Government response
1. (Recommendation 1) It was unhelpful of the
MoD to provide the written evidence we had requested only a day
before the evidence session we had scheduled. We expect better
cooperation from the Department in future, and accept the Permanent
Secretary's assurance that lessons have been learned and that
such failings will not happen again. This is essential if Parliament
is to undertake its role of scrutinising the work of the MoD effectively.
(Paragraph 4)
The Permanent Secretary has made clear that maintaining
a good relationship with the Committee to facilitate its scrutiny
of defence on behalf of Parliament and the public is very important
to us. As the Committee has recognised, we have reviewed what
went wrong on this occasion and have undertaken to ensure that
it does not happen again.
Public Service Agreement Targets
2. (Recommendation 2) We are very concerned to
learn that the MoD's assessment of its expected achievements against
its six 2004 Spending Review Public Service Agreement (PSA) targets,
which run until March 2008, has started to travel in the wrong
direction. In its previous Annual Report and Accounts published
in July 2006, the MoD reported that it was on course to achieve
all six PSA targets. However, at the end of 2007, the MoD did
not expect to achieve the PSA target relating to force readiness,
and expected "only partly" to meet the PSA targets relating
to recruitment and retention, and defence equipment procurement.
We note that the MoD considers that not achieving the force readiness
target is a consequence of the "high levels of deployment
". We recommend that, in its response to our report, the
MoD identifies the key factors which have led to the deterioration
in its expected achievements against its PSA targets and sets
out what action it is taking as a result. (Paragraph 12)
Readiness
It is simply not possible for the Armed Forces to
operate at the level and intensity they have sustained for some
years while simultaneously being prepared for the full range of
potential additional hypothetical contingent operations underpinning
Defence Planning Assumptions. We have therefore made clear for
some time that it is highly unlikely we will meet our readiness
targets. As we have made clear, success on current operations
in Iraq and Afghanistan is our overriding priority. We have therefore
deliberately prioritised resources to support current operations
over the preparation of force elements for scenarios much less
likely to be faced in the short-term. Examples include:
- the employment of personnel
outside their primary role in order to meet operational capability
gaps inevitably reduces their readiness in that primary role.
For example, we have recently re-roled tank squadrons to drive
Mastiff and Warrior; protected mobility is a high priority in
both Iraq and Afghanistan, but there is a very limited requirement
for main battle tanks;
- some specialist equipment (such as 16 Air Assault
Brigade's WMIK and 3 Commando Brigade's Viking) has proved well-suited
for a particular operation or environment. In these cases, the
requirement to support current operations has been accorded priority
over equipping forces at readiness;
- where training has been compressed, it has necessarily
concentrated on the skills needed for current operations and taken
risk against (for example) the high-end tactical manoeuvre of
an armoured brigade;
- reprioritisation of resources away from areas
of Defence with less practical application for current campaigns,
such as anti-submarine warfare, has inevitably reduced readiness
in these areas. The process of recuperation, which will require
significant time and resources, will aim to restore expertise
in these more general, but currently under-utilised, war-fighting
skills; and
- in some cases, niche capabilities have become
entirely committed to preparing for, conducting or recovering
from current operations. Their readiness for general war-fighting
has consequently inevitably deteriorated.
We are well aware of the risks and underlying issues
and are mitigating them where feasible. We continue routinely
to work within the resources available to improve current readiness
levels and controlling risks to readiness through contingency
planning, revising training patterns and manning plots, and working
with industry partners to address delivery challenges. Examples
include:
- Personnel: Financial
retention initiatives have proved a useful and focused tool to
improve retention of pinchpoint trades;
- Equipment: We are
making 14 additional support helicopters available for current
operations (albeit not all could be available simultaneously)
with six Merlin (from Spring 2008) and eight Chinook (from 2009).
Additionally, the procurement of two further C-17 aircraft will
also address readiness gaps as well as providing additional capability
for current operations;
- Training: A future
training programme for all types of military operations is being
developed to ameliorate the longer-term impact of focusing training
for current operations over the short term; and
- Logistic Support:
We continue to invest in the required spares and munitions to
support operations.
Readiness profiles provide a clear and relatively
objective assessment of the impact of the pressure under which
the Force Structure is operating. They are not a measure of the
ability of the Armed Forces to sustain current operations, but
a reflection of performance against the readiness profile we would
expect to see if the Armed Forces were operating within routine
concurrency levels. We expect them to start to improve (with about
a 6 month lag time) as commitments start to reduce.
Recruitment and Retention
Overall, recruitment is broadly satisfactory. Selection
standards have not been reduced and the quality of those joining
remains high. In 2006-07 we recruited 1,210 more people than the
previous year. But the recruitment market is challenging. We face
stiff competition from other employers, and more young people
are now opting for further education.
Sustaining current operations has made it impossible
to meet harmony guidelines across the Army and Royal Air Force,
but the recent National Audit Office study into Recruitment and
Retention in the Armed Forces confirmed our judgment that "it
is difficult to identify any one factor that leads people to leave
the Services". Each Service conducts its own exit interviews
or surveys to determine why people leave, and the results show
broadly similar trends.
- Royal Navy: The
main reason for leaving the Royal Navy given by personnel in Exit
Interview Reports since these began in 2003 is "separation
and domestic issues";
- Army: The most appropriate
assessment of the factors that influence officers and soldiers
to leave is the Army's Leavers survey. The most recent version
of this was published in March 2007, covering responses given
between November 2005 and October 2006. For Soldiers, the top
five retention-negative factors were the impact of Army lifestyle
on personal and domestic life; the amount of separation from spouse/partner;
job satisfaction; own morale; and civilian career prospects. The
top five reasons cited by officers were: own morale; the impact
of Army lifestyle on personal and domestic life; opportunities
outside; civilian career prospects; and the effect of operational
commitment and rates of stretch; and
- Royal Air Force: All
personnel who voluntarily leave the RAF, either through taking
Premature Voluntary Release or at a point where they had the option
to extend their service, are sent a survey. Over June 2005 to
April 2007 the five factors rated as the most influential and
important by Airmen and non-commissioned Aircrew were: expected
future job satisfaction; future of RAF; opportunities to spend
time with family; current job satisfaction; and Service morale.
For Officers from September 2005 to September 2006 the five main
factors were: If I stayed longer it would have been difficult
to start a second career; employment opportunities outside RAF;
direction and strategy of RAF; future of RAF; and future job satisfaction.
We have a wide range of focused initiatives in place
to improve recruitment and, especially, retention. These include:
- Commitment Bonuses: £5,500
is currently available to Other Ranks in all three Services for
a return of an additional two years service. On 19 March 2008
the Government announced that this would be significantly increased
from 2009 to a maximum of £15,000 for those who deliver nine
years service in total;
- Financial Retention Incentives: the RAF for example
runs a continuation package that is designed to encourage individuals
to continue service beyond their Option Point with a five year
Return of Service;
- Targeted recruitment initiatives such as the
"One Army" Recruiting campaign;
- Initiatives to improve work/life balance and
working conditions as the front line;
- Operational bonus of £2,320; and
- Prioritised investment in accommodation.
Equipment Procurement
The Department met this target in full in 2005-06
and 2006-07. But while we expect to meet the targets for delivery
of Key User Requirements and in-year variation on forecast costs
in 2007-08, in each case with an improved performance on 2006-07,
we do not expect to meet the target for in-year variation of In
Service Dates. As set out in the Autumn Performance Report, this
in part reflects a deliberate decision to delay deployment of
the Beyond Visual Range Air-to-Air Missile on Typhoon. Technical
difficulties have also emerged on a number of other programmes,
including the Next Generation Light Anti-Armour Weapon, Terrier
Engineer Tractor, the Airborne Stand-Off Radar and General Service
Respirator. We have taken mitigation action to minimise associated
slippage, but with varying degrees of success.
3. (Recommendation 3) The MoD does not expect
to meet the PSA Target relating to generating forces by the end
of March 2008. The performance on both of the performance indicators
underpinning PSA Target 3 has continued to deteriorate. We note
that the MoD considers that this reflects the pressure on the
Armed Forces which have been operating above the level of concurrent
operations they are resourced and structured to deliver. This
causes us deep concern. We fully acknowledge the pressures on
our Armed Forces and the commitment they have demonstrated. We
recommend that, in its response to our report, the MoD and the
three Service chiefs set out how they plan to reduce the pressures
on our Armed Forces and why they expect to see improvements relating
to generating forces. (Paragraph 20)
We welcome the Committee's recognition of the pressure
on the Armed Forces and the commitment they have demonstrated.
Operating above routine Defence Planning Assumptions over such
a long period has been demanding, but it is self-evident that
our people have more than risen to the challenge. Although we
have been heavily engaged in both Iraq and Afghanistan, their
performance has been outstanding.
We have noted and understand the Committee's concern.
Our priority has to be achieving success on current operations.
As we have made clear, this has required the Armed Forces to operate
in excess of the established planning assumptions for which they
are routinely resourced and structured. While this is undesirable,
it is not critical so long as it is not sustained indefinitely;
the force structure is both resilient and flexible. As well as
seeking and receiving additional funding for current operations,
the Department has reprioritised within the core defence budget
to ensure the delivery of key Defence outputsnotably success
on operations. Clearly, one result has been that certain areas
of Defence have been accorded a lower priority than we would like.
