Memorandum by Hallam Land and William
Davies (SHC 07)
THE ABILITY OF MILTON KEYNES TO ASSIST MEETING
THE STATED AIMS OF THE DEPUTY PRIME MINISTER
INTRODUCTION
Development Land and Planning Consultants have
been requested to make this submission on behalf of Hallam Land
Management Ltd and William Davies Ltd with particular reference
to the Deputy Prime Minister's comments regarding Milton Keynes.
Our clients have interests in two areas of land which are considered
to be fundamental to the future growth of Milton Keynes and as
such to the achievement of the Deputy Prime Minister's stated
objectives in his speech of 18 July 2002.
The first area is to the east of the City and
is contained by the M1 within the existing boundary of Milton
Keynes and currently identified in the emerging Local Plan as
"Strategic Reserve" land within The Eastern Expansion
Area (EEA) of Milton Keynes. This is an area of land is within
relatively few land ownerships and is capable of being brought
forward on a phased basis starting if planning permission was
granted in 2004 and would continue to provide dwellings to and
beyond 2011. This site is identified as being developed in all
of the scenarios of the Sub Regional Study and as such there can
be little question as to the long-term development of the site
it is more a question of both when and how. At present the site
is identified as strategic reserve land to be brought forward
as and when required. However it is our opinion that if the Deputy
Prime Minister is to tackle the serious under provision that is
occurring in the region at the present time then he should act
to release development land in locations that are able to provide
the ability to build new sustainable communities. As this area
is already identified for future development his intervention
to bring such sites forward in accordance with his stated role
for Milton Keynes represents a positive action which could be
regarded as actively attempting to resolve the problems identified
in his speech of the 18 July 2002. By requiring the whole of the
site to be planned comprehensively the Deputy Prime Minister could
achieve an integrated and sustainable development.
The second area of land in which our clients
have an interest is "Area eight" at Bletchley. It is
this land which forms a large part of another opportunity to rapidly
deliver further sustainable communities for Milton Keynes, albeit
land which falls within Aylesbury Vale District. The Milton Keynes
and South Midlands Study 2002 recommends substantial westerly
expansion of the city into Aylesbury Vale District in each of
its spatial development options for growth. In reviewing the Buckinghamshire
Structure (1991-2001), Milton Keynes Council (MKC), Aylesbury
Vale District and the County Council jointly commissioned a study
by Llewelyn Davis of land on the periphery of the city in order
to identify expansion opportunities. The "Milton Keynes Expansion
Study" identified this opportunity to the south of the city.
It is our opinion that if the Deputy Prime Minister
is to tackle the serious under provision that is occurring in
the region then he should act to release development land in locations
such as these which are able to rapidly deliver new sustainable
communities. His intervention to bring such sites forward in accordance
with his stated role for Milton Keynes represents a positive action
which could be regarded as actively attempting to resolve the
problems identified in his statement of the 18 July 2002. The
statement underlines the importance of achieving "quicker
growth" and "accelerating proposals". The conclusions
and recommendations of the Milton Keynes and South Midlands Study
are clear especially the realisation that the time frame for implementation
is critical if a meaningful impact on patterns of development
is to take place. It sets out that 2011 is the date from which
new patterns of growth should begin to be put in place although
planning for any change of direction will need to be put in place
well before hand.
With such an onus on beginning this "planning
to deliver" process sooner rather than later, it is disappointing
that both MKC and Buckinghamshire County Council appear to be
driving on with their development plan reviews without giving
due weight and consideration to this emerging sub-regional vision.
DEFINING THE
PROBLEM
It is important to note in any assessment of
housing requirements to 2016 the changes that have taken place
since the 1992 household forecasts on which the RPG figure is
based.
First it is now well accepted that the overall
level of housing provision for the South East and by implication
this county, set out in the RPG is substantially below that now
forecast for the Region. The further reduction in the level of
housing provision made in the final version of the guidance from
43,000 to 39,000 dwellings (a 9% reduction) is a short-term requirement
as is recognised by the guidance which explicitly states that
this figure is to be reviewed by 2006. Even if the figure is reviewed
at that time it will take a further four years to be incorporated
in new development plans and new allocations are unlikely to be
granted planning permission to accommodate any additional need
until after 2011. It must be assumed that without intervention
the low rate set in the RPG will continue throughout the next
10 years.
