SIXTH REPORT
The Environment, Transport and Regional Affairs
Committee has agreed to the following Report:
RAIL INVESTMENT: RENEWAL, MAINTENANCE
AND DEVELOPMENT OF THE NATIONAL RAIL NETWORK
Introduction
1. In May 2000, the Transport Sub-committee decided
that it would undertake a major inquiry into rail investment.
Our decision was made in the context of the publication of Railtrack's
2000 Network Management Statement for Great Britain[3]
and a National Audit Office report on the effectiveness of the
Office of the Rail Regulator.[4]
The two documents together describe in detail Railtrack's past
and planned investment in the renewal, maintenance and development
of the national rail network. In deciding to conduct the inquiry
we were also mindful of the then on-going review by the Rail Regulator
of track access charges paid by train operating companies to Railtrack,[5]
the process of re-franchising passenger rail services being carried
out by the shadow Strategic Rail Authority,[6]
and the forthcoming announcement of the Government's Ten Year
Plan for Transport.[7]
2. We therefore agreed that "with reference
to the 2000 Network Management Statement for Great Britain
and the recent Report by the Comptroller and Auditor General on
Ensuring that Railtrack maintain and renew the rail network,
the Transport Sub-committee will examine the renewal, maintenance
and development of rail infrastructure in the United Kingdom.
It will do so by considering particularly Railtrack's past performance
in renewing, maintaining and developing the national rail network,
and the likely impact of its plans for the future; the adequacy
of the oversight exercised in the past by the Office of the Rail
Regulator of Railtrack's performance, its contribution to the
development of Railtrack's future plans with particular reference
to the review of track access charges, and the means by which
the Office of the Rail Regulator intends to ensure that Railtrack
in future honours its commitments; and what role should be played
by the (currently shadow) Strategic Rail Authority in the renewal,
maintenance and development of the rail network both directly
and by securing investment from sources other than Railtrack,
including from train operating companies through the franchise
replacement process. In addition, the Sub-committee will consider
what criteria the Authority is using to decide on the replacement
of franchises".[8]
3. We invited written evidence from interested parties,
and received twenty-five memoranda. We then took oral evidence
in July from Railtrack, the Association of Train Operating Companies,
the shadow Strategic Rail Authority and the Rail Regulator.[9]
We also took evidence from Lord Macdonald, the Minister for Transport,
on the Government's Ten Year Plan for Transport once the Plan
had been announced.[10]
Over the Summer recess we invited further written evidence, particularly
to take account of the Ten Year Plan and the conclusions of the
track access charges review, announced by the Rail Regulator in
October. As a result we received a further eighteen memoranda,
and took oral evidence on a further five occasions, from the Association
of Train Operating Companies, Railtrack, the shadow Strategic
Rail Authority and the Rail Regulator for a second time, and from
the Rail, Maritime and Transport (RMT) Union, the Passenger Transport
Executive Group, the Rail Freight Group, and Lord Macdonald and
officials from the Department of the Environment, Transport and
the Regions.[11]
In addition to our evidence, we were helped throughout by our
specialist adviser, Mr Chris Bolt, the former Rail Regulator.
We are most grateful to him, to those who submitted written and
oral evidence, and to all who otherwise assisted us in our inquiry.
4. During our inquiry, on 17 October 2000, there
was a serious accident on the East Coast Main Line at Hatfield.
The crash was followed by an assessment of the state of the rail
network, and the institution by Railtrack of a programme to repair
parts of it. That programme is continuing still. As our inquiry
progressed, and we took further oral evidence, we attempted to
take account of developments since the Hatfield crash, and we
have commented on those developments in this Report. Inevitably,
therefore, we have given a great deal of attention to the maintenance
of the railway, the means by which such maintenance has been managed
and carried out, and the improvements proposed for the future.
On 1 November we invited the then Chief Executive of Railtrack
to give evidence specifically about the Hatfield accident and
Railtrack's immediate response to it:[12]
our conclusions about those matters were published in our Report
on Recent Events on the Railway.[13]
That Report is intended to complement what we say in this Report
about Railtrack and its record of maintaining, renewing and improving
the national rail network. As we prepared our Report, on 28 February
2001, there was another major rail accident, on the East Coast
Main Line near Selby. We have not taken evidence about that accident,
and do not refer to it in the remainder of this Report.
The state of the network
THE MANAGEMENT OF THE RAILWAY BEFORE PRIVATISATION
5. Before it was restructured in the run-up to privatisation,
the British Railways Board (hereinafter 'British Rail') was charged
with providing "railway services in Great Britain and such
other services and facilities as appear to the Board to be expedient,
having due regard to the efficiency, economy and safety of operation".[14]
In short British Rail was solely responsible for all aspects of
railway operations in Great Britain: it was the operator of passenger
and freight rail services and the provider of the railway infrastructure,
responsible for the maintenance, renewal and development of the
track, signalling, power supply, stations and so on. It also provided
other services: British Rail Maintenance Limited, headquartered
in Derby, carried out overhauls and repairs to British Rail's
locomotives and rolling stock, and another subsidiary, Transmark,
acted as a consultant to projects being carried out by foreign
railway companies and others.[15]
In 1990, British Rail employed more than 136,000 staff, the vast
majority in the company's rail and corporate activities, and its
turnover was £3,777 million. Annual Government grant to the
industry was approximately £700 million.[16]
6. British Rail's Organising for Quality process,
undertaken between 1990 and 1992, led to a significant restructuring
of the company in the run-up to privatisation. The process aimed
to give "managers ownership and bottom-line responsibility
for the assets they use and moves responsibility for decision-making
as close as possible to the customer".[17]
Three passenger rail businesses were established: Intercity, Network
SouthEast and Regional Railways. Each business was then further
divided: Intercity into five 'routes', Network SouthEast into
nine divisions, and Regional Railways into five regions, a structure
still recognisable in the current system of rail passenger franchises.[18]
The new organisation ended the division of the network into six
geographical regions,[19]
and transferred ownership of trains, stations, track and signalling
to the new passenger rail businesses. The parcels business and
the rail freight businesses were also restructured, and a number
of central divisions were established to support the new group
of businesses under the 'umbrella' of the British Railways Board.[20]
THE RUN-UP TO PRIVATISATION
7. During the next three years British Rail continued
to prepare for transfer to the private sector, following the framework
provided by the Railways Act 1993.[21]
The Act envisaged further restructuring of British Rail, including
the separation of the railway infrastructure from the operation
of passenger and freight train services. Regulation of the railway
would be carried out by a new Rail Regulator, responsible for
licensing all those involved in the railway, in accordance with
public interest duties which included protecting the interests
of users of railway services, promoting the use of the railway
network for the carriage of passengers and goods, and the development
of the network, to the greatest extent economically practicable,
enabling persons providing railway services to plan the future
of their business with a reasonable degree of assurance, and imposing
on the operators of railway services the minimum restrictions
consistent with the performance of the Regulator's functions.[22]
The Act also established a Franchising Director, charged with
letting time-limited franchises to those wishing to operate most
passenger rail services, and with disbursing subsidies to them
for doing so.[23]
In addition, the Act set out a framework through which train operating
companies could make arrangements with the owner of the rail infrastructure
for the use of the network, and for payments to be made to the
infrastructure owner in return.[24]
8. On 1 April 1994, Intercity, Network SouthEast
and Regional Railways ceased to exist as single units. Passenger
rail services became the direct responsibility of twenty-five
train operating units: over the following few years each unit
was operated as a shadow franchise, before finally being offered
for sale by the Franchising Director. Ownership of domestic passenger
trains and rolling stock was transferred from the passenger rail
units to three rolling stock leasing companies (ROSCOs), which
were eventually separated from British Rail in 1995 and sold.[25]
Ownership of the track, signalling and freeholds of stations,
other buildings and operational land were transferred to a new
public-sector company, Railtrack.[26]
The licence to operate the railway network granted to Railtrack
by the Secretary of State for Transport under the Railways Act
1993 also came into force at the same time.[27]
As well as taking responsibility for more than 19,000 miles of
track and associated signalling and electrical control equipment,
providing a network of almost 10,000 miles, Railtrack also took
ownership of bridges, tunnels and viaducts, level crossings and
light maintenance depots, as well as connections to more than
1,000 freight terminals.[28]
The company also owned 2,500 stations which, with the exception
of fourteen major stations, it has since leased to train operating
companies.[29]
The company was sold through a public flotation in May 1996: at
that time, its annual turnover was £2,300 million, and it
employed 11,340 staff.[30]
9. Freight services, which had already been restructured,
were also privatised. The three train-load freight units[31]
were sold in February 1996, and eventually amalgamated as English
Welsh and Scottish Railway (EWS). Later in 1996 EWS purchased
Rail Express Systems Limited, the division which dealt with mail
for the Post Office,[32]
and in 1997 it purchased Railfreight Distribution, the business
which dealt with international rail freight through the Channel
Tunnel.[33]
Red Star Parcels Limited was sold off in 1995,[34]
and Freightliner, which carried containers by rail, was privatised
as an independent company in May 1996.[35]
British Rail's heavy maintenance depots, which provided the ROSCOs
with heavy maintenance services, were sold off between April and
June 1995,[36]
and other subsidiaries which provided services as diverse as training,
engineering services, project management, information technology
maintenance, and a range of consultancy services, were disposed
of, mainly between July 1995 and March 1997.[37]
In all, British Rail was split into more than a hundred different
companies, most of which were then transferred to new private
sector owners.[38]
Privatisation of the maintenance and renewal companies
10. At the time of privatisation, Railtrack said
that its aim was to provide a "safe, modern and efficient
railway which not only meets but anticipates the needs of our
customers".[39]
To do so it would be required to maintain, renew and develop the
railway infrastructure. However, it was not intended that Railtrack
would carry out such work itself: instead, it had long been envisaged
that "much of the work involved in operating, developing
and maintaining the infrastructure will be contracted out".[40]
Initially, track, signalling, electrification and plant maintenance
and renewal work was carried out under contract to the company
by fourteen geographically-based infrastructure service units
which had not been transferred to Railtrack but instead continued
to be owned by British Rail.[41]
Improvement, development and enhancement work would, it was thought,
be carried out under contracts let for each specific project.
