Select Committee on Transport Written Evidence


Supplementary Memorandum by BT (RPM 47A)

ROAD AND PATHWAY MAINTENANCE

1.  PROVIDE CONFIRMATION OF THE FINES PAID AND LEVIED BUT AS YET OUTSTANDING UNDER SECTION 74 (OVERRUN CHARGES)

  We understand that, at the hearing, the Committee was using the figures from the Department of Transport that we have reproduced in Annex A. These figures are for just nine authorities and do not cover the whole country. In addition it should be noted that the figures are by industry sector and not broken down to individual company.

  As stated at the session on 5 February, BT has paid circa £3 million pounds in overrun charges since 1 April 2001. The precise figure paid to the 105 highway authorities currently operating the scheme was £3,442,380, from 1 April 2001 to 7 January 2003. The detail is shown in Annex B.

  At the Committee hearing on 5 February, it was suggested that BT had adopted a policy of not paying Section 74 (overstay) fines levied for periods after its works in the street had actually been completed, but where a formal statutory notice of completion was not served at the time of completion. We would like to clarify our stance on this issue.

  This matter is currently the subject of litigation between Transco and Leicester County Council. In many cases, the amounts involved are very large (up to £100,000), and it appears that in some cases authorities have allowed fines to accumulate, despite knowing that the works have actually been completed. Like Transco and other utilities, BT feels that it is unjust and inappropriate under the legislation that it should be required to pay fines in instances where it has restored the highway to normal use, but for a variety of reasons, (in particular the unfamiliarity of contractors with the scheme in its early stages), a formal notice was not served. For this reason, BT has decided not to pay invoices for such cases of purely "administrative" overrun, pending the resolution of this important issue by the Transco litigation.

  BT is co-operating fully with authorities in the payment of invoices in respect of periods where it has actually occupied the highway beyond the allotted time

  The difficulties BT has experienced in this area contribute to our view that the responsibility for co-ordinating streetworks would be better conducted by an independent organisation, rather than the highway authorities, which are themselves responsible for the majority of streetworks.

2.  PROVIDE DETAILS OF THE PERCENTAGE OF WORKS WHICH HAVE OVERRUN PRIOR TO AND SINCE THE INTRODUCTION OF SECTION 74

  Prior to April 2001 the concept of overrun did not exist in its present form and there are therefore no figures available with which to compare the before and after situation. The importance of the independent evaluation of schemes, which are intended to reduce the impact of streetworks on congestion, was a point BT made in its evidence to the Committee.

  For the period immediately after the commencement of overrun charges, Halcrow has provided some relevant data. Its figures show that in the period between April 2001 and September 2002 there was a reduction in average works duration from six days to three and a reduction in overstay days as an average of the total duration of the works from 14% to 0.4%.

3.  PROVIDE AVERAGE NOTIFICATION TIMES FOR MAJOR WORKS AND BT'S VIEWS ON WHAT A LONGER REASONABLE PERIOD FOR ADVANCED NOTIFICATION COULD BE

  BT carries out a very small number of Major Works (as defined by the Act these are works that appear in the annual operating plan). BT makes these works known to the highway authorities at co-ordination meetings at an early stage to maximise the potential for advanced planning. This is followed by formal notifications as required by the Act.

  BT believes that the most important factor is the use to which forward information about streetworks is put, rather than the formal notice period. It is the way in which this information is recognised, shared and acted upon by the highway authorities, that is crucial.

4.  EXPLAIN WHY OF 5 MILLION REQUESTS ONLY 250,000 RESULT IN NOTICES (WITH REFERENCE TO Q14)

  The 5 million requests relate to demand for service (both provision and repair). The majority of these are completed without the need to carry out notifiable street works. The 250,000 is the proportion of that 5 million which require excavation/reinstatement and give rise to notices, which under the current rules, are subject to s74 charges. Furthermore, of the 250,000, 90% do not require work in the carriageway, but are confined to the verge or pavement and do not of themselves cause congestion on the street.

5.  WHAT ISSUES WOULD NEED TO BE RESOLVED BEFORE THE TWO-YEAR GUARANTEE FOR REINSTATEMENT WORKS COULD BE EXTENDED?

  The main issue to be resolved is clarification of the advantage to be obtained from extending the guarantee period. While, at first sight, it may seem obvious that extending the guarantee would be beneficial, we believe that, in reality, it could cause additional problems to the highway authorities and the utilities, without providing benefits to road users.