The difference between the numbers of new households
forecast for the South East by the 1992 projections of 807,000
compared to the figure of 870,000 in the 1996 projections is 63,000
households (DETR Projections of Households in England 2021). This
is an 8% increase in the level of additional households above
the 1992 projections.
Further information in the 1998 population projections
indicate that the overall level of under provision for the region
will have increased by a further 73,000 by 2016. This represents
an increase of 9.7% from the 1996 projected figure of 753,000
(A Holman's 1999).
In the region as a whole the increase of demand
above supply taking into account the most up-to-date information
is approximately 26%.
This under provision is reflected at the lower
level in that the published government household projections for
Buckinghamshire 1996 to 2016 (DETR 2001) are 75,000 households
or 3,750 new households a year. Allowing for a 3% vacancy rate
this increases to 3,860 dwellings per year for the county. This
new projection is again some 20% higher than the current level
of proposed provision for the county in the RPG (3210 dwellings
per year) and would require an additional 630 dwellings a year.
This new projection takes no account of the enhanced role that
Milton Keynes is supposed to fulfil within the region with regard
to the accommodation of growth from outside of the county.
In light of this most recently published information
it must be concluded that the present rate of house building proposed
in the emerging structure and Local Plan is unlikely to meet the
requirements generated by local needs and past patterns of migration
let alone the Deputy Prime Minister's strategic objective for
Milton Keynes of accommodating increased levels of demand from
outside of the county. If the "reduced RPG rate" effectively
remains in force for the next 10 years then the Deputy Prime Minister's
objectives will remain unfulfilled.
The situation is not just that the RPG figure
is, in light of much more recent information, substantially under
supplying the housing needs of the county, but that other changes
to the economy have also impacted upon household formation since
even the 1996 household forecasts were published. The household
projections are not estimates of total need but forecasts of effective
demand for housing under recent socio-economic conditions. As
such these forecasts are likely to fluctuate depending upon a
number of variables including:
Increase in GDP Per head of 0.25%
per year may result in an increase of 5% in the household projections
to 2016.
Decrease of mortgage rate by 1% over
period of the projection may result in an increase of 7% in household
projections to 2016.
Decrease in unemployment by 1% over
period of projection may result in an increase of 1% in household
projections to 2016.
Source: "Projections of households in England
to 2021" Annex G.
These variables may not be independent and their
results can not be summed. The following changes however all suggest
that the economic conditions are moving in the direction of increased
forecasts of demand. Since 1996 the following has occurred:
The continued support for the economic
growth of the region.
A decrease in mortgage rates of 1.5%
A decrease in unemployment in the
South East to 3.4% by 2000 the lowest rate in the UK.
The impact of all these factors is to increase
the effective housing demand. It is therefore highly likely that
with economic conditions favourable to housing need becoming effective
housing demand that the levels of household formation from the
same population may increase by up to 7%.
It will no doubt be a strong part of the submission
of the anti development lobby that the recent findings of the
2001 Census should be interpreted as requiring a further reduction
on the rates of housing provision suggested in RPG's and in particular
in RPG9 (South East). Extreme care should be taken of such suggestions.
The difference between the mid year estimates 2000 and 2001 (the
later being corrected in line with the census) is some 295,000
less people than expected being resident in the South East (London
and SE). Therefore the emerging housing crisis is occurring despite
a lower than projected level of total population this provides
strong evidence that the original levels of housing provision
determined in the RPG are far too conservative and are seriously
under providing for the needs for the even this lower level of
population.
Taking into account the economic factors set
out above then Buckinghamshire would need to supply 4,130 dwellings
a year simply to accommodate its own locally generated housing
needs and past patterns of migration.
This assessment of demand is wholly consistent
with Buckinghamshire Councils own research regarding house prices
and build rates. It is no coincidence that in a period of increasing
prosperity and greater access to funding that the county is experiencing
substantial growth in property prices.
