Annex A
Update on projects
1. NAME OF
PROJECT AREA:
CHERNOBYL SHELTER
PROJECT
Rationale
Repair and replacement of the sarcophagus surrounding
Unit 4 at Chernobylthus preventing a further serious release
of radioactivity into the environment.
Long term: Complete new Shelter by 2008.
Objectives
Interim: Tenders for major construction elements
of projects released by end 2001. Lead contractors selected mid
2002. Construction work on the new containment to begin by mid/end
2003.
Risks
This will be a massive construction project
requiring tight project management by EBRD contractors if cost
and time over-runs are to be minimised. Potential for Ukrainian
Govt to try and renegotiate agreed design and other issues that
could (i) delay start date, (ii) increase scope of project beyond
current specification. Management of radioactive waste from the
site is one such issue.
EXPENDITURE
2001-02
| Allocation | Spend to date |
Outturn | 2002-03 AllocationForecast
| 2003-04 Allocation |
| Forecast | |
| | | |
|
| £5.53 million | |
£7.88 | £5.53 million |
£4.04 | £5.53 million |
£4.04 |
| | |
| | | |
The CCR estimated some £20 million was required for
this activity over the next 10 years. The budget for the Shelter
project within the FSU Programme stands at £16.59 million
total for the three years. The UK has pledged the money in two
tranches. The first pledge totalled US$16.82 million. The majority
of these funds were disbursed prior to April 2001. The balance
of £3.84 million was paid to the EBRD on 18 July 2001. The
second pledge is for £12.13 million and this is being paid
in three annual tranches. The £3.84 million spent this year
from the first pledge together with the £12.13 million committed
for the second pledge, totals £15.97 million over the three
year programme, Consequently there is a £0.65 million surplus
in the allocation for this programme area at present.
Project Status: This is a long running EBRD managed project
to stabilise and replace the sarcophagus surrounding the damaged
Unit 4 reactor at Chernobyl that exploded in 1986. The present
position is that all the major design phases of the project are
now completeincluding critically the design of the new
Shelterand tendering for the construction works will begin
this year. The project is not scheduled to complete until 2008.
2. NAME OF
PROJECT AREA:
PLUTONIUM DISPOSITION
IN RUSSIA
Rationale
Reduce the threat posed by the proliferation of fissile nuclear
material by converting weapons grade plutonium extracted from
dismantled surplus nuclear weapons into a non weapons useable
form.
Objectives
Long term: Conversion of at least 34 tonnes of Russian weapons
grade plutonium into a non-weapons usable form.
Short term: Completion of further negotiations between donor
governments and the Russian Federation to produce a politically
acceptable, technically feasible and cost effective programme
for the disposition of Russian surplus weapons grade plutonium.
Risks
The considerable uncertainty on when the Programme might
start impacts on the effective management of the FSU programme
budget. Difficulties in the negotiations to achieve the short
term objective may cause continued delay to the disposition programme.
Insufficient international funding may put further pressure on
the UK to increase its pledged contribution of £70 million.
EXPENDITURE
| 2001-02 | Allocation | Spend to date
| Outturn | 2002-03 Allocation
| Forecast | 2003-04 Allocation
|
| Forecast | |
| | | |
|
| £2.5 million | |
£0 million | £10 million
| £10 million | £10 million
| £10 million |
| | |
| | | |
Note: there is still considerable uncertainty about the future
spend profile of work on plutonium disposition. The forecasts
carry a very strong health warning!
Project Status: The UK has announced a contribution of £70
million over the next 10 years. Up to £20 million of this
will come from the new interdepartmental programme over the next
three years, although the precise level of our contribution is
probably fairly flexible. The US has now completed its review
of its non-proliferation programmes and reaffirmed its commitment
to the plutonium disposition programme whilst indicating that
search for a more cost effective solution must continue. The G8
Experts Group (PDPG) will recommence its meetings on 16 April
2002 with a view to progressing the main project for the Russian
disposition programme. In parallel, the US and Russian costings'
groups have expanded their work to include an evaluation of the
cost and effectiveness of hitherto unexplored disposition scenarios.
This work forms a part of the Experts' ongoing attempts to identify
the most cost effective disposition scenario. The UK has, throughout
this period, continued its close dialogue with US colleagues in
an attempt to identify projects which the UK might usefully fund
as a necessary contribution to whichever disposition scenario
is eventually decided upon.
