1 The increasing cost of hosting the
Olympic and Paralympic Games
1. On 15 March 2007 the Department for Culture, Media
and Sport announced a budget of £9.325 billion for the London
2012 Olympic and Paralympic Games. The announcement came twenty
months after London was awarded the Games and just ten days after
this Committee's previous hearing on preparations for the Games,
at which we expressed concern about the continuing absence of
an agreed budget for the Games.[2]
2. The revised budget does not represent the full
cost of preparing for and staging the Games, but represents the
cost to the public sector of building the venues and infrastructure
required to host the Games, as well as policing and wider security.
It excludes expenditure of £650 million by the London Development
Agency to acquire the land for the Olympic Park, the private sector's
contribution to the costs of the Olympic Village (which is still
being negotiated), and planned expenditure of some £2 billion
on staging costs. The London Organising Committee of the Olympic
Games and Paralympic Games (LOCOG), the organisation responsible
for staging the Games, is intended to be self-financing.[3]
3. The budget also excludes the costs of staff in
government organisations carrying out Olympic related work (including
the Government Olympic Executive set up to manage and co-ordinate
the Government's interest in the Games), and the costs of improving
wider transport links in London. These activities are essential
to the delivery of a successful Games. Expenditure incurred by
the public sector on improving transport links around London may
be brought forward or be higher than it would otherwise have been
without the Games.[4]
4. The cost estimate of £9.325 billion is £5.289
billion higher than the estimate of just over £4 billion
at the time of the bid to host the Games. The increase is mostly
accounted for by new provisions totalling £4.3 billion for
programme contingency, tax and security, and by the increase of
over £1.1 billion in core Olympic costs (Figure 1).
Following our hearing, the Olympics Minister made a further announcement
on 10 December 2007, confirming the high level breakdown of cost
estimates announced in March 2007.[5]Figure
1: Summary of the differences between the March 2007 budget and
the cost estimates at the time of the bid
| Costs and provisions
| March 2007 Budget
(£million)
| The estimates at the time of the November 2004 bid (£million)
| Difference
(£million)
|
| Olympic Delivery Authority budget:
| | | |
| Core Olympic Costs
| 3,081
| 1,966
| 1,115
|
| Infrastructure and regeneration
| 1,673
| 1,684
| (11)
|
| Contingency
| 500
| No estimate included
| 500
|
| Sub-total (Note)
| 5,254
| 3,650
| 1,604
|
| Other (non-ODA) Olympic
| 388
| 386
| 2
|
| Other provisions
| | | |
| Policing and wider security
| 600
| No estimate included
| 600
|
| Tax (Note)
| 836
| No estimate included
| 836
|
| Programme contingency
| 2,247
| No estimate included
| 2,247
|
| Sub-total
| 3,683
| | 3,683
|
| TOTAL
| 9,325
| 4,036
| 5,289
|
Note: The Minister's
announcement on 10 December increased the ODA's pre-tax budget
by £43 million to £5.297 billion, with an equivalent
decrease in the tax provision to £793 million.
Source: C&AG's report: The budget for the
London 2012 Olympic and Paralympic Games, HC612 (2006-07)
5. Asked whether it had deliberately excluded costs
from the bid to help win the Games, the Department said the bid
estimates had been prepared at a time when it was not certain
that the Games would be awarded to London, the land was not in
public ownership and detailed plans for the venues had not been
drawn up. Some costs had not been included because of significant
uncertainties, but the bid was the best estimate at the time and
there had been no intention to deceive.[6]
6. The largest single increase was the £2,747
million provision for programme contingency. An initial allocation
of £500 million had been made to the Olympic Delivery Authority
at the time of the budget announcement in March to meet known
financial pressures on the construction of venues and infrastructure.
This allocation left £2,247 million to cover factors such
as changes in statutory requirements (for example, environmental
protection and health and safety), unforeseen ground conditions
and potential increases in the cost of security and construction.[7]
7. HM Treasury guidance recommends that budgets for
major projects include a contingency to allow for optimism bias,
the tendency for the costs of projects to be underestimated. This
contingency should reflect a realistic assessment of the risks
of additional costs, but not be so generous as to undermine the
need for costs to be kept under control. Estimates at the time
of the bid included contingency provision for individual projects,
ranging from 10 to 23.5%. There was, however, no contingency for
the delivery programme as a whole, despite HM Treasury having
been consulted and the bid agreed across Government. The Department
said that before the bid, the size, scale and complexity of what
was to be delivered, as well as the need for this scale of programme
contingency, had not been fully appreciated.[8]
8. Following a detailed and quantified risk analysis,
the Department and the Olympic Delivery Authority considered that
the level of programme contingency was now prudent and realistic.
