Memorandum by M1MMS (MMS 52)
MODAL STUDY RECOMMENDATIONS
1. Brief background to study including area,
start and end dates of the study, duration of the strategy, forecast
traffic growth and key issues. Please provide details of any objectives
that strongly influenced the outcome of the studies.
The immediate origin of M1MMS was the proposals
for widening the motorway, including a bypass of Kegworth that
were placed on hold in the roads review.
The remit for M1MMS was to develop a long-term
(20-year) transport strategy that addressed the problems in the
study area. Within that context the study was to set out a plan
of specific interventions to address the most urgent problems.
The study was also tasked with making recommendations about the
motorway widening schemes that had been placed on hold.
The study area extends from the M1 Junction
with the M69 (Junction 21) in the south to M1 Junction 30 north
of Chesterfield.
2. Summary of the main options appraised
and the reasons for pursuing the final strategy (ie Heavy public
transport expansion including x, y and z, Some public transport
expansion and some road improvements including a, b and c and
Heavy demand management including d, e and f the options that
were rejected did not meet the following study objectives ......
and the preferred option was therefore.....).
The strategy development process was driven
by the wish of the steering group to test a strategy that precluded
new highway capacity increase. The four strategies tested were
therefore:
Package AMaximum public transport
improvement, maximum travel restraint and minimum highway capacity
increase;
Package BHigh public transport
improvement, high travel restraint and moderate highway capacity
increase;
Package CModerate public transport
improvement, moderate travel restraint and high road capacity
increase;
Package DModerate public transport
improvement, moderate travel restraint and maximum road capacity
increase.
Details of the schemes included within each
package are provided in Table 6.1 (page 79) of the Final Report
The results indicated that with a very high
level of public transport investment and strong travel restraint
measures including motorway tolling and urban road pricing, overall
only 7 per cent of the road traffic predicted for 2021 would switch
to using public transport. It should be noted that this converts
to a near 50 per cent overall increase in the level of public
transport use compared to the situation without the implementation
of the proposed schemes and measures.
Without the inclusion of motorway tolling, the
shift from road to rail had no material effect upon motorway traffic
volumes or congestion levels. The testing of motorway tolling
indicated that a substantial proportion of traffic would divert
off the motorway, mostly onto the rest of the road network. The
tests indicated that this would result in very significant increase
in traffic congestion on the wider road network and a substantial
increase in road traffic accidents.
The tests also indicated that if the motorway
were to be widened by adding an additional lane in each direction
throughout the study area, then congestion in 2021 could be at
a similar level to conditions in 2000.
The final strategy was then put together (following
further testing and consultation) mostly from schemes taken from
each of the four initial packages. It essentially consists of:
High public transport improvement,
High road capacity increase, and moderate travel restraint.
3. Details of the schemes, including costs
and timings, proposed in the final strategy. Please include information
on the split between expected public and private finance where
available.