In light of the above assessment even a substantial
increase in the level of provision at Milton Keynes would only
result in the county as a whole performing as it has done in the
past and would not allow Milton Keynes to perform any greater
role than previously in the region.
It is our evidence that the short-term undersupply
suggested by RPG9 has, together with the impact of PPG3, lead
to an undersupply of housing far greater than the 10,000 dwellings
required by RPG9. The solution not only requires the making up
the shortfall but the bringing forward the reassessment of the
RPG figure now rather than wait to 2006. As stated above any reassessment
published by 2006 is unlikely to result in additional dwellings
until after 2011.
THE ABILITY
OF MILTON
KEYNES TO
MEET ITS
EXISTING COMMITMENTS
AND TO
PROVIDE ADDITIONAL
DWELLINGS TO
MEET THE
CURRENT GROWING
SHORTFALL
The inability of Milton Keynes to deliver the
level of housing proposed in the extant Structure Plan is acknowledged
by the Buckinghamshire County Council (paragraph 19 Structure
Plan Housing Background Paper). Between 1991 and 2011 Milton Keynes
was to provide some 36,700 dwellings (1,835 dwellings a year)
by 2001 only 16,743 dwellings have been completed and there is
currently a shortfall of 3,257 dwellings compared to the extant
Structure Plan. This indicates a serious under performance of
Milton Keynes and this performance has decreased particularly
in the last five years when completions have fallen from an average
of 1,800 a year to 1,545 a year.
The Council state that this shortfall which
has emerged due to low completion rates particularly in the period
1996 to 2001 may not be made up in the remainder of the plan period
as it would require an annual completion rates of 2,000 dwellings
per year. The Council have previously stated that the reduced
level of completions for the end period of the Structure Plan
may not be exceeded to accommodate this recently acquired backlog
of need. It should of course be recalled that the Structure Plans
lower level of housing provision towards the end of the plan period
(2001 to 2011) was based upon the previous RPG which considered
that Milton Keynes should be completing its planned expansion
and would only need to accommodate its own development needs.
From the evidence above it is suggested that the proposed level
of provision is only likely to accommodate past patterns of migration
and not meet the wider strategic function that was either envisaged
for the City in the 1990s or as now being proposed by the Deputy
Prime Minister for the next decade.
In a way the situation at Milton Keynes is a
microcosm of the failings of the planning system. The extant Structure
Plan envisaged Milton Keynes being a focus of growth in the 1990s
and then slowing down its rate of growth in accordance with the
previous RPG. The emerging Local Plan although based upon this
previous guidance is debating whether it is necessary to fulfil
the housing requirements specified in that plan. In the meantime
the Deputy Prime Minister has approved a reduced housing figure
for the period 1998 to 2006 in the RPG which is to be reviewed
with reference to the outcome of the sub regional study, including
suitability of Milton Keynes as a centre of growth. This study
has now been completed and the Deputy Prime Minister has confirmed
the status of Milton Keynes. Notwithstanding this the Local Plan
is being processed effectively on the basis of the 1992 RPG (including
the tailing off of development in the post 2001 period) the Structure
Plan review is progressed in accordance with the new RPG (including
its reduced housing figure for the period 1999 to 2006 extrapolated
over the whole of the plan period).
The problem facing the Deputy Prime Minister
is that the existing Structure and Local Plan reviews, which do
not include a rate of dwelling provision commensurate with his
decision on the status of Milton Keynes, will not be complete
prior to 2005 at the earliest. Even if RPG9 can be revised by
2006 this will require the review of these development plans presently
being promoted through the system. Even accepting the increased
speed that may result from the adoption of Development Frameworks
and Action Area Plans the implications of RPG review with its
increased provision for Milton Keynes will not be incorporated
into development plans until 2008 at the very earliest. Allowing
two years for the granting of planning permission on the new allocations
made to meet the Minister's decision on the 18 July 2002 then
the earliest dwelling completions can be expected to achieve the
increased role for Milton Keynes will occur in 2010.
