Examination of Witnesses (Questions 80-99)
14 NOVEMBER 2007
DEPARTMENT FOR
CULTURE, MEDIA
AND SPORT
AND OLYMPIC
DELIVERY AUTHORITY
Q80 Mr Bacon: I would like to move on
to insurance which, for something like this, is going to be quite
a significant item. How much do you reckon it is going to be for
insurance roughly?
Mr Higgins: We have allowed roughly
£50 million.
Q81 Mr Bacon: So that leaves you
£175 million for the Olympic Village, does it not, roughly?
Mr Higgins: I am not sure. How
did you work that out?
Q82 Mr Bacon: Well, if you look at
paragraph 48, you will see that it is £161 million for additional
inflation. Have I got that right? Yes, I have. On page 21, £161
million for additional inflation. If you then go to Figure 6,
you will see that figure of £386 million, the third one down,
and it says, "Additional inflation allowance, contribution
to the Olympic Village and insurance". Well, if you knock
off the additional inflation that we know about, £161 million,
that only leaves you £225 and, if you knock off £50
million, that leaves you £175 million for the Olympic Village.
Is that correct? Have I got something wrong?
Mr Higgins: No, that is about
right. That is about the right figure for the Olympic Village
at that point, yes.
Q83 Mr Bacon: Which works out at
about £10,000 or £10,294, in this little spreadsheet
I have got here anyway, per bed in the Olympic Village, does it
not?
Mr Higgins: I think it is probably
inaccurate to take that figure
Q84 Mr Bacon: Because it is only
the public sector contribution, I appreciate that. How many dwellings
are there going to be in the Olympic Village?
Mr Higgins: Roughly 4,000.
Q85 Mr Bacon: And your actual expectation
is that they will pretty much all be sold off as private dwellings
afterwards or a mixture of affordable and private, but that they
will all be used afterwards for dwellings?
Mr Higgins: Absolutely, and 30%
are affordable and that is set out in the planning approval.
Q86 Mr Bacon: Could I ask you about
the legacy because the Chairman mentioned the drop in funding
from £738 million down to £165 million. It seems to
me that one of the reasons why the private sector has not been
throwing money at you is because there is still an enormous amount
of uncertainty about who will own the venues afterwards and who
will cover the conversion costs before the legacy, as it were,
can take effect. When do you think you will have more certainty
about all of that?
Mr Higgins: Progressively, we
are getting much more certainty about the legacy. In terms of
the private sector contribution, the two major items making up
this revised figure are for the broadcast facilities, both the
media and broadcast, and the figure is roughly around £90
million and we have got every expectation of getting a good contribution
from the remaining tenderers on that part there. Then, the second
part of that element is utilities and again we have had a very
good response from the private sector for a substantial contribution
to the utilities network and the power centre that is going to
be built up on the Olympic site, so that is strong. The private
sector contribution on the Village, as this Report notes here,
there is some £600 million in the 2004 costs for the costs
of the Village and we expect the vast majority, or all of that,
to be paid by a private sector partner.
Q87 Mr Bacon: And you expect that
it will yield a substantial profit overall, the Village site?
Mr Higgins: Yes, yes, it will.
Q88 Mr Bacon: How will that be shared?
Presumably, the Lottery, which is putting a lot of money into
this, over £2 billion, will be getting something back, will
it?
Mr Higgins: The agreement on the
London Development Agency's land allows the Lottery to recoup
profits after the LDA's costs, and you will see that is covered
in the Report here. On the balance of the land, we have allowed
for recovery of some profit from the Village and we are still
finalising the Village details, we have not released the complete
details of that, but, if there is surplus profit that comes through
from those deals, they obviously will be for the benefit of the
funders of the Games, which include of course the Lottery.
Q89 Mr Bacon: Will that put them,
as it were, pari passu to their original contribution?
Is that the idea?
Mr Higgins: No doubt it will reflect
their contribution when their contribution is finalised on what
parts goes to the overall funding and contingency.
Q90 Mr Bacon: I would just like to
ask one final question about programme management costs. The Chairman
referred to how they have exploded from £16 million to £570
million which is plainly just a failure to get a grip on what
it was likely to be to start with, although the £16 million
does sound very low. You, I think I am right in saying, got that
wrong because it was modelled on an urban development corporation.
Mr Higgins: Yes, that is right.
Q91 Mr Bacon: Who was the bright
spark who said, "Oh, this looks really like an urban development
corporation, let's model it on that" because they were 3,500%
out, were they not?
Mr Higgins: I can cover that because
at the time, and they still are, there is not one established
for the Games site already in place, so that modelling covers
that. Now, on the actual structure of the Games, the Act had not
been drafted at the time, therefore, what structure and whether
there was to be an ODA or a LOCOG or a central corporation running
the entire project was yet to be determined and, therefore, the
actual costing and the appointment of the delivery partner was
yet to be determined, so when, after the successful bid, the drafting
of the Act and the passing of the Act in April 2006 establishes
the ODA, the ODA then goes out to competitively find a delivery
partner and we can start to work out the brief and finally work
out the cost of the delivery partner. Now, the money allowed here
for the delivery partner from an external benchmarking point of
view is quite realistic, and it is very realistic compared to
other major infrastructure projects, the Channel Tunnel Rail Link
or major projects at airports, that is quite a standard charge,
but it is a very different model from what was envisaged. The
model envisaged originally was based on urban development corporations
which, frankly, worked very well for the Docklands, if you look
at the way that the Docklands and Canary Wharf were delivered,
or Milton Keynes or other major projects.