| Scheme/Intervention
| Agency | Cost
£ million
| Timescale |
| Heavy Rail | |
| |
| NR14/NR15: Station Access/Facility Improvements
| SRA/Railtrack/Local Authorities | 13
| 2005-06 |
| New Rail Services |
| | |
| IR2: South Coast-Birmingham-Nott-West Yorkshire
| SRA/Rail operators |
| 2003-06 |
| IR5: Manchester-Stoke-Derby-Leicester | SRA/Rail operators
| | 2003-06 |
| IR8: Sheffield-Alfreton-Leicester-St Pancras
| SRA/Rail operators |
| 2003-06 |
| IU1: Cardiff-Birmingham-Nottingham | SRA/Rail operators
| | 2003-06 |
| IU2: Birmingham-Leicester-Nottingham-Alfreton-Sheffield
| SRA/Rail operators |
| 2003-06 |
| IU4: Manchester Airport-Nott-Mansfield |
SRA/Rail operators/Railtrack |
| 2003-06 |
| UT1: Belper-Derby-Nottingham | SRA/Rail operators
| | 2003-06 |
| UT3a: Mansfield-Nottingham 2nd train per hour
| SRA/Rail operators |
| 2003-06 |
| UT4: Matlock-Derby-Leicester | SRA/Rail operators
| | 2003-06 |
| UT5: Worksop-Nottingham-Leicester | SRA/Rail operators
| | 2003-06 |
| IR3: South Coast-Birmingham-Nottingham-W Yorks
| SRA/Rail operators/Railtrack |
| 2006-11 |
| IR6: Manchester-Buxton-Derby-Nottingham |
SRA/Rail operators/Railtrack |
| 2006-11 |
| UT3b: Rotherham-Staveley-Mansfield-Nottingham
| SRA/Rail operators/Railtrack |
| 2006-11 |
| UT7: Chesterfield-Staveley-Mansfield-Nottingham
| SRA/Rail operators/Railtrack |
| 2006-11 |
| Rail Infrastructure (including stations)
| | | |
| NR5: Clowne Branch reopening | SRA/Railtrack/Local Authorities
| 29 | 2003-06 |
| NR6: Pye Bridge-Kirkby Summit reopening |
SRA/Railtrack/Local Authorities | 5
| 2003-06 |
| NR8: Castle Donington line reopening | SRA/Railtrack/Local Authorities
| 9 | 2003-06 |
| NR12: Matlock-Buxton reinstatement | SRA/Railtrack/Local Authorities
| 76 | 2003-11 |
| NR13: Newark Chord | SRA/Railtrack/Local Authorities
| 10 | 2006-11 |
| NR14: Network capacity improvements | SRA/Railtrack
| 69 | 2003-06 |
| New stations at Trowell, Derby South, Blaby
| SRA/Railtrack/Local Authorities | 29
| 2003-06 |
| Freight | |
| |
| FR1: Intermodal Railfreight Terminal | SRA/Railtrack
| 10 | 2009-11 |
| FR2: Loading Gauge Improvements | SRA/Railtrack
| 30 | 2011-16 |
| FR3: Humber Rail Link | SRA/Railtrack
| 10 | 2012-15 |
| TC7: Inland Port at Colwick | BWB/Humber Barges/Developer
| 10 | 2006-07 |
| Road Based Public Transport |
| | |
| LR1: NET extensions to Clifton, M1 J25/Beeston, Nuthall
| City and County Councils | 296
| 2003-06 |
| LR3: Additional NET routes to Nottingham South, Ilkeston
| City and County Councils | 254
| 2006-11 |
| LR5b/c: New LRT East Goscote-Leicester-Blaby
| City and County Councils | 296
| 2006-11 |
| New express coach services BC4, BC5, BC6, BC7
| Local Authorities/Coach operators |
| 2003-06 |
| Strategic Park & Ride |
| | |
| PR3a: Trowell Parkway (served by NET) including a new Road Link from the M1 Service Area with an M1 over-bridge
| Railtrack/Highways Agency/ Nottinghamshire County Council
| 10 | 2008-11 |
| PR3b: M1 Junction 26 (Nuthall)Served by an ext" n of NET
| Nottinghamshire County Council | 19
| 2004-05 |
| PR3c: M1 Junction 25served by NET via Beeston
| Nottinghamshire County Council | *
| 2008-11 |
| PR5: MEGZ (served by Heavy Rail via the re-opened Clowne Branch)
| Derbyshire County Council | *
| 2015-16 |
| Motorway | |
| |
| MW1: M1 Junction 21 roundabout carriageway widening and lane re-allocation/re-signing
| Highways Agency | 0.5 |
2003 |
| MW3a: M1 Junction 29 northbound off-slip and roundabout carriageway widening
| Highways Agency | 0.5 |
2003 |
| MW3: M1 Junction 28 roundabout carriageway and A38 approach widening
| Highways Agency | 2 | 2004-05
|
| MW10: M1 north to A610 Link Roads | Highways Agency
| 7 | 2006-07 |
| MW3b: M1 Junction 29A617 Flyover |
Highways Agency | 7 | 2006-07
|
| MW11: M1 Junction 23A to 25 Improvement |
Highways Agency | 64 | 2009-11
|
| MW8: M1 to M69 Link Roads and widening to M1 Junction 21A
| Highways Agency | 24 | 2009-11
|
| MW12a: M1 widening to five lanes Junction 25 to 27 with A610 flyover at Junction 26 and Junction 25 improvement
| Highways Agency | 176 |
2009-11 |
| MW15b: M1 widening Junction 27 to 30 with crawler lanes between junctions 27 and 29.
