APPENDIX 11
Memorandum submitted by Stagecoach Group:
Rail Division
EXECUTIVE SUMMARY
1. Stagecoach Group is the current operator
of South West Trains and Island Line on the Isle of Wight. We
are currently involved in the process of bidding for the South
Western franchise, which will cover both South West Trains and
Island Line.
2. In this submission we address particularly
two of the Committee's principal questions: how well does the
process for awarding franchises work; and are franchise contracts
the right size, type and length.
3. On the first point, introduction of the
franchise structure was intended to free the railway from an annual
round of budget-setting. But the corollary is that there is a
need to determine budgets and plans for the duration of the franchise
during the bidding process. This can of course be complicated,
and so time-consuming and resource-intensive, and has led to some
comment about bid costs. There is a particular issue with "over-heating"
in the specialist consultancy sector to support these bids.
4. The cost issue is compounded by the fact
that the Department for Transport has not had a procurement model
settled from one franchise to the next.
5. The resulting high cost of bidding in
the end impacts on the cost of the franchise. Any proposal that
would streamline the process, even to a limited extent, would
be welcomed by all train operators, including Stagecoach Group,
and would also benefit taxpayers and the travelling public.
6. On the second point, the main issues
are the length of each franchise and how prescriptive are its
terms. Operators are resourceful, and will adapt to the circumstances
presented to them. But longer franchises allow for improved planning,
and the possibility of greater and more imaginative investment
on the part of train operators.
7. The degree to which the franchise is
prescriptive also has a bearing on how imaginative investment
plans will be. In particular operators are resistant to over-regulation
on the revenue and timetable sides, since that limits their freedom
for manoeuvre and to deliver the management of capacity.
8. We accept the current structure of franchising,
but believe that there are changes that can be made that will
ultimately benefit the travelling public and taxpayers. The Committee's
inquiry is timely, and we welcome it. We look forward to its conclusions,
and to learning from its report.
INTRODUCTION
9. Stagecoach Group is one of the world's
leading transport operators with train, bus, tram and express
coach operations in the UK and North America. Our rail division
includes being franchise holder for South West Trains and for
Island Line on the Isle of Wight, as well as a 49% holding in
Virgin Rail Group, which runs the West Coast and CrossCountry
franchises.
10. We are proud of the way in which we
have managed the South West Trains and Island Line franchises.
Earlier this year we were awarded HSBC Rail Business of the Year,
and we were named the Passenger Operator of the Year at the National
Rail Awards in September 2005.
11. Stagecoach Group is currently bidding
to retain the South Western franchise, which incorporates the
existing South West Trains and Island Line. As the Committee will
understand, this has placed considerable demands on our resources,
and we have not been able to prepare written evidence as fully
as we would have liked. Nevertheless, we trust that this memorandum
is of use to the Committee.
How well does the process for awarding franchises
work?
12. Stagecoach Group has recently been involved
in the process of bidding for the Inter City East Coast, Greater
Western, Thameslink, Great Northern, and Integrated Kent and South
Western franchises. Stagecoach has operated the South West Trains
franchise from 1995, receiving a four-year extension to the franchise
in 2002. Our comments below derive from our experience as an operator
and as a bidder.
13. Prior to the introduction of the franchise
structure the railway was subject to an annual round of budget-setting
by the Department of Transport. It was argued that this inhibited
long-term planning and constrained investment. The franchise system
was intended to move the railway away from short-termism, and
it has generally been successful in doing so.
14. However, the consequence is that budgets
for each franchise must be set prior to its award, and they must
be valid for the duration of each franchise. Thus the plans and
documentation tend to be long and the process of compiling them
is time-consuming for all bidders, and is therefore costly.
15. Current invitations to tender for franchises
also require respondents to prepare a large number of very detailed
documents. Indeed, just to get on a tender shortlist and receive
a prequalification document requires the submission of two or
more substantial folders of evidence.
16. In addition, some aspects of the franchise
bid require the input of very specialist consultants. Their numbers
are necessarily limited, and with typically five companies short-listed
for each tender they are in high demand. This can lead to "over-heating"
in the consultancy sector, further inflating costs for the whole
rail sector. If consultancies are guaranteed a stable base of
franchise work then costs will come down over time. If there is
feast and famine then we expect the average cost of consultancy
to rise. This is particularly the case if a high level of detail
is asked for in the Invitation to Tender.
17. Another factor driving up costs is the
fact that the Department for Transport (DfT) has not made use
of a settled procurement model for different franchises. Indeed,
all bidders have experienced that the evaluation model can evolve
through "clarification" during a bid process,
leading to frustration and abortive cost. Greater uniformity in
the technical specification of each tender, and in the methodology
of bid assessment, would help to reduce the cost of bidding and
thus the cost to passengers and taxpayers.
