Supplementary evidence by Tom Winsor,
Rail Regulator (RI 21A)
FOLLOWING THE PUBLICATION OF HIS FINAL CONCLUSIONS
ON THE PERIODIC REIVEW OF RAILTRACK'S ACCESS CHARGES IN OCTOBER
2000
INTRODUCTION
1. This submission forms my supplementary
written evidence in response to the letter from the Clerk of the
Transport Sub-Committee dated 19 May 2000. As we agreed before
I submitted my initial evidence, and as we discussed at my last
appearance before the Committee on 12 July 2000, this submission
covers the decisions which I have reached in my final conclusions
on the periodic review of Railtrack's access charges. In particular,
it covers the regime, which I have put in place to ensure that
Railtrack is properly funded and incentivised to maintain and
renew the network, in a safe and efficient manner over the coming
five years, from 1 April 2001.
2. At the time of writing, the tragedy at
Hatfield and the subsequent need to impose speed restrictions
on large parts of the network are foremost in our minds. In my
last submission to the sub-committee, I noted the importance of
safety on the network. I reiterate that view and continue to work
closely with the Health and Safety Executive (HSE). The periodic
review has ensured that Railtrack will be funded as necessary
to protect safety on the network.
3. The periodic review of Railtrack's access
charges, which I have been working on since July 1999, has been
a major piece of work. We have consulted extensively with Railtrack
and other players in the industry and received advice from several
expert consultants in their fields. In total we have published
15 consultation documents and 19 reports from consultants. I have
held formal hearings with Railtrack and others, and have listened
very carefully to everything which has been said.
4. Following this consultation, I have assessed
Railtrack's revenue requirements for the next five years by considering
the level of expenditure required to operate, maintain, renew,
and enhance the network to deliver the baseline outputs (£14.9
billion). I have also established the required return on the company's
regulatory asset base or RAB (at £2.8 billion). Finally,
I have considered the income which it is expected to receive from
stations, property, freight, open access passenger services and
other sources (£3.7 billion). The net revenue requirement
over the next five years is therefore £14.0 billion (ie 14.9
+ 2.8-3.7).
5. The Government has decided that £4.6
billion of this revenue requirement should be supported by a direct
grant. Given this, I have concluded that £8.8 billion should
be paid through track access charges from franchised passenger
operators. I have also profiled Railtrack's revenues so that they
are lower at the start of the period than at the end. This profile
is intended to facilitate Railtrack's financing of its activities
and to meet the preferences of SSRA and DETR (since the implications
of the periodic review are passed on to SSRA through the terms
of the franchise agreements).
6. The remainder of the £14 billion
revenue requirement (£0.6 billion) has been added to the
March 2006 RAB and will therefore be funded beyond the next five
years. This is equivalent to including in the RAB the increase
in allowed expenditure since my draft conclusions in July 2000
(rather than funding this work on a pay-as-you-go basis).
7. The review has also been about defining
the outputs which Railtrack is expected to deliver, and establishing
appropriate arrangements for monitoring and incentivising delivery
of these outputs. I have also introduced new mechanisms which
ensure that Railtrack is fully funded to deliver additional obligations
which might be imposed upon it as well as providing a more robust
framework for enhancement. I have made wholesale changes to the
current regime. These changes, combined with the licence conditions
and model clauses for access agreements which I discussed with
the sub-committee in July, will put in place the right framework
for delivery of the railway which we all want.
8. This submission covers the following
issues which were raised at my last appearance before the Committee
(a full summary of my conclusions is contained in the introduction
to my conclusions on the periodic review):
Railtrack's record on maintenance
and renewal of the network over the last five years: including
additional renewals expenditure;
operation, maintenance and renewal
of the sustained network over the next five years: including
definition of that network, the improvements in efficiency which
Railtrack can achieve, and the new incentive framework within
which Railtrack will operate; and
Enhancements of the network:
including the West Coast Route Modernisation (WCRM) and the SSRA's
Incremental Output Statement, and safety related expenditure.
RAILTRACK'S
RECORD ON
MAINTENANCE AND
RENEWAL OF
THE NETWORK
9. Railtrack's performance over the last
five years is an important factor in assessing the value of its
RAB for the next control period. In particular therefore I have
considered the company's:
underdelivery of the outputs which
could reasonably have been expected from an efficient operator;
and
additional expenditure on renewal
of the network and enhancement of the network over the last five
years.
