest in taking surplus space on
the HMRC estate, in the majority of cases the surplus will be
returned to Mapeley under the STEPS contractual vacation allowances.
It makes sense to augment these allowances by sub-letting to OGDs
where possible. If HMRC did not include new MOTO agreement income
as efficiency savings, there would be a clear incentive to move
straight to disposing of surplus space to Mapeley to support the
Department's efficiency programme, rather than sub-let to other
Government bodies, reducing the opportunity for the wider Exchequer
benefits.
The Government is satisfied that HMRC's STEPS PFI
contract does not impose a constraint on the capacity of HMRC
to deliver estates efficiencies. The flexibility allowances within
the STEPS contract enable HMRC to deliver up to £100 million
in annual estate running cost savings by 31 March 2011.
The NAO report PFI: The STEPS Deal, published
on 7 May 2004 explains, in Part 1 para 7, the application of nil
cost vacation arrangements under the three designation headings
of "Core", "Flexible" and "Intermediate".
Approximately 70 per cent of the STEPS estate is designated as
"Core", but that does not mean that it cannot be vacated
within the agreed allowances at nil or small cost.
The STEPS contract flexibility has allowed HMRC the
opportunity to tailor its estate portfolio to meet the best combination
of customer need, operational priorities and HR responsibilities
by surrendering space where and when it suits the Department to
do so. Without the STEPS contract, HMRC's capacity for estate
rationalisation would have been constrained by and limited to
the terms of its legacy property leases. For example, buildings
would have been vacated at fixed lease break or end dates, regardless
of the fit with business needs. HMRC would also have been liable
for exit costs and additional staff costs to manage any protracted
negotiations surrounding dilapidation costs.
16. Evidence received by the Sub-Committee shows
that the indicators used by HMRC to measure the quality of its
services are not adequate to assess the experience of service
users, and in particular are not adequate to measure the extent
to which its services meet the very diverse needs of its different
client groups, including both taxpayers and tax credit claimants.
(Paragraph 109)
The Government accepts fully the importance of ensuring
that efficiency savings are not delivered at the expense of impacting
on service delivery. Within the Spending Review Efficiency Programme,
HM Treasury agreed with HMRC a basket of 12 specific measures
drawn from indicators which underpin its PSA targets which monitor
service quality. These quality measures were selected as being
the key performance indicators from areas within the Department
most affected by headcount reductions, for example, processing,
compliance, debt management and banking and customer contact,
which accounts for more than 90 per cent of the headcount reduction.
The NAO recognised in their recent report on the
Efficiency Programme (February 2007) that where HMRC's headcount
reductions are being made performance has not been adversely affected,
and in some areas performance has improved substantially. Furthermore,
the Adjudicator for HMRC (Dame Barbara Mills) says in her 2006-07
Annual Report that there is nothing to suggest that the merger
of the two former revenue departments (one of the key drivers
of efficiency) has so far had a negative impact on HMRC customers.
If HMRC used wider measures of customer satisfaction,
it would make it more difficult to isolate the impact of the efficiency
programme from the range of other factors influencing satisfaction
levels. It is important to note that tax credit administration
has not been affected by HMRC's headcount reductions. Indeed,
there are now more staff working on tax credits than there were
in 2004, and contact centre capacity has been expanded by 1,325
posts to provide an improved level of customer service.
HMRC has also established a Departmental Transformation
Programme, which will manage investment of over £1 billion
between 2007-08 and 2010-11 to deliver further efficiencies, increase
revenue yield, and take forward the Department's ambition to achieve
greater customer focus.
17. We recommend that HMRC accord high priority
to the preparation, in consultation with users of its services,
of measures of service quality which properly capture the experience
and needs of users, identifying separately those of taxpayers
and tax credit claimants. Such measures, when finalised, should
be used not only in monitoring the efficiency programme, but also
in making policy relating to HMRC servicesfor example,
to assist in formulating decisions relating to the geographical
location of offices and to the form in which services are offered.
We expect HMRC to ensure that there is proper consultation with
users and with the NAO in formulating appropriate measures. Subsequent
performance against the measures should be subject to consistent
methods of measurement and regular publication. Furthermore, in
order to underpin public and parliamentary confidence in these
measures, we recommend that they be subject to external validation,
in addition to the scrutiny work already undertaken in the course
of the NAO's regular programme. (Paragraph 110)
HMRC's extensive consultations have fed directly
into the development of the Department's CSR07 Departmental Strategic
Objective to "Improve customers' experience of HMRC and improve
the UK business environment".
