Examination of Witnesses (Questions 20-39)
7 JULY 2004
MR PETER
ALDRIDGE, MR
PAUL FRANCIS,
MR PHIL
VERSTER, MS
ALLISON INGRAM
AND MR
VINCE LUCAS
Q20 Mr Stevenson: It was a deliberate
decision by your company to order the trains, to force them to
do something they ought to have done in the first place?
Ms Ingram: I cannot honestly plead
that they were prescient but it did work.
Q21 Mr Stevenson: Was that the approach
of your company?
Ms Ingram: No. I cannot say that
we did it deliberately like that, but we knew we had that deadline
and therefore we had to order the rolling stock, otherwise I think,
rightly, we would have been criticised for not taking that action.
Mr Verster: Just to explain it
for South Eastern Trains, or Connex South Eastern at the time,
and I was not involved with the company, I joined in January of
this year. I think, to be fair to Railtrack at the time, it is
clear from our project records that even though we placed our
first order in July 1997, Mr Stevenson, throughout the latter
part of 1997 and in 1998 Railtrack was engaging very actively
with both Connex South Eastern and our supplier at the time, Adtranz,
to try to ascertain what was the impact of the traction characteristic.
That process definitely took place, and I have never worked for
Railtrack, I have no loyalties there, but to think that Railtrack
was blissfully unaware is not really the full perception as far
as South Eastern Trains are concerned. It was a very active programme
of meetings, interchange of questions, constantly trying to ascertain
what would be the impact on the power upgrade.
Q22 Chairman: You would rather expect
that though, would you not, Mr Verster, of anything that was going
to go onto their system?
Mr Verster: Yes, I would.
Q23 Chairman: Would not you regard it
as automatic that if you knew that someone was going to run trains
on your system you should at least be taking a mild interest in
whether or not you had the electricity to make that possible?
It is not much of a commitment is it, really? It shows willing
but it is not what you would call tremendously unusual, is it?
Mr Verster: No, but I think it
is appropriate in the context to understand that there was an
active process and that in a large project like this the onus
actually to manage something like this, which is an illusive aspect
of the process that is not resolved, lies with the Project Manager.
In terms of our procurement processes, it is fair to say that
the Project Manager which had to facilitate and resolve that at
the time were the operators. Therefore the operators had to push,
because we are the party between the supplier, the train-builder
and the other parties, to get those answers. I think the fact
of the matter is, the answer on what the traction characteristics
were, in some of the cases of design, was simply not forthcoming
because of some of the design uncertainties. Instead of pointing
fingers at parties I think we must understand that the procurement
process had as an uncertainty to it the design phase of the rolling
stock.
Q24 Chairman: Mr Verster, we are not
pointing fingers, we are trying to say that if caveat emptor
is the instruction to me when I go into a grocer's shop I would
have thought it was even more an instruction to your Project Managers
when they went into somewhere where they were ordering trains.
Still, that is just a personal hang-up. Mr Lucas?
Mr Lucas: The process in Southern
was a little bit different because the first 120 vehicles we have
got were ordered as part of the same order as South Eastern to
which Mr Verster has referred. Having said that, I think it is
worth just making a point that on new trains many of the things
which have caused the change in the traction supply characteristic
are a given, they are a given from beyond those people who are
ordering the trains. Firstly, the trains have to comply with new
crash-worthiness, which is right and proper and is a significant
step forward from the Mark 1 trains they are replacing. To do
that, their structure has to be different and that affects the
weight of the train. The weight of the train is one of the fundamental
characteristics required in calculating what the traction supply
requirements will be. Firstly, that affects it. Second is the
requirement for sliding doors, and that is part of the HMRI/HSE
requirement to get rid of slam-door trains. Then you have a requirement
on the new trains for sliding doors, which changes the way it
uses power, it changes the weight, it changes the profiles. With
any modern train I think people would be criticised if it did
not have air-conditioning. Part of making rail attractive compared
with road transport is to try to bring the quality of the interior
closer to that of the modern car. If you look at the trains in
the last 30 years, with the climate heating up, etc, it would
seem unreasonable if trains were not ordered with air-conditioning.