11. On 1 April 1995 the infrastructure service units
were restructured into British Rail Infrastructure Services, which
comprised seven Infrastructure Maintenance Units and six Track
Renewal Units, as well as a number of design offices. At that
time British Rail Infrastructure Services had a total workforce
of 25,204 and a turnover of £1,129 million.[42]
The relationship between Railtrack and the Maintenance and Renewal
Units was then formalised in a series of contracts which encompassed,
amongst other requirements, the Train Performance Scheme agreed
between Railtrack and British Rail Infrastructure Services. Contracts
between the Units and other companies within the rail industry
were also signed. In all, more than two thousand formal agreements
were made,[43]
before the Infrastructure Maintenance Units and Track Renewal
Units were sold between February and July 1996.[44]
Table: Maintenance Contracts up to March
2001 by Zone and Region[45]
| Zone | Region
| Rail Maintenance Company |
| Scotland | North, East and Central
West and South West
| First Engineering Limited
First Engineering Limited
|
| North West | Preston
Manchester
Liverpool and North Wales
Merseyrail
| GTRM Limited
First Engineering Limited
Jarvis Rail Limited
Jarvis Rail Limited
|
| London North Eastern | East Coast Main Line - North
East Coast Main Line - South
Central
| Balfour Beatty Rail Maintenance Ltd.
Balfour Beatty Rail Maintenance Ltd.
Jarvis Rail Limited
|
| Midlands | W. Coast Main Line - Central
W. Coast Main Line - South
W. Midlands and Cambrian
East Midlands
Chilterns
| GTRM Limited
GTRM Limited
GTRM Limited
SERCO Rail
Amey Rail Limited
|
| East Anglia | Great Eastern
Norwich
London Tilbury and Southend
West Anglia
North London Line
| Balfour Beatty Rail Maintenance Ltd.
GTRM Limited
Balfour Beatty Rail Maintenance Ltd.
AMEC Rail Limited
AMEC Rail Limited
|
| Great Western | Gloucester
Bristol
South Wales
Exeter
Reading
| GTRM Limited
GTRM Limited
GTRM Limited
Amey Rail Limited
Amey Rail Limited
|
| Southern | Kent
Wessex
Sussex
| Balfour Beatty Rail Maintenance Ltd.
Balfour Beatty Rail Maintenance Ltd.
AMEC Rail Limited
|
12. The seven Infrastructure Maintenance Units were
sold to six main buyers,[46]
which inherited the contracts agreed with Railtrack to undertake
maintenance work in specific geographical areas based on the old
British Rail zones. The maintenance contracts were actually based
on thirty-five smaller regions within the seven zones:[47]
over time contracts have been transferred or given up and re-let,
so that companies now rarely have responsibility for maintenance
across whole zones (see above). Maintenance companies are required
to inspect the railway in their contracted regions, and where
necessary repair the permanent way, signalling, electrification
equipment, operational telecommunication equipment and lineside
assets. The objective of such maintenance is to enable Railtrack
to "provide consistent and reliable train paths to ... customers".[48]
The original maintenance contracts (known as RT1a contracts) were
let for between five and seven years. As they have come up for
renewal, there have been further transfers between companies.[49]
13. Infrastructure renewal companies are contracted
to Railtrack on a geographical basis similar to that for the maintenance
companies. Rather than maintaining existing assets, renewal companies
are called in to replace assets which have reached the end of
their useful life, or to make replacements which will bring improved
performance to the network.[50]
Thus, for example, in 1999 Railtrack reported that it had sought
to target renewals at 200 or so critical locations which would
"have the greatest impact on train performance".[51]
Seven companies are currently under contract to Railtrack to provide
renewals.[52]
AFTER PRIVATISATION
Arrangements to manage maintenance, renewal and
development
14. Since the privatisation of the maintenance and
renewal companies, works on the railway network have been carried
out by them under contract to Railtrack. Similarly, development
and enhancement works have been undertaken by companies specifically
contracted to do so. Railtrack's role has been, as was envisaged
before privatisation, has been to manage the process through its
oversight of contractual arrangements with those working on the
railway, ensuring that they meet set quality standards, and are
competent and safe.[53]
It does so through the 'cascade model': contractors are required
to demonstrate to Railtrack that they have put in place management
structures and developed a safety case which will ensure that
they operate competently and safely. They are also required to
monitor their own performance. The contractors in turn are expect
to ensure that their sub-contractors put in place similar contractual
arrangements.[54]
15. Thus what Railtrack acknowledges[55]
is its sole responsibility for ensuring that infrastructure works
are carried out, for their quality, and for safety standards on
the network 'cascades' down through the system to contractors
and sub-contractors.[56]
In addition, Railtrack is expected to verify the quality and safety
of its contractors through 'end product' checks, random and periodic
site visits and safety management system reviews, as well as undertaking
safety audits.[57]
In its evidence to our inquiry into Railway Safety in 1998, Railtrack
argued that the structure of contracts and safety cases, coupled
with Railtrack's checking and auditing systems provided "an
open and effective framework within which it is not necessary
to 'second guess' those who are mutually committed to achieve
safe operation".[58]
The contractual and regulatory framework
16. The structure put in place by privatisation meant
that Railtrack's investment decisions could be formally influenced
in a number of ways. First, Railtrack is contractually committed
to enable the train operating companies to achieve better performance.[59]
Second, as has been said, Railtrack is subject to regulation under
the Railways Act 1993, on the grounds that it was "established
by and on behalf of the State to own and to be responsible for
the care and development of the nation's railway infrastructure
which is largely funded by the State or other public authorities
... Regulation is here to ensure that the railway network works
in the public interest. It has a particularly important role to
play in respect of Railtrack's investment in the renewal and development
of the nation's railway infrastructure - its stewardship responsibilities".[60]
Therefore the Network Licence granted to Railtrack in 1994, overseen
by the Rail Regulator, places duties on the company in respect
of investment in the railway network.[61]
Third, Railtrack's investment decisions, and particularly its
practices, are affected by the fact that it is overseen, on safety
grounds, by HM Railway Inspectorate, now part by the Health and
Safety Executive, which seeks to control risks to the health and
safety of employees, passengers and others affected by the operation
of the railway.[62]
17. In the years since privatisation, changes have
been made to the regulatory framework within which decisions are
made. Most important was the revision of Condition 7 of the Network
Licence in 1997, which followed the Rail Regulator's announcement
in May of that year that he had begun negotiations with Railtrack
with a view to "strengthening its existing contractual and
licence obligations to ensure it achieves three key purposes:
timely maintenance of the railway network; timely renewal and
replacement of the network in modern equivalent form; and improvement,
enhancement and development of the network".[63]
The Regulator said that contracts between Railtrack and train
operating companies were not strong enough in relation to investment,
since "they do not guarantee that train operators get the
modern equivalent railway that they and the Government (and Passenger
Transport Authorities) are paying for [and], in part because most
contracts are relatively short-term, they do not provide sufficient
incentives for required long term enhancement of the nation's
railway infrastructure".[64]
18. For that reason the Network Licence was seen
to be "of critical importance",[65]
allowing the Rail Regulator to influence Railtrack's investment
decisions on public interest grounds. Condition 7 of the original
Network Licence required Railtrack to "prepare and publish
annually in a form, and covering a period, approved by the Regulator
a statement showing projections of future network capacity requirements,
planned modifications to Railtrack's network and the method proposed
for financing such requirements and modifications within Railtrack's
overall financial framework".[66]
In other words, Railtrack was obliged to go beyond the requirements
of its contracts with the train operating companies and publish
its plans to deliver on its investment and stewardship role, according
to a form determined by the Regulator. This statement is called
the Network Management Statement.[67]
19. The 1997 Network Management Statement
set out plans for the renewal and development of the railway network,
and detailed a higher level of projected expenditure by Railtrack
than had originally been planned.[68]
Nevertheless, the Regulator concluded that the 1997 Network
Management Statement was unsatisfactory because it did not
give detailed forecasts of demand to use the network, or of the
actions Railtrack is taking to provide capacity to meet those
demands, because it did not set out specific action in respect
of investment in stations and depots, because its proposals in
respect of freight were not detailed enough, and because more
positive commitments were needed in respect of network development
and enhancement and working with customers over the renewal programme.