| Highways Agency | 185 |
2009-11 |
| MW15a: M1 widening Junction 21A to 23A with crawler lane on southbound approach to Junction 22
| Highways Agency | 98 | 2009-11
|
| Strategic Roads | |
| |
| SR4: M1 Junction 24: A453 to A50 left turning lane
| Highways Agency | 0.2 |
2003 |
| SR7a: Minor improvement of the A453: Crusader Junction to University.
| Highways Agency | 1 | 2003
|
| SR5: Kegworth Bypass | Highways Agency (or Leicestershire County Council if A6 de-trunked)
| 7 | 2005-06 |
| SR18: A617 Pleasley Bypass Extension | Nottinghamshire County Council
| 5 | 2006-07 |
| SR18: A617 Glapwell Bypass | Derbyshire County Council
| 11 | 2006-07 |
| SR12: New Bridge across River Trent east of Nottingham City Centre-
| Local Authorities | 23 |
2009-11 |
| Policy Interventions |
| | |
| Policy Intervention Programme | GOEM/EMRLGA lead
| 30 | 2003-07 |
| Strategy Implementation and Monitoring Body
| GOEM/Local Authorities |
| 2002-21 |
| Public Transport Co-ordinating Body | Central Government/EMRLGA
| | 2006 |
| Integrated Ticketing | Central Government/TOCs
| | 2006 |
| Goods Vehicle Restriction on motorways |
Central Government | |
2011 |
*Costs included elsewhere Quick win
Subject to further assessment Quick win
Note: The Table excludes on-going operating costs incurred
by private sector operators. It also excludes annual maintenance
and operating costs associated with major infrastructure.
| Total | £1,816m
| |
| Public Transport / Freight | £1,175m
| 65% |
| Highways | £611m | 33%
|
| Policy | £30m | 2%
|
4. Details of the timing and scale for the introduction
of charging measures in the study area
A wide range of charging scenarios were tested both as part
of the study and also separately at the request of the DfT. The
implications of the different charging regimes have been reported
in a study Technical Note.
Due to there being no indication from Government that legislation
to enable charging would be introduced in the foreseeable future,
charging was not included within the final strategy. However,
it was stated that the full level of motorway widening recommended
would not be needed if road charging were to be introduced in
the medium term.
In terms of the charging strategythis was linked to
a much improved public transport system that would be delivered
through the M1 recommendations. The thinking was that public transport
needed to be improved to become a transport choice for significantly
more people before charging being introduced to encourage greater
mode shift away from the private car.
5. The costs and forecast impact on traffic levels of
the behaviour change measures proposed and a list of suggested
measures.
A programme of policy measures (including behaviour change)
is included in the recommended strategy. This was costed at a
figure of £30 million for the first five years. The following
is extracted from the Final Report.
POLICY INTERVENTIONS
As the Executive Summary to the Consultation on the Draft
Preferred Package Report of December 2001 indicated, even with
significant investment in public transport use, increases in highway
capacity will be necessary if traffic conditions are not to get
worse. In this context, "significant behaviour change is
needed to reduce reliance on the car, increase public transport
use and thus reduce the growth in traffic". The longer term
M1MMS strategy depends on travel demand management and behaviour
change.
For this to be successful, people need to understand today's
transport problems, and their implications for the future, and
the part they can play in helping to resolve the situation through
travel behaviour change. There is also the need to identify practical
ways by which the partners in the East Midlands can act to facilitate
behaviour change, incorporating it as a distinct component of
all the recommended activity streams, and also pursuing it as
an area of activity in its own right.