As the Chief of the Defence Staff said in December,
reducing the number of our military deployed on operations is
the key to restoring the training base within the UK and more
widely. 2007 saw the successful conclusion of Operation BANNER
in Northern Ireland after 38 years, and Operation OCULUS in Bosnia
after 15 years. We were also able to reduce substantially the
number of British forces deployed in the South of Iraq and close
a number of bases. While force levels in Afghanistan increased
over the same period to meet the very demanding challenges of
that campaign, overall activity levels and the pressure on the
force structure have reduced. Extrapolation of future commitments
and force levels is inherently uncertain, but we expect to be
able to reduce further in Iraq, and while our military contribution
in Afghanistan is certainly not going to be short-term, we expect
the Afghan security forces, particularly the Afghan National Army
which has been performing very well recently, to take on an increasing
share of the military burden. As the Committee would expect, we
have plans in place to recuperate the force structure further
over time, subject to the necessary resources being available,
once commitments return to a level where this is possible without
taking risk against success on current operations.
Service Personnel Issues
4. (Recommendation 4) We note that the MoD does
not expect, for different reasons, to achieve manning balance
in the Royal Navy / Royal Marines and the Army by the end of March
2008. We recommend that, in response to our report, the MoD sets
out how it plans to achieve manning balance in the future for
the Royal Navy/Royal Marines and the Army. (Paragraph 27)
All three services were outside the manning balance
range (2% below and 1% above the required trained strength of
the Service) on 1 January 2008, although we expect the Royal Air
Force to achieve manning balance by 1 April 2008. The current
situation within each Service is:
- Royal Navy:
There are no critical manning shortfalls preventing deployment
of Royal Navy Units, and we are working to close the current deficit
by 2009-10. This includes:
- a combination of a restructuring
measures to ensure there are sustainable specialist branches for
the future and to reflect newer, less manpower intensive vessels
being brought into service;
- a number of initiatives to grow Strength such
as increased recruiting, further expenditure on marketing, and
streamlining of career progression to accelerate the filling of
gaps at critical levels; and
- review of training and remuneration to improve
retention. Financial Retention Initiatives for Royal Marine Other
Ranks, specialist nurses and naval aviators are already in place,
and the Armed Forces Pay Review Body 2008 recommendations included
a realistic pay rise and substantial retention package for the
fragile Submarine community.
- Army:
Reaching full manning is the Army's highest priority after operations.
We have therefore introduced a package of further measures over
and above existing recruiting and retention programmes and activities.
In particular we are introducing incentives to improve retention
within the training and recruiting system as we recognise that
the current level of wastage is unsatisfactory. These include
improved mentoring, activities to inject greater variety in training,
and facilitating greater parental involvement. We are also introducing
incentives for recent leavers to rejoin. In combination with the
retention incentives and other elements in this year's AFPRB settlement,
we expect these measures to support progress towards achieving
manning balance; and
- Royal Air Force: We
expect the RAF to achieve manning balance by 1 April 2008, although
there is a risk that it may subsequently fall again. A programme
of retention and recruiting measures to address this is therefore
now underway.
5. (Recommendation 5) The MoD continues to experience
shortages within some specialist groups in all three Armed Services,
including substantial shortages within the Army Medical Service
and Elsewhere. The MoD have put in place measures to try and reduce
the number of manning pinchpoints. We note that the MoD also expects
that force level reductions in Iraq will reduce some of the pressure
in these specialist groups. We recommend that, in its response
to our report, the MoD provides us with an update on the position
relating to manning pinchpoints and its assessment of the success
of the measures introduced to reduce their number. (Paragraph
31)
Manning Balance is a very broad measure and within
the overall picture there can be larger shortfalls or excesses
against particular trades and specialist groups. We therefore
devote considerable effort to managing the balance of personnel
at those more detailed levels. Where there is a shortfall in trained
strength in a particular trade or area of expertise or a commitment
that exceeds the formal establishment this is identified as a
manning Pinch Point. Considerable effort is devoted to managing
these to alleviate shortfalls, and we welcome the Committee's
recognition of this work. A variety of measures are used, including:
financial bonuses to incentivise recruitment and retention; continuous
review of the posts required and the rank and expertise required
to fill them; mobilisation of Reserves; contractorisation; and
increased training (including fast-tracking for some trades).
Over the longer term, the Services also adapt their manning structures
to reflect the skills and expertise required for the type of operations
we expect to undertake.
ROYAL NAVY
As of 21 January 2008 there were 15 identified pinch
points in the Royal Navy:
- RN Harrier GR7 Instructors
- Lt GR7 Harrier Pilots
- Merlin Observers
- Able Bodied Seaman
- Merlin Pilots
- Able Bodied Diver
- Leading Hand Warfare
- Strategic Weapons Systems Junior Ranks
- Able Bodied Warfare Specialist (Sensors Submariner)
- Petty Officer Mine Warfare
- Nuclear Watchkeepers
- Able Bodied Warfare Specialist (Tactical Submariner)
- Merlin Aircrew
- Sea-King & Lynx Avionics Supervisors
- Royal Marines Other Ranks
Across the RN there are currently over 60 recruitment
and retention initiatives, including a number of specific Financial
Retention Incentives. Over the longer term the Navy is working
to resolve many of these pinch points through Project Fisher and
other Navy Board Personnel Change Programme projects.
ARMY
As of 18 February 2008 there were 28 identified pinch
points in the Army:
- Army Medical Service Radiologist
- Army Medical Service General Surgeon
- Army Medical Service Anaesthetist
- Army Medical Service Orthopaedic Surgeon
- Royal Engineers Explosive Ordnance Disposal
- Royal Artillery Operator Unmanned Aerial Vehicle
- Royal Logistics Corps Ammunition Technician
- Army Medical Service Radiographer
- Royal Logistics Corps Petroleum Operator
- Army Medical Service Operation Department Practitioner
- Royal Engineers Military Engineer Geographic
- Royal Electrical and Mechanical Engineers Recovery
Mechanics
- Army Medical Service Emergency Medicine Nurse
- Army Medical Service Registered General Nurse
(Officer)
- Intelligence Operational Military Intelligence
- Army Medical Service Intensive Therapy Unit Nurse
- Royal Electrical and Mechanical Engineers Vehicle
Mechanic 1
- Royal Engineers Mechanical Engineer Fitter
- Royal Logistics Corps Postal and Courier Operator
- Royal Engineers Clerk of Works
- Adjutant Generals Corps Military Administrator
- Royal Engineers ME C3S
- Royal Electrical and Mechanical Engineers Armourer
- Army Medical Service General Medical Practitioner
- Royal Logistics Corps Chef
- Infantryman
- Royal Electrical and Mechanical Engineer Avionics
Technicians
- Royal Signals Information Systems Engineer
The introduction of various Financial Retention Incentives
such as Golden Hellos has resulted in steady improvements in some
pinch point trades. Non-remunerative measures have also had effect.
For example, deficits have reduced against the following trades:
| Trade |
Deficit
April 2006
| Deficit
January 2008
| Measures taken
|
| Intensive Therapy Unit Nurses
| 97% | 23%
| Golden Hello £20K
|
| Emergency nurses
| 96% | 30%
| Golden Hello £20K
|
| Petroleum operators
| 11% | -10%
| Improved recruiting
Extra course to get more people into trade
|
| Unmanned Aerial Vehicle operators
| 51%
(October 2006)
| 48% | 100% take-up on recently introduced £10,000 payment for three years return of service. The benefits will be seen in the future.
|
| Royal Signals Engineer
| 18% | -1%
| Conversion courses from other trades.
|
Financial retention incentives continue to be used to manage voluntary
outflow among carefully targeted groups, such as the commitment
bonus for Infantry soldiers at the four-year point. New incentives
for Army Vehicle Mechanics have also recently been announced.
ROYAL AIR
FORCE
As of 31 December 2007 there were 14 identified pinch points in
the RAF:
- Medical
- Weapons Support (Linguist)
- Princess Mary's RAF Nursing Service
- Weapons Support (Air Load Master)
- Gunner
- Operational Support (RAF Regiment)
- Staff Nurse (Registered General Nurse) Accident
and Emergency
- Air Traffic Control/Flight Operations Manager/Flight
Operations AssistantSergeant
- Operational Support (Provost/Security)
- Operational Support (Flight Operations)
- RAF Police
- Operational Support (Intelligence)
- Movements Operations/Controller
- Motor Transport Technician
Examples of measures being taken to alleviate shortfalls
include continuing recruitment efforts, retention bonuses; golden
hellos and other incentives.
6. (Recommendation 6) We are concerned that there
are signs that voluntary departure in the Armed Forces, in particular
the Army, is increasing and that in the RAF personnel are not
extending for a further engagement to the extent that had happened
in the past. This may well reflect the pressure that our Armed
Forces continue to experience. We look to the MoD to monitor this
issue closely. (Paragraph 36)
A reasonable level of voluntary outflow is healthy
for any organisation and the Armed Forces compare well with other
public and private sectors. Outflow rates are also in part a reflection
of past recruitment rates. On average, other ranks serve for eleven
years. Military staff turnover is in the region of 10% per year,
of which 4.5% is voluntary outflow. The remainder largely comprises
those who complete their full engagements or are discharged involuntarily
for a wide range of reasons including medical and disciplinary.
Voluntary outflow rates are broadly stable but edging upwards
slightly, but average rates can mask higher rates in some very
significant areas, and high rates in certain specialisations can
contribute to Manning Pinch Points. As the Committee would expect,
we therefore keep this under close review.
In some important areas, voluntary outflow is currently
too high. For example, the rate for soldiers in the Army is running
at 5.8% against a target of 5.1%. We are therefore reviewing ways
of retaining our people, including a number of measures specifically
aimed at reducing Voluntary Outflow, such as:
- Commitment Bonuses: £5,500
is currently available to Other Ranks in all three Services for
a return of an additional two years service. As noted above, on
19 March 2008 the Government announced that this would be significantly
increased from 2009 to a maximum of £15,000 for those who
deliver nine years service in total;
- Financial Retention Incentives, such as the Army's
payment of £4,500 for Infantry Other Ranks, paid for return
of service between the four and six year point;
- Initiatives to improve work/life balance and
to introduce more flexible ways of working; and
- The new operational bonus of £2,320.
