Support to SMEs
60. The Government's initiatives to encourage SMEs
to compete for government contracts included
- establishing a website (Supply2Gov)
through which lower value contracts (worth less than £100,000)
can be accessed. The OGC reported that, since its launch in March
2006, more than 50,000 businesses and over 3,500 public sector
authorities had registered, and nearly 50,000 contracts had been
published, on the website;
- the introduction of a Small Business Concordat
for Local Government;
- the standardisation of the pre-qualification
questionnaire for smaller contracts;[151]
and
- a training programme, piloted in the West Midlands,
for SMEs in the public procurement process.[152]
61. The FPB felt that, while welcome, these developments
did not go far enough.[153]
It said that SMEs needed more information and training on how
to access government contracts, noting that in the USA this was
supplied partly through the Small Business Association and partly
through the government, which had paid for training for potential
suppliers, both small and large. The US government had also required
its primary contractors to work with their sub-contractors to
improve their understanding of and ability to tender for public
contracts.[154] On
the other hand, Midlands Fashion Showcase, a regional trade association
for the textile and clothing industry, thought there was scope
for small specialist contractors to work together on a regional
or even inter-regional basis to secure procurement contracts.[155]
Other witnesses, such as Amicus, thought that tendering processes
might be simplified further by greater use of information technology,
though they did not specify which parts of the process could be
improved in this way.[156]
Conversely, the British Furniture Confederation Public Sector
Working Group cautioned against e-auctions on the basis that they
precluded any development of a relationship between purchaser
and potential supplier, ruling out any possibility of improvements
to specification or delivering environmental or other benefits
additional to the specification, because they operated merely
on the basis of the lowest bid.[157]
The OGC argued that e-auctions did not have any effect on specifications
or the employment of environmental criteria, etc, because they
were undertaken only at the very end of the procurement process,
when all other factors had been taken into account and the sole
difference between bids was the price. It also pointed out that
e-auctions had produced significant savings: in the half dozen
or so IT projects that had been subject to e-auctions, savings
of 20-50% had been achieved.[158]
62. The FPB proposed other changes: the setting of
a target percentage not, it emphasised, a quota
of government contracts to be awarded to SMEs; 'set asides', limiting
tendering for contracts to small businesses where, for example,
the small firms in an industry are so economically dependent on
one or two large companies that the small companies would be deterred
from bidding if the large companies took part; limits on non-competitive
tendering (or 'preferred bidders'); more public consultation on
procurement regulations; and guidelines on the use of lists of
qualified bidders.[159]
The FPB argued that several of these, together with provisions
enabling 'smart' procurement, would be likely to be ruled illegal
under the WTO Agreement on Government Procurement ('AGP'), which
was why it considered the UK should seek opt-outs from the AGP.[160]
It denied that an opt-out could be equated with simple protectionism:
the goal was to give special support to small companies, whatever
the nationality of the owner or the country where the goods or
services were produced.[161]
Nor did it think that any opt-out would have a significant effect
on the ability of UK businesses to win public contracts abroad.[162]
63. None of our other witnesses claimed that the
AGP formed a significant barrier to adopting practices that might
better assist SMEs to compete for public sector contracts. Furthermore,
the opportunity for seeking an EU opt-out from provisions of the
AGP has now passed. We, therefore, leave the issue of the AGP
to one side.
64. The FPB argued vehemently that only a target
for the award of contracts to SMEs would suffice to entrench best
practice in the many government organisations that have to procure
goods and services.[163]
It suggested that the target should be set above the current level
of participation but below that prevalent in the private sector.[164]
The Small Business Service specifically rejected targets for SME
involvement, arguing that case-by-case comparisons were a more
effective form of analysis.[165]
The OGC repeated the Small Business Service's view that
it was impossible to decide what the right level of SME participation
was so, by implication, a target was not only difficult
to establish but also unhelpful.[166]
In practice SMEs in the UK have almost reached the target set
in the USA for SME participation in public procurement
of 23% of direct procurement and 40% of sub-contracted procurement.[167]
Also, the target for SME participation in government-procured
R&D in the UK has been not only met but exceeded, but it appears
that quality the benefits to the Government and to the
companies themselves has been more difficult to achieve
than quantity. We doubt whether
the establishment of a target in relation to general procurement
would greatly assist small businesses.
