Appendix B: Illustrative example of a
Risk Description Table
| Category | Construction and Development
|
| Risk | Incorrect Cost Estimate
|
| Definition | The cost to complete the construction phase may be different from that estimated in the tender.
|
| Impact On | Construction timetable and cost
|
| Commentary | PSC: Construction costs in the FBC are based on a standard variation of price government contract. It could change as the design and the programme are developed, or if problems arise.
PFI: The construction cost is a fixed price turnkey price. The risk of changes in cost, during the construction phase, is transferred in full to the private sector.
|
| Risk Retained by Trust | PSC: 100 per cent
PFI: 0 per cent
|
| Estimated Cost of Risk | PSC: £1,323,000
PFI: £0
|
| Overall Probability | 25 per cent
|
| Timing | Risk is apparent throughout the construction period - Years 1 and 2
|
| Evidence for assumptions | PSC: Experience shows that contract prices are not the final price paid by the trust. The original estimate may be higher or lower than the final contract sum.
SourceTrust's technical adviser and workshop discussions, NHS Estates Database.
|