The Royal Air Force is taking forward a Retention
Action Plan, which has contributed to the work of the Armed Forces
Pay Review Body. Elements include: use of financial retention
incentives and/or specialist pay to address Operational Pinch-point
Trades; review of selected allowances; introduction of an enhanced
Career Management Strategy, broadening opportunities, reviewing
Career Terms and Conditions of Service; accommodation issues;
and greater awareness of the identity and profile of RAF personnel.
7. (Recommendation 7) We note that the Army and
the RAF are failing to meet both individual and unit harmony guidelines,
and that the percentage of RAF personnel exceeding the individual
harmony guidelines has risen sharply during 2007. We find the
reported performance against Unit Tour Interval harmony guidelines
for the RAF much less precise than for the other two services,
with some RAF squadrons just reported as "heavily tasked".
We look to the MoD to identify how the setting and measuring of
Unit Tour Interval harmony guidelines for the RAF can be improved.
(Paragraph 43)
The Armed Forces have always taken the impact of
separation on people and their families very seriously and they
therefore set harmony guidelineswhich are not rigid rulesthat
are designed to ensure that they can perform the tasks that the
Government requires of them without asking their people to bear
an excessive long-term burden. Performance against Individual
Separated Service guidelines, reflecting the balance between the
amount of time spent on operations and training away from home
as against in the home base, is effectively used to monitor the
work-life balance of military personnel. The guidelines are set
by each Service to reflect their individual operating contexts,
cultures and practices. The current approach is quite new, having
been introduced in 2005, and we continue to refine how it is measured
and monitored. We are also reviewing whether there should be a
common standard across all three Services.
The percentage of Royal Air Force personnel exceeding
the Individual Separated Service Guidelines (of no more than 2.5%
of RAF personnel with over 140 days over a 12-month rolling period)
rose sharply during 2007. In large part this reflected the change
in measurement methodology in the second quarter of 2007-08 to
bring the RAF in line with the other Services by counting single
nights away, rather than periods of Separate Service of three
or more consecutive nights away. This accounted for the majority
of the rise from 6.7% of RAF personnel exceeding Individual Separated
Service guidelines in the first quarter of the year to 9.2% in
the second quarter.
Unit Tour Intervals are difficult to apply to most
RAF units because only the RAF Regiment deploys as complete formed
units in the same way as the majority of the Royal Navy and Army:
- Air Combat Units have only
had to deploy either at, or near, full unit strength in the first
stages of operations in Iraq and Afghanistan. Subsequent stages
of these enduring operations have required less combat air support.
As a result we have not been deploying full formed units but have
rather rotated personnel between their home station and the deployment
location for shorter periods at more frequent intervals, in order
to ensure that complex flying and engineering skills are maintained
at appropriate levels;
- Air Support and C4ISTAR units generally have
a Headquarters element and deployable aircraft/crews or teams.
The units themselves therefore do not deploy as whole entities
but as numbers of aircraft/crews or teams in support of deployed
locations; and
- Enablers, such as the Air Transport fleet and
Air Movements do not deploy as formed units, but deploy individual
aircraft and crews as required to meet in theatre tasks and movements
to and from deployed locations.
Consequently, the way most RAF units currently operate
makes it impossible to measure deployments against the formal
Unit Tour Interval guideline of four months on deployed operations
in 20 months. This has been reflected by our use of terms such
as "very hard pressed". Recognising this, we have therefore
been developing an alternative way of measuring operational deployments
against this guideline by taking that element of Individual Separated
Service arising from operational deployments and calculating from
that the level of operational service against the Unit Tour Interval
guideline. Measured this way, 10.6% of RAF personnel exceeded
the guideline in the first quarter of 2007-08, 11% in the second
quarter, and 7.1% in the third quarter. We are working to try
and apportion this data to formed units from the first quarter
of 2008-09.
8. (Recommendation 8) We are very disappointed
with the failure to meet harmony guidelines in the Army and RAF.
This is another clear indicator of the pressure on our Armed Forces
from the continuing high level of operations. The MoD expects
the position to improve with a reduction in the current operational
pressure. We certainly hope so, as we find the continuing failure
to meet harmony guidelines unacceptable. In its response to our
report, we expect the MoD to set out what impact the failure to
meet harmony guidelines is having, such as the impact on the retention
of Service personnel. (Paragraph 44)
We have noted and understand the Committee's concern,
but our priority has to be achieving success on current operations.
As we have made clear, this has required the Armed Forces to operate
in excess of the established planning assumptions for which they
are routinely resourced and structured. Some parts of the Army
and Royal Air Force have consequently exceeded harmony guidelines.
While this is undesirable, it is neither critical nor unacceptable
so long as it is not sustained indefinitely; the force structure
is both resilient and flexible. It is not possible precisely to
quantify the impact. With regard to retention, as set out in the
response above to question 2, the recent National Audit Office
study into Recruitment and Retention in the Armed Forces confirmed
our judgment that "it is difficult to identify any one factor
that leads people to leave the Services". While the level
of operational pressure reflected in the failure to meet harmony
guidelines is clearly one factor in why personnel leave the Services,
it is neither the only nor the preponderant one.
9. (Recommendation 9) We continue to be extremely
disappointed and concerned to learn that all three Services missed
their targets for UK ethnic minority recruitment and that the
RAF performed particularly poorly against its target. Our concern
is strengthened by the fact that we considered this in our report
on the Annual Report and Accounts 2005-06 and the figures appear
to have worsened. The fact that some 60% of ethnic minority Service
personnel come from outside the UK, serves to heighten our concern.
We acknowledge that the three Services have put in place arrangements
to improve recruitment. We look to the MoD to ensure that the
planned recruitment activities of the three Services are adequately
funded so that the expected improvements in UK ethnic minority
recruitment are delivered. We expect the MoD to address this matter
both in response to our report and in its command papers to be
delivered in the spring. (Paragraph 51)
We welcome the Committee's continuing interest in
this area, and note its disappointment and concern. We agree that
more is needed. As the Committee has noted, despite considerable
and continuing effort, the Services did not meet their ethnic
recruiting targets for 2006-07. We wish the Armed Forces to reflect
the UK's full diversity and for UK citizens from all backgrounds
to want to serve in them. Moreover, a growing proportion of the
pool of young people from whom we recruit will come from ethnic
minority backgrounds in future, and if we are unable to attract
enough of them to join, it will be much more difficult to meet
the Armed Forces' manning requirements over the longer term. We
have set out in previous evidence to the Committee the factors
underlying the Royal Air Force's performance in this area. We
have also set out in some detail the wide range of outreach and
recruiting activities all three Services are taking forward across
the UK, with particular emphasis on high ethnic minority population
areas. We are making progress. From a baseline of just over 1%
in 1999 ethnic minority representation in the Armed Forces has
risen to 6% in January 2008, against a goal of 8% by 2013. The
quality of the Services' policies in this area is recognised by
their consistent high placement in national rankings under schemes
such as "Opportunity Now" and "Race for Opportunity".
We are pleased that the Committee has recognised that arrangements
have been put in place to improve recruiting. All this work is
fully funded.
Civilian Personnel Issues
10. (Recommendation 10) We are disappointed that
the MoD only met two of its nine diversity targets in relation
to civilian personnel. We recommend that in response to our report,
the MoD sets out how it plans to improve its performance in this
area, particularly given that the MoD has announced that there
are to be substantial civilian job losses. (Paragraph 54)
Although there has been some progress, we share the
Committee's disappointment. We remain committed to improving the
diversity of the Department's civilian workforce and we have a
positive story to tell within our "talent feeder" schemes
aiming to develop individuals for early promotion to Band B and
beyond. The Fast Stream scheme is 48% female with 11% of participants
coming from an ethnic minority. 5% have a registered disability.
The MIDIT scheme (through which we bring on internal talent) is
also 48% female with 8% of participants coming from an ethnic
minority. 6% have a registered disability. The challenge is to
ensure that these statistics are reflected in the future leadership
of the department. We also support a number of schemes to develop
the potential of individuals in identified diversity groups, such
as the internal New Horizons programme for personnel from ethnic
minority backgrounds, and various Cabinet Office schemes for disabled
and ethnic minority staff. In this way we are working to improve
diversity at more senior levels in the Department over time, although
the limitations on progression and promotion in a shrinking department
constrain the scope for rapid progress. But the continuing reduction
programme means that our scope to make more general improvements
across the Department through external recruitment has been, and
remains, very limited. We have therefore focused our diversity
efforts in other areas, and in particular on benchmarking. We
participate in the annual Opportunity Now and Race for Opportunity
exercises, where we perform well and often gain awards. As one
example, on 10th January it was announced that the
Ministry of Defence Police service had improved from 125th
to 24th place in the Stonewall Index.