SMEs and the Government's efficiency
drive
65. We also examined the effects on small businesses
of the Gershon programme of efficiency savings, part of which
involves the centralisation and rationalisation of procurement.
We have already mentioned that the OGC considered the framework
approach the bundling of contracts into larger, longer-term
ones to offer a reduction in bureaucracy and to benefit
both government and business. This view was disputed by several
organisations. The FPB argued that there might be economies of
scale in the short run from centralising procurement, but in the
long term, as potential suppliers were squeezed out of the market,
there would be less competition in the supply of goods and services
to the public sector, with a resulting increase in cost and reduction
in quality.[168] The
FPB gave an example of where it thought better value for money
and greater competition might have ensued from the breaking down,
rather than bundling up, of contracts: the provision of 69 regional
interview offices for the issue of biometric passports and identity
cards.[169] The Federation
of Small Businesses also thought that SME participation in procurement
contracts would be improved if the UK government imitated the
practice of 93% of German and 98% of French public authorities
by breaking down contracts into smaller parcels.[170]
66. The National Federation of Builders has recently
completed research which measures the impact of the efficiency
agenda on SMEs in the construction industry.[171]
460 companies responded, representing 27% of the Federation's
membership. About two-thirds of these companies undertook work
within the private sector, and a total of 205 companies reported
that public sector work represented more than half their turnover.[172]
For our purposes, the most significant findings were that while
32% of companies overall reported that there had been a decrease
in the volume of public sector work they had undertaken over the
last five years, SMEs[173]
were more likely to have experienced stagnation or a decrease,
while larger companies were more likely to report an increase.
All 19 companies that reported they had ceased to work for the
public sector in the previous five years had turnovers of less
than £10 million a year.[174]
For all companies, the most frequently cited cause of a decline
in public sector work was "changes in public procurement
practices" and the second most frequent was "changes
in the volume of public sector work". However, companies
with a turnover of less than £500,000 were more likely to
think that a decrease in the volume of public sector work was
the main reason for the decline.[175]
The Federation concluded: "This suggests that relatively
smaller enterprises are disproportionately experiencing a decrease
in the availability of public sector work, a situation that may
have arisen as a result of the drive towards efficiency gains
in public sector work (Gershon, 2004), the establishment of frameworks
or a re-prioritisation of maintenance and/or small scale projects."[176]
Also, despite the belief that frameworks would provide better
opportunities for SMEs through sub-contracting, the Federation's
findings were that such opportunities "have either not materialised
or are not being pursued." Only 59 companies reported that
they had worked as sub-contractors within a framework contract.
Although 34 of the 59 were companies with a turnover of under
£2 million, these were a minority (23%) of all companies
with a turnover of less than £2 million that had worked for
the public sector.[177]
67. The British Printing Industries Federation was
of the view that some approaches designed to speed up procedures
hindered rather than helped competition. It said the OGC had established
that tenders for print services above the EU threshold typically
took 12 months to complete and had developed a different system
in which such contracts were broken down into lots below the threshold,
and those lots were then subject to competition among companies
on a list. The problem from the point of view of the British Printing
Industries Federation was that the list comprised only 200 out
of the 12,000 print companies and was valid for about four years.[178]
68. Centralising
procurement, bundling tenders and seeking economies of scale appear
to conflict with the Government's aim of increasing SMEs' access
to public procurement contracts. The findings of the National
Federation of Builders about the overall decline in SME participation
in construction work and the failure of frameworks to provide
the sub-contracting opportunities hoped for indicate that it will
be difficult to avoid disadvantaging SMEs (and therefore, in the
medium term, reducing competition and innovation) as the efficiency
drive in procurement goes ahead.
69. The FPB argued: "By far the
greatest economic folly committed by government is single-sourcing.
It is simply not economic not to seek as many tenders as possible
for each and every contract, and yet, in many cases, preferred
suppliers are used without the necessary competitive tendering
process. Firstly, this discriminates against smaller businesses,
and causes misallocation of resources in the economy. Secondly,
a lack of or limited competition in the tendering process causes
prices to be inefficiently high and wastes taxpayers' money."