Moreover, the Regulator observed that there was an outstanding
backlog of expenditure on network assets, stations and depots,
and that Railtrack's "delivery against its plans to date
has been disappointing".[69]
Finally, the 1997 Network Management Statement did not
set out the results, in terms of improved quality and capability,
expected to be delivered by the investment programme: the Regulator
argued that Railtrack should "develop measurable benchmarks
and targets for what Railtrack should be achieving".[70]
20. In short, the Regulator concluded, "at present
Railtrack's obligations under its Licence Condition 7 are extremely
light",[71]
principally because "there is no direct means of ensuring
that Railtrack complies with its acknowledged duty to spend the
money it receives for investment and to spend these large sums
wisely. Assurances that the capital and maintenance programme
will be carried out, the more especially when most of the annual
expenditure in effect is funded by the State, require something
more bankable than the expression of intentions or the short-term
pressures to meet contractual obligations".[72]
Consequently, with Railtrack's agreement, Condition 7 was revised
so that rather than simply being obliged to produce an annual
Network Management Statement, Railtrack was required to
secure the timely, economic and efficient maintenance, renewal
and replacement, and improvement, enhancement and development
of the rail network.[73]
21. Another significant development has been the
establishment of the Strategic Rail Authority. The new Government
elected in May 1997 declared that it intended to create such an
Authority "to provide a clear, coherent and strategic programme
for the development of the railways",[74]
a proposal addressed in our first Report of the current Parliament.
The Authority was set up in shadow form in July 1999,[75]
taking over the duties and functions of the Office for Passenger
Rail Franchising and the residual duties of the British Railways
Board.[76]
The Authority actually came into being on 1 February 2001, when
it began to operate the powers and duties given to it by the Transport
Act 2000.[77]
22. The Strategic Rail Authority says that its responsibilities
"cover the three sectors of Passenger, Freight and Infrastructure
... the Strategic Rail Authority's key role is to promote and
develop the rail network and encourage integration. As well as
providing overall strategic direction for Britain's railways,
the Strategic Rail Authority has responsibility for consumer protection,
administering freight grants and steering forward investment projects
aimed at opening up bottlenecks and expanding network capacity.
It is also responsible for letting and managing passenger rail
franchises".[78]
In terms of investment in the rail network, the Authority is concerned
with encouraging and enabling enhancement and development, and
not with maintenance and renewal, which it says "are funded
through access charges, paid by train operators, managed by Railtrack
and subject to regulation through licence conditions by the Rail
Regulator".[79]
The investment record
23. Track access charges, which are regulated under
the Railways Act 1993, provide 90 per cent of Railtrack's revenue.[80]
Thus the track access charges regime established by the Regulator
is of critical importance in determining that revenue, and therefore
the level of investment to be made by the company. In January
1995, the then Rail Regulator set track access charges for the
price control period 1995-2001. He allowed £8.6 billion for
the maintenance and renewal of the infrastructure over that period,
plus an additional £570 million to tackle a backlog of expenditure.[81]
The prospectus published to accompany the flotation of Railtrack
in 1996 increased that estimate, and indicated that the company
would spend £10.5 billion on maintenance and renewal over
the period, an average of £1.7 billion each year.[82]
24. Railtrack has told the Rail Regulator that it
has in fact spent an average of £2.25 billion each year on
maintaining and renewing the network since privatisation. Thus
its expenditure has exceeded that allowed for in the 1995 charging
review by £2.2 billion, and that expected at the time of
flotation by £900 million.[83]
The company has also invested in the development and enhancement
of the network: of its total expenditure of £3.1 billion
in 1998-99, for example, 9 per cent, or £280 million, went
to network enhancement. By contrast, 22 per cent (£682 million)
was spent on maintenance, and 38 per cent (£1,178 million)
on renewals.[84]
25. Nevertheless, although investment in the railway
has increased, it is generally accepted that it has not been adequate.
Research commissioned by the Office of the Rail Regulator examined
Railtrack's performance in the first regulatory control period
from privatisation until 2001. Although it found that although
Railtrack had spent more money on renewal work than had been expected,
there were significant areas of underachievement: in particular,
the company's performance in terms of reducing train delays and
asset renewal, for example, had generally been below expectations.[85]
26. Moreover, the level of investment by Railtrack
must be seen in light of the fact that usage of the network has
increased substantially. Between 1995-96 and 1999-2000 the total
number of miles covered by passenger trains increased by 10.7
per cent,[86]
while the equivalent figure for freight trains was an increase
of 19.6 per cent.[87]
Those increases, coupled with greater numbers of passengers on
each train, and larger average loads, meant that total passenger
miles rose by 27 per cent between 1995-96 and 1999, and freight
traffic rose by 35 per cent.[88]
It is argued that the reason why investment has failed to keep
pace with increased usage is because of expectations when the
industry was privatised: rather than planning for a bigger and
better railway, it was assumed that there would be little, if
any, increase in traffic.[89]
Railtrack told us that the objective of privatisation was "to
maximise proceeds to the Treasury and minimise future subsidy
requirements....There was no vision of the size and type of railway
the country needed".[90]
Railtrack also claimed that the structure put in place from 1995
did not reflect the extent of the investment backlog nor provide
the company with adequate incentives to invest in growth and development:[91]
from its inception, Railtrack was expected to operate a railway
with "static growth".[92]
The Chairman of the then shadow Strategic Rail Authority agreed
that it was widely believed at the time of privatisation that
the railways would not grow significantly. As a consequence, the
task facing Railtrack was not perceived as being as big as it
is now. Although he did not think that Railtrack was wrong not
to have done more during the early years of privatisation, he
thought that it could be criticised for not anticipating the pace
of the growth that has occurred more recently.[93]
27. The Rail Regulator agreed with Railtrack's assessment.
He told us that the "ill-thought through" financial
framework put in place at the time of privatisation was deficient,
did little to promote investment, and that there was "no
specification of what Railtrack had to do for the access charges
which it receives and very little was done...to encourage the
making of investment".[94]
In particular, the incentives given to Railtrack were neither
adequate nor properly aligned with those of the train operating
companies.[95]
As we have described, the only commercial incentives for Railtrack
to invest were provisions of the contracts that it held with train
operators, which allowed for penalties or bonuses depending on
Railtrack's performance in avoiding delays. These contracts were
not satisfactorily framed: for example, Railtrack received a £25
million bonus in 1998-99 at a time when it remained responsible
for around one-third of the total time that passenger and freight
services were being delayed, and when the Regulator was considering
enforcement action against Railtrack because it had missed its
target for reducing the levels of delays occurring in that year.[96]
The Rail Regulator has concluded that "the Network Licence
which Railtrack holds is not fit for purpose for a private sector
company".[97]
28. The regulatory regime, and the practices of the
Regulator since Railtrack was privatised, have been examined by
the Comptroller and Auditor General. He found a number of weaknesses,
including the failure to specify clearly at the beginning of the
first control period what was expected by the company from its
maintenance and renewal expenditure, which has meant that it has
been difficult to measure what Railtrack has achieved. Railtrack
has said that as a result it has found the Rail Regulator's expectations
unclear and unpredictable.[98]
Another difficulty he uncovered centred on the concept of renewing
assets in 'modern equivalent form', since it has not been clear
what is meant by the term. Moreover, when new assets have been
able to do a better job than those they replace, it is difficult
to determine whether the replacement constitutes renewal, which
is paid for from existing access charges, or enhancement, for
which Railtrack is entitled to charge extra.[99]
29. A third problem identified by the Comptroller
and Auditor General has been the lack of a national database detailing
the condition of Railtrack's assets. Without such a database it
has been difficult to assess the effectiveness of maintenance
work, thus undermining Railtrack's management of its contractors.
It has also limited the effectiveness of regulation: the Rail
Regulator has said that his efforts to reach provisional conclusions
about the next control period beginning in April 2001 "have
been hindered by difficulties arising from the company's lack
of knowledge about the condition of its assets".[100]
Railtrack has in the past argued that the Regulator should focus
on its performance, in terms of capacity, delays and ride quality,
rather than on monitoring the state of the infrastructure directly.[101]
The company has now, however, conceded that "at privatisation,
Railtrack inherited an asset base which had been neglected for
many years and very poor data records, many of which were still
paper based":[102]
it has now accepted that "its asset knowledge [is] ... unsatisfactory".[103]
The advisors to the Rail Regulator, Booz Allen and Hamilton, told
the Comptroller and Auditor General that, compared with the water
industry which faced similar problems at privatisation, Railtrack
has been "very slow in determining the condition of their
structural assets and devising suitable measures for them".[104]
30. The fourth concern raised by the Comptroller
and Auditor General is related to the quality of the asset database:
he said that the Regulator should seek independent verification
of the key monitoring data provided to him by Railtrack.[105]
The final problem also relates to Railtrack's inadequate knowledge
of the state of the railway. Railtrack has said that it intends
to change its approach to renewal work, focussing on small-scale
renewals of assets according to their condition, rather than more
general renewals of large groups of assets based on their age.[106]
The Rail Regulator has been concerned, however, that Railtrack's
knowledge of its assets is not yet good enough "to allow
them to adopt this approach without running the risk of unexpected
failures of equipment in service or a decline in the long-term
health of the network".[107]
In short, improved data is required.