11. (Recommendation 15) We note that the MoD's
Permanent Under Secretary considers that progress has been made
over the last few years to improve the way the MoD procures and
acquires defence equipment and that the Defence Equipment and
Support (DE&S) organisation, formed in April 2007, is becoming
more capable. We welcome the recognition by the Permanent Under
Secretary that much depends on making sure that the necessary
skills exist at all levels. We are examining the progress made
by DE&S in our current Defence Equipment inquiry. (Paragraph
69)
12. (Recommendation 32) We share the Permanent
Under Secretary's concern that the MoD needs to be more highly
skilled and look to the MoD to set out in its response to our
report what steps it intends to take to achieve this. (Paragraph
140)
While individuals are responsible for their own direction
and pace of development, it is the Department's policy to help
all our employees to realise their full potential. We provide
central advice, guidance and information on opportunities to learn
and develop new skills and knowledge. Since April 2007, a pilot
of an enhanced management information tool, designed to allow
us to better understand the data captured in our civilian personnel
Management System, has shown considerable potential to provide
better quality information on skills and training. Following a
trial period, the software is now being made more generally available
across the Department to help identify the gaps between our current
workforce skills set and our organisational needs. A new Development
Review process has been launched for civilian staff to give a
higher profile to staff development. This brings together several
key development tools, including post and personal skills profiles
(which help staff and managers assess and record skills gaps),
the mid-year development discussion between individual and line
manager, and the updating of the Personal Training and Development
Plan through which staff are required to plan and record their
future learning activities. The associated completion of skills
profiles and training plans will also increase the amount of management
information available to the Department.
The Department has also made substantial investments
in acquisition skills training during the year. The Defence Industrial
Strategy (DIS), published in December 2005, signalled the need
to address shortages in project delivery skills. To achieve the
objective of "battle-winning people and equipment",
we need to ensure our people have the right professional skills.
The Defence Acquisition Change Programme (DACP) has enabled the
development of a cost effective and coherent acquisition training
curriculum that is combined with strong leadership and effective
people management and built around the acquisition Skills Champions
areas. In 2007-08 £5.5M was invested in the DACP upskilling
programme. This provides tailored training in Commercial Management;
Project and Programme Management; Integrated Logistic Support;
Through Life Capability Management (TLCM); and the Defence Acquisition
Management Education Programme. £6.6M was invested in the
Defence Equipment and Support (DE&S) Upskilling programme,
which has focused during the year on: Engineering; Project and
Programme Management; Logistics; Resource Management; and Commercial/
Procurement. All acquisition staff will have access to awareness
training and staff in key acquisition roles will be able to receive
specific practitioner and expert level training. Training is delivered
through the Defence Academy using a range of e-learning and distance
learning, classroom teaching and workshops, and professional examinations.
This investment in the skills of our people helps
them to develop and apply those skills and ways of working in
acquisition. It also contributes to the Professional Skills for
Government agenda. DE&S has set targets that by March 2008
50% of professional posts should be filled by qualified people,
and 85% of its workforce undertaking six days of development plus
four days of additional Continuous Professional Development for
those in the five key areas. DACP is also working to embed the
Defence Values for Acquisition and TLCM into the ways of working
for all civilian and military staff in acquisition, and through
performance management and recognition, instil the changes in
leadership and behaviour that are necessary to deliver more agile
and effective acquisition. DE&S is also taking forward the
PACE programme based on a realistic assessment of skills, numbers
and capabilities required to deliver our forward plan to improve
our support to the frontline.
The Department has a number of corporate development
schemes to help those who have been identified as having greater
potential to progress more quickly. In particular:
- the Band B development scheme
supports the development a small number of selected Band B's who
have been identified as having the potential for promotion into
the Senior Civil Service within one to five years;
- the "Aspire" scheme
(formerly Acquisition Leadership Development Scheme) supports
the development of individuals with the potential for leadership
posts in the Acquisition community;
- the MoD Fast Stream programme provides an opportunity
for high calibre individuals, who demonstrate the required potential,
to benefit from intensive development and training to equip them
for early promotion to Band B and beyond; and
- the MIDIT (Means of Identifying Internal Talent)
scheme Stream aims to develop the Department's future managers.
It typically require participants to reach Band B2 at a relatively
early stage in their career and be deployable across a broad range
of posts at that level.
In June 2007 the Permanent Secretary also signed
the Leitch "Skills Pledge". This emphasised the Department's
commitment to raising the skills levels of its workforce, Service
and civilian, by undertaking to support every employee without
a Level 2 qualification in reaching at least functional levels
of literacy and numeracy, and to provide them with the opportunity
to gain an NVQ Level 2 or equivalent qualification.
Efficiency and Streamlining
13. (Recommendation 16) We congratulate the MoD
on the progress it has made against the 2004 Spending Review Efficiency
Target. We note that the MoD expects to meet all four targets
which underpin the overall Efficiency Target by 31 March 2008,
and to exceed three of these four targets. (Paragraph 74)
14. (Recommendation 17) We welcome the news that
the MoD is expected to save some £50 million by combining
its office supplies requirement with those of other Government
departments. We note that the MoD is planning further collaboration
with other Government departments across a range of categories
and look to the MoD to make quick progress in this area so that
potential savings can be delivered as soon as possible. (Paragraph
77)
We welcome the Committee's comments on our progress
towards meeting the 2004 Spending Review Efficiency Target. The
Department is already engaged in a number of other collaborative
procurement programmes with other Government Departments. We are
leading a pan-government collaborative pilot on energy aiming
to deliver significant financial benefits across government by
the end of the CSR07 period. This involves a number of other departments
and agencies, including the NHS Purchasing and Supplies Agency,
OGC Buying Solutions, the Department of Work and Pensions, Local
Government, The Energy Consortium (which buys for Universities),
The London Energy Project, HM Prison Service and the Department
for Business, Enterprise and Regulatory Reform. We are leading
a number of collaborative programmes to provide professional services
in areas such as consultancy and relocation services and we use
contracts managed by other departments to procure other professional
services. And we are pursuing a number of other areas with potential
for collaborative arrangements with various departments.
15. (Recommendation 29) We note that the MoD has
to achieve savings of £2.7 billion by 2010-11 and that it
plans to achieve these savings by introducing leaner processes
and new arrangements which will deliver better value for money.
Leaner processes and value for money improvements should generate
savings which can be used elsewhere. However, the MoD must ensure
that, in achieving these savings, the speed and quality of the
support provided to the front line is not diminished. (Paragraph
128)
We have no intention of achieving savings in ways
that would not provide the front line with the speed and quality
of support required, nor would any such saving represent value
for money.
16. (Recommendation 30) We note the assurance
given by MoD that the £50 million annual savings that are
expected to be delivered from the implementation of the "streamlining"
exercise of the MoD Head Office will not be returned to the treasury
and used to fund the costs of operations. (Paragraph 133)
17. (Recommendation 31) We call on the MoD to
address the concerns about the militarisation of civilian posts
and the related issues that have been raised with us by Prospect
in full in its response to this Report. (Paragraph 139)
18. (Recommendation 33) We note that the MoD is
to streamline its Head Office in London with the loss of around
1,000 civilian jobs. The aim of the "Streamlining" is
to deliver savings of £50 million a year and also, we are
told, to make the MoD more agile and better able to respond to
the needs of those on operations. We remain to be convinced that
improved agility and responsiveness will follow from the reduction
in staff. We look to the MoD to keep staff fully informed as the
"streamlining" exercise is implemented and to provide
adequate support for those civilian staff who are to lose their
jobs. (Paragraph 141)
19. (Recommendation 34) We consider there to be
a real risk that some of the MoD's best staff will leave and look
to the MoD to identify ways to prevent this from happening. We
are concerned to learn that civilian staff dissatisfaction with
the MoD as an employer has increased over the last year. The MoD
must monitor closely staff morale during the implementation of
the "streamlining" exercise and ensure that the Head
Office continues to deliver the services which Government, parliament,
the Armed Forces and the public expect. (Paragraph 142)
While we note the Committee's reservations, and do
not underestimate the difficulties, we are in no doubt that the
Head Office function in the MOD needed radical review, and that
the course we are now pursuing is capable of delivering a more
responsive and agile Department. Streamlining is not about reducing
high-priority defence outputs; it is about achieving those outputs
more effectively. The aim is for swifter decision making based
around clearer roles and responsibilities, clearer accountability
and elimination of over briefing and unnecessary or duplicated
staff work, with senior officers setting the example Staff themselves
know best where changes in the way work is done are likely to
bring benefits. The design of the streamlined Head Office is being
driven through workshops that give members of staff the opportunity
to be fully involved. The new governance structure will reduce
the number of standing boards and committees reporting to the
Defence Board.
We agree with the committee that maintaining staff
morale during Streamlining is of critical importance and we will
be closely monitoring Head Office morale as the programme is implemented.
Although our Continuous Attitude Survey shows that there has been
a decline in overall satisfaction with the MoD as an employer
over the last two years, this may reflect inevitable pressure
and uncertainty at a time of change. The Survey also shows the
commitment of our civilian workforce to defence remains strong
both in absolute terms and in comparison with most other large
employers. We recognise that we will need, therefore, to pay particular
attention to the way we manage the process of change, including
consultation and communication over the next few years. Staff
will continue to be fully informed about Streamlining as it progresses.
We publish a weekly newsletter, which has been well received,
and have an email account through which we respond to staff comments
and enquiries. There have been cascade briefings by managers,
38 face-to-face discussions between Defence Board members and
staff, and sessions with Ministers.
Support for civilian staff whose posts disappear
will be provided through the Redeployment Pool. This provides
a mechanism for assisting staff to find a new position in MOD
or elsewhere in the Civil Service. In addition, a voluntary Early
Release Scheme has now been launched, following consultation with
the Trades Unions. Set criteria, against which applicants to the
scheme will be judged, will ensure we retain staff with the key
skills (especially scarce skills) needed for the future organisation.
We will encourage all those leaving through the scheme to make
full use of the MoD Outplacement Service or retirement planning
advice. The Streamlining process will be fully Equality and Diversity
proofed and an Impact Assessment produced. The Trades Unions have
been and will be actively engaged throughout.
