Supplementary memorandum by Parsons Brinckerhoff
Ltd (LU 14A)
LONDON UNDERGROUND
Thank you for your letter of 22 November 2001.
We are fully understanding of the reasons behind the abbreviated
nature of the inquiry on 21 November and we are pleased to provide
the following responses to your written questions.
1. You highlighted in your report the
fact that London Underground could be exposed to "uncontrolled
cost overruns" as a result of updating the standards during
the PPP. Could you elaborate as to the potential seriousness of
this problem and provide some indication of the potential cost
of such overruns. The Committee will be interested to know whether
the cost of the overruns could exceed the cost of updating the
standards and to what extent.
The issue of changing the standards after the
award of the PPP contracts becomes a contractual issue. It is
inevitable that changes to the standards will be required both
from LUL and from the Infracos. Changes requested by the Infraco
will be targeted at making their work more cost effective and
over a 30 year period this could represent savings of many tens
of millions which would be a windfall for the Infracos and is
unlikely to be shared with LUL. Changes requested by LUL will
be focused on revising the standards so as to define the required
performance of the assets and their requirements for safety. The
Infracos may perceive that these performance targets and safety
requirements are greater than their undefined assumptions during
bidding and would therefore require additional costs to implement.
Our opinion is that the potential additional
costs and/or loss of savings will be many times greater than the
estimated £5-£10 million required to update the standards.
2. The Infracos are able to alter 29 per
cent of the standards in agreement with LUL in isolation of the
other Infracos. Do you feel that this could cause a significant
problem if at the end of 30 years the infrastructure were to be
combined as a unified network again? What provisions could be
made in order to avoid such problems occurring?
There is scope for each Infraco to change standards
through modifying the 29 per cent of Category 2 (non-mandated)
standards and by applying for individual concessions from the
71 per cent of Category 1 (mandated) standards. This, in itself,
is not necessarily a great problem except that there is a high
degree of self regulation and it increases the workload and complexity
for LUL staff in auditing different standards for different Infracos.
At the end of 30 years there could be a wide variety between the
standards being used by the three Infracos and the working methods
adopted. Again this is merely a complication, for LUL who may
wish to revise/rationalise the standards back to a single set
following the end of the Infraco contracts.
The PPP requires Infracos and LUL to attend
Asset Performance Review Meetings (APRM). This is the forum at
which revisions to standards are agreed. The mandate of this APRM,
which must be led by LUL, should be to ensure that any and all
(ie 100 per cent of standards) changes to standards are identical
across all three Infracos. This should be included in the PPP
contracts prior to signature as it may be costly to implement
after award.
3. Your report also highlighted the possibility
of the Infracos acting on safety issues without involving London
Underground for up to seven days under the TANC process and that
there is potential for contractual abuse of this process. Can
you clarify who would be responsible for any safety related incidents
that were to occur during such a period and how serious this problem
might be? What would be the likely impact if the Infracos flood
London Underground with a wave of such requests?
Our understanding of the Temporary Approved
Non Compliance (TANC) process is that Infracos can apply for an
exemption from current standards for a period of seven days. During
these seven days the Infraco must either clear the non-conformance
or submit justification for a permanent concession. The responsible
person, as defined in the TANC process, is an "Infraco Authorised
Person". Review of the requests for concessions by LUL can
be lengthy (up to nine months) before approval and it is unclear
if the temporary exemption applies throughout the review period.
If a safety related incident happens at any time on the system,
LUL would be ultimately responsible as LUL is the Infrastructure
Controller and responsible for the Safety Case. Each Infraco will
have its own contractual safety case and this is accepted by LUL
but is not, in the eyes of the Health and Safety Executive, the
ruling document. The problem is potentially serious as LUL has
a legal responsibility for safety of the system and the Infracos
can, under the contract, carry out work not in accordance with
LUL standards.
It is also possible given the TANC and the concession
processes and the time consuming nature of the approval process
that a "wave of requests" could extend the duration
that Infracos continue to work outside the LUL standards. It could
also require competent LUL auditing staff to be diverted from
vital inspection and audit roles to deal with the TANC concession
process.
I trust the above responses are adequate to
meet the concerns of the members and we would be happy to provide
additional clarification should this be required.
Parsons Brinckerhoff Ltd
A J Mustard, DirectorRailways
27 November 2001
|