CUSTOMER EXPERIENCE STANDARD
Drawing on existing knowledge and research carried
out by the legacy departments, and in consultation with business
customers, agents and advisers, HMRC has drawn up a standard to
describe the experience that customers should expect when interacting
with the department:
- I know what I have to do
- I feel you make it easy
- I can contact you easily and get the answers
I need
- I can rely on you to get it right and am confident
I have got it right
- I feel well treated
- I can rely on you to make sure individuals and
businesses keep to the rules
HMRC uses this standard when designing new products,
processes and services to keep the designers focussed on the needs
of customers and has developed a toolkit to help those designing
new policies, processes and systems to do so in a more customer
focused way.
These customer statements will also form the core
of a new quarterly customer survey that will be used as part of
HMRC's assessment against its customer experience objectives,
replacing the current survey-based measures.
In addition, HMRC is also committed to meeting specific
targets to reduce the administrative burdens of the tax system,
based on research undertaken in 2005 with business customers:
- reduce the administrative burdens
on business of dealing with HMRC forms and returns by at least
10 per cent over 5 years;
- reduce the administrative burden on business
of dealing with HMRC's audits and inspections, by 10 per cent
over three years and at least 15 per cent over five years.
The implementation of the recommendations in Sir
David Varney's 2006 Review of links with large business also
forms part of this objective. Key recommendations concerned large
businesses' need for certainty and consistency in their dealings
with HMRC, which have led to HMRC planning to do more work with
large businesses before they submit their tax returns, including
the provision of "rulings" on significant transactions.
The efficiency programme in the Chancellor's other
departments
18. We recommend that, in its response to this
Report, the Government clarify whether there is any scope for
monetary efficiency savings from expenditure by the Treasury outside
its administration budget and, if so, how such savings would be
recorded. (Paragraph 116)
The main focus of the Treasury's efficiency plans
is its administration budget. This is the largest part of the
budget and is where costs are most controllable, and therefore
where the biggest potential efficiencies exist. However, the Treasury's
efficiency plans and recorded progress do also include its programme
budget.
The two main elements of the Treasury's near cash
programme budget are the supply of UK circulating coinage by the
Royal Mint and the management of the UK's foreign exchange reserves
by the Bank of England, both under service level agreements with
the Treasury. The Treasury is aiming to achieve value for money
in its negotiations of new service level agreements with the Mint
and the Bank. Until those negotiations are concluded the Treasury
will be cautious on the value of efficiency gains recorded from
the programme budget.
Efficiencies are measured as the change in the real
terms cost of output. In the case of coinage, the total cost to
the Treasury is made up of manufacturing costs and distribution
costs, at set prices per unit, and metal costs, at the market
prices borne by the Mint. Together with the Mint, the Treasury
is aiming to achieve efficiencies on the manufacturing and distribution
costs. Changes in the market price of metal are uncontrollable
and do not represent efficiency gains or losses.
Because the Treasury' capital budget is very small,
the department does not record capital efficiencies, although
efficiencies in capital spend are being realised from broader
improvements in procurement practice.
19. We recommend that the Government, in its response
to this Report, set out how the OGC's monetary savings baseline
is calculated and how the OGC, OGCbuying.solutions and the Treasury
contribute to achievement of the relocation targets. (Paragraph 120)
OGC's internal efficiency programme consists of several
workstreams to generate efficiency savings. The baseline cost
used to measure monetary savings in each workstream is the cost
before efficiency savings initiatives in the workstream. The saving
is the cost after the efficiency activity compared with the baseline
cost. The principal baseline year is 2003-04 as most efficiency
activity in the workstreams started in 2004-05; however, some
efficiency initiatives started after 2004-05 and baselines for
those were therefore 2004-05 costs.
In response to the Lyons review, OGC has relocated
10 posts from London to Norwich, of which 5 have subsequently
become part of Group Shared Services. With the launch of Transforming
Government Procurement, OGC has undertaken a programme of
restructuring, with consequent staff reductions leading to a workforce
target of 250 by April 2008. In keeping with the aspirations of
the original relocation targets, our policy for the location of
posts in the new OGC is to consider the business need of the location
of individual posts, market availability and value for money.
Core Treasury has transferred 5 posts, as part of
the Group Shared Services programme from London to Norwich. OGCbuying.solutions
has relocated 22 posts from London. The posts have been transferred
to Liverpool (15 posts) and Norwich (7 posts).