3. NAME OF
PROJECT AREA:
NUCLEAR MATERIALS
ACCOUNTANCY
Rationale
Proper nuclear materials accountancy (NMA) at FSU facilities
reduces the risk that nuclear materials could be lost or otherwise
removed without detection.
Objectives
Overall: to improve NMA at key Russian facilitiesin
particular the Mayak RT-1 reprocessing plant, the Angarsk uranium
centrifuge enrichment facility and in due course other Russian
facilities.
More specific objectives are defined and developed in the
context of particular projects (eg development, delivery and installation
of accountancy software/hardware packages).
Risks
The projects are collaborative to the extent that "intellectual"
(as opposed to hardware) input on the part of the Russian facilities
has not been funded by DTIsuch dependency brings with it
some risk of delays in milestone delivery.
EXPENDITURE
| 2001-02 | |
| | 2002-03 |
| 2003-04 |
| Allocation | Spend to date
| Outturn | Allocation
| Forecast | Allocation
| Forecast |
| £150,000 | | £43,000
| £150,000 | £200,000
| £150,000 | £150,000
|
| | |
| | | |
Note: the CCR estimated some £1.5 million was required
over 10 years for this activity.
Project Status: This programme has been operating for several
years and has been rolled into the FSU programme. Projects at
Mayak and Angarsk are continuingthe projects are managed
by UKAEA on behalf of DTI (as part of the UK Safeguards Programme)
and involve exchange between British and Russian NMA specialists.
Future projects are currently under early stage discussion, and
may involve a small increase in the material accountancy budget.
4. NAME OF
PROJECT AREA:
INTERNATIONAL VERIFICATION
OF EXCESS
WEAPONS MATERIAL
Rationale
To provide the international community with assurance that
nuclear materials declared excess to weapons requirements are
indeed not re-used for weapons purposes.
Overall: to establish an effective international verification
regime for excess-weapons material disposition programmes.
Objectives
Specifically: to contribute to funding IAEA verification
of nuclear material from the dismantlement of Russian nuclear
weapons.
Risks
See project status notescontinuing uncertainty about
the timing and extent of US and Russian programmes for the disposition
of surplus military plutonium are compounded by uncertainties
about the IAEA's role in verifying these programmes (eg its timing
and costs).
EXPENDITURE
| 2001-02 | |
| | 2002-03 |
| 2003-04 |
| Allocation | Spend to date
| Outturn | Allocation
| Forecast | Allocation
| Forecast |
| £200,000 | | £0 million
| £200,000 | £0 million
| £300,000 | £0 million*
|
| | |
| | | |
Note: the CCR estimated that expenditure over the next 10
years would be £3 million.
* at present due to the delay in reaching agreement on Pu
disposition it is unlikely any funds would be committed during
the first part of 2004 (see below).
Project Status: Russia, and the US and the IAEA have yet
to reach agreement on arrangements for IAEA verification of material
from the dismantlement of Russian nuclear weapons and the subsequent
conversion of that material into forms not suitable for use in
such weapons. In the absence of such agreement, and then endorsement
of the IAEA's role in it by the IAEA's Board of Governors, it
is not possible to be more precise about likely funding requirements
and timescales (in which context it should be noted that implementing
such verification does not now feature amongst the IAEA's expected
accomplishments by 2003 but instead in its tentative budgetary
planning for 2004 and 2005).
5. NAME OF
PROJECT AREA:
NUCLEAR SAFETY
PROGRAMME
Rationale
To improve safety at nuclear reactors in CEE/FSUand
assist moves towards the early closure of these reactors.
Objectives
To deliver safety improvements through small scale projects
involving the transfer of technology, best practice, training
of nuclear regulators and plant operators and management and some
very small scale equipment supplies. There are specific objectives
for the 20 odd projects supported under the programme.
Risks
Risks include duplication of effort in reproducing activities
that are being supported by other bilateral donors; failure to
effect change through activities by not focusing projects onto
recipients requirements; lack of impact through inability of recipients
to exploit support.
EXPENDITURE
| 2001-02 | |
| | 2002-03 |
| 2003-04 |
| Allocation | Spend to date |
Outturn | Allocation | Forecast
| Allocation | Forecast |
| £2.76 million | |
£2.4 million | £3.5 million
| £3.5 million | £5.0 million
| £5.0 million |
| | |
| | | |
The budget was discussed at the Advisory Committee at its
November 2001 meeting. A rising increase in the allocation for
those programme areas was recommended and is shown above.