Unless the Deputy Prime Minister is willing
to intervene either to approve an amended RPG within the next
two years or to increase the level of provision to be made in
Milton Keynes via the Structure or Local Plan process then his
recent announcement will have little impact on meeting housing
needs prior to 2010.
The inability of the development plan system
to respond to changing circumstances is well documented however
in the case of Milton Keynes the delivery of the identified housing
provision through the Local Plan is also problematic. In adopting
the sequential approach the planning authority in its 1st Deposit
Local Plan policies have restrained the release of strategic sites.
The impact of the proposed policies is to delay the start of the
site and the policies fail to take into account the build rates
that may be achieved on any one site. The implication is that
although in theory the land has been identified to meet the housing
needs its release and the timescale for construction are such
that it will not actually provide the dwellings within the time
period required. Table 1 was submitted in response to the 1st
Deposit Local Plan and demonstrates that the implications of the
phasing policies as then drafted would be a shortfall of 4,400
dwellings.
It is possible that the Local Plan may be revised
so that the start dates of both expansion areas are brought forward
to 2004-05. A realistic build rate on these sites will still result
in an under provision of 2,500 dwellings (table 2). Again table
2 was submitted as part of our representations to the first deposit
of the Local Plan and actually required applications to be submitted
for both expansion areas by now. This has not happened and a period
of two years has transpired and unless any subsequent applications
are dealt with quickly then there is likely to be an increase
in the shortfall by 2011.
The emerging policies of the draft Milton Keynes
Local Plan will fail to deliver even the reduced housing figure
of the extant Structure Plan which is commensurate with the winding
down of the city's strategic role. By 2011 there is likely to
be a level of under provision of approximately 3,500 to 4,400
dwellings unless alterations are proposed to the phasing policies
in the 1st Deposit of the Local Plan.
The ability for the area to deliver the 8,700
dwellings in the period 2011-16 would require a build rate of
1,740. This is an increase in the level of activity over that
which is presently occurring. It is important to recall that this
level of provision is that required in light of the slowing down
of the rate of growth and Milton Keynes no longer performing a
regional role. This is not the future now identified for the city.
The implication of emerging changes to Milton
Keynes Local Plan are illustrated in table 4. This demonstrates
if the second deposit removes all the phasing policies and the
council are willing to grant permission for both areas in the
next three years then the under provision within the time period
of the emerging Local Plan will be reduced to 1,300 dwellings.
To achieve this, the council will also have to be successful in
bringing forward all of their urban priority sites. Failure to
achieve bring forward all these urban sites will increase the
shortfall.
Action is required to be taken immediately if
the emerging Local and Structure Plans are not to proceed in accordance
with the extant policy for the area which is a planned slow down
of development and a reduction in the city's strategic role.
MAKING THE
MOST OF
OPPORTUNITIES TO
DELIVER HIGH
QUALITY SUSTAINABLE
COMMUNITIES
In light of the above analysis it is suggested
that the Deputy Prime Minister consider the long-term planning
of areas so that the planning system may provide the development
needed and these developments may in turn deliver the benefits
required. The five year timescale of development plans for identifying
sites is counter productive in terms of bringing forward the type
of development that the Deputy Prime Minister wishes to see. Large
well planned city and town extensions require time to be planned
and delivered so that appropriate levels of infrastructure maybe
provided.
Enclosed is a Master Plan reference (ENK001/001/revisionD)
prepared by David Lock Associates. Up-to-date Surface Water Drainage
and Transport strategies have also been prepared for the site.
Hallam Land Management and other consortium members are currently
using this work to promote the comprehensive development of the
city's Eastern Expansion Area (EEA) through the Local Plan preparation
process. It demonstrates how such a high quality site is readily
available now to provide a sustainable community for the future.
English Partnerships have fully endorsed this comprehensive approach
to site assembly.