Air-conditioning also affects the weight and electrical power
supply of the train. All those components are given, so you end
up with not much leeway in some of the things which make up what
the traction supply will be. If you wanted to reduce the drawing
traction supply on those trains you would have to leave out some
of the core elements which were part of the reason for the trains
being constructed. Railways are a complex environment, each of
these trains has four cars, you are looking at £1 million
per car, roughly, in terms of capital cost, slightly less but
of that region, it is a complex electrical beast. At the time
the trains are built, as well as looking at what happens on power
supply the other component which has to be looked at is how that
tractive effort which the train uses affects the complex signalling
systems which are on the railway. The signalling system on the
railway will also have an impact on how the traction supply works,
because if you put outputs from the train at a frequency of around
50 hertz and above and up to 200 hertz you can affect the signalling
supply. When you are designing this train it becomes incredibly
complex. What you find is that once the train is manufactured
you have a design parameter and then you test it, and the approval
that is given to the train companies and to Connex South Central,
which is the predecessor of the company I am now in, the first
approval is for tight testing on the network on which it is going
to operate. It is at that time, when you see how that is going
to operate, that you begin to understand how that will affect
in a single case the way it uses power. It is not a simple case
of just taking out more electrons because it affects also how
long the power draw is and the rating in the sub-stations. Once
then you multiply that out, for us, for 700 vehicles that is a
very, very different scenario, in a complex environment, with
other train operators. For us, we share with Gatwick Express some
Connex South Eastern trains and that whole network needs to be
modelled, so at the stage when we took an order for 120 vehicles,
actually probably 120 vehicles in the network would not have caused
a drain on the power supply over and above that which was there.
We had to face a decision to order 700 vehicles to replace our
existing fleet. During 2002 there was extensive work done with
South Central and Railtrack to model that effect on the network.
There was extensive modelling carried out on both the high voltage
distribution network and the way it works on the trackside components.
At the end of that, that work led to the core specification which
became the Power Supply Upgrade Programme. That work had to be
done iteratively and if there was something which could have been
done better at the startI think it is a question we will
come to laterit is a question of that system integration
and multiplying it up into a whole system effect.
Q25 Chairman: Mr Lucas, I would not disagree
with any of that but that must have been one set of circumstances,
not those particular processes. That set of circumstances, the
need to relate the quality of the rolling stock, the ability to
run it efficiently, the matching of the rolling stock with the
power system, frankly, that must have been faced ever since electrification
came in. It has been altered in the type of train. You are not
saying it is anything that the railway has not had to go through?
Mr Lucas: No, but also it affects
the types of trains and the number of trains, and during the late
nineties we were also increasing the number of trains on the network,
with the growth, 24% plus, 1 March.
Q26 Chairman: You were aware of that.
Those were the calculations of your business. Your business was
running trains, your business was buying in trains to replace
the broken down stock you had got.
Mr Lucas: That is precisely why
the modelling has been done.
Q27 Mr Stringer: There is something I
do not understand through your responses we have had. South West
Trains, I think I am right in saying that you said Railtrack were
not working on an upgrade?
Ms Ingram: Not for our area.
Q28 Mr Stringer: South Eastern and Southern
seemed to say that they were working intensely?
Mr Lucas: During 2002 they were.
Q29 Mr Stringer: And from 1997-98. What
was the difference? Were Railtrack prejudiced against you?
Ms Ingram: No. We ordered our
trains in 2001. On the South Western bit we have probably the
weakest power supply. Also we take part of our supply from what
is geographically bits of our neighbouring TOCs. It was the Railtrack
view that you could not look at South West in isolation, you had
to look at the whole of the Southern Region and all of the users,
so you had to have a totally integrated approach to upgrading
the power supply for the whole of the Southern. They would not
be prepared to work with South West Trains only doing the South
West Trains bit.