Chairman: Well, thank you very much,
Mr Higgins, and the one thing which has emerged from that line
of questioning is that such is the uncertainty of these future
profits from land sales that we cannot be sure that the Lottery
will be reimbursed at all, and I find that very concerning.
Q92 Mr Davidson: I wonder if I could
just say at the beginning, Chairman, that I wonder whether or
not by the end of this hearing our visitors from Nigeria will
think themselves lucky that Abuja did not win the Commonwealth
Games! Could I ask about construction costs. Because of the booming
economy that we have and the growth in construction across the
South East and the UK in general, is construction cost inflation
rising more than expected?
Mr Higgins: The original bid had
5% and you will note that that figure of 167 allows for it to
be 6%. You will have seen market evidence on rising steel prices,
so obviously iron ore and steel prices have gone up considerably,
so there are inflation pressures. If, for example, inflation was
to go up by 2% in the next two years, that would probably add
around a figure of £50 million to the cost pressure if it
then returned to its original figure, so yes, we are exposed to
cost pressures, as any other major project is.
Q93 Mr Davidson: But you have not
detected so far that construction cost inflation is greater than
that anticipated in your bid and your contingency?
Mr Higgins: We are well in the
process of tendering at the moment and now we have major tenders
closing on the major venues, the Village, roads and bridges, so
it is different. In fact, with roads and bridges and highways,
infrastructure, we do not see the same cost pressures that we
are seeing in other venues and buildings, so with the building
boom in the City of London, and there is a massive number of commercial
projects under way, that is probably creating more pressures in
that area than it is in the area of infrastructure.
Q94 Mr Davidson: One of the things
that does worry us a bit is that builders, whilst not quite as
voracious as farmers, are nonetheless somewhat keen to exploit
the situation where perhaps the client is over a barrel. I am
a bit concerned with the lack of competition for some of these
contracts. As I understand it, the Olympic Stadium has only got
one bidder and the Aquatic Centre has only got one bidder, which
is not quite the strongest position for yourselves to be in. Did
you anticipate having only one bidder at this stage when you were
drawing up the initial estimates?
Mr Higgins: I suppose high-profile,
iconic structures are not the sort of projects that the industry
necessarily is originally attracted to, and there is some history
on stadiums across the country which does not make it easy. I
suppose the best of describing it is to say that we have spent
£13 million now on the Stadium since we appointed McAlpine's
in design development work and in testing the design, what is
termed as Stage D which was launched last week. You could not
do that sort of work with three other competitive bids or two
other teams working together, we just would not have the capacity
to do that, so at some stage on these sorts of projects you have
to get to one bidder. We are not in the luxury of being able to
complete the design and go out and do a fixed-price tender. That
would be one way of doing it, but we do not have the years it
would require, so our protection, to answer your question as briefly
as I can, is that we do choose a partner, but then we insist on
absolute transparency to drill down to the actual trades, tenderers
and suppliers and hope for greater competition there. One of the
benefits of having a delivery partner, like our partner CLM, is
that they can act and allow us to scrutinise the tender process
of the trades.
Q95 Mr Davidson: So I should not
be worried?
Mr Higgins: It is a concern. It
is set out in paragraph 51 of this Report, that it is one of the
major risks, inflation, but also market appetite, so as much as
possible we try and make the Olympics an attractive site to work
on and we invest money in infrastructure, in strong plans on health
and safety and in speedy decision-making.
Q96 Mr Davidson: On the question
of the other contracts on the infrastructure, are you happy with
the state of competition for those contracts?
Mr Higgins: Yes, we are. We are
well down the track on all of the enabling works and we have got
over £½ billion worth of work contracted to all the
enabling works, the tunnelling work is completed, we will be awarding
the major bridge contracts in the next month or so and the competition
levels there were very strong and we are very pleased with that.
Q97 Mr Davidson: Can I now go on
to the question of employment. We have discussed before issues
relating to the scale of direct employment which was considered
to be one of the reasons for success in previous big contracts.
How well are you doing here in relation to having a proportion
of direct employment as distinct from full self-employment?
Mr Higgins: It is still early
days, but we do have around 1,500 employees on the site there
with around three-quarters at this stage, we understand, that
are directly employed, which is very high in the industry standards,
and we hope to increase that, so we are putting a lot of time
into getting the right data and facts, so we are really requiring
complete disclosure of our sub-contractors and suppliers and we
are having good figures on that. Probably the most encouraging
figures are that nearly 50% of our workforce and our suppliers
are coming from outside the direct London area, so that should
put less pressure on inflation, and around 180 of those people
currently employed on the site have come from positions where
they have not been employed for a considerable time, so getting
unemployed people into work on the project is something we have
put a lot of time and effort into, so we are quite pleased with
that.
Q98 Mr Davidson: My understanding
was that around 50% of those who are employed on the site presently
are from within London, but I am not clear whether or not that
includes Poles and other Eastern Europeans who are presently living
in London or whether or not it actually is London inhabitants
who have been living in London, say, for the last five or ten
years.
Mr Higgins: I do not have that
detail, but I do know that these are people who are living in
London. We have strong figures in the boroughs, so we looked at
the five boroughs of the London area and around roughly a quarter
of people
Q99 Mr Davidson: Well, the figure
from the five London boroughs was, I think, 20%, but, if somebody
has moved into one of those boroughs yesterday from Warsaw, then
the capital in which they live in a sense is Warsaw rather than
London and I am, therefore, just seeking clarification as to the
percentage of the workforce that have actually originated in Eastern
Europe and how many are actually genuinely of the London community.
Again the fact is welcomed that I think you said that 10%, and
that was my figure, had been previously unemployed.
Mr Higgins: That is right.
|