Project Status: Proposals for the 2001-02 Nuclear Safety
Programme were evaluated following an open EU wide tender, and
27 contracts were awarded. At the end of quarter three an additional
seven projects were commenced, some of which will continue within
financial year 2002-03. 24 projects have been completed at the
end of quarter four; four projects are planned to be completed
in financial year 2002-03 and six projects have slipped, such
that they will be completed in 2002-03, although they had been
planned to complete within 2001-02. In addition, the portfolio
includes a further seven projects continuing from 2000-01, six
projects were completed in 2001-02 and one will be completed in
2002-03.
The launch of the 2002-03 programme took place in December
and the majority of the associated work for this competition has
been completed at the end of quarter four. The first stage in
the competition has resulted in 71 proposals being submitted with
a value of £13.4 million spread over a three-year period.At
the end of quarter four, contracts totalling just over £3.0
million for 2002-03 have been awarded or are planned. Further
work is being undertaken in collaboration with NII to identify
support programmes to the nuclear regulators in Bulgaria and Russia.
Other activities are planned that will result in contracts for
the total £3.5 million budget being allocated to projects
in 2002-03.
6. NAME OF
PROJECT AREA:
PHYSICAL PROTECTION
OF PROLIFERATION
SENSITIVE NUCLEAR
MATERIALS
Rationale
Ensuring that proliferation sensitive nuclear materials in
FSU are adequately protected from theft and/or sabotage.
Overallto assist with the protection of proliferation
sensitive nuclear materials in FSU to International standards.
Objectives
Specifically, (a) to identify with Minatom additional projects
by end December 2001 and (b) to provide physical protection systems
for two icebreakers in the Atomflot fleet in collaboration with
Norway and Sweden. Provisional start date April 2002 and completion
January 2003.
Risks
That the equipment supplied and fitted would either not be
properly operated or maintained during its designed life. Projects
are evaluated 6 and 12 months after completion and equipment warranted
for two years by suppliers to minimise the risk. Also plan long-term
evaluation as part of overall FSU Programme evaluation in 2003.
EXPENDITURE
| 2001-02 | |
| | 2002-03 |
| 2003-04 |
| Allocation | Spend to date |
Outturn | Allocation | Forecast
| Allocation | Forecast |
| £1 million | |
£293,000 | £1 million |
£1.7 million | £1 million
| £1 million |
| | |
| | | |
Project Status: The UK collaborated with Sweden on providing
a physical protection system for a nuclear-propelled cargo ship,
the Sevmorput, in NW Russia. This project was successfully completed
by the target date of September 2001. Further projects are under
discussion with the Russian Ministry of Atomic Energy, but it
may take some time to identify further suitable projects, as Minatom's
recent suggestions were not considered suitable. Potential future
proposals include protection systems for two icebreakers, 15 buildings
on civil/military site and a proposal from the Russian Navy. We
will also be exploring as part of the work on NW Russia whether
any of those projects merit including physical protection elements
(eg Andreeva Bay).
The UK has been in discussion with potential Swedish and
Norwegian partners and the Murmansk Shipping Company for the provision
of a physical protection system for two icebreakers in the Atomflot
fleet. Discussions held at DTI in November 2001 agreed the main
areas requiring physical protection, and to proceed under a contract
along the lines used for the Sevmorput project. It was agreed
that the UK should meet 65 per cent of total project costs for
the equipment and installation, the total UK contribution amounting
to £736k for two vessels, subject to Ministerial approval
of the proposal.
7. NAME OF
PROJECT AREA:
DECOMMISSIONING IN
CEE/FSU
Rationale
To aid the closure of Chernobyl and other reactors in EU
accession candidates.
Objectives
Chernobyl to stay closed. Ignalina (Lithuania) Unit 1 closed
by 2005 and Unit 2 by 2009. Kozloduy (Bulgaria) Units 1 to 2 closed
by 2003 and Units 3 to 4 by 2008. Bohunice (Slovakia) Units 1
to 2 closed by 2008. Decommissioning for all these reactors to
move forward.