Q30 Mr Stringer: I still do not understand
because we were told that they were working with South Eastern
and Southern?
Ms Ingram: At that particular
time, in 2001, South Eastern were not introducing that much in
rolling stock.
Mr Verster: South Eastern trains
were introducing it in 2001.
Q31 Mr Stringer: They had been working
with you on the same problem since 1997-98, you said?
Mr Verster: Yes, I agree with
that. I do not agree with the comment that South Eastern was not
introducing in 2000-01. Our introduction programme of new rolling
stock was delayed significantly. We introduced most of our rolling
stock during 2000 and 2001.
Q32 Mr Stringer: So Railtrack were saying
to South West, "We won't work with you because we want to
integrate it," but even in 2004 South Eastern and South West
do not have an agreed history of what went on?
Mr Verster: Can I make it abundantly
clear, probably with the PSU team that Network Rail have got,
over the last few years the co-operation between what was Connex
South East and is now South Eastern Trains, they have been working
together continuously to make sure that the upgrades required
for South Eastern Trains
Chairman: That is not what Mr Stringer
asked you, is it?
Q33 Mr Stringer: We are being told that
South West did not believe Railtrack were doing any work because
they wanted integrated work across the whole system for all three
of you and yet two of you say they were doing work and you are
still arguing about the truth of that statement. That is the case,
is it not?
Ms Ingram: I can only repeat what
we were told at the time.
Q34 Mr Stringer: On the same point, can
I ask a slightly different question, because you posed the problem,
Ms Ingram, the Health and Safety Executive were saying you had
to hit this deadline and so you ordered trains not knowing that
they would work, essentially.
Ms Ingram: I think I said we ordered
trains knowing we would have to improve the infrastructure.
Q35 Mr Stringer: What was the difference
in the cost between a decision of waiting for an extra year until
the problems were sorted out and the different parties talked
to each other and ordering at that time?
Ms Ingram: There would be no difference
in the cost, it would be one of compliance, the order timescale.
We have ordered 785 vehicles and we were told by manufacturers
that in order to produce those the latest we could place an order
was in early 2001.
Q36 Mr Stringer: You are saying there
is no extra cost that you can quantify when in actual fact you
did not know the extent of the problem because you say that Railtrack
were not working on it. That is not a credible position, is it?
Ms Ingram: Why do you think it
is not a credible position?
Q37 Mr Stringer: If Railtrack had not
started the work, how could they know how much it was going to
cost either them or you at that stage?
Ms Ingram: Some consultants who
work for us came up with an estimate of the work we needed to
do on the infrastructure. In terms of ordering the trains, what
drives the ordering of the trains is the timescale needed to produce
the trains, test them and introduce them, and that was timescale-driven
in order to comply with the deadline. The variable is how much
you will spend on the infrastructure.
Q38 Mrs Ellman: I would like to ask all
these train operators, where would you look for compensation or
financial adjustments now if the trains could not run because
of infrastructure problems?
Ms Ingram: We have an agreement
with the SRA about the provision of new infrastructure needed
for Mark 1 replacement. That was an agreement which was signed
during Railtrack being in administration when we were unable to
get Railtrack to do the work we wanted.
Q39 Mrs Ellman: You would go to the SRA.
Does that apply to the other train operators? Where would you
seek compensation or financial adjustments if the trains could
not run because of infrastructure problems, if that happened now?
Mr Verster: In the case of South
Eastern Trains, we are in a slightly different position from the
other two operators, in the sense that we have benefited from
network upgrades associated with the introduction of the Networker
a number of years ago and also the introduction of the Eurostar.
So all along over the last two years we have had less of a bottleneck
or a risk in terms of power system upgrades. To be fair and to
be honest with you, we have not considered that we will have that
problem.
|