Prior to the 18 July Statement, Milton Keynes
Council (MKC) have deliberated over which of two Expansion Areas
(East and West) should accommodate the majority of their housing
requirement. Notwithstanding English Partnerships call for the
East to be comprehensively planned via a consortium, MKC have
only allocated less than 50% of this 360 Ha site, placing the
majority in strategic reserves for future needs. Such a piecemeal
approach to this strategic site will prejudice is overall deliverability
and infrastructure provision. With Milton Keynes identified as
an important growth area but with a legacy of failing to deliver
housing to meet Structure Plan requirements, such "ready
to go" sites as the EEA should surely now be reconsidered
for comprehensive development within the next plan period to 2011.
In order to achieve the new "living communities"
agenda, the step change in both quantity and quality of new development
in such growth areas requires deliverability in a comprehensive
manner. Such deliverability can be achieved in the EEA and so
justify its identification as a development opportunity, which
the news release"Key Regeneration Role for English
Partnerships" of 24 July 2002, wishes to see expedited. In
line with the wishes of MKC and English Partnerships, the EEA
has already been comprehensively planned via a small and viable
consortium of land interests controlling the Expansion Area and
working together in partnership.
The EEA is a good example of how the City's
original master plan has "open edges" which have been
left to enable the city to grow in any number of different ways
both east and west within the Borough. The logical growth of Milton
Keynes is however still restricted by more than just physical
boundaries.
The statement on behalf of MKC into the RPG9
Public Examination"The Milton Keynes Sub-Region 1999"
refers to the constraint of administrative boundaries.
In reviewing the Buckinghamshire Structure Plan
(1991-2001), Milton Keynes, Aylesbury Vale District and the County
Council jointly commissioned a study by Llewelyn Davies of land
on the periphery of the city in order to identify expansion opportunities.
The "Milton Keynes Expansion Study" identified an opportunity
to the south of the city known as "Area eight" and it
is this which forms a large part of the land in question. The
1998 review of this study identified Area eight as a medium term
development opportunity.
The main body of Area eight is an 80 Ha site
on predominantly low-grade agricultural land bounded by the A421
to the north, the disused Bletchley-Aylesbury railway line to
the south and the hard edge of Bletchley Milton Keynes to the
immediate east. This is shown on the enclosed plan ref: DWB6.
Whilst the land abuts the south western fringes of the City and
development would no doubt serve the City, the site falls completely
within Aylesbury Vale District.
Notwithstanding the following merits of the
site, the current review of the Buckinghamshire Structure Plan
2016 has failed to even consider land adjoining Milton Keynes
as a potential strategic development option:
Its proximity to the Bletchley-Aylesbury/Oxford
railway line forming part of the East West Rail scheme and incorporating
a new rail station.
A public transport interchange and
express park and ride service to central Milton Keynes.
Its ability to fund in part the proposed
Bletchley Southern Bypass linking the A4146 Fenny Stratford bypass
and A421 Buckingham Road.
The absence of substantial technical
or physical constraints.
The ability to rapidly deliver comprehensive
development.
The inherent sustainability of the
land given its proximity to employment, educational, cultural
and leisure facilities in Milton Keynes and Bletchley.
The failure of the Structure Plan to consider
land adjoining the city seems inconceivable given the context
provided by RPG9 and the Milton Keynes and South Midlands Study
2002 which identifies Milton Keynes as a growth area and emphasises
the need for cross-boundary co-operation. The Study clearly recommends
substantial westerly expansion of the city into Aylesbury Vale
District in each of its spatial development options for growth.
To achieve a step change in both the quantity
and quality of new development in Milton Keynes, it is considered
essential that some as of yet unallocated but readily deliverable
sites are reconsidered for meeting the short-to medium-term growth
needs of the City. Two such sites are the EEA and Area eight at
Bletchley. I trust that in the light of your policy statement
you will emphasise to MKC the importance of a comprehensive approach
to the EEA, otherwise the lack of a robust framework for inevitable
growth will see the City "stumbling into it" via short-term
land allocations in successive Local Plans.
My clients consider that action is required
now rather than attempt to rely on the subsequent reviews of RPG's
and development plans which will not deliver any change on the
ground in this important location until 2010 at the earliest.