Risks
Beneficiaries extending the scope of the project and/or requesting
increasing financial support to de-commissioning, beyond the scope
of the current de-commissioning support funds, managed by the
EBRD.
EXPENDITURE
| 2001-02 | |
| | 2002-03 |
| 2003-04 |
| Allocation | Spend to date |
Outturn | Allocation | Forecast
| Allocation | Forecast |
| £2.86 million | |
£2.86 million | £2.63 million
| £2.63 million | £2.0 million
| £2.0 million |
| | |
| | | |
Note: payments can be made in a lump sum to EBRD at any time
during the financial year.
Project Status: The UK has pledged
1.5 million to EBRD managed decommissioning funds for Ignalina
and Kozloduy. In Q3 a similar pledge of
1.5 million was made for Bohunice (Slovakia). The latter fund
has now been set up, and the
1.5 million for Bohunice was dispersed in Q3. Under the EBRD managed
Nuclear Safety Account, support is also being extended for decommissioning
facilities at Chernobyland further requests for UK assistance
may be required.
8. NAME OF
PROJECT AREA:
CLOSED NUCLEAR
CITIES INITIATIVE
Rationale
To prevent the transfer of nuclear weapons expertise in Russia
to "rogue states".
Objectives
Short Term: The provision of non-weapons employment to a
specified number of Russian Federation (RF) nuclear weapons' scientists
and technicians.
Medium Term: Re-deployment/retraining of a specified number
of Russian weapons' scientists to non-weapons projects/employment
with a commercial focus.
Risks
Delays in recruiting specialist project managers to develop
projects and take forward projects.
Failure to foster material commercial engagement in the Closed
Cities because of the difficulties in operating therein.
EXPENDITURE
| 2001-02 | |
| | 2002-03 |
| 2003-04 |
| Allocation | Spend to date |
Outturn | Allocation | Forecast
| Allocation | Forecast |
| £1.0 million | |
£0 million | £1.0 million
| £1.0 million | £1.0 million
| £2.0 million |
| | |
| | | |
The CCR indicated expenditure of some £5 million would
be required over the next 10 years for this area of work.
Project Status: An Updated Strategy Paper was presented to
the Inter Departmental Advisory Committee meeting in March 2002
and has now been approved by the representatives of all departments
represented at the Committee. A submission to Ministers will follow
at the earliest opportunity.
Efforts will now be intensified to identify specific areas
and projects for UK support. These efforts will be in close collaboration
with the ISTC in Moscow, and with colleagues and experts in the
ENCI and in the US and Russia.
9. NAME OF
PROJECT AREA:
NW RUSSIA
Rationale
Assist process of de-fuelling and decommissioning nuclear
submarines in NW Russia, in order to diminish the risks of a nuclear
accident or leakage of large amounts of radioactivity into the
environment.
Objectives
Overall: to increase the annual rate of decommissioning of
submarines.
Short term: to conclude bilateral Supplementary Agreement
with Russia, by June 2002 and to start physical work on SNF interim
storage facility, SNF cask transport ship, Andreeva Bay site characterisation
and cutting up an early generation submarine projects in NW Russia
immediately thereafter.
Risks
The key risk remains the need to conclude the Supplementary
Agreement without which we could not proceed with most of the
NW Russia projects. Financial risks, as with all FSU Programme
projects, will be minimised by close project management to ensure
value of money, modular approach to project design and only paying
on delivered milestones. There may also be construction delays
for some projects.
EXPENDITURE
| 2001-02 | |
| | 2002-03 |
| 2003-04 |
| Allocation | Spend to date |
Outturn | Allocation | Forecast
| Allocation | Forecast |
| £5 million | |
£80,000 | £3.5 million |
£8 million | £3.25 million
| £5.5 million |
| | |
| | | |
Note: the CCR estimated that some £20 million would
be required over the next 10 years.
Project Status: The first two projects in this policy area
are ready to start. That is the SNF interim storage facility at
Polyarnyi and, in collaboration with Norway, funding of the construction
of a SNF cask transport ship. This work and other efforts on other
projects are being held up by the continuing delay in concluding
the Supplementary Agreement to provide cover on critical issues
such as nuclear liability, tax and access. We expect to conclude
the text and sign the Agreement before June 2002. Despite the
delay we have pressed ahead in negotiating further projects. These
include the SNF transport ship project with Norway mentioned above
and the dismantling of a Victor class nuclear submarine. In addition,
we have offered assistance for and are beginning work on a feasibility
project to deal with the problem of SNF at Andreeva Bay. Current
storage provisions for large quantities of SNF at the site is
totally inadequate and represents a major risk of nuclear contamination.