  Two winters are sufficient to show up any major inadequacies in the surface levels of the reinstatement. Any cases of the reinstatement subsiding due to inadequate compaction or the use of unsuitable materials should also usually be revealed within a two-year period.

  The longer the period of time since the completion of the reinstatement the more difficult it would be to establish with any certainty that a defect in that part of the road could be attributed to the reinstatement, particularly if the reinstatement had performed satisfactorily for the first few years. There could therefore be conflicts between highway authorities and utilities as to which was responsible for rectifying any deficiency in the road in the area of a reinstatement.

  Moreover, highway authorities have the added protection afforded by the 1999 BT v Nottinghamshire County Council case in that if a reinstatement is not constructed in accordance with the specification at the outset then the guarantee period does not start to run. Liability for future maintenance of a reinstatement will only revert to the highway authority where the reinstatement has been properly constructed in accordance with the Specification and two years have elapsed. Since the High Court ruling there have been a number of occasions where utilities have been called back to carry out remedial works long after the expiry of the two year guarantee period.

  Furthermore, we note that the highway authorities, which are responsible for reinstatement inspections, did not request a longer guarantee period in either their written or verbal evidence.

6.  WHETHER YOU ALLOW OTHER CABLE COMPANIES TO SHARE YOUR DUCTS, IF NOT WHY NOT?

  BT does share its duct with other cable companies at "pinch points" (bridges etc). However, apart from these special circumstances we have good reasons for not doing so. Widespread duct sharing would have serious impacts on security and integrity of the network with the potential for accidental and malicious damage by third parties. It becomes very difficult to plan for investment for growth and repair when demand for duct space could be subject to sporadic and unpredictable demand from other operators.

  It is also worth recalling the recent context in which telecommunications infrastructure has developed. The liberalisation of telecommunications 20 years ago was carried out by the Government on the principle of encouraging the development of competing networks. Existing cable operators now have fully mature networks such that any initiative to share would now have a minimal impact on the volume of streetworks. More recently the policy has shifted in the UK from the former emphasis on constructing separate networks to one in which the sharing of cable capacity is encouraged. This goes beyond duct sharing and, where practiced, avoids altogether the need for multiple operators to dig the streets.

ADDITIONAL COMMENTS

    —  BT has stressed in its written and oral evidence the positive contribution that telecommunications and other infrastructure makes to reducing congestion on our roads. A good telecommunications infrastructure can reduce the need for certain journeys. In many other cases it can enable individuals to choose less congested periods in which to travel. We believe that this makes a positive contribution to reducing congestion.

    —  A point arose during the hearing of evidence from the highway authorities on which we would like to comment. There was a suggestion that BT does not always advise highway authorities of the need to conduct streetworks as early as it might in response to customer demands for service and repair. This can sometimes appear to be the case when customers order new services. As explained above in most cases these orders require no notifiable streetworks to take place. However, when streetworks are required this is only known after checking on the status of the existing infrastructure. If it is then found that streetworks are required the highway authority is immediately advised.

February 2003

Annex A

The following is an extract from the Department for Transport's report for "Assessing the Extent of Street Works and Monitoring the Effectiveness of Section 74 in Reducing Disruption" (Halcrow Report)

October 2002—Volume 1

INVOICES SENT AND INCOME RECEIVED

  6.6.3.1

  Table 61 shows details of invoices from data that has been submitted by the following authorities to Halcrow:

    —  two Inner London Boroughs;

    —  four County Councils;

    —  one Unitary Authority; and

    —  two Metropolitan Boroughs.

  This is a relatively small sample, and consequently the robustness of any conclusions that can be drawn from it is likely not to be as great as one would hope. Halcrow will work with the Local Government Association and the sample authorities to increase the delivery and reliability of this data in time for the next report. An approach will also be made to the undertakers to check the amounts paid.