The biggest risk was the immovable deadline, and to avoid cost
escalation at the end of the programme it was essential to do
as much work as possible early on. The Delivery Authority said
good progress had been made, with some £600 million of the
budget now committed to major projects, but construction price
inflation remains a significant risk given the existence of other
major construction projects and the high demand for skilled labour.
In the Department's view, the only safe assumption was that all
of the contingency would be used.[9]
9. Provision for tax costs was omitted from the original
bid estimate because at that time the delivery arrangements for
the Games, and thus the tax implications, were unclear. Following
HM Treasury confirmation that the Olympic Delivery Authority would
be unable to reclaim VAT, tax liabilities of £1,173 million
were included in the March 2007 budget (£836 million included
in Figure 1 above, plus £337 million within the programme
contingency).[10]
10. The original bid estimate included £190
million for site security during construction, which increased
to £268 million in the March 2007 budget. The March 2007
budget, however, provided an additional £600 million for
policing and wider security, tasks shared between a number of
bodies including the Home Office, Metropolitan Police, regional
police forces and the emergency services. The Home Secretary is
in overall charge of security for the Games and has appointed
an Assistant Commissioner of the Metropolitan Police as the Olympic
Security Co-ordinator, supported by the Olympic Security Directorate.[11]
11. The figure of £600 million was a preliminary
estimate pending development of the detailed plan for security,
and a further £238 million was included within the programme
contingency. The Department confirmed that it had been consulted
on the Government's plans, announced on the day of the Committee's
hearing, for improving security precautions more generally in
the UK (for example, restrictions on car access and checks at
railway stations), and that the programme contingency was designed,
amongst other things, to cover the impacts of regulatory changes.[12]
12. The other main change from the estimates at the
time of the bid to host the Games was the £1.1 billion increase
in the core Olympic costs. This area of costs included venues,
those transport projects to which the Olympic Delivery Authority
was contributing, site security and programme management. More
than half the increase, from £16 million to £570 million,
was for the Olympic Delivery Authority's programme management
costs, including the cost of its delivery partner, CLM. The Department
had modelled the original estimate on an urban development corporation
and prepared it before setting up of the Olympic Delivery Authority.
The Delivery Authority had since commissioned an external review
of its delivery partner's costs, and considered them realistic
compared with other major infrastructure projects.[13]
2 C&AG's Report, para 2; Committee of Public Accounts,
Thirty-ninth Report of Session 2006-07, Preparations for the
London 2012 Olympic and Paralympic Games-Risk assessment and management,
HC 377 Back
3
C&AG's Report, paras 3, 49, 73; Figures 5 and 6 Back
4
C&AG's Report, para 49; Figure 5; C&AG's previous report,
Session 2006-07, Preparations for the London 2012 Olympic and
Paralympic Games-Risk assessment and management, HC 252, para
75 Back
5
C&AG's Report, paras 7, 36; Figure 6; HC Deb, 10 December
2007, cols 9WS-14WS Back
6
Qq 4-6, 138-139 Back
7
C&AG's Report, Figures 6 and 7 Back
8
Qq 140, 163-166, 175-180; C&AG's Report, paras 60-62 Back
9
Qq 7-10, 92-93, 119, 131, 133, 146 Back
10
Qq 2, 142; C&AG's Report, para 6; Figures 6 and 7 Back
11
Qq 76, 182-184,; C&AG's Report, para 59; Figures 6 and 7.
The Olympic Security Directorate, led by the Assistant Commissioner
of the Metropolitan Police, comprises members from the regional
police forces and the emergency services. Back
12
Qq 75, 116; C&AG's Report, para 59; Treasury Minute on the
Thirty Ninth Report from the Committee of Public Accounts 2006-07;
http://security.homeoffice.gov.uk/news-publications/news-speeches/PM-security-speech Back
13
Qq 13, 90-91, 121; C&AG's Report, Figures 6 and 7; CLM is
a consortium of three companies - CH2M Hill, Laing O'Rourke and
Mace Back
|