The feasibility work, to be concluded by 2003, will detail proposals
for substantial remediation and new storage construction over
a number of years,
10. NAME OF
PROJECT AREA:
KEDO
Rationale
Preventing North Korea from becoming a nuclear weapons state.
Objectives
Implementation of the agreement between North Korea and the
international community (KEDO) on the provision of two new light
water reactors, in return for agreement by North Korea to abandon
its nuclear weapons programme. The decommissioning and dismantlement
of North Korea's existing graphite-moderated reactors.
Risks
Uncertainty about the level of influence KEDO can exert on
North Korea abandoning its weapons programmes. Breakdown of relations
between North Korea and the US (a major stakeholder in KEDO) could
lead to North Korea reneging on its commitments under the agreement.
EXPENDITURE
| 2001-02 | |
| | 2002-03 |
| 2003-04 |
| Allocation | Spend to date
| Outturn | Allocation | Forecast
| Allocation | Forecast |
| £2.4 million |
| £2.043 million | £2.4 million
| £2.4 million | £2.4 million
| £2.4 million |
| | |
| | | |
The CCR originally allocated £3.5 million
per annum to the KEDO project. The revised allocation is the amount
required to meet the lower than anticipated EU contribution to
KEDO.
The CCR indicated that some £10.5 million
might be required over the next 10 years for this project. The
UK has agreed to contribute to the EU KEDO project for five years,
with funding agreed for the first three years from the FSU Programme.
Project Status: The construction of the reactors is at least
eight years behind schedule, and work is progressing only very
slowly. The original planned completion date of 2003 has now been
revised to end-2010. As a result the bulk of KEDO funds are currently
being used for the purchase of heavy fuel oil to meet North Korea's
on going energy needs. The new US Administration is still reviewing
its policy in this project (and on its relations with North Korea
more generally). The EU is only a minor contributor to the KEDO
project.
Rising oil prices have resulted in a shortfall of funds in
the KEDO project. The KEDO Executive Board sought additional bilateral
contributions from EU member states (and others) last summer to
cover this shortfall. The UK, in common with EU partners decided
against the provision of any additional funds.
A new agreement between the EU and KEDO, guaranteeing continued
EU involvement in the project for five years was signed on 18
December 2001. The EU contribution for 2001 (20 million euro)
has been transferred to the KEDO account in New York. A new delivery
protocol with a timetable for meeting key milestones in the project
has been drafted and discussion of it with North Korea should
commence early this year.
11. NAME OF
PROJECT AREA:
KAZAKHSTAN (DECOMMISSIONING
OF THE
FAST REACTOR
AT AKTAU)
Rationale
Reduce the threat of proliferation of fissile nuclear material
and mitigate the humanitarian and environmental risks posed by
the Aktau nuclear reactor.
Objectives
The safe and irreversible shutdown and decommissioning of
the Akau reactor.
Risks
That international effort to decommission the Aktau reactor
will continue to proceed in an unplanned way or may not be sustained
at all.
EXPENDITURE
| 2001-02 | |
| | 2002-03 |
| 2003-04 |
| Allocation | Spend to date |
Outturn | Allocation | Forecast
| Allocation | Forecast |
| £0.1 million | |
£0 million | £200,000 |
£50,000 | £200,000 |
£150,000 |
| | |
| | | |
The CCR indicated that some £2.5 million would be required
over the next 10 years for this project.
Project Status: Discussions within the IAEA on the decommissioning
of Aktau are continuing. The US is helping with the removal of
fuelthe EU may offer help with more general decommissioning,
although its present position is uncertain. The UK is one of the
few countries with a comparable fast reactor undergoing decommissioning
(at Dounreay) and there has already been some transfer of expertise
from the UK to the Kazakhs on this problem. A paper on the proposal
was presented to the FSU Programme Committee in July 2001.
The DTI has confirmed with the IAEA that UK funding of $20,000
will be available to finance the Peer Review of the Top Level
Decommissioning Plan currently being produced by the Kazaks with
US/EC assistance.