Under-delivery
10. Since the December 1999 provisional
conclusions on Railtrack's revenue requirements, it has been clear
that I do not believe Railtrack provided all the outputs for which
it was paid over the last five years. This is confirmed by the
advice which Booz Allen & Hamilton, a leading firm of consultants
in this field, gave in their November 1999 report on Railtrack's
stewardship of the network. In particular, I have been advised
that, on track and signalling, Railtrack has not delivered what
might reasonably have been expected (eg track renewal rates were
less than assumed at privatisation, particularly sleepers and
ballast).
11. In considering the case for an adjustment
to the RAB, I have had regard to the fact that the outputs, which
Railtrack was expected to deliver, were not fully specified. I
have also taken account of the additional expenditure which Railtrack
has incurred since privatisation and the extent to which this
has been included in the RAB (see below). Finally, on determining
the appropriate adjustment to the RAB, I considered the approaches
adopted by other regulators. My final conclusions therefore reduced
the March 2001 RAB by £120 million, which is the minimum
amount consistent with the available evidence on under delivery
and the adjustments made by other regulators.
adjustments made by other regulators.
Additional renewals and enhancement
12. Despite this evidence of under delivery,
Railtrack points out that it has spent around £1.9 billion
more on renewals than was anticipated when the initial price controls
were set. I have included two elements of this additional expenditure
in the RAB:
£700 million of additional renewals
which were anticipated at privatisation (net of the associated
reduction in tax) have been included in the RAB since these additional
requirements were equivalent to selling the company with additional
debt (which would have been included in the RAB);
£514 million of additional expenditure
which was not anticipated at privatisation has been included in
the RAB. Although this expenditure had initially been classified
as renewals, it represents an investment in additional outputs
such as improved performance (this is in addition to £851
million of enhancement expenditure in the first control period
which has also been included in the RAB).
OPERATION MAINTENANCE
AND RENEWAL
OF THE
NETWORK
The level of activity required to sustain the
network
13. The level of expenditure which the periodic
review has provided for will enable Railtrack to deliver the baseline
outputs in accordance with best practice, and in a timely, economic
manner so as to satisfy the reasonable requirements of its customers
and funders in respect of the quality and capability of the network.
14. I have assessed this expenditure based
on detailed analysis of the level of maintenance and renewal activity
required to sustain the network. This has involved extensive discussion
with Railtrack and the use of external consultants. In most areas,
Railtrack has accepted my conclusions on the required level of
maintenance and renewal activity. In the case of track renewal,
however, following the advice of my consultants, I have allowed
for significant additional activity, and therefore expenditure,
compared to the company's initial projections.
15. Although I have made expenditure projections
for the next five years, I would generally expect Railtrack to
be funded for the efficient cost of meeting additional obligations
which are imposed upon it during this period (eg additional safety
or environmental obligations). I have indicated that I would generally
expect this to be achieved through an adjustment to the RAB at
the next periodic review (eg I have proposed an automatic mechanism
for adjusting the RAB to compensate Railtrack for any additional
cost arising from the current investigation into broken rails).
In some cases, however, the short term impact on Railtrack's financial
position may mean that charges need to be adjusted before the
next review. I have therefore provided for the possibility of
an interim review of access charges and would expect Railtrack
to make representations to me if it believes that there is a compelling
case for such a review.
Improvements in efficiency
16. The initial assessment of Railtrack's
revenue requirements was based on current costs and expenditure.
However, I also consider that Railtrack should be able to work
more efficiently. Given the requirement for increased activity,
there is no suggestion that Railtrack should reduce its expenditure,
rather it should do more with the money it receives.
17. To assess the scope for efficiency gains,
I have examined:
bottom-up engineering estimates of
possible efficiency gains;
improvements in efficiency achieved
by other privatised utilities;
international comparisons with other
railways;
Railtrack's efficiency at privatisation
and the improvements made in the first control period; and
the conditions of the supply market.
18. All this evidence has led me to conclude
that Railtrack should be able to achieve significant efficiency
improvements. I have therefore assumed savings of 2 per cent in
the first year, 3 per cent in the second year, 4 per cent in the
next two years, and 5 per cent in the last year of the control
period. This is equivalent (in present value terms) to a constant
rate of 3.1 per cent per annum compared to 2 per cent per annum
proposed by Railtrack and 3.8 per cent per annum assumed in my
draft conclusions in July 2000. The reduced efficiency assumption
since July is attributable primarily to the impact of increased
activity in the construction sector on the input prices which
Railtrack is likely to face over the next five years.
on the input prices which Railtrack is likely to
face over the next five years.
