Examination of Witnesses (Questions 320-339)
MR ANDREW
ROLLERSON
7 MARCH 2007
Q320 Mr Bacon: It is not being immodest
to say that.
Mr Rollerson: No.
Q321 Mr Bacon: I did not think you
were being immodest. Mr Hutchinson also raised in a letter last
Junethis was at my request, that the letter was sent to
the Committeethe number of patient administration systems
that were being installed between June and the end of October,
just a period of four months. In his letter Mr Hutchinson said
that there would be 12 hospitals and he listed them, we have copies
of those in our evidence already. So far only four of those have
installed the systems and the other eight have not. Why do you
think that is? Is it basically because there are serious problems
with the software because it is not suitable for the NHS in its
present form if it has got things like billing on it, which is
an American concept and is not appropriate here, or what? What
are the reasons for those delays?
Mr Rollerson: The initial reason
for the delay was the change of supplier, of course.
Q322 Mr Bacon: You mean when IDX
were sacked?
Mr Rollerson: Yes, when IDX were
sacked and they were replaced by Cerner.
Q323 Mr Bacon: Can you remind the
Committee how long IDX were there for before they were sacked?
Mr Rollerson: I honestly cannot
remember, but it was a matter of maybe 12 months, I am not sure.
Subsequently, the service system was modified to meet the requirements
and Fujitsu has worked with the local NHS trusts through the contracted
mechanism to make the changes to the specification to meet the
requirement, and the deployment projects have been underway in
many trusts for some time.
Q324 Mr Bacon: But this was a fairly
short-term schedule, this was saying at the end of June what they
had done by the end of October.
Mr Rollerson: There is no difference
actually in some of the problems faced by this particular programme
from many IT programmes; in other words, it is when it comes to
things close to implementation, such as data migration, Reporting
or printing across networks and things of this sort, that problems
tend to emerge which need to be addressed before a go-live can
take place. These cannot necessarily be anticipated and I think
many of these problems caused the implementation timescales to
be drawn out more than one would have hoped, but the momentum
for deployments has now risen significantly. I think there are
five rather than four deployments under way and the rest are scheduled
over the next few months, so the momentum has picked up and the
programme has recovered in that respect.
Q325 Mr Bacon: There are loads of
bugs in the software, are there not?
Mr Rollerson: There are always
bugs in software.
Q326 Mr Bacon: Is it not true that
some of the hospitals, like Winchester, have had to take many
steps backwards rather than forwards in terms of having to do
things like clinical noting and prescribing compared with where
they were before?
Mr Rollerson: That is nothing
specifically to do with bugs in the software. In order to be part
of the programme, the trusts have had to accept that they will
be taking Cerner Millennium in its entirety, built to a specification,
as it is laid down in the contract, over a series of releases.
In some cases, the trusts have invested in the sorts of point
systems which have functionality that goes beyond the functionality
they will receive as the first stage of the Millennium deployment,
but this is the price a number of them need to pay in order to
be part of a much broader, larger programme and it is inevitable
that will be the case.
Q327 Mr Bacon: When the go-live date
is set and then there is a delay, there is a cost to the trust
in terms of staff time, training foregone which is not used and
so on. It is very disruptive having a new computer system installed.
Mr Rollerson: Delays, yes.
Q328 Mr Bacon: That includes, effectively
to the trust, a financial cost.
Mr Rollerson: It does, but the
delays are not necessarily attributable to the software. There
have been delays on both sides.
Q329 Mr Dunne: Mr Rollerson, the
Computer Weekly article of 13 February referred to the
concerns of 23 senior academics. Were you aware of the concerns
raised by that group?
Mr Rollerson: I was not.
Q330 Mr Dunne: Have you had sight
of the open letter to the Health Select Committee that group submitted
in April last year?
Mr Rollerson: No, I have not.
Q331 Mr Dunne: Have you had any discussions
with any of the 23 signatories to the letter?
Mr Rollerson: Yes, I have. I met
a number of them at the London School of Economics last October.
Q332 Mr Dunne: One of signatories
was Dr Ewart Carson who happens to be a constituent of mine and
somebody you spoke to directly. Do you recall that?
Mr Rollerson: I do not recall,
it is possible that I did speak to him.
Q333 Mr Dunne: The thrust of their
concerns fell, I think, into two broad categories, the first was
the risks to the security and confidentiality of patient data,
and the second was the lack of technical oversight within the
Department of Health for the project that they were embarked upon.
Do you recognise those as the principal thrusts of those concerns?
Mr Rollerson: Yes, I do.
Q334 Mr Dunne: Do you share their
views?
Mr Rollerson: No, I do not. Personally,
I see no concern around data confidentiality because a lot of
effort is going into making sure that is dealt with adequately.
Clearly, no matter how old the system is, if users share their
smart cards or log-ins, there is nothing that the most rigorous
system design can cater for.
Q335 Mr Dunne: Does the system, as
far as you are aware, conform with patient data confidentiality
required under the Data Protection Act?
Mr Rollerson: I am not qualified
to answer that.
Q336 Mr Dunne: Are you aware that
the Health Select Committee has decided to instigate a review
into this project this year?
Mr Rollerson: I am not aware of
that either.
Q337 Mr Dunne: You have not been
asked to submit evidence to that select committee?
Mr Rollerson: No, I have not.
Q338 Mr Williams: Does this mean
state-of-the-art work?
Mr Rollerson: I am sorry?
Q339 Mr Williams: Does this project
mean state-of-the-art work or is it possible to use off the hanger,
equipment and software?
Mr Rollerson: It is essentially
being deployed with existing technology which is being modified,
as all applications are, to meet the requirements of the contract.
|