31. The proposals made by the Comptroller and Auditor
General to improve the regulation of Railtrack,[108]
have been broadly accepted by the Rail Regulator.[109]
Some steps have already been taken to improve the situation. For
example, Railtrack has already begun to try to improve its knowledge
of its asset base.[110]
One step it has taken has been to institute a review of its asset
management activities, and to seek to increase the quantity and
quality of information that it holds. Another step has been to
introduce new 'IMC2000' contracts which require the rail maintenance
contractors to provide a great deal more information about the
railway, unlike the "old RT1A contracts ... [which] did not
provide us with full access to the key data necessary for effective
asset management".[111]
Railtrack's efforts are to be built on by the Rail Regulator,
who has proposed amendments to the conditions of the Network Licence,
which will require the creation of a proper asset database, the
establishment of a system of independent reporters to provide
information to the Rail Regulator, and other changes to the way
in which the condition of the railway is monitored.[112]
Moreover, as we describe below, the track access charges review
recently concluded by the Regulator has sought to establish better
definition and monitoring of what Railtrack is expected to achieve,
improved accountability of Railtrack to the Regulator and its
customers, improved incentives for Railtrack to deliver a better
railway, and greater transparency and stability in the regulatory
framework.[113]
32. Although there are welcome signs that the
regulatory framework in which Railtrack operates is being tightened,
it remains the case that the regulation of Railtrack since its
privatisation has not been adequate, considering the significant
growth in passenger and freight traffic following privatisation.
The regulatory regime set up at the time of privatisation was
not intended to deal with a growing railway, and consequently
has failed to ensure that Railtrack has delivered what has been
required of it by train operators, passengers and the wider public
during a period of growth. An example of the weakness of the regulatory
regime is its failure to ensure that Railtrack had adequate knowledge
of the condition of its assets. Without such knowledge it is difficult
to know how Railtrack was supposed to manage its assets properly,
or how the Regulator was to oversee investment by the company.
Moreover, the actions of the Regulator were for a long time half-hearted
and ineffectual: we welcome recent signs of a more vigorous approach.
Delays on the network
33. Weaknesses in the financial structure of the
railway have contributed to increasing problems of congestion
as traffic has grown on the network. Railtrack told us that a
one per cent increase in passenger miles leads to 2½ per
cent increase in delays to services:[114]
both the total number of passenger train miles and freight tonne
miles have, as we have seen, increased substantially. In 1998-99,
Railtrack was found to be responsible for 46 per cent of passenger
train delays (around seventy seconds per train), and 13 per cent
of freight train delays (around four minutes per train). Railtrack
was responsible for 8.6 million minutes delay to all trains, approximately
one-third of the total.[115]
Of those delays attributable to Railtrack, 70 per cent resulted
from maintenance and renewal problems, such as track circuit failures,
points failures, temporary speed restrictions resulting from the
condition of the track, and broken rails and other track faults.[116]
34. Other delays result from a failure to enhance
and improve the network in order to eliminate long-running causes
of delays. There are particular problems with bottlenecks, or
pinch-points, where infrastructure constraints cause endemic delays:
fifteen such points were identified in the Integrated Transport
White Paper, including problems on the West Coast Main Line, the
East Coast Main Line and the Great Western Main Line, as well
as on the approaches to major stations in London, Glasgow, Birmingham
and Leeds.[117]
Such problems can only be addressed through substantial programmes
of investment, such as has been carried out in recent months at
Leeds Station,[118]
and is being carried out on the West Coast Main Line.[119]
35. Railtrack included in the 1998 Network Management
Statement targets to reduce delays to train services: these,
the Regulator told us, were considered by his predecessor to be
inadequate.[120]
Subsequently it was agreed that Railtrack would reduce delays
for which it was responsible to passenger and freight trains by
7.5 per cent by 31 March 1999. Whilst the company met the freight
target, it did not achieve that for passenger trains: delays to
passenger train movements fell by just 2.2 per cent. In the interim
Railtrack had set a target in the 1999 Network Management Statement
for further reductions of 7.5 per cent in 1999-2000, and 5 per
cent in 2000-2001.[121]
The Rail Regulator told Railtrack that he expected the company
both to meet its new target, and to make up the shortfall from
the year before by 31 March 2000 (a cumulative reduction in delays
to passenger trains of 12.7 per cent).[122]
When Railtrack refused to commit to meeting this target, the Regulator
made an enforcement order requiring Railtrack to meet it, subject
to a penalty of £4 million for each percentage point by which
it failed to do so. Railtrack has subsequently challenged this
enforcement order in the courts,[123]
although it later abandoned its legal challenge. It has been estimated
that Railtrack in fact managed to reduce those delays attributable
to it by around ten per cent by the end of March 2000.[124]
36. Even before the Regulator took action, the proportion
of delays to trains attributable to Railtrack had already begun
to decline. In the 2000 Network Management Statement the
company pointed out that although it remains responsible for more
than 40 per cent of all delays to trains, its share has fallen
to that level from more than 70 per cent at the time of privatisation.[125]
Cancellations attributable to maintenance and renewal problems,
too, have fallen from 41,500 in 1995-96 to 20,500 in 1998-99.[126]
Nevertheless, it is acknowledged that the company could do more:
for example, Railtrack itself says that it anticipates an average
annual reduction of 2.5 per cent in delays attributable to it
between 2000-2001 and 2005-2006.[127]
The state of the track
37. One cause of delays, and a risk to the safety
of passengers and others on the railway, is the quality of the
track. Following a number of derailments, including that at Bexley
in 1997,[128]
HM Railway Inspectorate undertook a major assessment of track
quality on the national rail network. It concluded that track
quality was worsening. The quality of the track on 45 per cent
of the network was found to be unchanged: 33 per cent was deteriorating,
and only 22 per cent improving. The Inspectorate argued that safety
would be affected if the overall deterioration was not reversed.[129]
In addition, the Health and Safety Executive was increasingly
worried by the number of broken rails on the network. The number
of broken rails reported rose from 656 in 1994-95 to a provisional
total of 945 in 1999-2000: in 1998-99, 973 incidents had been
recorded. The Executive said that the figure was "unacceptably
high"and "a significant cause for concern".[130]
The Rail Regulator also examined the matter,[131]
and the research he commissioned concluded that Railtrack appeared
to perform "significantly worse" than other passenger
railways in terms of the number of broken rails removed per year
per track mile and at a level similar that of typical North American
freight railways which carry much heavier axle loads.[132]
38. Railtrack has also been criticised by English
Welsh and Scottish Railway (EWS), which has expressed concern
that Railtrack has not introduced rail used by railways adopting
international standards of best practice, which would last longer
and require fewer repairs. EWS contended that using rail that
was best suited to British traffic conditions would reduce by
93 per cent the instance of defects that lead to broken rails.
The company was very concerned at the growing number of weight
and speed restrictions that were being imposed by Railtrack as
the freight infrastructure deteriorated. EWS estimated that the
speed restrictions were costing the company up to £8 million
per annum.[133]
39. The decline in track quality has been attributed
to the unprecedented number of trains running on the network.
This increase in the number caused the infrastructure to degrade
more quickly and to require earlier renewal than originally anticipated.[134]
The present Rail Regulator agreed that track quality had declined
before privatisation, but pointed out that there had been little
sign of improvement until his predecessor took action in July
1998,[135]
when he reached an agreement with Railtrack that the condition
of the track should be restored to its 1994 level by April 2000
where maintenance was required, and by April 2001 where renewal
was needed.[136]
Railtrack has now said that because of the unprecedented number
of trains running on its network, its assets have degraded more
quickly and require earlier renewal than originally anticipated.