Monitoring and incentivising delivery
19. As part of the review I have defined
the baseline outputs which Railtrack is expected to deliver over
the next control period. These include measures relating to the
capability and performance of the network as well as measures
of the condition and serviceability of the assets. I have also
proposed three licence modifications to enable me to monitor delivery
of these outputs more effectively (these relate to regulatory
accounts, the annual return and the appointment of independent
reporters).
20. In addition, I have set out the approach
which I would expect to adopt for the next periodic review. In
particular, I propose to adjust the RAB to compensate for under-
or overspend on train control systems. In other areas, I propose
to increase the RAB so that Railtrack retains the benefit from
unanticipated efficiency savings for a period of five years (regardless
of whether they are achieved at the beginning or end of the period).
On the other hand, I would also expect to reduce the RAB in the
event of significant underdelivery against the specified baseline
outputs in these areas. This approach should therefore provide
a clear incentive for Railtrack to deliver the baseline outputs
as efficiently as possible.
21. Given this incentive based approach
to the next periodic review, failure to deliver the expected levels
of serviceability and condition, or the assumed activity levels,
would not generally need to result in enforcement action. However,
if the company is seen to be falling well short of the relevant
targets, this may be an indicator of serious stewardship problems,
necessitating immediate enforcement action. Railtrack has provided
constructive input towards defining the relevant targets and my
final conclusions have defined both the circumstances in which
action would be required and the basis for establishing monetary
penalties (if any) if enforcement action is required.
Structure of charges and the performance/possessions
regimes
22. I have argued consistently that Railtrack
has public interest obligations in its stewardship of the network.
I have now put in place a framework which will incentivise it
to meet those requirements and I believe that this should minimise
the need for intrusive regulation. The main changes to the structure
of charges which I have introduced will:
ensure that Railtrack's charges are
broadly cost-reflective by increasing the extent to which these
charges vary with the level of traffic;
charges vary with the level of traffic;
increase transparency and predictability
of charges by replacing negotiated charges with predetermined
tariffs;
provide an incentive for Railtrack
to be more responsive to the needs of its customers and funders
through an explicit volume incentive in the RAB; and
ensure that Railtrack has an incentive
to manage its property portfolio efficiently while ensuring that
any outperformance is shared with the industry.
23. I have also made significant changes
to the performance and possession regimes:
the incentive rates in the performance
regime have been increased to reflect the increased societal values
proposed by the SSRA and recalibrate the performance points (benchmarks)
to the expected level of performance over the next control period.
The arrangements have also been simplified to a significant degree
to improve the transparency and effectiveness of the regime. However,
as emphasised in both my draft conclusions and my final conclusions,
safety is paramount and well managed companies will be both safe
and efficient; and
the possessions regime has been modified
to remove the free possessions allowances (which are different
for different operators) and to provide the same compensation
for operators regardless of whether the possessions arise from
enhancements or renewal work. This should incentivise and make
it simpler for Railtrack to make better use of possessions including,
where appropriate, use of longer but less frequent possessions.
In addition I have incentivised Railtrack to give operators early
notification of the proposed possessions where this is possible.
ENHANCEMENTS OF
THE NETWORK
Enhancement framework
24. Although the precise terms for most
new enhancements to the network are outside the scope of the periodic
review (eg those arising from the franchise replacement process),
I have provided considerable detail on the regulatory framework
for enhancement. In particular, I have clarified the basis upon
which I would expect charges to be established where these are
subject to my approval. I have also clarified the way in which
these enhancements will be treated at future periodic reviews
(ie how they will be treated in the RAB). The basic principle
is that the terms should be agreed at the outset so that these
terms can be adhered to. This should provide the necessary transparency
and predictability to facilitate investment in the network.
West Coast Route Modernisation
25. As part of the periodic review, I have
assessed the cost of the West Coast Route Modernisationthis
includes substantial expenditure on renewal of the network which
is subject to the periodic review as well as enhancement expenditure
which is outside the scope of the review. In June 2000, I indicated
that Railtrack's estimate of the cost of the entire project had
increased from £2.3 billion to around £5.8 billion.
My assessment of the total cost of the project is around £5
billion which is made up as follows:
£1,092 million of expenditure
on renewal in the first control period£371 million
of this was paid for in access charges in the first control period.