There is no distinction between military and civilian
posts in determining what counts towards the Administrative Cost
Regime. Streamlining will operate within the current guiding principle
that the financial premium for employing military over civilian
staff should only be justified where it produces clear benefits
to Defence.
Equipment
20. (Recommendation 11) We note that the latest
Annual Report and Accounts state that for the second year running
the MoD "met or exceeded its Public Service Agreement targets
for equipment procurement, despite them being more demanding than
those for 2005-06", and that the Defence Procurement Agency
met all its Key Targets in 2006-07 for the second consecutive
year. The Defence Procurement Agency and the Defence Logistics
Organisation merged on 1 April 2007 to form Defence Equipment
and Support. We hope that the new organisation will maintain this
momentum. (Paragraph 61)
As the Committee has noted, the Department met the
PSA equipment target in full in 2005-06 and 2006-07. As set out
in our most recent PSA reports, we currently expect only partly
to meet this target in 2007-08, as while we expect to meet the
target for delivery of Key User Requirements and are working hard
to meet the cost growth target, we do not expect to meet the 2007-08
target for in-year variation of In Service Dates. DE&S is
working to mitigate this as far as possible.
21. (Recommendation 12) We are concerned to learn
that the Astute submarine and the Type 45 destroyer programmes
have experienced further forecast cost increases, totalling some
£500 million, since the Major Projects Report 2006. While
we note that the Permanent Under Secretary says that much of the
cost in the papers we received relates to the "toxic legacy"
of earlier years, we note his admission that costs have risen
by some £500 million since the end of March 2006. He attributes
this to work to understand the cost base of the Astute and to
resource the Type 45 programme more efficiently with subsequent
renegotiation of fixed price contracts which he says there is
good reason to believe will now control the costs of both programmes.
It is, nevertheless, disappointing that the MoD has failed to
limit further cost growth on these programmes which had already
experienced forecast cost increases totalling some £1.7 billion.
(Paragraph 62)
We note the Committee's concerns. We share the Committee's
disappointment that it has not been possible to avoid further
cost growth. As the Permanent Secretary has made clear, we have
taken measures that we believe should contain the costs of both
programmes.
22. (Recommendation 13) Yet again there have been
problems with the Nimrod MRA4 programme which is experiencing
further cost growth. We note that the MoD recognises it has to
"attend" to these problems now and we look to the MoD
to do this as a matter of some urgency given the current pressures
on the defence budget. We look to the MoD to undertake a review
of the Nimrod MRA4 programme in order to ensure that best value
for money is achieved in maintaining this important capability,
both in quality and quantity of platforms. (Paragraph 63)
The Nimrod MRA4 aircraft will provide the RAF with
a significantly enhanced maritime patrol aircraft capability.
Recent cost increases are largely the result of the need to implement
essential changes in the production aircraft and the cost of converting
the trials aircraft to production standard. Like all defence programmes,
Nimrod MRA4 is kept under review to ensure we obtain the best
value for money.
23. (Recommendation 14) It is disappointing that
there has been further in-service date slippage relating to the
Type 45 destroyer programme and that further delays are likely
on the A400M transport aircraft programme. We are particularly
concerned about the delays on the A400M programme as new transport
aircraft are desperately needed by our Armed Forces who are already
having to use ageing transport aircraft. We look to the MoD to
continue to work closely with the contractors on these programmes
to reduce the risk of any further delays and, where possible,
to identify ways to recover some of the forecast delays. We look
to the MoD to undertake a review of the A400M programme given
the problems experienced to date. (Paragraph 67)
We note the Committee's concerns. As the Committee
expects, we continue to work closely with the contractor to manage
the risks and schedule. The DE&S Chief Operating Officer commissioned
an independent assessment of the A400M programme last year, and
its recommendations are now being implemented.
24. (Recommendation 24) We welcome the announcement
by the Secretary of State in July 2007 that the MoD will be placing
orders for two aircraft carriers, a key programme which the Defence
Committee has closely monitored. (Paragraph 107)
The finalisation of the Joint Venture between BAES
and VT is closely interlinked with signature of the carrier contracts.
We are working closely with the companies to ensure that these
are placed as soon as practical. In the interim, a number of contracts
have been placed with the supply chain for design and engineering
data and materials in support of manufacture.
25. (Recommendation 35) We find it disappointing
that the original timetable for the publication of a revised version
of the Defence Industrial Strategy has slipped and is now not
expected until early in 2008. We hope that this does not indicate
that the impetus given by Lord Drayson, the former Minister for
Defence Equipment and Support, is starting to wane. It is crucial
that the MoD come to speedy decisions on the current planning
round and the implications for the equipment programme so that
the revised version of the Defence Industrial Strategy can be
published and industry given the clarity it requires about future
work. In its response to our report, we expect the MoD to inform
us of the date when the revised version of the Defence Industrial
Strategy is to be published. (Paragraph 146)
We are committed to publishing a revised version
of the Defence Industrial Strategy. The change in planned publication
date does not indicate a lack of impetus but reflects our desire
to ensure DIS v2.0 takes full account of the results of the current
planning round. This approach was welcomed by industry, with whom
we have been engaging extensively as we develop DIS v2.0. Work
continues apace. As Baroness Taylor said in her letter of 20 November
2007 to the Chairman, we are not yet in a position to announce
the publication date.
Defence Agencies
26. (Recommendation 18) We have no objection to
the budgets of former agencies being included in the MoD's main
vote, because in our view that is a straightforward way of dealing
with public money. We continue however to be concerned to ensure
that Defence Equipment & Support, which is responsible for
procuring equipment and managing it through-life, should not reduce
the scope for proper accountability and parliamentary scrutiny.
We note that the MoD intends to report on the activities and performance
of DE&S in its Annual Report and Accounts 2007-08, but it
remains to be seen whether this course of action, rather than
the publication of a separate annual report from DE&S, will
best meet our objectives. We will consider this matter closely
when we examine the next MoD Annual Report and Accounts. (Paragraph
82)
As the Permanent Secretary has made clear, we have
no intention of reducing proper accountability and parliamentary
scrutiny through the disestablishment of agencies. We note the
Committee's particular interest in the activities and performance
of Defence Equipment and Support, and its intention to review
how well inclusion of reporting on this in the Department's Annual
Report and Accounts meets its objectives.
27. (Recommendation 19) We note that in 2006-07
Defence Agencies have generally performed well against their targets
with over 40% of the agencies meeting all their targets. However,
the one exception is the MoD Police and Guarding Agency which
met only 40% of its targets, a similar level of performance to
that achieved in 2005-06 and 2004-05. (Paragraph 86)
28. (Recommendation 20) We are concerned to learn
that "a major" gap in the funding of the MoD Police
and Guarding Agency has been identified and that it is unlikely
that the funding gap will be closed until the end of 2009-10.
In its response to our report, we expect the MoD to provide us
with a full account of why this funding gap has arisen and what
effect it is expected to have on the services expected by the
Agency's customers. We also look to the MoD to set out the reasons
why the Agency has continued to perform to poorly against its
targets and the action being taken to improve performance and
plug any security deficiencies that may have arisen as a consequence
of the funding gap. (Paragraph 87)
We welcome the Committee's recognition that Defence
Agencies have generally performed well against their targets.
The financial shortfall referred to by the Chief
Constable/Chief Executive in the MoD Police and Guarding Agency
(MDPGA) Annual Report and Accounts for 2006-07 resulted from the
establishment of the Agency in April 2004, when the MoD Guard
Service and the then MoD Police Agency were brought together under
a single new Defence Agency. Until that time responsibility for
managing and funding the MoD Guard Service had fallen to the Top
Level Budgets where they were based. A detailed financial reconciliation
following formation of the MDPGA revealed that the financial provision
which had been transferred to the Agency by the TLBs on formation
was insufficient to fund the tasks that were required of it. This
is the major cause of the funding gap. A further, but much smaller,
part of the gap was due to police pay rises outstripping the allowance
that had been made for them.
The funding gap is being addressed through a programme
of work known as "Closing the Gap", which is being led
by the Agency Chief Constable/Chief Executive in consultation
with TLB customers. The outcome of the "Closing the Gap"
process will be to bring the cost of providing the policing and
guarding services supplied by the MoD Police and Guarding Agency
into line with available funding. This will be achieved by a combination
of increased efficiency in the way that the Agency achieves its
outputs (such as improving rostering and reducing overheads in
the MoD Guard Service), additional funding provided by TLB customers
and negotiated reduced requirements for policing and guarding.
The target is to complete the Closing the Gap exercise and bring
tasks into line with resources by the end of Financial Year 2010-11,
and the Agency is on track to achieve this.