Table 1
THE IMPLICATIONS OF PROPOSED PHASING POLICIES
ON LEVEL OF PROVISION OF NEW HOUSING IN MILTON KEYNES
|
| | East flank
| Proposed | West flank
| Proposed | Other 3388 + 2250
| northern expansion area
| Rates of completion
| Totals |
|
| Existing | 3857
| 1060 | 6442
| 5300 | 5618
| | | Structure Plan
requirement 22277
|
| | Annual build rate
| Expansion area | Annual build rate
| Expansion area | Annual build rate
| Annual build rate | Annual build rate
| |
| 1999-2000 | 600
| | 600 |
| 500 | 0
| 1700 | |
| 2000-01 | 600
| | 600 |
| 500 | 0
| 1700 | submission of application for eastern expansion area
|
| 2001-02 | 600
| | 600 |
| 500 | 0
| 1700 | |
| 2002-03 | 600
| | 600 |
| 500 | 40
| 1740 | permission granted for eastern expansion
|
| 2003-04 | 600
| | 600 |
| 500 | 100
| 1800 | |
| 2004-05 | 600
| 60 | 600
| | 500 |
100 | 1860
| first dwellings on site eastern expansion area
|
| 2005-06 | 257
| 200 | 600
| | 500 |
100 | 1657
| submission of application for western expansion area
|
| 2006-07 | 0 |
200 | 600
| | 500 |
0 | 1300
| |
| 2007-08 | 0 |
200 | 600
| | 500 |
0 | 1300
| permission granted for western expansion
|
| 2008-09 | 0 |
200 | 600
| | 500 |
0 | 1300
| |
| 2009-10 | 0 |
200 | 442
| 158 | 500
| 0 | 1300
| first dwellings on site western expansion area
|
| 2010-11 | 0 |
0 | 0
| 400 | 118
| 0 | 518
| |
| Total | 3857
| 1060 | 6442
| 558 | 5618
| 340 | 17875
| Structure Plan shortfall 4402
|
| Ave 1999 2011 | 321
| | 537 |
| 468 | 28
| 1490 | |
|
Table 2
THE IMPLICATIONS OF AMENDED PHASING POLICIES ON LEVEL
OF PROVISION OF NEW HOUSING IN MILTON KEYNES
|
| East flank
| Proposed | West flank
| Proposed | Other 3388 + 2250
| northern expansion area
| City total |
|
|
| Existing | 3857
| 1060 | 6442
| 5300 | 5618
| | | |
| Annual build rate
| Expansion area | Annual build rate
| Expansion area | Annual build rate
| Annual build rate | Annual build rate
| |
| 1999-2000 | 600
| | 600 |
| 500 | 0
| 1700 | |
| 2000-01 | 600
| | 600 |
| 500 | 0
| 1700 | submission of application for both expansion areas
|
| 2001-02 | 600
| | 600 |
| 500 | 0
| 1700 | |
| 2002-03 | 600
| | 600 |
| 500 | 40
| 1740 | permission granted for both expansions
|
| 2003-04 | 600
| | 600 |
| 500 | 100
| 1800 | |
| 2004-05 | 600
| 60 | 600
| | 500 |
100 | 1960
| first dwellings on expansion areas
|
| 2005-06 | 257
| 200 | 600
| 400 | 500
| 100 | 2057
| |
| 2006-07 | 0 |
200 | 600
| | 500 |
0 | 1700
| |
| 2007-08 | 0 |
200 | 600
| 400 | 500
| 0 | 1700
| |
| 2008-09 | 0 |
200 | 600
| 400 | 500
| 0 | 1700
| |
| 2009-10 | 0 |
200 | 442
| 400 | 500
| 0 | 1542
| |
| 2010-11 | 0 |
0 | 0
| 400 | 118
| 0 | 518
| |
| Total | 3857
| 1060 | 6442
| 2500 | 5618
| 340 | 19817
| Structure from Structure Plan 2460
|
|
Table 3
IMPLICATION OF BRINGING FORWARD LARGER PART OF EASTERN
EXPANSION SITE
|
| East flank
| Proposed | West flank
