ANNEX 1: VISIT REPORTS
Visit to Transco, Wardour Street Area Gas Mains
Replacement Site, 8 April 2003
Participants:
Transco
Edwin Bannock MBE, Network Director, London
Lester Callanan, Transco Customer Service Manager,
London
Jane Smith, Public Affairs Liaison Manager
Kevin Wood, Transco's, Network Operations Manager,
London
Transport Committee
Dr Greg Marsden, Committee Specialist
Background
Transco owns and operates the majority of the UK
gas transmission and distribution network. 93 per cent of UK gas
demand flows through the Transco network serving 20 million homes
and businesses. It is responsible for a network of 275,000 km
of gas mains. It has a programme, agreed with the Health and Safety
Executive to replace all metallic gas mains within 30 metres of
buildings within 30 years. This programme will inevitably cause
significant disruption to traffic.
Site Visit Description
The Committee Specialist visited a major gas main
replacement site in London to examine how such works are managed.
The site was based around Wardour Street and Chinatown in the
centre of London. The works being undertaken were at the heart
of some of the most sensitive areas of central London. For example,
Oxford Street was closed for two weeks to carry out some of the
works. However, advanced notification meant that serious traffic
disruption was avoided. The streetworks ran outside many shop
frontages and along side several theatre frontages in the West
End. In addition, the mains replacement required digging up through
the centre of Chinatown which could not be done without disrupting
the vehicular access to shops and restaurants fronting the area.
Minimising Disruption
Transco made strenuous efforts to forewarn and consult
on the likely disruption that the work would cause. Close liaison
with an official representing Chinatown traders ensured that deliveries
were able to be brought in past the works by trolley and sack
truck while the main was being replaced. The work programme was
adjusted to avoid clashing with the Soho festival. In addition,
working practices were altered to avoid disrupting matinee theatre
performances. Night working was not possible due to the mixture
of theatres, business and residents in the area.
Technology to reduce disruption
A range of new technologies is being employed to
reduce the disruption caused by the mains replacement programme.
In particular, the plastic pipe technology allows the mains to
be replaced inside the existing cast-iron main structures in some
circumstances. This reduces the amount of trench digging required
as only entry and exit holes are required. The plastic piping
is also more versatile than the cast-iron mains it replaces and
is faster to install.
Joint working with other companies
There was mixed evidence of joint working between
Transco and other utilities. Transco made their plans available
to the local authority and highlighted a number of instances where
combined works had been carried out and where defects in other
utility pipes or local authority drains were identified and rectified
during their works. However, within one month of repaving the
centre of Chinatown, the walkabout tour identified further works
by another utility company that resulted in the block paving being
removed and poorly reinstated.
Summary
The site in London was a particularly complex and
sensitive section of work. It had been well managed and considerable
costs incurred by Transco in advising, consulting on and reducing
the disruption both to traffic and the business environment. It
would be disadvantageous if a scheme of purchasing the right to
work in a road led the contractors away from this process of open
dialogue with local businesses and residents.
Visit to BT, Marconi control centre, Basildon,
11 April 2003
Participants:
BT
Roger Newson, Senior Contracts Manager
Granville Taylor, General Manager Regulatory Compliance
Andy Steele, Street Works Consultancy Manager
Tim O'Sullivan, Head of Parliamentary Affairs,
Marconi
Martin Giles, Operations Manager, Marconi
Transport Committee
Dr Greg Marsden, Committee Specialist
Background
BT supplies telecommunications services nationally
to business and residential customers. 90 per cent of its works
are for repairs or to connect new customers and occur at relatively
short notice. 10 per cent of its work is planned over longer periods.
89 per cent of its work is carried out off the road carriageway,
in footpaths or verges. The total cost of its civil engineering
programme of works is around £150 million per year.
The Site Visit
The Committee Specialist visited the Basildon office
of Marconi, which is responsible for implementing street works
for BT for much of the network on the East and South East of London.
The visit consisted of two main parts: a tour of the information
management office and a visit to a site in Dagenham.
Managing the New Roads and Street Works Act
The first part of the visit was a discussion and
tour of the communication facilities for the management of BT's
obligations under the New Roads and Street Works Act. The system
and the subsequent civil engineering works are managed on behalf
of BT by Marconi. The Basildon office manages street works over
a large network on the East and South East of London.
Marconi have developed new software to manage the
communication of information between themselves, the local authorities
and the teams working on the street. The software system has been
upgraded several times to overcome some of the initial glitches
experienced when the requirements of Section 74 of the New Road
and Street Works Act were enacted. There is a dedicated team of
operators each responsible for communications with a small number
of local authorities. The operators received a period of training
and were encouraged to develop a rapport with the local authority
highways department to ensure co-operative working. Marconi believe
that the new system has reduced the number of administrative mistakes
in passing the information to local authorities on when works
start and finish.
Problems
BT pointed out that there were still a number of
occasions when street works were finished and cleared away but
a small amount of equipment, such as a cone or barrier, were left
on site. BT were being charged for this by many local authorities
at the same rate that would be levied if the works overran. BT
accepted that this encouraged them to clear the sites more thoroughly
but felt that this process could be dealt with through a courtesy
call by the local authority in the first instance and perhaps
then a fine at a later stage. It noted the variety of working
practices adopted by the local authorities it had to work with.
Site works
A visit to a customer installation site in Dagenham
was provided. The work was in the pathway in an urban residential
area. Two other sites could not be visited as parked cars had
meant that the work could not be carried out. This adds to the
complexity of scheduling works. The works were being carried out
in one day, with a minimum of disruption to passing traffic and
pedestrians. Whilst it was not possible to see the standard of
the surface repair as the works were on-going, the quality of
the aggregate to fill the hole was much higher than that which
had been dug out from the pavement.
Summary
BT and Marconi have invested heavily in systems to
try and make Section 74 of the New Roads and Street Works Act
function properly. This reduces the costs that they incur. The
new system has not yet been in operation long enough for the Department's
monitoring data to pick up any improvements.
|