The seven key targets agreed by the MoD Police Committee
for the MoD Police and Guarding Agency in 2006-07 were challenging
and sought to stretch the performance of the Agency. Performance
against them was as follows:
- Key Target 1: to increase overall
customer satisfaction with MoD Police and MoD Guard Service services
to 90%. The result achieved for the MoD Police was a customer
satisfaction rate of 86.5%, an increase of 7% over the previous
year. This was therefore a very near miss. It is likely to be
explained by the fact that not all taskings were delivered (see
Target 3 below);
- Key Target 2: to increase the detection rate
of crimes that impact significantly on Defence by 3% above the
level achieved in 2005-06. This was achieved. A detection rate
of more than 72% was achieved, an increase of 34% on the figure
achieved the previous year;
- Key Target 3: to deliver 95% of funded and agreed
MDPGA customer taskings. The MoD Police delivered 91% of its customer
tasking and the MoD Guard Service 87%. The shortfall was due to
a combination of factors: insufficient funding provided by MoD
customers (the gap referred to above); agreed rundown of complements
in anticipation of reduced customer requirements and diversion
of officers to other tasks at the request of the customer;
- Key Target 4: to achieve all international tasks
agreed with the FCO in support of wider defence and foreign policy
objectives. This was fully achieved, with the Agency delivering
all tasks requested by the FCO including peace support operations
and post conflict reconstruction missions in locations such as
Kosovo, Bosnia, Iraq, Sudan, Jordan and Sierra Leone;
- Key Target 5: to increase the number of female
police officer by 6% and ethnic minority officers by 5%. By the
end of 2006-07 the number of female officers had increased by
just over 4%, but the number of officers self-recording as ethnic
minority reduced by 3.8%. The MoD police and Guarding Agency is
fully committed to improving the representation of women and members
of the ethnic minorities across the organisation. The Chief Constable/Chief
Executive has personally taken on the role of Diversity Champion
for the Agency demonstrating top level commitment. A new Agency
Diversity Strategy, which flows from the MoD's own Unified Diversity
Strategy, has been introduced. Benchmarking of the Agency's work
on Diversity against other organisations has continued with the
Agency participating in the Opportunity Now benchmarking exercise
and achieving the highest score in the MoD in the Stonewall workplace
equality index exercise;
- Key Target 6: to demonstrate the recovery or
prevention of loss to the MoD of a minimum of £2M is assets
based on all Fraud investigation activities within the Agency.
This was achieved. By the end of 2006-07 the total monies recovered
via compensation, restraint, forfeiture or disruption was in excess
of £4.4M, more than double the target; and
- Key Target 7: to achieve 32 efficiency targets
set out in the Agency efficiency plan. Of these, 14 were fully
met, eight were nearly met and four were missed. The remaining
six targets were set aside in year as either unviable, disproportionate
in terms of effort required to achieve results, or impossible
to measure.
Funding of Operations
29. (Recommendation 21) We note that the C&AG
qualified his audit opinion on the MoD's 2006-07 resource accounts
because of an excess vote on Request for Resources 2 (net additional
cost of Operations) and that the MoD has identified improvements
in both the forecasting and accounting for Request for Resources
2. We look to the MoD to ensure that the improvements identified
are implemented. We acknowledge that it can be difficult to predict
exactly how much ammunition is to be fired during operations and
we accept that a reasonable contingency is needed in the MoD's
estimate of its forecast expenditure. (Paragraph 96)
The Department continues to monitor the procedures
for reporting RFR2 costs and implement improvements in areas requiring
further development. We recognise that requesting resources for
operations two thirds of the way through the year leaves the Department
at risk of any unforeseen additional costs particularly those
directly attributable to the tempo of the operation such as firing
of guided weapons and missiles. We have taken steps to ensure
the accurate reporting of these costs and will apply realistic
and robust forecasts when seeking future resources. All this work
is visible to and scrutinised by the National Audit Office.
30. (Recommendation 36) We note that the 2007
Comprehensive Spending Review has set down a new funding arrangement
for Urgent Operational Requirements (UORs). The arrangements appear
far from straightforward and we will be interested to see how
they work out in practice when they are implemented. We look to
the MoD to ensure that the new arrangements do not, in any way,
undermine the success of the UOR process seen to date. (Paragraph
155)
We note the Committee's interest in the implementation
of the new Urgent Operational Requirement arrangements in the
2007 Comprehensive Spending Review. Support to current operations
remains our highest priority, and the revised funding arrangement
will not affect the speed and agility of the UOR process. We remain
committed to ensuring that it continues to deliver theatre-specific,
battle-winning capabilities to the Armed Forces at the front line.
Losses and Special Payments
31. (Recommendation 22) We note that the total
value of losses and special payments in 2006-07 are just over
1% of the MoD's total expenditure and that the advance notifications
of losses and special payments have continued to fall. We welcome
the continued reduction in advance notifications of losses and
special payments and look to the MoD to build on the action it
has taken to date to minimise losses in the future. (Paragraph
99)
We welcome the Committee's recognition of the continued
reduction in advance notifications of losses and special payments.
We are always working to minimise losses. The continuing work
to improve project, risk and performance management performance
will inter alia reduce the risk of future losses and special payments.
The Department routinely undertakes internal reviews of all losses
and special payments throughout the year at both TLB and Departmental
level, ensuring that all payments are accurately reported, that
the circumstances surrounding each loss are fully understood and
that, where appropriate processes are reviewed and lessons learnt
to avoid any reoccurrence. The DE&S "Learning from Experience"
team draws on this work to provide guidance to new projects to
try and eliminate any repeat of procurement errors. Performance
in this area is also scrutinised by the Defence Audit Committee,
chaired by a non-executive member of the Defence Board, and is
visible to the National Audit Office.
JPA
32. (Recommendation 23) We are concerned to learn
that the Joint Personnel Administration (JPA) system, which was
rolled-out to all three Services during 2006-07, has experienced
problems and that a substantial number of Armed Forces personnel
have had incorrect deductions from their salaries. We have written
to the MoD separately about the problems experienced and the progress
in resolving them. We look to the MoD to ensure that the remaining
problems are resolved as quickly as possible and that the training
for the users of the system is improved. This is a matter which
we plan to monitor closely. (Paragraph 104)
The Department has already provided a detailed memorandum
in response to the separate questions on this programme the Committee
refers to. For completeness and convenience that response is repeated
below (in italics, indented).
What is the background to the JPA system (the
purpose of the new system, the expected benefits, the approved
and current forecast cost, and the approved and current forecast
in-service date)?
JPA is a programme to modernise administrative
support to approximately 190,000 regular and 80,000 reserve members
of the Armed Forces. Although payroll is a critical and highly
visible outcome, JPA covers the full range of administrative processes
(other than those involving "medical-in-confidence"
information) and provides world-wide support, including to those
deployed on military operations.
The programme was delivered by the Armed Forces
Personnel Administration Agency (AFPAA) with support from its
commercial partner Electronic Data Systems (Defence) Ltd (EDS)
and in close collaboration with the Services and MOD Centre. Work
started in late 2000 and went through feasibility, assessment,
demonstration and manufacture stages before implementation to
the Services commenced in March 2006. AFPAA became the Service
Personnel and Veterans Agency (SPVA) in April 2007, following
its merger with the Veterans Agency. This briefing Paper will
only refer to SPVA from this point.
The Armed Forces (both Regular and Reserves) personnel
policies, rules and processes, and resultant pay structures, are
uniquely complex, especially in the areas of specialist pay and
allowances. Prior to JPA, pay and personnel administration were
supported by three separate, single-Service suites of IT and associated
business processes involving individuals, unit staffs, single-Service
career management (posting, promoting, recruiting, training) staffs,
central policy staffs and SPVA as the payroll delivery organisation.
The three IT suites were all custom designed and supported increasingly
divergent single-Service interpretations of the common over-arching
policy framework. In most cases both the IT software and hardware
were old and approaching the point where cost effective support
was no longer available. The age of the systems also meant that
amending them was difficult; this was preventing the implementation
of flexible employment packages that would best meet the needs
of today's Armed Forces.
The increasingly joint nature of modern military
operations highlighted the differences in the way that policy
had been interpreted by the single-Services and this was proving
to be a cause of dissatisfaction in the operational environment
where, for example, personnel from the different Services working
under the same conditions might have differing entitlements to
allowances. Replicating the existing bespoke IT suites with modern
software and hardware would not address the causes of dissatisfaction
and was deemed unaffordable. An assessment study in 2000/2001,
sponsored by Deputy Chief of the Defence Staff (Personnel) (DCDS(Pers))
and using both internal and external expertise, identified that
the use of a commercial personnel software application to replace
the existing IT applications could both significantly reduce the
development and implementation risk and offer financial benefits
of up to £100 Million per annum which could then be used
in other areas of Defence. This solution incorporated a degree
of self-service by individual Service personnel, an approach that
was seen as both empowering the individual and being consistent
with the expectations of today's younger personnel who are joining
the Armed Forces familiar with the benefits of on-line transaction
processing. The proposed solution would also, for the first time,
provide a complete whole-life record for each Service person from
a single administration system and, thus, would provide MOD with
a comprehensive picture of the size and shape of the Armed Forces.
Data would be captured once and used many times.
The Defence Management Board endorsed the findings
of the study and the vision of personnel administration for the
Armed Forces that it presented to 2010 and beyond. They further
endorsed the use of a "commercial off the shelf" (COTS)
software package and mandated that the personnel policies, rules
and processes were to be adapted to achieve the simplest possible
implementation of the COTS approach. In doing so they recognised
that JPA was, in fact, a major business change programme involving
harmonisation and simplification across the whole of Defence and
not just an IT project.
The Investment Approval Board approved the JPA
programme at a total cost of £244.94 Million (excluding VAT).
The approval comprises all extramural costs for JPA and includes
the cost of personnel administration services using JPA up to
the end of financial year 2008-09. At the end of financial year
2006/07, actual spend on JPA was £162.8 Million which was
on target for that stage of the programme.
What is the progress to date in rolling out
the system across the three Services and when is the system expected
to be available to all Service personnel/other users?
In late 2001 the decision was taken to select
the ORACLE Human Resource Management System (HRMS) as the under-pinning
software application. Linked with this decision was a recognition
that the integrated nature of the personnel and pay processes
within both HRMS and the existing IT suites meant that it was
not feasible to "drip feed" functionality and gradually
move from the old to the new. It was, therefore, agreed that the
lowest risk option was a full implementation to each of the Services
in turn; this recognised that each of the Services would be faced
"over night" with a significant cultural change across
all areas of personnel support. The chosen implementation sequence
was RAF, RN, Army. Experience to date has shown that these decisions
were correct.