It added that the Small Business Administration in the USA had
advocates working with government departments to ensure that tenders
were put out to competition rather than being allocated to a preferred
supplier.[179] In contrast,
British Expertise thought that other government departments could
become much more efficient in procurement if, like the Department
for International Development, they allowed desk officers to purchase
straightforward items of below a certain value without any form
of tendering.[180]
70. Much that
the Government has been doing improving the availability
of information about contracts, encouraging local authorities
to sign up to the Concordat, training both purchasers and sellers
was considered by our witnesses to be helpful to
SMEs, even though in some
cases they felt the Government should do more in these respects.
There was far less agreement on other avenues that the Government
should pursue. In almost every case, any recommendation for changes
to procurement practice made by one of our witnesses was opposed
by another. Procedures designed to increase efficiency were seen
as harming SMEs; attempts to make contracts more accessible to
SMEs as slowing down procurement or increasing costs; social clauses
and environmental aims as adding bureaucracy; attempts to promote
innovation as increasing complexity for the officials who make
procurement decisions, or giving 'insider' companies advantages
over their competitors. There is clearly a limit to what can be
achieved through across-the-board changes to procedures. The focus
must be on the way individual decisions are taken. There is no
shortage of OGC-sponsored advice and best practice guidance on
these issues. Better performance against the Government's objective
of increasing SME participation in public procurement therefore
depends on two things that we strongly support: better trained
and more experienced personnel in charge of procurement, and a
change in the emphasis of the OGC from advice to enforcement.
130 DTI's Departmental Annual Report 2006,
p 145 Back
131
Small Business Service, A Study of the Benefits of Public
Sector Procurement from Small Businesses, 2005, pp 101-103 Back
132
Appendix 25 (FPB) See also Appendix 29 (Leslie Kossoff) Back
133
Appendix 24 Back
134
Small Business Service (2005) Access to Public Procurement
for Small and Medium Sized Enterprises Progress Report - December
2005 p. 4 In both cases the statistics exclude Health
Service and Ministry of Defence spending. Back
135
Appendix 25 (FPB) See also Appendix 29 (Leslie Kossoff) Back
136
Qq 401-403 Back
137
European Commission (2004) The Access of SMEs to Public Procurement
Contracts p. 240-242 Back
138
Some aspects of the USA's approach are discussed in Paragraphs
61, 62 and 64below For details of the USA's procurement policy
since 1942, see Appendix 25 Back
139
Appendix 25 Back
140
Appendix 24 Back
141
Appendix 25 (FPB) Back
142
Appendix 29 (Ms Kossoff) Back
143
Appendix 25 (FPB) Back
144
Qq 454-456 See also 'NHS suppliers hit by late payment of bills',
Financial Times, 13 February 2007, p4 Back
145
C20 Back
146
Of payment within 30 days. See, for example, the figures for
financial year 2005-06 in HC Deb, 24 July 2006, col 93 WS Back
147
Appendix 25 (FPB) Back
148
Trade and Industry Committee, Second Report of Session 2002-03.
The Use of Retentions in the UK Construction Industry,
HC 127 and Fifteenth Report of Session 2002-03, Retaining Retentions?,
HC 976 Back
149
Q 750 Back
150
Q 453 Back
151
See paragraph 18 above Back
152
Appendix 18 and Q 711 Back
153
Appendix 25 Back
154
Qq 444-445 (Ms Kossoff) and Appendix 25 (FPB) Back
155
Appendix 36 Back
156
Q 220 Back
157
Appendix 6 Back
158
Q 751 Back
159
Appendix 25; on set aside, see also Q 441 Back
160
Q 411; Appendix 25 gives details of the AGP Articles that may
preclude specific changes to the UK's procurement rules Back
161
Qq 407-410 and Appendix 25 Back
162
Q 412 Back
163
Appendix 25 Back
164
Q 405 and Appendix 25 Back
165
Small Business Service, A Study of the Benefits of Public
Sector Procurement from Small Businesses, 2005, pp 101-103 Back
166
Q 714 Back
167
Q 405 Back
168
Qq 439-440 Back
169
Appendix 25 Back
170
Appendix 24 Back
171
The impact of public sector procurement on SME construction
companies, September 2007 (hereafter 'NFB Report') Back
172
Ibid., Executive Summary Back
173
Defined for the purposes of the National Federation of Builders's
report as companies with a turnover of less than £25 million
a year Back
174
NFB Report, pp 25-26 Back
175
Ibid., p 27 Back
176
Ibid., pp 46-47 Back
177
Ibid., p35 Back
178
Appendix 8 Back
179
Appendix 25 Back
180
Q365 Back