It introduced a major track quality improvement programme in May
1999, which included additional maintenance and ultrasonic testing
amongst other measures.[137]
The company told us prior to the Hatfield accident that it intended
to restore track quality to 1994 levels by 2001, and said that
it was within 1.2 per cent of its 2001 target.[138]
40. Railtrack has also taken specific action to deal
with the problem of broken rails.[139]
When he appeared before us in June 2000, the then Chief Executive
of Railtrack, Gerald Corbett, reported that in the first three
months of 2000 the number of broken rails had been reduced by
more than 20 per cent.[140]
Nevertheless, as the Regulator told us, it is "very regrettable"
that Railtrack allowed the quality of the network to deteriorate
to such an extent: if the company had "spent wisely and well
and in a timely manner, then these problems would not have occurred".[141]
Moreover, the Health and Safety Executive has raised concerns
about the priorities set by the track quality improvement programme,
which it fears might distract Railtrack and its contractors from
ensuring that preventative track maintenance is undertaken.[142]
Railtrack's record on maintenance and renewal
41. Thus the question of whether or not the delivery
of investment in maintenance and renewal of the railway network
since its privatisation has been acceptable was a matter of some
contention. Railtrack argued that by 2001 it has spent considerably
more on rail maintenance and renewals than was expected at the
time of its privatisation. It also pointed to its apparent successes
in reducing the proportion of delays to trains attributable to
it, in improving the quality of the track by, for example, reducing
the number of broken rails, and in improving its knowledge of
the condition of its assets. Moreover, Railtrack put its record
in context. It said that it had taken over an infrastructure which
had suffered from long-term under-investment under British Rail:
between 1982 and 1995, investment in the railways in the United
Kingdom was 0.12 per cent of gross domestic product in the United
Kingdom, compared to an average of 0.25 per cent across Europe.[143]
The company also pointed out that there had been a significant
increase in usage of the railway since privatisation, compared
to a decline in its use before.[144]
The then Chief Executive of Railtrack told us that "we have
... delivered a bigger, better railway ... we have delivered output
way ahead of what we were set up to deliver and way ahead of what
we were funded to deliver".[145]
42. Railtrack's view conflicts with that of the Rail
Regulator. He told us that he does "not believe that Railtrack
provided all the outputs for which it was paid over the last five
years ... I have been advised that, on track and signalling, Railtrack
has not delivered what might reasonably have been expected".[146]
He suggested that Railtrack had not been very efficient, and that
its spending on maintenance and renewals had not necessarily been
well directed.[147]
Even before the Hatfield crash track quality had declined sharply,
the number of broken rails has, until recently, increased markedly,
and speed restrictions imposed have increased. It has also been
reported that the Chief Inspector of Railways is concerned about
the state of bridges, embankments and track beds across the network.[148]
Railtrack has undoubtedly spent a great deal of money on the
maintenance and renewal of the rail network since privatisation.
It has faced the problems of historic under-investment in the
railways in the United Kingdom, and greatly increased rail passenger
and freight traffic following privatisation. Nevertheless, we
note that track quality had been shown to have deteriorated even
before the inspections of the network which followed the Hatfield
crash. We therefore agree with the Rail Regulator's assessment,
that Railtrack has not maintained and renewed the network to a
standard which could reasonably be expected of it. Its past record
is simply not acceptable.
Safety of staff working on the railway
43. It is, however, important to find a balance between
requiring Railtrack to improve its record in rail maintenance
and renewals and ensuring that the company reduce delays as much
as possible. A desire to maintain operational capacity can reduce
opportunities for carrying out maintenance, and can lead to more
work being done between train movements in order to avoid line
closures. This places maintenance staff at greater risk.[149]
Finding the right balance is always difficult, but the problem
has been particularly severe during the national rail recovery
programme. The RMT agreed that track workers are finding it increasingly
difficult to gain completely safe access to the railway, when
the movement of trains has been stopped (known as 'green zone'
working). Instead, tasks are being undertaken while services are
running ('red zone' working) and this leaves staff reliant on
the traditional 'lookout' system to warn them of the need to move
out of the path of oncoming trains.[150]
The Health and Safety Executive has recently undertaken an inquiry
into the dangers of 'red and green zone' working, which concluded
that fatality rates amongst trackside workers were too high, and
that a number of changes were needed to the procedures followed
by such workers and their managers.[151]
44. The RMT said that trackside staff were put at
risk because of the performance regime which penalises Railtrack
when infrastructure-related delays to trains are above a certain
level. It said that signallers had been instructed not to allow
'green zone' access unless it was necessary in order to repair
a fault that was already causing delays. Further pressure had
been placed on Railtrack by the Regulator's enforcement order
which required delays to be reduced.[152]
In short, as the RMT pointed out, growing rail traffic leads to
increasing wear and tear on the infrastructure, but also means
that less time is available for maintenance and renewal work.
The union has called for a performance regime which enables targets
to be achieved without compromising the ability of staff to carry
out maintenance and renewal work safely.[153]
45. In addition, the RMT expressed concern about
the casualisation of the workforce as the sub-contracting of railway
maintenance has increased.[154]
It told us that the number of permanently-employed staff engaged
in maintenance work has fallen by as much as half between 1994
and 2000, from 31,000 to between 15,000 and 19,000.[155]
The union told us also that there are, however, 84,000 holders
of the Personal Track Safety Certificate, the majority of whom
are casual staff. There have also been allegations that contractors
have been using unqualified and inadequately trained staff to
work on the railway.[156]
Failings in the way that Railtrack manages its infrastructure
maintenance contractors and sub-contractors[157]
and problems related to the recruitment of staff of these companies
have been highlighted repeatedly.[158]
We recommend, therefore, that HM Railway Inspectorate review
Railtrack's management of its contractors once again, to ensure
that the company either takes full responsibility for the training
of maintenance staff or puts adequate safeguards in place to ensure
that they are already properly trained before they are allowed
to work on the railway.
The Hatfield accident and its aftermath
46. The Hatfield rail crash occurred during our inquiry,
on 17 October 2000. Four passengers died in the accident, and
seventy people were injured. The accident was the result of the
derailment of an Intercity train at 115 miles per hour: the derailment
was caused by a broken rail.[159]
The broken rail has been attributed to a phenomenon known as 'gauge
corner cracking', which is a specific form of a failure known
generically as 'rolling contact fatigue': these are cracks which
appear in the rail as a result of stresses placed on it by the
wheels of trains, and which weaken the rail. The rail at Hatfield,
which was only five years old,[160]
broke up during the accident: 35 metres of rail broke into 300
fragments, and another length of 54 metres also fragmented.[161]
Other sections of rail, which did not actually break during the
accident, were seen to be badly affected by rolling contact fatigue.[162]
47. Railtrack announced on the day of the accident
that it intended to put in place emergency speed restrictions
at a large number of sites on the network, pending their inspection
for signs of rolling contact fatigue.[163]
Within a month, 3,000 sites had been inspected.[164]
Where track quality was found to be poor, the company embarked
on track renewal. The programme of speed restrictions, inspections
and renewals became known as the national rail recovery plan,[165]
and caused extensive disruption to the network through cancellations
and delays for a number of months after the accident: between
17 October and 11 December there was no advertised timetable at
all.[166]
Work on the railway according to the rail recovery plan has continued
into 2001, with particular progress being made over Christmas
and New Year. By mid-January Railtrack was able to announce that
23 out of 28 of the train operating companies were able to operate
according to their 'pre-Hatfield' timetables, and that more than
260 miles of rail had already been replaced, relieving many of
the speed restrictions which had been placed on the network.[167]
It was expected that rail services would return to normal by Easter.[168]
48. We took evidence from Railtrack about the Hatfield
crash two weeks after the accident, and published a Report on
the matter in December 2000.[169]
We concluded that Railtrack's management of the company responsible
for rail maintenance on the southern section of the East Coast
Main Line, Balfour Beatty, had been totally inadequate,[170]
that the culture of safety espoused by Railtrack was not always
shared by those actually working on the railway,[171]
and that Railtrack's decision to employ more staff with engineering
and other relevant experience throughout the company, and especially
at the highest levels, had come rather late, and was somewhat
half-hearted.[172]
We recommended that Railtrack "should now institute radical
changes to the way the company is managed, and to the personnel
involved, to ensure that Railtrack once again takes control of
events on the railway".[173]
49. Our concerns about Railtrack's management of
its contractors have deepened since the Hatfield accident took
place. The fact that Railtrack has been compelled to undertake
so many inspections of the network in order to ascertain the state
of the track demonstrates how ineffective its monitoring of contractors
had been: it is impossible not to conclude that the company had
little knowledge of its own infrastructure, and could not rely
on the information provided by contractors. In particular, the
degree to which the track at Hatfield had been allowed to deteriorate
without remedial action being taken, is profoundly disturbing.[174]
Finally, the fact that so much rail has been replaced as part
of the national rail recovery plan shows that maintenance and
renewal work across the country had not been carried out when
it should. In short, the system of managing contractors who
carry out maintenance and renewal work on the railway through
the system of 'cascaded safety cases' has been shown to have utterly
failed. It is not just the system that has failed: Railtrack's
management of its contractors has been woeful.
50. Railtrack told us that in light of the accident
at Hatfield it intended to take "a hard look at our maintenance
and renewal contractual arrangements".[175]
We welcome that review, although we are disappointed by the new
Chief Executive's comment that it would be "several months"
before the company reached the conclusion of its review.[176]
We also note Railtrack's commitment to employ more engineers,[177]
and that the company is considering taking over inspection of
the railway, and of the works carried out by contractors, and
perhaps some of the "engineering decision-making".[178]
In 1998, we undertook an inquiry into Railway Safety, during which
we noted the concerns of HM Railway Inspectorate about Railtrack's
selection, control and monitoring of its maintenance contractors.[179]
The Inspectorate said that it "expected Railtrack to institute
systems that enabled it to assure itself and the Inspectorate
that the track was being maintained safely":[180]
we concluded that "the monitoring of the work of contractors
by Railtrack has not been good enough".[181]
We note that Railtrack appears not to have acted on those warnings
until after the Hatfield accident: Railtrack has been told
several times that its management and monitoring of maintenance
and renewals contractors has not been adequate. It is clear that
it was only after a major accident that Railtrack decided to take
steps to address the issue.
