1 The savings achieved so far
1. In 2006-07 the BBC spent £531 million on
goods and services ranging from broadcast specific products, such
as props, costume, locations, lighting, studios, production equipment,
recording and storage media, to more generic items such as travel,
office supplies and consultancy advice.[3]
2. At the time of our hearing the BBC was on course
to achieve its target of delivering cumulative procurement savings
of £75 million in the three years to April 2008. It had achieved
savings of £10 million in 2005-06 and £27 million in
2006-07, slightly exceeding the annual target for those years,
and expected to meet its £42 million target for 2007-08.
Savings had been achieved by various means, including obtaining
reduced prices when contracts had been re-tendered and negotiating
with suppliers not to apply annual inflationary price increases,
against the backdrop of overall spending on goods and services
having increased by 6% from April 2004 to March 2007.[4]
3. Figure 1 shows that across the seven categories
of goods and services on which the BBC spends money, the savings
made in 2006-07 ranged from 2.9% to 12.1%. While the overall saving
was 5%, the savings were lower in five of the seven categories
and lowest in those categories where the BBC had spent mostProduction
Resources (3.2%) and Technology and Broadcast Equipment (2.9%).
One of the BBC's approaches to securing savings was renegotiating
or re-tendering contracts when they came to an end, but that point
had not been reached in these two categories, where overall savings
of £7 million were made, compared with £231.6 million
spent. In the coming year, however, the BBC was expecting to save
more than 10% (£13 million) in the Production Resources category.
As regards Technology and Broadcast Equipment, the BBC considered
that it was already getting good value for money because of previous
savings, and that future savings would depend upon changes in
technology and its working practices.[5]
Figure 1: Analysis of the BBC's annual savings from procurement by category in 2006-07
| Category
| Examples of type of spending
| Spending
(£ million)
| Savings
(£million)
| Savings as a percentage
of category spending
|
| Production Resources
| Post production; studios, scenery and lighting; outside broadcast and locations; props, costume and make-up
| 128.6 | 4.1
| 3.2 |
| Technology and Broadcast Equipment
| Production equipment; audio visual equipment; recording and storage media
| 103.0 | 2.9
| 2.9 |
| Logistics
| Hotels and conferences; travel; couriers
| 76.1 | 6.3
| 8.2 |
| Property and Workplace
| Utilities; facilities management; stationery and office supplies; catering; security contracts
| 69.9 | 3.3
| 4.7 |
| People and Resources
| Recruitment agencies; training and development
| 52.8 | 2.5
| 4.8 |
| Marketing Services
| Market research; advertising; promotional merchandise
| 51.1 | 1.7
| 3.3 |
| Corporate Services
| Advisory services and consultancy; insurance; legal services; banking and financial services
| 48.3 | 5.9
| 12.1 |
| Total |
531.4 | 26.7
| 5.0 |
| Note: Other spending of £1.6 million did not fit within the existing category structure
|
Source: C&AG's Report, Figures 2 and 6
4. The overall savings also conceal underlying increases
in some categories of spending. For example, while savings of
4.8% (£2.5 million) had been made in the People and Resources
category (Figure 1), which included the cost of temporary
staff, spending had doubled from £26.3 million to £52.8
million in the three years to April 2007.[6]
5. The BBC used a mix of temporary and permanent
staff because it gave flexibility and because using temporary
staff saved overhead costs such as pension contributions. Large
numbers of programme staff were freelancers, but temporary staff
were also used for one-off projects, such as the iPlayer, where
specialist skills were needed. As projects ended, temporary staff
costs had fallen, and the BBC was expecting to spend under £35
million on the People and Resources category in 2007-08.[7]
6. The use of temporary staff also had to be seen
in the context of planned staff reductions at the BBC of between
1,800 and 2,500 over the next five years, with the biggest reduction
due to take place in the coming 12 to 18 months. Asked about the
risk of temporary staff being used to backfill permanent posts,
the BBC acknowledged the importance of making sure total staff
costs, including for temporary staff, were reduced. The BBC also
expected that some areas of procurement spending would fall as
staff numbers declined.[8]
7. In addition to the more routine procurement covered
by this Report, some 45% of all spending across the BBC was for
work outsourced to other service providers, including long-term
contracts for services such as finance and human resources, as
well as programme content made by independent production companies.
One way organisations can get better value for money from the
supply chain is to encourage suppliers to use best practice procurement.
Although the BBC's contractors generally do not take advantage
of its purchasing arrangements, and its expertise in particular
markets, the BBC confirmed that they could.[9]
3 C&AG's Report, para 1 Back
4
Q 36; C&AG's Report, paras 4, 6 and Figure 5 Back
5
Qq 1, 83 Back
6
C&AG's Report, para 4 Back
7
Qq 33, 37-38, 88-89 Back
8
Qq 83-86. The Director General's speech to BBC staff announcing
the job loses is available at: http://www.bbc.co.uk/pressoffice/speeches/stories/thompson_staff_181007.shtml
Back
9
Qq 98-100 Back
|