Supplementary written evidence from the
Rail Passengers' Committee Wales
THE SEVERN TUNNEL
1. INTRODUCTION
RPC Wales is concerned that Wales-England rail
services are increasingly constrained by the Severn Tunnel and
considers that now is the time for a serious look at how additional
capacity should be provided for the long term.
This non-technical paper is intended to identify
four options, to introduce issues to be considered as part of
the assessment of each option and to promote further consideration
of the proposals by and further debate with the relevant authorities.
These authorities include:
the Welsh Affairs Committee;
the Welsh Assembly Government;
the South West Regional Assembly;
the Strategic Rail Authority;
No effort is made to estimate one crucial issue:
cost. This would have to be an integral part of the next stage
of assessment of these four and any other identified options.
2. BACKGROUND
The Severn Tunnel is four miles and 629 yards
long and links the English and Welsh sections of the Paddington-South
Wales main line.
Construction began in early-1873 and, after
enormous difficulties which included two major floods from "the
Great Spring", was opened to passengers on 1 December 1886.
In conjunction with the "Badminton Line" between Patchway
and Wootton Basset Junctions, it shortened the original LondonSwansea
route via Gloucester by 47 miles. It was then the longest non-London
Underground rail tunnel in Britain and the longest underwater
tunnel in the world.
Its benefits include:
reasonably graded approaches, (1/90
climb into Wales and 1/100 climb into England);
electrified pumping stations, (and
water sold for industrial use);
every day, about 130 passenger trains
and 80 freight trains passing through.
The tunnel, however, is not trouble free; constraints
include:
long signalling sections which restrict
train paths;
confined drainage tunnels and shafts,
hard to access and maintain;
75mph speed restriction;
inadequate alternative routes when
closed for maintenance and renewal;
no headroom for electrification.
Much work was essential in the tunnel in the
late 1990's and the maintenance engineers gained some notoriety
for closing the tunnel frequently and at short notice, causing
serious delays to and disruption of regular services. Some of
this work followed the numerous recommendations of the public
inquiries in Bristol and Cardiff in 1992 into the collision between
two trains within the tunnel on 7 December 1991, recommendations
arguably made more numerous by the uncertainty as to the precise
cause of the accident. Safety provisions were enhanced with considerable
difficulty and expense.
In the last couple of years however, apart from
a couple of serious and avoidable clashes with major sporting
occasions at the new Millennium Stadium in Cardiff, the tunnel's
reliability and availability is greatly improved, with a significant
reduction in unplanned closures.
Nevertheless, taking all aspects of service
performance into account, RPC.W considers the Severn Tunnel to
be a significant constraint on existing rail services. More fundamentally
and seriously, RPC Wales considers the tunnel will be unable to
cope with the planned and anticipated increases in rail traffic
along this vital route.
Better use of the Severn Tunnel can certainly
be achieved by improvements within and near the tunnel, eg:
safely reduce intervals between trains
by installing addition signals within the tunnel which reduce
the length of signalling sectionsplanned for years but
still not implemented;
raise the line-speed through the
tunnel to 90 or 100mph;
remove single lead junctions near
Filton Junction, especially on the route to Bristolpromised
for 2004;
additional platforms at Filton Abbey
Wood Station so stopping trains do not obstruct through trainspromised
for 2004;
reinstate two more tracks (to total
four) between Filton Junction and Bristol Temple Meads, so trains
to/from South Wales do not obstruct trains to/from Bristol Parkway
Station and beyond to the North and Eastno known plans.
As they are implemented, these projects will
progressively enhance capacity through the approaches to the Severn
Tunnel and therefore through the tunnel itself. It is however
estimated that traffic growth will still exceed this additional
capacity sooner rather than later; say, well within 10 years.
Within that period it is assumed that the following
national schemes will be complete:
WCML PUG 1 and 2 (at last);
ECML bottle-neck removals;
CTRL Section two, from Fawkham Jct.
to London Kings Cross;
and that the Great Western Renewal will be making
rapid strides in a westerly direction.
Meanwhile, the Severn Tunnel will become a more
and more severe constraint on all services, especially on the
key South Wales-Bristol and London services for which, unlike
South West England and Bristol-London services, there is no effective
alternative route.
Recognising that the right option to provide
additional capacity between England and Wales will be a major
project with lengthy lead time, probably over ten years to successful
completion, RPC.W consider work should begin now to consider the
options and to identify the preferred solution.