In order to release the resultant financial benefits
of JPA back to the rest of Defence at the earliest opportunity,
it was decided at the time of Defence Management Board endorsement
that implementation timescales and remaining within the approved
funding framework would be the key drivers for the project. The
availability of Defence Information Infrastructure (DII)[1][1]
would also be a key factor, and JPA timescales had to be adjusted
slightly to maintain alignment with the DII programme; JPA was
critically dependent on DII to ensure that sufficient IT hardware
would be in place to support the self-service concept. The DII
dates changed and, therefore, JPA dates had to change to maintain
alignment. The interface between the two programmes was successfully
managed by the Department's Change Delivery Group (chaired by
Second PUS). As a result, JPA achieved its implementation timescales
for the RAF (April 2006), RN (October 2006) and Army (April 2007).
The decision to focus on timescales required compromises to be
made, particularly in the critical areas of:
- Policy harmonisation and simplification
(with consequential impact on the complexity of the final HRMS
product).
- Single-Service, particularly RAF, ability to
complete the necessary training to utilise the new processes correctly
(with consequential impact on perceptions of JPA within the Services).
It is still, however, considered that any other
approach would actually have increased the risk to successful
implementation.
A strong programme governance structure was put
in place. The programme was sponsored by the then Vice Chief of
the Defence Staff (VCDS) and latterly by the 2nd
Permanent Under Secretary (2PUS) as head of the overall Defence
Change Programme; the Senior Responsible Owner (SRO), with full
accountability for its successful delivery, was DCDS(Pers). The
single Services and EDS, as the supplier of the IT solution and
much of the associated administrative support, were fully integrated
into the governance structure at equivalent levels.
As part of the governance, prior to each of the
3 Service implementations a series of formal Readiness Reviews
was conducted. These involved all levels of the governance structure,
up to and including 2PUS, and all stakeholder areas, both internal
to MOD and key suppliers, were fully engaged. The reviews considered
the readiness of all areas of the programme, technical and non
technical, and specifically addressed issues such as the readiness
of the receiving user community. The risks to the programme from
proceeding with the implementation at that point, versus those
associated with delay, were carefully analysed. At the end of
the process for each implementation there was unanimous agreement
from the senior stakeholders that, on balance, the implementation
should proceed in accordance with the planned timescale.
A key area of risk related to the harmonisation
and simplification of policy, rules, and processes. Service concerns
about issues such as impact on ethos meant that although very
significant progress was made, particularly with harmonisation,
there were some areas that, by the time that the design for the
technical development needed to be finalised, had not progressed
as far as envisaged at the time of Defence Management Board approval.
This meant that the technical solution was more complex and thus
took longer to develop than planned, with consequential impact
on time available for user training and cultural change; it also
had some impact on the financial benefits to be deliveredthese
have not yet been fully captured but are generally a reflection
on increased complexity including enhanced support arrangements.
An example of this was where an initial surge in the number of
service requests from personnel not familiar with the system meant
that an additional support team was formed. Notwithstanding this,
the implementation timescales were achieved and not a single payroll
run was missed at any stage of the preparation or implementation
processes; this is a very significant achievement on a payroll
of this scale and complexity. The Office of Government Commerce
recognised this in their recent "Gateway" review of
the JPA programme.
What are the problems experienced to date with
the system and what has been the impact of these problems? In
particular, what is the scale of the problems experienced by Service
personnel (including the number of Service personnel who have
been wrongly paideither overpaid or underpaid)?
There were relatively few technical issues at
implementation. The most significant issue arose very early after
RAF "go live" when system performance for self-service
users slowed to an unacceptable level, although background activities
such as payroll were not affected. As a result, self-service access
for all types of user was withdrawn for two weeks at the end of
April/beginning of May 2006, and there were also restrictions
for two to three weeks before and after this. The problem, which
related to the interaction between HRMS and MOD security profiles,
had not shown during the very extensive testing because it only
manifested when large numbers of self-service users were attempting
to log on to the system simultaneously.
Another major issue at RAF implementation was
the accuracy of specialist pay components, most notably Flying
Pay for aircrew. Although some technical issues were identified,
in the vast majority of cases the root cause was the unfamiliarity
of the various personnel in the end-to-end pay process (in the
case of Flying Pay, predominantly RAF career management and SPVA
staff) with the critical initial setting-up activities required.
This was down to delivery of the final product prior to implementation
being delayed by the complexity issue described above; it was
only available immediately prior to RAF go-live and this significantly
impacted on the ability to fully train all types of user.
The very constrained time for final preparations
prior to RAF implementation also seriously affected the ability
of the RAF senior management to prepare their Service for the
cultural change that would result from moving to a self service
environment from one where individuals predominately completed
paper forms which were then assessed and transferred to the IT
systems by Human Resource clerical support staff.
The EDS staff within SPVA's telephone and e-mail
Enquiry Centre (EC), set up to support JPA, also suffered from
the same very limited training window and, thus, were unable to
provide struggling users with adequate levels of support.
The lessons were learned after the RAF implementation
and the RN and Army implementations both went more smoothly. That
said, a number of issues have been apparent across all three implementations.
Key amongst these are:
- "Multiple referrals"
(where individuals
are passed backwards and forwards between SPVA EC staff and their
unit support staff or Service career management staff, with no
one seemingly able to resolve their problem).
- The effectiveness of the termination of employment
process.
- The ability of JPA and, in particular, the
COTS package which underpins it, to support MOD's existing finance
and accounting processes.
- The provision of adequate training at all
levels.
In all of these cases measures, such as revised
processes, have been agreed and implemented.
The media have reported a number of cases of personnel
being "underpaid". Payroll accuracy, however, is now
consistently in excess of 99% and, although a range of discrete
issues were identified at implementation, there are now no known
IT issues of any significance. The majority of the pay errors
are due to late or incorrect human input, either within SPVA or
by individuals and/or their unit support staff. In the early period
of implementation, there was a lack of robust support processes
and, as described earlier, both SPVA and Service HR professionals
lacked some of the training necessary to operate the system effectively.
Through the introduction of new support arrangements and better
training, the situation has been significantly improved.
In a number of cases, although a JPA pay error
has been reported, the impact on the individual was negligible.
For example, in August 2007 it was reported that some 35,000 RN
personnel had been underpaid; in fact this underpayment was only
£3 per individual and was the result of an error within SPVA
that was corrected the next month. There is no complacency and
the MOD acknowledges that all such errors should be eliminated
if at all possible. Whilst it is recognised that it is not necessarily
the IT solution that is to blame, there remains an ongoing requirement
to raise the awareness of those who play a part in the pay process
of their responsibilities in following the process correctly in
order to avoid unnecessary errors. A more detailed breakdown of
pay errors in the period January to November 2007 is below. This
does not include individual errors dealt with at unit level as
these are not captured centrally.
JPA OVER AND
UNDERPAYMENTS
| Month |
Overpaid |
Underpaid |
Total | Notes
|
| January | 161
| 1,383 | 1,544
| See Note 1 |
| February | 70
| 0 | 70
| |
| March | 229
| 54 | 283
| |
| April | 13,908
| 252 | 14,160
| See Note 2 |
| May | 0
| 1,181 | 4,521
| See Note 3 |
| June | 0
| 90 | 90
| |
| July | 2,978
| 416 | 3,394
| See Note 4 |
| August | 0
| 46,305 | 46,305
| See Note 5 |
| September | 0
| 722 | 4,971
| See Note 6 |
| October | 213
| 50 | 263
| |
| November | 1,987
| 311 | 2,298
| See Note 7 |
| Total | 19,546
| 50,764 | 77,899
| See Notes 3 & 6
|
| Notes (specifically relating to months with 500+ overpayments/underpayments):
1. Comprised 763 underpayments ranging from £98 to £348 due to a JPA formula error, fixed in month and 620 Substitution pay errors (~£150 underpaid) fixed in February.
2. A decision was made not to recover some elements of Service debt and miscellaneous charges until data accuracy on transition could be proved (13,908). Some of the underpayments (~100) were caused by non receipt of payable orders whilst 121 were caused by Late Entry Majors not being transitioned to their correct pay scale and was corrected in June.
3. The majority of the 1,181underpayments were caused by University Officer Training Corps input of bounties and training nights; other factors were mess subscriptions and disturbance allowance. The majority of the underpayments were resolved in May and June. There were a further 3,340 minor errors due to migration of some data elements which were mainly resolved in June, though the breakdown of underpayments vs overpayments is unknown.
4. The majority of the overpayments (2,611) were due to double payment of the female clothing grant (£4.50). The underpayments relate to late input of Cadet Force Home To Duty, which was resolved in month.
5. Comprised 35,553 incorrect deductions of £3.00 for the discontinued Royal Navy and Royal Marines Dependants' Fund, and 10, 752 underpayments of Home to Duty Travel claims for Royal Navy reservists. The former was re-credited to pay accounts in October, and the latter in September.
6. 4,249 additional cases occurred where the incorrect rank on JPA generated an incorrect payment. The breakdown between underpayments and overpayments is unknown, corrective action was taken in time for the October 2007 pay run.
7. A formula error resulted in 1,978 personnel receiving incorrect refunds of accommodation and CILOT charges. Corrective action was taken in November 2007.
|
What progress has been made in resolving the problems experienced
to date and what outstanding issues have still to be resolved?
There are four main areas where more work is required
before JPA can be considered to have delivered its Vision, as
endorsed by the Defence Management Board. These are:
- Improvements to the provision
of Management Information (MI).
- The control framework around the JPA processes
to ensure that not only are the processes being followed correctly,
but that the processes themselves do not allow opportunity for
fraudulent behaviour such as, for example, individuals making
multiple or inflated claims.