This was effectively a fixed price contract. However, I have included
£170 million of the additional expenditure in the RAB since
this represents investment in improved outputs (eg performance).
This therefore implies unremunerated expenditure of around £551
million in the first control period;
£2,524 million of maintenance
and renewals expenditure has been provided for in access charges
over the next control period. In addition, £105 million of
costs are expected to arise in the third control period and will
therefore be subject to further assessment at the next periodic
review. Although these costs are much higher than originally estimated,
this element of the project was clearly not intended to be subject
to a fixed price contract; and
clearly not intended to be subject to a fixed price
contract; and
the cost of the enhancements required
by West Coast Trains plus the cost of the additional 42 slow line
paths is estimated at £1,306 million. The West Coast Trains
element is subject to a fixed price contract valued at £546
million and the Regulator has concluded that delivery of the 42
slow line paths would also be a reasonable requirement if Railtrack
is paid £500 million linked to delivery of these enhancements.
This therefore leaves around £260 million of unremunerated
costs associated with these enhancements.
26. In addition to the charging arrangements,
I have set out the way in which I propose to establish milestones
for delivery of the project in conjunction with the SSRA and Railtrack.
Given the importance and the history associated with this project,
I have also set out the way in which I expect to monitor and incentivise
delivery of these milestones. If Railtrack fails to deliver a
milestone it would be required to take remedial measures and may
face penalties if it fails to implement these.
Incremental Output Statement (IOS)
27. As well as the large programme of enhancement
on the West Coast, the SSRA has asked Railtrack to cost a programme
of small enhancements to the network which can be delivered quickly
and at relatively low cost. The total cost of this programme currently
stands at around £409 million.
28. I have concluded that there is more
work to be done in defining these outputs and the SSRA wishes
to consider further the value for money which each represents,
and hence I intend to review these schemes by around July 2001.
Following that review, operators will pay Railtrack only on delivery
of the outputs (or part of the output if I agree that it has been
delivered).
Safety related expenditure
29. The periodic review includes substantial
allowance for safety related expenditure. This includes £3.7
billion for maintenance and renewal of track, including £150
million specifically targeted on reducing the incidence of broken
rails, and £4.2 billion on maintenance and renewal of train
control systems (ie signalling and telecoms).
30. Further expenditure in respect of the
second control period has been included in the RAB. This consists
of £781 million of expenditure on signalling, including £460
million of enhancement expenditure relating to TPWS and other
train control systems, plus £42 million on platform stepping
distances.
31. As noted above, I have also introduced
new mechanisms to ensure that Railtrack is funded to deliver any
further obligations which are imposed during the next control
period.
any further obligations which are imposed during
the next control period.
CONCLUSIONS
32. The most significant single part of
my programme of reform has been the restructuring and resetting
of the financial regime in which the company operates. The financial
framework of the railway industry needs to provide the companies
concerned with a stable and sound environment for investment.
That means improving the incentives to invest in new capacity
and better services, and ensuring that they have certainty and
predictability in how that investment will be treated in future
regulatory reviews. This is essential if the industry is to raise
the finance needed to deliver the required level of investment
in the network.
33. Accordingly, I have also announced new
accountabilities of Railtrack for the proper and timely use of
this money, with the ability to check on the progress and quality
of spending and work and the ability to correct shortcomings before
they become serious. My reforms involve new licence conditions
relating to provision of information by Railtrack and the verification
of this information by independent reporters. They also include
restraints on the disposal of its assets (including land) which
may be needed for railway uses in the future, and the establishment
of a reliable and comprehensive register of the condition, capacity
and capability of the company's assets.
34. This review delivers a financial framework
for Railtrackand through Railtrack the industrywhich
establishes a better, clearer and fairer balance of responsibility
and obligation in the industry. It creates a virtuous circle of
effective incentive-based regulation, strong and empowered management,
clear contracts and sound accountability. These things are necessary
for a long-term framework for sustained improvement in performance.
35. This review equips Railtrack to invest
strongly and efficiently. The shortcomings of the current regime
are swept away, replaced by a sound framework for investment and
the finance to carry out a rail renaissance whose momentum must
increase strongly and quickly. Thus endowed, Railtrack has no
more excuses. The responsibility on Railtrack, buttressed by increased
accountability through stronger and fairer contracts, a reformed
network licence and clear financial incentives, is considerable.
Together, this public-private partnership can and must be made
to work well for the industry, for investment and above all for
passengers and freight.
November 2000
|