RPC.W reaffirms its suggestion that the options
considered should include:
the Second Severn Road Crossing;
a dedicated rail bridge;
the Severn tidal barrage.
3. THE FOUR
OPTIONS
Each option is now outlined in a little more
detail.
3.1 The Second Severn Road Crossing
Road and rail have shared bridges over rivers
and estuaries for years, especially in developing countries with
limited resources and rugged terrain, eg Canada, India, NZ and
Australia.
Examples in Britain are few, apparently because
of a lack of strategic thinking, but perhaps also due to inter-agency
indifference. The few working examples in Wales include the Britannia
Bridge (as re-built) between Bangor and Holyhead and the Briwet
Bridge on the Cambrian Coast near Penrhyndeudraeth.
Modern bridges however commonly have full provisions
for both rail and road, eg Denmark-Sweden, Hong Kong Airport,
etc. Such bridges are conceived, designed and built for this shared
purpose.
Although not designed and built to include rail,
the Second Severn Road Crossing, (SSRC) may hold potential for
rail use. Merits include:
its alignment, which is very close
to that of the rail tunnel beneath, (indeed, great care had to
be taken during bridge construction to control foundation works
straddling the tunnel);
its arrangement of long multi-span
approach viaducts and short central span;
the modern road freight loads for
which the bridge is designed may well be comparable with the loads
of modern medium-paced light-weight rail cars suitable for Bristol-Newport-Cardiff
shuttle services;
The revised and additional loadings would certainly
require significant alteration and strengthening of the crossing,
just as almost every other road bridge has experienced as traffic
intensities and permitted lorry loadings have increased since
the bridges were first designed. It is considered that the design
and construction techniques to modify the SSRC suitably are already
available.
Rail connections to the existing network would
be short on both Severn banks, and track grades and curvatures
throughout should not be operationally onerous at all.
3.2 A Dedicated Rail Bridge
The original high-level rail bridge was completed
in 1879 between Sharpness and Lydney but was badly damaged by
a ship in 1960 and never re-opened before demolition. Its alignment
is reasonably favourable for reconstruction on the West bank,
but its Eastern approaches are unsuitable for direct and speedy
access to either Bristol, to the GW mainline at Westerleigh Junction
or to the Gloucester-Stroud route to Swindon.
The preferred option for a dedicated rail bridge
would therefore be a new bridge on a new alignment.
The first choice option that the SSRC be a joint-rail
crossing (by design) having been lost, the rail bridge alignment
now has considerable freedom. Preferred alignment is likely to
be somewhere in a band between a mile upstream and five miles
downstream of the Severn Tunnel.
Opportunities exist of enhancing existing network
connections by aligning the bridge with existing rail-lines, eg:
to Avonmouth, making it attractive
for Bristol and freight traffic, but less directly attractive
for London trains, except by releasing capacity in the original
tunnel;
to Hallen Marsh Junction on the Severn
Beach line from Bristol Parkway, making it attractive for high
speed trains straight through Filton Junction.
On any alignment it would be prudent to design
foundations and superstructure capable of accommodating a future
road deck, perhaps particularly for an Avonmouth alignment.
3.3 A New Rail Tunnel
Thanks to the excellent experience already gained
on the Channel Tunnel Rail Link to London, the levels of tunnelling
expertise in the UK have soared and the costs have plummetted.
Certainly the Severn geology and hydro-geology will always be
more complex and challenging than English chalks and clays, but
a new rail tunnel may well be the quickest, easiest and most cost-effective
way of enhancing English-Welsh rail links.
In principle, the alignment of a new rail tunnel
has the same flexibility as a new rail bridge.
In practice it will be more restricted by the
geology and a bored tunnel in stable rock may therefore be impractical
as far downstream as Avonmouth.
Estuary bed conditions may, however, favour
an immersed tube similar to, but much longer than, the A55 under
the Conway estuary on the North Wales Coast.
A new bored tunnel alongside the existing provides
the additional and valuable opportunity to up-grade the old Severn
Tunnel to modern standards of safety and services by cross-connections
throughout their length, including:
passenger escape routes in the event
of emergency;
controlled bi-directional ventilation;
modern drainage and lighting.