20. There is a risk that the practice of excluding
certain categories of staff increases from calculations of headcount
reductions for the purposes of the efficiency programme detracts
from the overall credibility of the headcount statistics. We recommend
that the Government explain the rationale for the exclusion of
increases in the staffing of OGCbuying.solutions more fully in
its response to this Report. (Paragraph 121)
OGCbuying.solutions is
excluded from the calculations for headcount reductions because
of its Trading Fund status and role as an enabler of wider efficiency
savings across government. A headcount reduction target would
have had a perverse impact on government's ability to achieve
these wider savings, so OGCbuying.solutions agreed targets
for financial efficiencies and relocation that contribute directly
to the overall targets for the Chancellor's departments. The Treasury
Group has agreed a headcount reduction target of 150 in support
of its overall efficiency targets, and this is being met by HM
Treasury. OGCbuying.solutions is entirely responsible for
generating sufficient sales income to cover its costs and generate
a 6.5 per cent Return on Capital Employed. Since its formation
in 2001 from a number of smaller procurement organisations, OGCbuying.solutions
has more than tripled its procurement influence in Government
and the wider public sector, consistently delivering 25 per cent
year on year growth in terms of savings, which has been in excess
of its ministerial targets. Following the publication of the Treasury
report 'Transforming Government Procurement' (January 2007),
OGCbuying.solutions is seen as a key player to help both
Government and the wider public sector enjoy even more efficiency
savings through its approach to collaborative procurement.
Efficiency and the 2007 Comprehensive Spending
Review
21. We recommend that, in advance of the announcement
of the outcome of the Comprehensive Spending Review, the Government
clarify how it intends to monitor the reporting of efficiency
gains by departments such as HMRC, the Treasury and the GAD that
will be required to make monetary savings beyond the efficiency
target. (Paragraph 126)
The current Efficiency Programme has demonstrated
the importance of public accountability as a powerful driver for
improved value for money. In the CSR07 period departments will
therefore continue to measure and monitor their savings against
departmental targets and report them in public so that they can
be held to account for any gains claimed. Reflecting the higher
level of ambition in the CSR07 programme, the new monitoring and
reporting framework will put more emphasis on mainstreaming value
for money into core departmental business, including through stronger
integration with the PSA framework. Greater accountability will
therefore be devolved to departments, with common requirements
for reporting progress to the public to ensure rigour and consistency.
The Government also expects that the National Audit Office will
play an important role in reviewing reported savings, providing
Parliament and the public with a further level of assurance.
22. The apparent centrality of further headcount
reductions to HMRC's budgetary plans for the period from 200809
to 201011 is an understandable source of concern to staff,
and carries with it potential risks to the quality of service
provided by HMRC. We recommend that the Government clarify whether
the possibility that HMRC might exceed its headcount reduction
target of 12,500 before 1 April 2008 affects HMRC's
assessment of the scope for further reductions thereafter. We
further recommend that HMRC prepare plans for budgetary savings
from 200809 onwards which are transparent about the overall
budgetary savings from headcount reductions on the same basis
as for other planned measures. (Paragraph 131)
HMRC's budgets for 2008-09 to 2010-11 reflect a year
on year reduction of 5 per cent in real terms, as required by
its early CSR07 settlement. To make the necessary savings across
the CSR07 period it is inevitable that levels of staffing will
need to be reduced, as paybill makes up some 60 per cent of the
Department's total budget. HMRC will also look to achieve savings
within other operating costs, such as Estates, Information Technology
and procurement of goods and services. If HMRC exceeds its SR04
efficiency target of reducing by 12,500 Full Time Equivalent staff-in-post
before 1 April 2008, any additional or early savings
will be taken into account when setting the plans for the further
savings required in the CSR07 period. Any potential risks to the
quality of service provided will be mitigated by enabling the
staffing reductions through the Departmental Transformation Programme
(DTP). The DTP represents a major investment designed to transform
Departmental processes, reduce workloads, improve the customer
experience, and deliver productivity and value for money benefits.
HMRC is in the process of preparing plans for budgetary
savings from 2008-09 onwards, covering both headcount reductions
and other expenditure. These will be transparent, and, in line
with Treasury guidance, will be published by the end of the year.
23. Earlier in this Report, we examined the challenges
associated with the efficiency programme for the ONS and recommended
that the relocation programme in particular be subject to review.
Responsibility for matters which are currently within the control
of the ONS will pass to the new Statistics Board from April 2008
onwards. We consider it essential that the new independent Board
is given the authority to make all dispositions within its budgetary
settlement. It would be inappropriate for the Treasury to seek
to apply any explicit efficiency or relocation targets which relate
to the period beyond 1 April 2008, and we recommend
that the Treasury make a clear public statement to that effect
at the earliest opportunity, as well as detailing how it will
ensure a smooth transition for financial planning and staffing.