51. Another way of managing maintenance and renewal
work would be for Railtrack to take it 'in-house', employing and
managing railway workers itself rather than using contractors.
This proposal is being considered by Railtrack.[182]
Given that the previous means of managing maintenance and renewal
contractors has failed, we strongly recommend that Railtrack take
over direct responsibility for inspecting the network, and for
directly employing those who work on the maintenance and renewal
of the rail network. It should do so without any further prevarication
and delay, and without awaiting the outcome of a spurious 'review'.
In order to carry out these functions properly we recommend that
Railtrack employ adequate engineering and project management expertise.
Moreover, the Board of Railtrack should reflect a knowledge of
engineering that complements these responsibilities.
52. Railtrack initially announced that it intended
to set aside £250 million to cover the cost of the national
rail recovery plan, in part to recompense train operating companies,
and in part to fund the plan itself.[183]
By mid-January 2001, the company estimated that costs had risen
to £600 million, and were likely to rise still further.[184]
By mid-February, it was reported that the Rail Regulator now doubted
whether train services would be back to normal by Easter, as had
been expected, since Railtrack's concentration on the rail recovery
plan had created a backlog in scheduled maintenance and renewal
work which would not be eliminated until the Summer.[185]
As a result train operating companies were believed to be seeking
additional compensation from Railtrack: they had been offered
£400 million, and were understood to require at least an
additional £200 million.[186]
By the end of February, it was reported that the total cost of
the rail recovery plan and the compensation to be paid to train
operating companies would be at least £800 million.[187]
53. The impact of the Hatfield accident and its aftermath
is likely to extend beyond the short- to medium-term. Many passengers
have been forced to use alternative means of transport: BAA, for
example, has reported "unusually robust growth in [air] passenger
traffic", in part because of disruption to the rail industry.[188]
Some of those passengers, and others forced to travel by car,
may not return to rail travel even when the situation improves.
The rail freight industry, as we have previously described,[189]
already faces strong competition from the road haulage industry,
and some competition from air freight: the loss of confidence
caused by the disruption following the Hatfield accident may cause
it long-term difficulties.[190]
If passenger and freight volumes do decline, or do not grow as
strongly, as a result of Hatfield and the rail recovery plan,
there will obviously be serious implications for income for the
rail industry, and therefore for investment in the rail network.
54. The disruption following Hatfield has, as we
have said, cost Railtrack a great deal of money. The current structure
of funding of the railway is such that the Government is likely
to be obliged to provide additional money, either directly or
via the Strategic Rail Authority and the train operating companies,
to Railtrack in order that investment in the railway will be maintained
at the expected, and indeed required, level. It has been widely
reported that Railtrack has already sought additional funding
so that it can meet the costs of the national rail recovery plan
and still deliver the investment expected in the next control
period:[191]
indeed it has been suggested that Railtrack "cannot survive
as it is without the injection of further Government money".[192]
Recent reports suggest that the Government has decided to bring
forward payment of £1 billion due to be made to Railtrack
in a few years time.[193]
The short-term and long-term costs which have arisen as a result
of the Hatfield accident and the national rail recovery plan have
arisen principally because Railtrack has failed in the past properly
to manage maintenance and renewal of the national rail network.
Such costs are likely to end up being borne, in one way or another,
by the Government: the only alternative would be to permit Railtrack
to cut back vital investment in the railway. It is unacceptable
that the taxpayer should be compelled to bail out a private monopoly
company which has acted so incompetently, without taking any stake
in the company in return.
DEVELOPMENT
55. As we have said, since the mid-1990s the railways
have been experiencing a remarkable period of increasing passenger
rail demand with growth averaging more than six per cent per annum
over the last four years. In 1999, the number of passenger kilometres
travelled reached its highest level since 1947.[194]
Growth has been experienced across the passenger rail sector,
although recently demand has been particularly strong for inter-city
and London commuter services.[195]
The trends in rail freight have also been encouraging. The amount
of freight carried by rail was declining until the mid-1990s,
but this position has since reversed with a 40 per cent increase
in rail freight tonne kilometres and a market share that has returned
to its mid-1980s level.[196]
56. As a consequence of the new traffic, the network
in operating close to capacity in many places, which, as well
as affecting the quality of service experienced by existing passengers
and freight customers, has implications for future growth. In
the Ten Year Plan for Transport, the Government anticipates that
passenger rail travel, measured in terms of passenger kilometres
travelled, will increase by more than 34 per cent by 2010, but
that this growth could be limited to 23 per cent by capacity constraints.
Conversely, the provision of additional capacity and improved
services could enable a 50 per cent in passenger travel.[197]
Similarly, the Government believes that rail's share of the freight
market could rise to ten per cent by 2010, which is equivalent
to an 80 per cent increase on current levels.[198]
Without major investment in the sector and the removal of capacity
constraints on the network, however, the Government has estimated
that rail freight traffic might grow by only ten per cent by 2010,
which would mean that its market share would fall to 6.5 per cent.[199]
57. Railtrack has forecast that rail passenger traffic
will increase by 47 per cent over the next ten years.[200]
The company's plans for developing the network to respond to that
forecast growth in demand are set out in the 2000 Network Management
Statement,[201]
which sets out a range of options for investment costing up to
£52 billion over 12 years. Railtrack has initially recommended
that an £8 billion programme of enhancements should be carried
out over the next five years in order to provide for the 25 per
cent increase in traffic projected for that period.
58. The initial £8 billion programme of investment
has been developed on a route-by-route basis, and includes major
projects where work is underway, such as the upgrading of the
West Coast Main Line and improvements to the East Coast Main Line,
where remodelling of the track layout at Leeds station has already
taken place, and other projects such as improvements to the route
between London and Stansted Airport, the up-grade of the North
Trans-Pennine route, capacity improvements around Manchester,
Coventry and Birmingham, and the Thameslink 2000 project.[202]
Prior to the reported difficulties with funding after the Hatfield
accident, Railtrack had committed £3 billion of the cost
of the programme and was discussing the remaining £5 billion
with the Strategic Rail Authority and the Rail Regulator.[203]
Construction of the first phase of the Channel Tunnel Rail Link
is also already underway.[204]
59. Railtrack admitted that its programme of developing
and enhancing the rail network represents "a particularly
demanding challenge",[205]
but said that it had taken action to ensure that its plans are
"delivered effectively and efficiently".[206]
The company told us that lessons had been learned from the West
Coast Main Line modernisation project,[207]
where the cost of the project had risen from £2.3 billion
to about £5.85 billion,[208]
and where a lack of progress with the scheme led to the Regulator
taking enforcement action against Railtrack.[209]
Similarly, problems which arose during the work at Leeds station
have also been reviewed,[210]
and have led to further changes.[211]
Railtrack told us in December 2001 that its new approach to major
projects had already brought benefits at Leeds, and had helped
to ensure that the first section of the Channel Tunnel Rail Link
was proceeding on time and within budget. Railtrack claimed that
it now had the proper incentives and capability to complete major
infrastructure works on time and within budget.[212]
60. Doubts remain, however, that the rail industry
will be able easily to cope with the scale of the investment planned,
particularly since it follows a long period of under-investment.