18. The DfT has been open to change and
hasfor exampleheld trade days where bidding groups
can feedback on DfT's processes. Whilst this supports continuous
improvement in principle it can create continuous change from
franchise competition to competition in practice. This has increased
costs.
19. This memorandum is not a criticism of
the franchising process per se. As we have said, we do
understand the need for robust budget-setting and planning before
franchises are awarded. However, judging from train operating
company owning groups' reports and accounts, it is the case that
the cost of bidding is high. In the end costs incurred in bidding
are reflected in the cost of the franchise, and thus impact on
DfT finances.
20. Therefore, streamlining and simplifying
the bidding process, even to a limited extent, would be of direct
benefit to taxpayers. Our initial proposal is that DfT establish
a settled procurement model which is used for different franchises.
We look forward to the other recommendations of the Committee.
Are franchise contracts the right size, type and
length?
21. Our concerns in respect of this second
question are the duration of franchises, and the degree to which
their terms are prescriptive. Although train operating companies
are resourceful and adaptable, there are clear benefits for taxpayers
and the travelling public if franchise lengths and conditions
are optimised.
22. It is self-evident that train operating
companies will only plan for investments that will deliver improvements
during the term of the franchise. Franchises of shorter durations
inevitably discourage investments for radical change. Instead
train operating companies focus on incremental, relatively small-scale
improvements. It is equally evident that longer franchises allow
companies to plan greater and more imaginative investment, particularly
in relation to managing for capacity.
23. For example, the 20-year Chiltern Railways
franchise is often rightly cited as including plans for investment
which were far more wide-ranging than were contained in shorter
franchises elsewhere. Clear benefits for passengers and indeed
for taxpayers, in terms of the rail service delivered and particularly
in station and capacity improvements, have resulted.
24. It was originally mooted that the new
South West Trains franchise to run from 2002 would be for 20 years.
Stagecoach Group's proposals for the franchise included plans
for investment which would have led to a step-change in the service
provided. This was particularly the case in relation to capacity,
where we planned for platform extensions at many stations to permit
a 10-car railway. It is not surprising that the one year franchise
extension plus three year new franchise that was eventually agreed
did not include such measures.
25. To develop the point, Stagecoach Group
also supports the idea of vertical integration within franchises,
bringing together those responsible for the operation of trains,
and those responsible for the track. That was the proposal for
the 20 year South West Trains franchise proposed in 2002. Such
integration would, in particular, help in the co-ordination of
the investment required for capacity improvements, since it would
allow consideration of platform extensions alongside the need
for longer trains and more rolling stock.
26. There is also a casewhich the
Government has to an extent taken upfor fewer and bigger
franchises. The travelling public, and the taxpayer, want a joined-up
railway in which services complement one another, and in which
operators are best placed to respond flexibly to demand, delivering
additional capacity where it is required. Bringing together smaller
franchises, such as is the case with the Greater Western franchise,
helps to provide that flexibility.
27. Another issue to be considered is the
degree to which franchises are prescriptive. If operators are
unduly trammelled by franchise conditions that will also affect
how imaginative their plans will be.
28. Particular concerns relate to the regulation
of fares and the specification of timetables. Having freedom,
to a degree, to set fares allows operators to manage demand. There
is of course a good case for controlling peak fares, but outside
the peak it is important that fares can be increased or decreased
to respond to demand, and to maximise usage. Having this freedom
has, for example, allowed Stagecoach Group to institute its megatrain
service on South West Trains, and now on Virgin Trains services.
29. Similarly, over-prescription in relation
to the timetable constrains operators in the services they can
deliver. It is clearly the case that on some lines, particularly
close to London, variations in the timetable are not possible
due to a lack of capacity. But it is important to allow operators
to be responsive to passengers. Setting the timetable in stone
at the beginning of the franchise may mean that such responsiveness
is impossible. We also firmly believe that Train Operators are
best placed to optimise timetables.
30. In short we believe that franchises
should balance the need for Departmental oversight and management
with being of sufficient length, structure and flexibility to
allow operators to plan for investments that will deliver significant
change. They must also give operators room for manoeuvre.
CONCLUSION
31. Stagecoach Group accepts the current
structure of franchising, but believes there are areas in which
improvements might be made that would improve both the structure
and the process. We have described some of those areas in this
memorandum; other stakeholders will doubtless have other proposals.
32. There are lessons that can be learned
from the on-going round of recent and forthcoming franchise awards.
Therefore the Committee's inquiry is timely. We look forward to
its conclusions, and to learning from its report.
29 June 2006
|