(Paragraph 134)
Planning for the period post-April 2008 has always
taken into account the fact that responsibility for ONS will then
fall to the Statistics Board and decisions on the future of ONS
will be taken by the Board. It will be for the Board to decide
how to distribute and allocate resources, within the limits of
the CSR. It is anticipated that the Board will formally assume
these responsibilities at the start of April 2008, following enactment
of the relevant parts of the Statistics Act. However, the Chair
designate, Sir Michael Scholar, has already been appointed and
is being kept informed on these matters. ONS has existing targets
like all Departments and a comprehensive plan for getting there.
For now, those plans stand.
The Committee's conclusions
24. We accept the complexity of the process which
led to the establishment of targets as part of the efficiency
programme. We welcome evidence that the Government Actuary's Department,
the Debt Management Office, the Office of Government Commerce
and the Treasury seem set to exceed their efficiency targets.
However, if the Treasury is examining why some targets have been
exceeded as part of what Mr Macpherson termed "a learning
process", it follows logically that the Treasury should also
examine the lessons of targets which may prove to have been over-ambitious.
(Paragraph 136)
The SR04 Efficiency Programme remains on course to
achieve its overall efficiency and workforce reduction targets,
alongside overachievement by many departments, including HMT,
OGC, DMO and GAD. HMT and OGC have been working closely with departments
from the beginning of the programme to monitor progress against
targets and assess the impact of the programme. This has informed
the preparatory work for the forthcoming CSR.
HMT has already set out its value for money ambitions
for departments in the forthcoming CSR period, building on the
success of the SR04 programme. Departments have agreed to identify
annual net, cash-releasing savings equivalent to at least three
per cent of their baseline spend by 201011, as well as significant
real terms reduction in administration budgets.
25. In determining how the efficiency programme
would apply to the Chancellor's departments as a group, we are
concerned about the differential impact on those departments.
In the case of the ONS, the organisation is facing a range of
pressures. Unless action is taken to alleviate some of those pressures,
there is a significant risk that the new Statistics Board will
inherit an organisation which is unable to perform its tasks to
the necessary standard because of structural weaknesses. In the
case of HMRC, the success of that organisation in meeting its
efficiency targets is highly dependent upon further headcount
reductions. The role played by financial savings arising from
headcount reductions within HMRC's efficiency programme appears
to be greater than is warranted by the overalland commendableambition
to modernise that organisation and its capacity to serve taxpayers
and claimants effectively, efficiently and economically. (Paragraph 137)
In respect of ONS, the Government's response to this
recommendation is included with the response to Recommendations
7 and 8 above.
As also noted above (in response to Recommendation
22), headcount reductions in HMRC will be facilitated and enabled
by the implementation of the Departmental Transformation Programme.
This will support the Department's aim of delivering value for
money through improving operational and organisational productivity
and capability, as well as providing a modern and improved service
to its customers. In planning to make savings HMRC does and will
look at non-headcount budgets. Some of these involve contractual
commitments (which of themselves have delivered improved VFM)
or are essential for operational delivery. Although plans have
yet to be finalised it is likely that over one third of the savings
required during the CSR07 period will come from non-headcount
budgets.
26. Significant financial savings have been reported
as a result of the efficiency programme in the Chancellor's departments.
The programme has imposed new disciplines upon management and
encouraged new approaches towards securing value for money. It
has paved the way for a substantially more ambitious efficiency
project in the spending period covered by the 2007 Comprehensive
Spending Review. The challenge now for the Treasury is to ensure
that the benefits of the programme in the Chancellor's departments,
and confidence in the value of the programme among staff and customers,
are consolidated. (Paragraph 138)
The Government welcomes the Committee's recognition
that the Efficiency Programme has secured new disciplines and
approaches towards securing value for money. Departments will
continue to implement their SR04 Efficiency Programme in the remaining
months of the SR04 period.
HM Treasury is seeking to build on the success
of the SR04 Efficiency Programme in the CSR period. Departments
have already agreed to significant further cash-releasing savings,
including reductions in administration budgets. All of the Chancellor's
Departments (other than ONS) agreed an early settlement with HM Treasury
that will see their budget decline by 5 per cent a year in real
terms over the CSR period. This will consolidate the existing
efficiency reforms, and ensure these departments go further in
becoming even more cost effective.
|