It is clear that success will require the political willingness
to become engaged at national, regional and local levelsa
willingness which is not yet generally apparent. Some of the pioneering
work already undertaken in the East Midlands could, however, form
the basis of efforts to make the region a recognised centre for
excellence in the field of travel demand management. Clearly Regional
Planning Guidance and the Regional Transport Strategy are central
to the definition of how to take things forward.
As indicated in a recent Soft Factors Report produced for
the DTLR1, individual measures are likely to have little impact,
but a coherent, integrated set of policy interventions may be
more effective. The policy interventions and measures identified
in that report as offering significant change should be given
due prominence in the M1MMS behaviour strategy. These are:
workplace travel plans;
public transport fares and ticketing;
individual marketing campaigns; and
bus quality partnerships.
A number of other policy interventions and measures will
also be critical components of a behaviour change strategy for
the M1MMS. These include:
urban chargingcongestion/road user or workplace;
parking strategy and its application;
development control policy and its implementation;
school curriculum contributions;
household and community behavioural change approaches;
improved interchange; and
Given that the two basic aims of the policy interventions
are to educate, and facilitate travel behaviour change, the framework
of interventions by which the aims might be achieved should incorporate
actions to:
ensure the next generation(s) are better informed
and more discerning in their travel behaviour;
ensure a consistent application of travel demand
management policy interventions such as parking supply and management,
charging (road user and/or workplace) development control etc;
ensure that investment in infrastructure and service
improvements is matched by action to maximise their utility;
create a deliberate and open monitoring programme
early in the plan programme, to assess in a robust manner the
programme outcomes;
demonstrate success in the first five years; and
promote an ambition for regional excellence and
a pre-eminence in the subject that will help achieve the plan
and benefit local employment.
Six areas of intervention are identified which could be taken
forward as discrete programmes of activity. These are set out
below, together with an indication of some of the tasks which
each could entail. Clearly the study cannot be prescriptive. The
suggested components are illustrative and not a blueprint. Further
details of the strategy are set out in the study report: "Policy
Interventions: The Programme of Measures".
Strategy Programme
The programme of activity recommended by the study includes
infrastructure measures, public transport service improvements
and policy interventions concerned with travel demand management
and behaviour change. The success of the third element will determine
what is needed in future years with respect to infrastructure
and service development.
In developing the strategy programme, it is assumed that
an oversight roleEast Midlands Partnership for Transport
Policy Interventions (EMPfTPI)would be appropriate. This
could be chaired by GOEM, but operate through, and in close partnership
with, the local authorities that have the responsibility for much
in terms of local transport as well as with the proposed Public
Transport Co-ordinating Body (or Executive).
The strategy programme tasks might entail:
championing the strategy, and communicating the
successes;
leading/co-ordinating the implementation programme
for infrastructure and service improvements; advising on prioritising
of expenditure on infrastructure, services and policy interventions;
developing area-wide policy responses and seeing
their implementation progresses satisfactorily and consistently
in accordance with the objectives set;
providing region-wide local authority officer
training, with respect to various areas of policy applicationparking
supply and management, freight transport, interchange, development
control etc;
developing and representing the centre of excellence
in the policy area of travel demand management and behaviour change;
leading the work of regionally significant interventions,
such as a regional freight transport strategy, transport assessments
and facilitation of measures at major business parks alongside
the M1 or in the corridor; and
monitoring and reviewing the strategy.
Workplace Travel Plans
The workplace travel plan is a policy intervention that is
central to ambitions for travel demand management and behaviour
change. Significant change for the better has already been demonstrated
in the monitoring of some existing plans. Employers' initiatives
in Nottingham have been regarded as good practice exemplars for
some years, as has the partnership sponsored by the City Council.
The strategy proposes that the EMPfTPI would provide a regional
dimension to the promotion of these initiatives. Specific tasks
might entail:
extending the work of local authorities that is
already underway;
facilitating measures at major business parks
along the route of the motorway;
providing a regional scheme of assistance in measuring
and monitoring progress; and
promoting a programme of development of tele-working/teleconferencing.