- Improvements to the EC and back-office functions.
- Reduced "cost of ownership" through
further harmonisation and simplification of the personnel administration
and pay policies, rules and processes.
Of these, it is only the provision
of MI that would not necessarily be considered as part of the
normal business improvement agenda at this stage of a programme
as large and complex as JPA. It was envisaged that, for the first
time, JPA would provide a single authoritative source of military
personnel data (other than medical information) and, as such,
that it would allow for the production of high quality information
to support decision making across Defence. SPVA and the Services
are working closely together to exploit what is available and
to establish a common basis for future development but this is
still in its early stages. It is being taken forward not just
as part of JPA development but also alongside the MOD-wide initiative
to develop improved MI capability.
What is the current relationship with the contractor
for the JPA system, given the problems experienced to date?
JPA was delivered through the existing contract
between SPVA and EDS rather than through a separate commercial
arrangement. The decision to follow this route was subject to
Defence Investment Approvals Board (IAB) endorsement and was taken
on a combination of value for money and risk to successful and
timely implementation grounds. The initial performance issue at
RAF implementation with the system slowing down to an unacceptable
degree was dealt with as a joint problem, with EDS bringing in
not only their own best people from around the world but also
using their influence upon ORACLE and others, including Microsoft,
to ensure that their deep experts on HRMS were fully involved.
Throughout the JPA development and implementation process, the
relationship with EDS has remained strong, with excellent support
and regular dialogue between MOD and the Corporation at the highest
levels. From a technical perspective, EDS have built a product
that is fit for purpose against a very demanding user requirement
(due to the limited achievement of harmonisation and simplification)
and timescale. They do, however, recognise that some aspects of
their non-technical support to SPVA were not as mature as they
might have been at the time of implementation and they have applied
much effort and resource to correcting that since RAF implementation
18 months ago, working closely with the MOD to bring about the
necessary improvements.
SUMMARY
JPA should be considered as a business change
programme with IT as a key enabler, rather than as just an IT
project. As such, its impact on personnel administration and the
associated culture across both the Armed Forces and SPVA has been
significant. As a business change programme, at the time of its
development, it was one of the largest being undertaken anywhere
in the World. It was delivered to time and budget in spite of
the final technical solution needing to be significantly more
complex than originally envisaged. Although the initial system
performance issues got the implementation off to a difficult start,
few of the issues that have arisen since then have been due to
fundamental flaws within the HRMS IT solution constructed by EDS
to meet MOD's requirement. SPVA/EDS staff and personnel throughout
the Services are, however, still coming to terms with how JPA
impacts on their individual roles. In some areas the JPA processes
themselves are proving difficult to utilise reliably and accurately,
with consequential impacts on payroll accuracy. Overall, payroll
delivery is as least as good as under the previous IT environments
and processes, but there remain a number of areas where further
improvements are required. JPA is now a stable product that provides
an excellent foundation for further optimisation and modernisation
of the administrative support arrangements for members of the
Armed Forces.
The Comprehensive Spending Review
33. (Recommendation 25) The Comprehensive Spending
Review 2007 settlement for defence announced in July 2007 provides
"an additional £7.7 billion for defence by 2011, and
a 1.5 per cent average annual real terms increase". We welcome
the increase in the MoD's budget for the next Spending Review
period. However, the defence budget will be under substantial
pressure in the period covered by the 2007 Spending Review, given
that several funding commitments, such as the future carrier programme,
a pay increase for the Armed Forces, and further investment in
accommodation for Service personnel, have been announced. These
will need to be met from the average annual 1.5% real terms increase
and the cumulative efficiency savings which are referred to in
paragraphs 108-109 of the report. In order to fully appreciate
how significant these pressures are, we would like to see a clearer
description of what resources from these "savings/efficiencies"
are available to meet these pressures and urge the MoD to seek
ways of spelling this out more clearly in future reports. (Paragraph
110)
In playing its part in Value for Money (VfM) delivery,
the MoD has committed to making at least £2.7Bn in net cash-releasing
savings over the CSR07 period. These will be aimed at ensuring
resources are delivered to front line priorities through cash-releasing
savings generated by: continuing to improve efficiency in all
aspects of defence business; by taking advantage of technological
gains which improve the effects of modern weapons and delivery
platforms and by re-prioritisation of activities and capabilities
within Defence. Over 25% of the Department's VfM savings are expected
to derive from major efficiency measures such as 5% real annual
reductions over the CSR period in administration costs (primarily
delivered by streamlining corporate services) and further reform
in logistics delivery. Additional efficiencies, albeit on a smaller
scale, will also be delivered through continued improvement in
energy efficiency, and from the programme of normalisation in
Northern Ireland. The Department will also make allocative savings
within the defence programme. This means that to ensure a continued
focus on the delivery of Departmental Strategic Objective (DSO)
outputs, we will take decisions to reallocate resources from lower
priority areas thus freeing up resources to the front line. In
all cases, the aim will be to achieve the performance indicators
set in the DSOs. A high level outline of how these savings are
to be achieved is set out in our VfM Delivery Agreement.
34. (Recommendation 26) We note that the costs
of replacing the current nuclear deterrent will amount to some
£1 billion over the three years of the Comprehensive Spending
Review 2007 period. The MoD told us that the undertaking in the
White Paper, that these costs are "provided additionally"
and will not impact upon conventional capability, has been met.
(Paragraph 112)
The Comprehensive Spending Review Settlement has
provided resources in the core Defence Budget to allow work to
proceed on the successor for the nuclear deterrent. This honours
the Government's commitment in the White Paper on the Future of
the Nuclear Deterrent "that the investment required to maintain
[the nuclear deterrent] will not come at the expense of the conventional
capabilities our armed forces needs."
35. (Recommendation 27) We note that the MoD is
currently preparing advice to ministers about the defence budget
for the three years 2008-09 to 2010-11. The MoD acknowledges that
there are pressures in the defence programme and that there are
likely to be cuts in some areas, including cuts to the equipment
programme. We look to the MoD to be realistic about the number
of equipment programmes, the number of platforms within equipment
programmes, and the phasing of equipment programmes, that can
be funded. We plan to monitor the progress and the outcome of
the current planning round closely. (Paragraph 117)
We recognise the need to be realistic about the equipment
programme, to ensure that it provides the tools that the Armed
Forces require to meet the challenges that they face both today
and tomorrow. We are currently engaged in our regular planning
round to ensure that this is the case. We welcome the chance to
engage with the Committee once decisions on future priorities
have been made.
36. (Recommendation 28) The Comprehensive Spending
Review 2007 settlement for defence is reported as being a 1.5
per cent average annual real terms increase against the MoD Comprehensive
Spending Review baseline. But this is based on the general rate
of inflation and takes no account of the reportedly higher rate
of inflation which applies to defence products, in particular
advanced equipment projects. We look to the MoD to press ahead
with its plans to develop a robust price index for defence products
which will assist the MoD in both its financial planning and in
its negotiations with the Treasury in future spending reviews.
We consider that a robust price index for defence products is
vital for allowing real comparisons to be made and to enable the
Committee to undertake more effective scrutiny in this area. (Paragraph
123)
Work is underway on developing a robust measure of
inflation for total defence expenditure. We note the Committee's
close interest in this. It includes identification and collection
of suitable data; the design of methods and applications for storing
and aggregating the data; and the validation and testing of the
outputs. To construct a measure for total defence expenditure
we will need to collect data relevant to: service and civilian
pay; long-term equipment, support and construction expenditure;
and shorter term commodity and service purchases:
- service and civilian pay data
should be available from MoD administrative systems, although
its coverage and quality will require some work. A base-weighted
index for military pay is already published in UK Defence Statistics
and a similar index for civilian pay could be calculated;
- measuring defence equipment inflation is inherently
difficult as it involves measuring price change for defence products
adjusted for quality and quantity. Our initial approach based
on matching micro level producer price data from the Office for
National Statistics to MOD contractors failed to produce a sufficiently
robust measure because there is no single industrial classification
for defence, and capital expenditure is often through long-term
contracts for unique pieces of equipment which do not lend themselves
to price comparisons across time. For successive generations of
equipment it is not usually possible to separate out the changes
in specification from pure price movements, and this can be further
complicated by contracts that offset some current costs with future
payments to make programmes more affordable. To construct an index
for this element of Defence expenditure we will therefore need
to collect detailed information on extant contracts; develop a
robust data store for the data; and then ensure the data is kept
up-to-date with details of new and amended variation of price
clauses; and
- identifying all logistic commodity buys and separating
out the inflationary element of the prices will be a challenge,
although good information on the prices and quantities of fuel
purchased already exists. Expenditure data by Standard Industrial
Classification is available from the Department's contracts database
and this can be linked to relevant Producer Price Indices to produce
a base-weighted index.
These different sources of inflation can then be
aggregated together based upon the Department's expenditure in
the previous year, from which it should be possible to produce
a Defence Inflation Index for total Defence expenditure. This
will however be resource intensive and we expect it will take
up to two years to complete. Until then it will be difficult to
provide coherent estimates for the different rates of inflation
that affect the Defence budget.
1 1 DII's Strategic
Intent is to provide 'One Information Infrastructure' by delivering
to Defence a secure and coherent information infrastructure at
minimum whole life cost whilst maintaining continuity of service.
The Project's scope is 154,000 terminals to 300,000 users at all
static land based sites in UK, all Permanent Joint Operational
Bases and other permanent overseas sites, to component Commander
HQs, all maritime platforms, 3 Commando Brigade, Deployed Operating
Bases and the Deployed Land Environment. Back
Back
|