The Passenger Transport Executive Group told us that the investment
plans would lead to disruption of existing services, and that
it was concerned that projects would not be completed within budget
and to the required standards.[213]
The RMT felt that the Railtrack's poor stewardship of the West
Coast Main Line modernisation scheme brought into question its
ability to manage major projects effectively.[214]
Finally, Railtrack's liaison with franchise operators and those
providing funds about major renewals projects was also described
by Merseytravel as poor.[215]
61. Recent events have shown such concerns to be
well-founded. Major works scheduled to be carried out over Christmas
and New Year 2000 at Willesden in north London, as part of West
Coast Route Modernisation scheme, and at Leeds station were not
completed on schedule, which caused considerable disruption for
passengers and freight users.[216]
Both projects should have been completed before the end of the
holiday period, but Railtrack missed four deadlines for finishing
the work at Leeds,[217]
and two extra weeks were required for completion of the Willesden
project, after the original timetable proved to be untenable.[218]
There was considerable dissatisfaction with Railtrack's conduct
of these projects, which were described as being "seriously
badly handled" by the Chairman of the Association of Train
Operating Companies.[219]
In the light of these failures, the Regulator said that he was
considering further action against Railtrack in order to improve
the way in which it plans and manages the temporary closures that
are required to enable major work to be undertaken on the railway.[220]
Channel Tunnel Rail Link
62. Specific concerns have been expressed about the
future of the Channel Tunnel Rail Link project. It has been reported
that a review commissioned by Railtrack suggests that the second
phase of the link will cost "much more" than the initial
cost of £2.5 billion at 1997 prices, and that the company
is ready to withdraw from the project without additional financial
support from the Government.[221]
Railtrack had originally intended to exercise its option for the
second phase in late 2000, which would have enabled construction
to start in 2001.[222]
In November 2000, the company told us that it was "too early"
for it to take a decision: instead Railtrack would decide whether
to exercise its option during the first quarter of 2001 after
the periodic review of its access charges had been completed and
other factors could be taken into account. The company did say
that rumours about the increased cost of the project were "wide
of the mark".[223]
After the costs of restoring the network in the wake of the Hatfield
derailment became apparent, however, Railtrack said that it would
not proceed with the second phase of the Channel Tunnel Rail Link
if payment of £1 billion by the Government under the Ten
Year Plan was not brought forward: as we have said, recent reports
have suggested that the Government will do so.[224]
The company claimed that without the additional funds, it would
be £8 billion in debt by 2003 and unable to afford any new
schemes.[225]
Railtrack's record on development
63. Major infrastructure projects under Railtrack's
charge have generally been subject to delays and rising costs,
most notably in the case of the modernisation of the West Coast
Main Line. Difficulties with the project to re-model the track
at Leeds station have exposed, by Railtrack's own account, "inadequate
planning, over-ambition and poor site management".[226]
We are also concerned at the possible escalation of the cost of
the second stage of the Channel Tunnel Rail Link and the uncertainty
that surrounds Railtrack's future participation in the project.
In short, Railtrack's record in managing major infrastructure
projects is a matter of serious concern. Doubts remain about the
company's ability to deliver developments and enhancements to
the network. We are far from confident about Railtrack's competence
in this regard.
3 2000 Network Management Statement for Great Britain,
Railtrack PLC, March 2000: Volume 1, Sustaining and developing
Britain's rail network, and Volume 2, Customer plans, zone
plans and route strategies. The 2000 Network Management
Statement for Great Britain, which can be viewed at www.railtrack.co.uk/corporate/2000nms/index.html. Back
4
Ensuring that Railtrack maintain and renew the railway network,
Report by the Comptroller and Auditor General, HC (1999-2000)
397, which can be viewed on the internet at www.nao.gov.uk/publications/nao_reports/9900397es.pdf. Back
5
Published in October 2000 as The Periodic Review of Railtrack's
Access Charges, Office of the Rail Regulator, which can be
viewed on the internet at www.railreg.gov.uk/prdcrev/prfinal1.pdf. Back
6
For more information, see www.sra.gov.uk/SSRA_news/Replacement.htm. Back
7
Published in July 2000 as Transport 2010 - The Ten Year Plan,
Department of the environment, Transport and the Regions, which
can be viewed on the internet at www.detr.gov.uk/trans2010/index.htm. Back
8
Environment, Transport and Regional Affairs Committee Press Notice
No.34, 18 May 2000, which can be viewed on the internet at www.parliament.uk/commons/selcom90/etrpnt34.htm. Back
9
On 5 July and 12 July: see Press Notice No.42, at www.parliament.uk/commons/selcom90/etrpnt42.htm. Back
10
On 26 July: see Press Notice No.47, at www.parliament.uk/commons/selcom90/etrpnt47.htm. Back
11
On 15 November, 22 November, 29 November, 6 December and 12 December:
see Press Notices Nos.59 and 70, at www.parliament.uk/commons/selcom90/etrpnt59.htm
and www.parliament.uk/commons/selcom90/etrpnt70.htm. Back
12
Announced in Press Notice No.56, at www.parliament.uk/commons/selcom90/etrpnt56.htm. Back
13
Recent Events on the Railway, HC (2000-2001) 17: the Report
can be viewed on the internet at www.publications.parliament.uk/pa/cm200001/cmselect/cmenvtra/17/1702.htm. Back
14
British Railways Board Annual Report and Accounts 1990-91,
p.1. Back
15
British Railways Board Annual Report and Accounts 1990-91,
p.27. Back
16
British Railways Board Annual Report and Accounts 1990-91,
pp.54 and 56. Back
17
British Railways Board Annual Report and Accounts 1990-91,
p.11. Back
18
Intercity included East Coast Main Line (now the Great North Eastern
Railway), Great Western Main Line (First Great Western), West
Coast Main Line (Virgin West Coast), Cross Country and Midland
Main Line (Virgin Cross Country and Midland Main Line), and Gatwick/Anglia
(Gatwick Express and Anglia Railways). Network SouthEast comprised
Thames and Chiltern (Thames Trains and Chiltern Railway), South
West (South West Trains), South Central (currently Connex South
Central), South East (Connex South East), London Tilbury and Southend
(c2c), Great Eastern (First Great Eastern), West Anglia (West
Anglia Great Northern), Thameslink (still Thameslink), and North
(Silverlink). Regional Railways included North East (Northern
Spirit), North West (First North Western and Merseyrail Electrics),
Central (Central Trains), South Wales and West (Wales and West
and Valley Lines), and ScotRail (still known as ScotRail). The
only current franchise not mentioned is Island Line on the Isle
of Wight. Back
19
Anglia, Eastern, London Midland, ScotRail, Southern and Western. Back
20
See British Railways Board Annual Report and Accounts 1990-91,
p.11. Back
21
Railways Act 1993, Chapter 43. Back
22
See the Railways Act 1993, Section 4(1)(a), (b), (f) and (g). Back
23
See the Railways Act 1993, Section 5. Back
24
See the Railways Act 1993, Sections 17 ff. Back
25
See Privatisation of the Rolling Stock Leasing Companies,
Report by the Comptroller and Auditor General, HC (1997-98) 576. Back
26
See British Railways Board Annual Report and Accounts 1993-94,
p.9. Back
27
See the Network Licence granted to Railtrack plc, Part
I, paragraph 1: the whole of the Network Licence can be viewed
on the internet at http://www.railreg.gov.uk/public_register/netwrk_licence.pdf. Back
28
See the 1999 Network Management Statement for Great Britain,
p.14. Back
29
The fourteen major stations owned and operated by Railtrack are:
Birmingham New Street, Edinburgh Waverley, Gatwick Airport, Glasgow
Central, Leeds City, London Bridge, London Charing Cross, London
Euston, London King's Cross, London Liverpool Street, London Paddington,
London Victoria, London Waterloo, and Manchester Piccadilly. Back
30
Railtrack Annual Report and Accounts 1996, pp.2 and 46:
see http://www.railtrack.co.uk/pdfs/ara96/annual9596.pdf. Back
31
Mainline, Loadhaul Limited and Transrail Limited: see the details
given in British Railways Board Annual Report and Accounts
1995-96, p.21. Back
32
See British Railways Board Annual Report and Accounts 1995-96,
p.8. Back
33
See http://www.ewsrailway.co.uk/index2.html. Back
34
See British Railways Board Annual Report and Accounts 1993-94,
p.9. Back
35
See British Railways Board Annual Report and Accounts 1996-97,
p.52. Back
36
See The Flotation of Railtrack, Report by the Comptroller
and Auditor General, HC (1995-96) 583. Six maintenance depots
and an electronic service centre were sold, for a total of £32
million. Three of the depots and the service centre were purchased
by Adtranz (formerly ABB) for £19 million, a further two
were purchased for £6 million by Railcare (a joint venture
between Babcock and Siemens), and the remaining depot was sold
to a management buy-out team, Wessex Traincare Limited, for £7
million. Back
37
See the British Railways Board Annual Report and Accounts 1995-96
and 1996-97, p.74 and p.52 respectively. Back
38
See the British Railways Board Annual Report and Accounts 1997-98,
at http://www.brb.gov.uk/brb.htm. Back
39