| Proposed | Other 3388 + 2250
| northern expansion area
| Rates of completion
| | Totals
|
|
| Existing | 3857
| 1060 | 6442
| 5300 | 5618
| | | | 22277
|
| Annual build rate
| Expansion area | Annual build rate
| Expansion area | Annual build rate
| Annual build rate | Annual build rate
| Cumulative dwelling total
|
| 1999-00 | 600
| | 600 |
| 500 | 0
| 1700 | 1700
| |
| 2000-01 | 600
| | 600 |
| 500 | 0
| 1700 | 3400
| submission of application for both expansion areas
|
| 2001-02 | 600
| | 600 |
| 500 | 0
| 1700 | 5100
| |
| 2002-03 | 600
| | 600 |
| 500 | 40
| 1740 | 6840
| permission granted for both expansion
|
| 2003-04 | 600
| | 600 |
| 500 | 100
| 1800 | 8640
| |
| 2004-05 | 600
| 100 | 600
| 100 | 500
| 100 | 2000
| 10640 | first dwellings on expansion areas
|
| 2005-06 | 257
| 400 | 600
| 400 | 500
| 100 | 2257
| 12897 | |
| 2006-07 | 0 |
400 | 600
| 400 | 500
| 0 | 1900
| 14797 | |
| 2007-08 | 0 |
400 | 600
| 400 | 500
| 0 | 1900
| 16697 | |
| 2008-09 | 0 |
400 | 600
| 400 | 500
| 0 | 1900
| 18597 | |
| 2009-10 | 0 |
400 | 442
| 400 | 500
| 0 | 1742
| 20339 | |
| 2010-11 | 0 |
400 | 0
| 400 | 118
| 0 | 918
| 21257 | |
| Total | 3857
| 2500 | 6442
| 2500 | 5618
| 340 | 21257
| | Structure Plan shortfall 1020
|
| 321 |
| 537 | |
468 | 28
| 1771 | |
|
|
Table 4
IMPLICATION OF EMERGING CHANGES TO MILTON KEYNES LOCAL
PLAN DEMONSTRATING THAT THE REMOVAL OF THE PHASING POLICIES IS
STILL LIKELY TO LEAD TO AN UNDER PROVISION WITHIN THE TIME PERIOD
OF THE EMERGING LOCAL PLAN
|
| East flank Proposed
| West flank Proposed | MK Existing commit- ments *
| northern expansion area | Total Rates of completion
| | Totals |
|
| Proposed** | 1320 | 1850
| 16037 | 440 |
| | 19957 |
| Expansion area | Expansion area
| Annual build rate | Annual build rate
| Annual build rate | Cumulative dwelling total
| |
| 2001-02 | | |
1600 | 0 | 1600 |
1600 | submission of applications for eastern & western expansion area
|
| 2002-03 | | |
1600 | 40 | 1640 |
3240 | |
| 2003-04 | | |
1700 | 100 | 1800 |
5040 | permission granted for expansion areas
|
| 2004-05 | | |
1700 | 100 | 1800 |
6840 | |
| 2005-06 | 75 | 75
| 1700 | 100 | 1950
| 8790 | first dwellings on site expansion areas
|
| 2006-07 | 200 | 200
| 1700 | 100 | 2200
| 10990 | |
| 2007-08 | 200 | 200
| 1700 | 0 | 2100
| 13090 | |
| 2008-09 | 200 | 200
| 1600 | 0 | 2000
| 15090 | |
| 2009-10 | 200 | 200
| 1500 | 0 | 1900
| 16990 | |
| 2010-11 | 200 | 200
| 1237 | 0 | 1637
| 18627 | |
| Total | 1075 | 1075
| | 440 | 2590
| | Structure Plan shortfall 1330
|
| Ave 1999 2011 | 108 | 108
| 1604 | 44 | 1863
| | |
|
Notes:
*Existing commitments (excluding Newton lees 1,000 dwgs and MK13 231) 13,256 revised infill estimate 2010 new housing in rest of borough 755 infill in rest of borough 247.
**Calculated at 40 dwellings per hectare net density.
|
|