  6.6.3.2

  The column "Invoice Period" refers to the month in which invoices were dispatched by the authorities. The month of billing could be up to six months after the month in which the overrun that incurred the charge occurred

  6.6.3.3

  Halcrow has examined the records of invoices sent to ascertain what was agreed in each case between the authority and undertaker concerned. It emerges that in the majority of cases a greatly reduced sum was agreed. For those invoices where agreement had been reached, the original invoices amounted to £1.1 million whereas the amounts agreed for payment amounted to £308,000 in all. The breakdown in terms of amounts initially billed and eventually agreed is as follows:

Table 61

NINE AUTHORITIES—RECORD OF OVERRUN CHARGES INVOICED AND RECEIVED APRIL 2001—MARCH 2002
Invoice Period DataElecGas TelecomWater Total
Apr-01Invoice Amount4,900 2,2502002,000 9,350
Amount Recovered4,900 1,0002001,500 7,600
May-01Invoice Amount7,300 28,2005,8508,600 49,950
Amount Recovered2,300 25,0005,8507,700 40,850
Jun-01Invoice Amount12,700 160,00018,40043,600 234,700
Amount Recovered2,800 1,4007,800600 12,600
Jul-01Invoice Amount3,200 65,6005,10031,950 105,850
Amount Recovered3,200 51,4005,1002,800 62,500
Aug-01Invoice Amount11,400 56,6006,15071,350 145,500
Amount Recovered8,200 29,7503,85015,200 57,000
Sep-01Invoice Amount438,150 299,900142,350100,750 981,150
Amount Recovered28,100 43,45012,60021,750 105,900
Oct-01Invoice Amount32,600 393,70059,90047,650 533,850
Amount Recovered4,500 102,1009,00010,950 126,550
Nov-01Invoice Amount131,200 276,050277,85032,450 717,550
Amount Recovered100 43,0506,900600 50,650
Dec-01Invoice Amount9,100 324,95024,1006,850 365,000
Amount Recovered0 14,45015,4002,750 32,600
Jan-02Invoice Amount2,850 234,0007,350153,200 397,400
Amount Recovered0 18,4007,05018,600 44,050
Feb-02Invoice Amount240,850 127,750232,700192,200 793,500
Amount Recovered6,850 18,6002,9504,300 32,700
Mar-02Invoice Amount27,050 178,5006,400336,750 548,700
Amount Recovered1,950 16,8501,8002,050 22,650
Total Invoice Amount921,300 2,147,500786,3501,027,350 4,882,500
Total Amount Recovered62,900 365,45078,50088,800 595,650