Transport Quality Partnership Scheme
Quality partnerships provide the means by which transport
operators and local authorities can find ways to develop best
practice solutions in service supply. Successful partnerships
have been shown to make a major difference, to the benefit of
users. The concept has recently been extended to freight transport
in connection with distribution strategies for Local Transport
Plans. Whilst local partnerships already exist, many of the public
transport improvements suggested in the strategy would benefit
from area wide co-ordination and "branding".
This aspect of activity would be led by the proposed Public
Transport Co-ordinating Body and involve establishing study area
or regional partnerships with a view to achieving improvements
in transport operations and operating practice. It might thus
entail:
communicating and promoting change and system
improvement over time;
taking forward an East Midlands passenger transport
ticketing initiativethrough tickets on different modes/services,
electronic ticketing/smartcard initiatives etc;
taking forward initiatives relating to freight
transport policy, such as fuel initiatives and improved co-ordination;
introducing system-wide information improvements;
branding and communicating the East Midlands passenger
transport network; and
actively marketing and promoting (not just informing
of the existence of) the East Midlands network of passenger transport
services.
Awareness Raising Programme
Whilst there have been awareness raising campaigns under
the auspices of DTLR and local Travelwise initiatives, the strategy
requires more direct promotion of the local interventions. The
introduction of climbing lanes or narrower lanes on the motorway,
for example, could make it appropriate to try to influence driving
standards through an advertising campaign.
This strand of activity would entail such elements as:
communicating the plan and programme over time;
and
providing information designed to dispel the "perception
gaps", particularly with respect to public transport, identified
in the study.
Educational Programme
While a number of education authorities, in connection with
their Local Transport Plans, are taking forward initiatives aimed
at devoting parts of the curriculum in primary and secondary schools
to transport and related issues, this area of intervention will
be particularly important in ensuring that the next generation(s)
are better informed and more discerning about their travel behaviour.
It will be targeted at both schools and universities/colleges,
and involve:
assessing the extent of schools' travel plans
implementation;
researching the scope for introducing travel behaviour
training into the curriculum, given that a new "Education
for Sustainable Development" approach to the whole national
curriculum is due to be introduced in 2002;
researching the possibilities of introducing more
university/college travel behaviour related courses and research
programmes; and
exploring the scope for these institutions to
become involved in monitoring progress.
Community Programme
Individualised marketing and personalised journey planning
initiatives have demonstrated that people do make changes to their
travel behaviour, if it can be shown that there are benefits to
be gained by so doing. Cost savings are important, but some respond
well to environmental improvements, health improvements and so
on.
This area of intervention might thus involve:
identifying the range and nature of current community
activity;
identifying the scope and scale of a possible
programme of community intervention designed to influence travel
behaviour, in conjunction with or in addition to current activity
including Agenda 21 programmes; and
one or two demonstration projects per year, to
demonstrate individuals'/organisations' ability to change their
travel behaviour, to the overall benefit of others.
Key Partners
In addition to GOEM and the Regional Planning Authority,
a wide range of organisations would be needed to participate in
and to support the activities required. These would include:
LGA and local authorities;
East Midlands Development Agency;
Strategic Rail Authority;
Transport trade bodies including CPT and FTA;
Public transport operators;
Employers' representatives and chambers of commerce;
Environmental and community interest groups;
Retailing representatives.
This programme of policy interventions has been costed at
£30 million for the first five years within the overall cost
of the recommended strategy.