The pair of tunnels in close parallel would
offer greatly increased flexibility of operation and maintenance
as well as increased capacity, with segregation by speed and power
generally leading to passenger trains normally using the modern
tunnel and the original tunnel restricted to freight traffic.
A new tunnel some distance from the old would
not have many of these benefits.
Any modern tunnel should be sized to accommodate
future electrification with UK standard overhead lines.
Modern train power units probably mean the new
tunnel approaches could be steeper than present, hence reducing
the tunnel length and cost. However, fuel costs would rise and/or
train speeds would fall as a consequence, albeit for only a short
section of their overall journeys.
3.4 The Severn Tidal Barrage
The Severn Tidal Barrage to harness the enormous
energy of the rising and falling tides in the estuary was first
proposed in the 19th Centurya contemporary engraving shows
a train crossing it!
It is considered that in time and due to:
continuing growth in UK electricity
demand and of our economic and social reliance on it;
the pollution from and relative inefficiencies
of coal, oil and gas energy sources;
the increasing political and technical
risks of imported fuels and energy;
the relative unpredictability and
unreliability of many renewable energy sources, especially wind;
increasing success in identifying
the environmental impacts of large projects and of managing them
acceptably;
active interest in the potential of tidal power
in general and of the Severn Estuary in particular will revive
sooner rather than later.
Sites for the barrage have been investigated
on many alignments between as far upstream as Aust Cliff-Beachley
Point (almost exactly under the First Severn Road Crossing) and
as far downstream as Porlock (West Somerset)-Nash Point (Glamorgan).
Most proposals have concentrated on the an alignment between Weston-super-Mare-Lavernock
Head near Penarth.
Wherever sited and whenever built, it too provides
an opportunity for rail and road crossings.
Current estimates suggest the barrage would
be such a large project, and because it would not be available
as a transport link until virtually complete, it will almost certainly
not be available within the period necessary to supplement the
Severn Rail Tunnel. Nevertheless, it is a project which could
clearly contribute to cross-Severn transport links, and its development
should be positively monitored.
Rail access for construction purposes on both
shores should be aligned with permanent use in mind.
4. CONCLUSIONS
At this preliminary stage RPC Wales concludes:
the Severn Rail Tunnel is old and
difficult and expensive to maintain;
its alignment for train services
between London and South West England and South Wales is most
suitable for modern transport needs;
its usage is on the practical limits
of capacity, and enhancements available cannot keep ahead of the
growth in demand in the mid- and long-term;
additional and alternative capacity
must be provided on this strategic route.
Therefore, the options, including the four outlined
in this Note, should be assessed, budgeted, ranked and considered
in further detail until the single all-round best-value option
is identified for further detailed assessment.
5. RECOMMENDATIONS
This Note is issued to the Welsh Affairs Committee
as supplementary evidence to its recent Inquiry into The Provision
of Rail Services.
It is also issued to:
the Welsh Assembly Government;
the Strategic Rail Authority;
the Welsh Transport Forum;
the South West Regional Assembly;
Rail Passengers' Committee for Western
England;
London Transport Users' Committee;
also to all other interested parties, including
all Train Operating Companies using the Severn Tunnel; with an
invitation to all to comment on, help to improve and to adopt
and promote.
The Second Severn Rail Crossing
From time-to-time, RPC.W should review, revise
and re-issue this Note to include additional facts, issues and
options that emerge and that RPC.W considers strengthen the case
to be considered for the Second Severn Rail Crossing.
6. APPENDICES
6.1 Location Plan of Severn Crossings
To be developed for the next issue.
6.2 References
1. Channel Tunnel Rail Link Section 1 Proceedings
of the Institution of Civil Engineers, Vol 156, Nov 2003
2. The Oxford Companion to British Railway
History; edited by Jack Simmons and Gordon Biddle, 1997.
3. The Great Western Railway, A New History;
by Frank Booker, 1977.
4. Railways: Civil Engineering; by Bryan
Morgan, 1973.
5. Hidden DangersRailway Safety in
the Era of Privatisation, by Stanley Hall, 1999.
6. The Severn TunnelIts Construction
and Difficulties 1872-87, by Thomas A Walker, 1888.
6.3 Acknowledgements
To colleagues in the industry and on RPC Wales
for their advice and encouragement; however all errors remain
those of the author.
Owen P Williams
Chartered Civil Engineer
Clive G Williams
Secretary
December 2003
|