  End of Halcrow Report Extract

Annex B

Highway AuthorityValue Highway AuthorityValue
BARNSLEY METROPOLITA Total£42,200.00 NORTH EAST LINCOLNSH Total£9,600.00
BEXLEY COUNCIL Total£200.00 NORTH LINCOLNSHIRE C Total£29,800.00
BLACKBURN WITH DARWE Total£9,100.00 NORTH SOMERSET£30,450.00
BLACKPOOL BOROUGH CO Total£3,300.00 NORFOLK£1,025,300.00
BOLTON METROPOLITAN Total£17,200.00 NORTH TYNESIDE COUNC Total£3,500.00
BOURNEMOUTH BOROUGH Total£100.00 NORTH WEST LEICESTER Total£100.00
BRACKNELL FOREST BOR Total£12,000.00 NORTH YORKSHIRE COUN Total£25,500.00
BRADFORD METROPOLITA Total£72,950.00 NORTHUMBERLAND COUNT Total£6,500.00
BUCKINGHAMSHIRE COUN Total£310,850.00 NORWICH CITY COUNCIL Total£400.00
BURY METROPOLITAN BO Total£6,300.00 NOTTINGHAM CITY COUN Total£450.00
CAMBRIDGESHIRE COUNT Total£1,900.00 NOTTINGHAMSHIRE COUN Total£4,350.00
CHARNWOOD BOROUGH CO Total£3,500.00 OXFORDSHIRE COUNTY C Total£16,550.00
CHRISTCHURCH BOROUGH£500.00 POOLE BOROUGH COUNCI Total£700.00
CITY OF WESTMINSTER Total£11,800.00 PORTSMOUTH CITY COUN Total£14,200.00
CITY OF YORK COUNCIL Total£9,200.00 READING BOROUGH COUN Total£4,800.00
CORNWALL COUNTY COUN Total£4,500.00 ROCHDALE METROPOLITA Total£900.00
COVENTRY CITY COUNCI Total£11,100.00 ROTHERHAM METROPOLIT£8,600.00
CUMBRIA COUNTY COUNC Total£13,000.00 ROYAL BOROUGH OF KEN Total£28,600.00
DARLINGTON BOROUGH C Total£23,310.00 ROYAL BOROUGH OF WIN Total£16,450.00
DERBY CITY COUNCIL Total£300.00 RUTLAND COUNTY COUNC Total£3,200.00
DERBYSHIRE COUNTY CO Total£1,600.00 SANDWELL METROPOLITA Total£24,150.00
DEVON COUNTY COUNCIL Total£106,500.00 SEFTON METROPOLITAN Total£40,200.00
DORSET COUNTY COUNCI Total£12,000.00 SHEFFIELD CITY COUNC Total£2,500.00
DURHAM COUNTY COUNCI Total£21,350.00 SOLIHULL METROPOLITA Total£13,350.00
EAST SUSSEX COUNTY C Total£13,500.00 SOMERSET COUNTY COUN Total£5,100.00
ENTERPRISE-LIVERPOOL Total£2,200.00 SOUTH GLOUCESTERSHIR Total£4,900.00
ESSEX COUNTY COUNCIL£79,850.00 SOUTHAMPTON CITY COU Total£1,550.00
GATESHEAD METROPOLIT Total£1,600.00 ST HELENS METROPOLIT Total£400.00
GLOUCESTERSHIRE COUN Total£18,800.00 STAFFORDSHIRE COUNTY Total£5,500.00
HAMPSHIRE COUNTY COU Total£37,800.00 STOCKTON-ON-TEES BOR Total£1,100.00
HARTLEPOOL BOROUGH C Total£4,700.00 STOKE ON TRENT CITY Total£59,150.00
HEREFORDSHIRE COUNCI Total£1,200.00 SUFFOLK COUNTRY COUNCIL£18,901.00
HERTFORDSHIRE COUNTY Total£68,000.00 SURREY COUNTY COUNCI Total£200,750.00
IPSWICH BOROUGH COUN Total£25,500.00 SWINDON BOROUGH COUN Total£16,350.00
ISLE OF WIGHT COUNTY Total£500.00 THURROCK BOROUGH COU Total£17,900.00
KENT COUNTY COUNCIL Total£35,100.00 TORBAY COUNCIL Total£1,900.00
KINGSTON UPON HULL C Total£1,000.00 WANDSWORTH BOROUGH C Total£13,400.00
KIRKLEES METROPOLITA Total£44,700.00 WALSALL METROPOLITAN£104,100.00
LANCASHIRE COUNTY CO Total£16,400.00 WARWICKSHIRE COUNTRY COU£48,350.00
LEEDS CITY COUNCIL Total£28,000.00 WEST SUSSEX COUNTY C Total£11,300.00
LEICESTERSHIRE COUNT Total£62,350.00 WAVENEY DISTRICK COU£23,400.00
LINCOLNSHIRE COUNTY Total£4,000.00 WIGAN METROPOLITAN B Total£1,050.00
LONDON BOROUGH OF BA Total£6,300.00 WILTSHIRE COUNTY COU Total£36,100.00
LONDON BOROUGH OF BR Total£6,500.00 WOKINGHAM DISTRICT C Total£7,200.00
LONDON BOROUGH OF CA Total£20,100.00 WOLVERHAMPTON CITY C Total£2,300.00
LONDON BOROUGH OF CR Total£20,300.00 WORCESTERSHIRE COUNT Total£1,700.00
LONDON BOROUGH OF EA Total£3,700.00
LONDON BOROUGH OF GR Total£26,069.00
LONDON BOROUGH OF HA Total£21,200.00
LONDON BOROUGH OF ME Total£29,600.00
LONDON BOROUGH OF RI Total£3,200.00
LONDON BOROUGH OF SU Total£11,500.00
LONDON BOROUGH OF WA Total£14,400.00
LUTON BOROUGH COUNCI Total£17,750.00
MANCHESTER CITY COUN Total£38,000.00
MIDDLESBROUGH BOROUG Total£14,000.00
MELTON BOROUGH COUNCIL£3,900.00
MILTON KEYNES BOROUG Total£170,600.00
NEWCASTLE CITY COUNC Total£2,750.00 Grand Total£3,442,380.00



 
previous page contents

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2003
Prepared 19 September 2003