6. A summary of outcomes including mode shift and congestion
reduction.
| Measure | Change
|
| Access to New Rail Station | +2060
|
| Access to LRT | +118,000 |
| Accidents | -5% |
| Vehicle kilometres | -3%(HGV -14%)
|
| Vehicle Hours | -6%(HGV -15%)
|
| M1 Journey Times | -15%(-9% compared to base year)
|
| Total Traffic | -1% (HGV -4%)
|
| Stress on M1 | -65%(-35% compared to base year)
|
| Stress on other roads | -25%(+12% compared to base year)
|
Table 8.4 from final report
HIGHWAY NETWORK AND M1 AM STRESS LEVELS (2001 AND 2021)
| | % of links at 2001
| % of links at 2001 |
|
| | |
Do Min | Preferred |
| All Links | Below | 60%
| 60% | 62% |
| Approaching | 17%
| 17% | 19% |
| At | 9% |
9% | 6% |
| Above | 14%
| 15% | 13% |
| M1 Links | At | 20%
| 33% | 13% |
| Above | 0%
| 17% | 0% |
Table 8.15 from final report
RECOMMENDED STRATEGY AND DTLR's PUBLIC SERVICE AGREEMENT
| DTLR's Public Service Agreement |
M1MMS Recommended Strategy Contribution |
| To reduce road congestion on the inter-urban network and in large urban areas in England to below current levels by 2010 by promoting integrated transport solutions and investing in public transport and the road network.
| The motorway widening, junction improvements, new link roads and new local bypasses will result in a reduction in congestion in the most of the seriously congested locations in the study area. At 2011 the preferred strategy will reduce AM peak hour motorway stress to 7% from 20% in the base yeara reduction of 65%.
|
| To increase rail use in Great Britain (measured in passenger kilometres) from 2000 levels by 50% by 2010, with investment in infrastructure and capacity, while at the same time securing improvements in punctuality and reliability.
| The recommended strategy is forecast to increase rail use for trips in and to/from the study area by 48% in the peak and 107% in the off-peak (including light rail). Most schemes can be implemented by 2010 or soon after this.
|
| To increase bus use in England (measured by the number of passenger journeys) from 2000 levels by 10% by 2010, while at the same time securing improvements in punctuality and reliability
| Notwithstanding the significant increase in rail usage, bus use will increase by 28% in the peak with a small decrease in the off-peak. The wider improvement of bus services between the major urban areas and to/from rail interchanges will add to this increase.
|
| To double light rail use in England (measured by the number of passenger journeys) by 2010 from 2000 levels.
| The strategy recommends a total of six New Light Rail lines. This will provide a very substantial increase in light rail use within the study area compared to the situation with just the NET Line 1 that is due to be operational by 2003. This excludes that significantly larger patronage that can be expected to be attracted to light rail from within the urban areas but that has not been assessed as part of this strategic study.
|
| To cut journey times on London Underground services by increasing capacity and reducing delays.
| Not applicable. |
| To improve air quality by meeting DTLR's National Air Quality Strategy targets for carbon monoxide, lead, nitrogen dioxide, particles, sulphur dioxide, benzene and 1-3 butadine.
| At 2021 the strategy will reduce emissions as follows: NOx663(tonnes/year)PM1013 (tonnes/year)
|
| To reduce greenhouse gas emissions by 12.5% from 1990 levels, and move towards a 20% reduction in carbon dioxide emissions by 2010.
| The recommended strategy will result in a 5% reduction in greenhouse gas emissions at 2006 but no change at 2021. Congestion reduction brought about through the recommended strategy will reduce carbon dioxide emissions. Many of the schemes can be implemented by 2010.
|
| To reduce the number of people killed or seriously injured in Great Britain in road accidents by 40% by 2010 and the number of children killed or seriously injured by 50%, compared with the average for 1994-98
| The recommended strategy will result in a reduction of nearly 8,000 road traffic casualties over the 30 year assessment period saving 1,300 fatal or serious injuries.
|
7. A list of key implementation issues and risks identified
by the studies.
The need for a specific body to be established to champion
and monitor the implementation was recommended.
The main risk is associated with the delivery of the Heavy
Rail schemes. Not only because of the issue of satisfying value
for money criteria but simply in terms of the overall national
spend resulting from the multi-modal studies and also the substantial
resource issues associated with delivering the many schemes that
are in addition to those included in the SRA's Strategic Plan.
October 2002
|