A further IAEA sponsored conference on Aktau decommissioning
was held in March 2002 with UK officials participating. The Top
Level decommissioning Plan is in an advance state of preparation
and a first draft has been seen by the IAEA which expressed itself
satisfied with the efforts now being made to complete it. The
formal submission of the Plan is not now likely however before
August 2002.
In line with the Strategy Paper on Kazakhstan agreed by the
Inter departmental Committee in July 2001, detailed discussions
will shortly commence to further specify areas where the UK could
fund assistance to ensure the completion of the Plan at the earliest
opportunity.
It remains the case that no decisions can be taken on the
provision of UK funded design, technical or engineering assistance
at the reactor site until the Top Level Plan has been Peer Reviewed.
A further IAEA sponsored Conference will be convened as soon as
this has been done.
12. NAME OF
PROJECT AREA:
SOCIAL AND
ECONOMIC IMPACTS
OF NUCLEAR
PLANT CLOSURE
Rationale
Support wider objectives of plant closure through helping
local communities address the social and economic consequences
of closure.
Objectives
Overall: to aid the economic diversification/regeneration
of local regions in the FSU which are adversely affected by nuclear
plant closure and in order to ensure high levels of operational
safety during pre-closure operation of plants scheduled for early
closure, where such closure has been requested by the international
community.
Current specific objectives:
to continue to promote the activities and capabilities
of the International Chernobyl Centre (ICC) and to aim for self-sustainability
of the ICC by 2004-05;
to investigate further projects in Slavutych,
including the possibility of assisting with the communications
infrastructure there;
to help with the setting up of a functioning "new
business incubator" in the Visaginas area near the Ignalina
plant in Lithuaniaincubator set up by 2003;
in 2002-2003 to identify activities that may be
undertaken in Lithuania, Bulgaria and Slovakia.
Risks
Risks include lack of impact and duplication and/or lack
of co-ordination with activities being pursued by other donors.
EXPENDITURE
| 2001-02 | |
| | 2002-03 |
| 2003-04 |
| Allocation | Spend to date |
Outturn | Allocation | Forecast
| Allocation | Forecast |
| £250,000 | | £144,000
| £250,000 | £250,000
| £250,000 | £250,000
|
| | |
| | | |
The CCR estimated that some £1.5 million would be required
over the next 10 years.
Project Status: The UK is providing small-scale assistance
to develop the ICC, principally through the development of ICC's
communications strategy and capabilities, supported by a UK communications
expert. An exploratory mission by BESO to the Visaginas region
to work up plans for a business incubator approach to regional
development has been completed and this has lead to a second phase
of work, focused at developing entrepreneurial skills and knowledge
in the region. Work has also been undertaken to develop a business
case for a fibre optic cable link to Slavutyich.
The Inter-departmental Advisory Committee meeting, held in
March 2002, supported a proposal to develop the Social Consequences
Programme in 2002. The approach of directing assistance to people
directly affected by plant closure was endorsed and the future
programme will be examining what more can be done to develop wealth
creation and jobs in affected communities. Work in Lithuania and
Ukraine will continue. Scoping projects will be undertaken to
develop country specific plans for these countries and for Bulgaria
and Slovakia. It is anticipated that a contract will be established
under the call-off contract scheme to support this work.
The 2001-02 programme had a budget of £250k. A continuing
commitment to the existing project in Lithuania is valued at £108k.
The Interdepartmental Advisory Committee supported an increase
to the budget in 2002-03 to £500k, giving £518k for
projects in the next financial year. Scoping activities will be
used to develop proposals for the 2003-04 budget and programme.
OVERALL BUDGET SUMMARY
| 2001-02 | 2002-03
| 2003-04 |
| Total Budget | £23.9 million
| £27.4 million | £32.5 million
|
| Programme outturn | £15.74 million
| £34.1 million | £33 million
|
| (of which fully committed) |
| £8.44 million | £9.49 million
|
| Project Spend to date | £15.74 million
| 0 | 0 |
| Forecast Running cost draw down | £0.08 million
| -£0.35 million | -£0.4 million
|
Forecast underspend/overspend |
£8.08 million | (£7.05 million)
| (£0.9 million) |
| | |
|
Notes:
Project information as of beginning of April 2002.
Project spend includes contracted out project
management costs.
Includes payment for KEDO which has already been
paid to HM Treasury and treated as an accrual.
FSU Programme
January-March 2002
|