Railtrack Network Management Statement 1995-96, p.2. Back
40
Ensuring Safety on Britain's Railways, Health and Safety
Commission, January 1993, para.6.25. Back
41
See British Railways Board Annual Report and Accounts 1993-94,
p.9. Back
42
See British Railways Board Annual Report and Accounts 1995-96,
p.23. Back
43
See British Railways Board Annual Report and Accounts 1995-96,
p.23. Back
44
See British Railways Board Annual Report and Accounts 1995-96,
p.23, and British Railways Board Annual Report and Accounts
1996-97, p.52. Back
45
Based on information supplied by Railtrack. Not all regions are
included. Back
46
The Infrastructure Maintenance Units (IMUs) were distributed as
follows: Scotland IMU (Railtrack's Scotland zone) to First Engineering
(a management team backed by the Weir Group, 3i and the Bank of
Scotland), Northern IMU (North West zone) to Jarvis, Central IMU
(Midlands zone) to GTRM (Alstom UK and Carillion plc), Western
IMU (Great Western zone) to Amey Rail, South Western IMU (Southern
zone) to AMEC Rail, and both South Eastern and Eastern IMUs (East
Anglia and London North Eastern zone) to Balfour Beatty Rail Maintenance
(information supplied by the National Union of Rail, Maritime
and Transport Workers). Back
47
The 1999 Network Management Statement for Great Britain,
p.36. Back
48
See the 1999 Network Management Statement for Great Britain,
p.36. Back
49
Most recently, contracts for the Central region of the London
North Eastern Zone has been let to Jarvis, for the Preston region
of the North West zone to GTRM, for the Manchester region of the
North West Zone to First Engineering, and for the East Midlands
region of the Midlands zone to Serco Rail. See Infrastructure
Maintenance Contracts, Railtrack Press Notice, 14 August 2000. Back
50
See the 1999 Network Management Statement for Great Britain,
p.37. Back
51
The 1999 Network Management Statement for Great Britain,
p.37. Back
52
Scotland is covered by First Engineering Limited and by Jarvis
Rail Limited; North West, London and North Eastern, and Midlands
are all covered by Jarvis Rail Limited; East Anglia is covered
by Centrac Limited and Grant Rail Limited; Great Western is covered
by Amey SECO JV; and Southern is covered by Balfour Beatty Rail
Renewals Limited. In addition, Motherwell Bridge Rail carries
out works in various locations (information provided by Railtrack). Back
53
See Ensuring Safety on Britain's Railways, Health and Safety
Commission, January 1993, para.6.25. Back
54
See Railway Safety (HC (1998-99) 30), para.15. Back
55
See HC (1999-2000) 17, Q.7; see also Q.571. Back
56
Ensuring Safety on Britain's Railways, Health and Safety
Commission, January 1993, para.6.25. Back
57
See Railway Safety (HC (1998-99) 30), p.56. Back
58
Railway Safety (HC (1998-99) 30), p.44. Back
59
See Railtrack's Investment Programme: Statement by the Rail
Regulator, May 1997, para.3: the statement can be viewed on
the internet at http://www.railreg.gov.uk/docs/40rtinvs.htm. Back
60
Railtrack's Investment Programme: Statement by the Rail Regulator,
May 1997, para.2. Back
61
See the Network Licence, p.1 and Conditions 3 and 7 (http://www.railreg.gov.uk/public_register/licence.pdf);
see also the Office of the Rail Regulator Annual Report 1993-94,
para.27. Back
62
See HM Railways Inspectorate's Role, at http://www.hse.gov.uk/railway/rihome.htm#role
- the relevant legislation includes the Health and Safety at Work,
Etc Act 1974, the Railways (Safety Case) Regulations 1994 and
the Railways (Safety Critical Work) Regulations 1994. Back
63
Railtrack's Investment Programme: Statement by the Rail Regulator,
May 1997, para.1. Back
64
Railtrack's Investment Programme: Statement by the Rail Regulator,
May 1997, para.4. Back
65
Railtrack's Investment Programme: Statement by the Rail Regulator,
May 1997, para.5. Back
66
Railtrack's Investment Programme: Statement by the Rail Regulator,
May 1997, para.5. Back
67
Five have been produced, annually: the latest can be viewed at
http://www.railtrack.co.uk/corporate/2000nms/. Back
68
See Railtrack's Investment Programme: Statement by the Rail
Regulator, May 1997, para.7. Back
69
Railtrack's Investment Programme: Statement by the Rail Regulator,
May 1997, paras.7 and 8. Back
70
Railtrack's Investment Programme: Statement by the Rail Regulator,
May 1997, para.9. Back
71
Railtrack's Investment Programme: Statement by the Rail Regulator,
May 1997, para.11. Back
72
Railtrack's Investment Programme: Statement by the Rail Regulator,
May 1997, para.13. Back
73
See Railtrack's Investment Programme: Increasing Public Accountability,
July 1997, Annex B, p.19. Back
74
Third Report of the Environment, Transport and Regional Affairs
Committee, HC (1997-98) 286-I, para.1, which can be viewed via
our website at http://www.parliament.uk/commons/selcom/etrahome.htm. Back
75
See http://www.opraf.gov.uk/sra/about/Default.htm. Back
76
Mainly relating to the disposal of property: see http://www.brb.gov.uk/property.htm. Back
77
Transport Act 2000, Chapter 38, which can be viewed at http://www.hmso.gov.uk/acts/acts2000/20000038.htm. Back
78
See http://www.opraf.gov.uk/sra/about/Default.htm. Back
79
See RI12, para.2. Back
80
See Ensuring that Railtrack maintain and renew the railway
network, NAO, HC (199-2000) 397, para.1.5. Back
81
See RI21, para.5. Back
82
See HC (199-2000) 397, para.13. Back
83
See RI21, para.7. Back
84
See HC (199-2000) 397, figure 6, p.20. Back
85
Railtrack's Performance in the Control Period 1995-2001: Final
Report, Booz Allen and Hamilton, April 1999, paras. 126-132. Back
86
From 231.3 million to 256.0 million: see RI21, para.13. Back
87
From 24.5 million to 29.3 million: see RI21, para.13. Back
88
See HC (1999-2000) 397, para.2.7. Back
89
RI07. Back
90
RI20. Back
91
RI20. Back
92
Q. 2. Back
93 Q.
793. Back
94
Q. 255. Back
95
Q. 43. Back
96
HC (1999-2000) 397, para. 2.25. In 1998-99, Railtrack was responsible
for 46 per cent of passenger and 13 per of freight train delays
respectively. Maintenance and renewal and renewal problems accounted
for approximately 70 per cent of Railtrack's delays (ibid, para.
2.6). Delays to passenger services for infrastructure-related
reasons have fallen since privatisation (see RI20). Back
97
Q.255. Back
98
See HC (1999-2000) 397, para.3.30. Back
99
See HC (1999-2000) 397, Executive Summary, para.17(b). Back
100
Regulator sets out Railtrack's future financial framework,
Press Notice ORR 99/53, 15 December 1999. Back
101
See HC (1999-2000) 397, Executive Summary, para.17(c). Back
102
2000 Network Management Statement for Great Britain, p.40. Back
103
Consultation on proposed modifications to Railtrack's network
licence, Office of the Rail Regulator, 14 September 2000,
p.5. Back
104
Ensuring that Railtrack maintain and renew the railway network,
para. 3.50. Back
105
Ensuring that Railtrack maintain and renew the railway network,
para.17(d). Back
106
Ensuring that Railtrack maintain and renew the railway network,
para.17(d). Back
107
Ensuring that Railtrack maintain and renew the railway network,
para.17(d). Back
108
See Ensuring that Railtrack maintain and renew the railway
network, para.18 ff. Back
109
See RI21, para.27. Back
110
See Consultation on proposed modifications to Railtrack's network
licence, p.5, and the 2000 Network Management Statement
for Great Britain, p.40. Back
111
2000 Network Management Statement for Great Britain, p.40. Back
112
See RI21, para.32; see also Consultation on proposed modifications
to Railtrack's network licence, Office of the Rail Regulator,
14 September 2000. Back
113
See RI21, para.29. Back
114
Q. 8. Back
115
HC (1999-2000) 397, para.2.6. The remainder of all delays were
caused by train operators themselves. Back
116
See HC (1999-2000) 397, Figure 8, p.27. Back
117
A New Deal for Transport: Better for Everyone, Cm 3950,
map on p.162 (Annex F). Back
118
See the 2000 Network Management Statement for Great Britain,
Volume 2, p.71. Back
119
See the 2000 Network Management Statement for Great Britain,
Volume 2, p.58. Back
120
See RI21, para.26. Back
121
See the 1999 Network Management Statement for Great Britain,
p.9. Back
122
See RI21, para.26. Back
123
See RI21, para.26. Back
124
See RI21, para.26. Back
125
See the 2000 Network Management Statement for Great Britain,
Volume 1, pp.32 and 33. Back
126
See HC (1999-2000) 397, Executive Summary, para.12. Back
127
See the 1999 Network Management Statement for Great Britain,
p.9. Back
128
On 4 February 1997, a freight train derailed when crossing a bridge
close to Bexley station. Four members of the public were injured
in the accident which caused extensive damage was caused to a
railway viaduct and nearby buildings. The condition of the track
support and its fastenings on the bridge and deteriorated so badly
that the rails moved apart under the weight of the train. The
South East Infrastructure Maintenance Company, Southern Track
Renewals Company and Railtrack were fined a total of £150,000
plus costs for Health and Safety at Work etc Act 1974 offences.
Railtrack was criticised by the Railway Inspectorate for failing
to monitor the performance of its contractor and, although it
was aware of the unsafe condition of the track, it failed to take
action to address the problem (Railway Accident at Bexley,
HM Railway Inspectorate, 1999). Back
129
RI06, paras. 6 and 7. Back
130
RI16, paras. 9-12. Back
131
Rail Failure Assessment for the Office of the Rail Regulator:
an Assessment of Railtrack's Methods for Managing Broken and Defective
Rails, Transportation Technology Center Inc, October 2000. Back
132
Ibid, p. ii. Back
133
RI9. Back
134
RI21. Back
135
RI21, para. 10. Back
136
HC (1999-2000) 397, exec summary, para. 15. Back
137
Q. 10. Back
138
See RI20, pp. 4 and 5. Back
139
Q. 10. Back
140
Q. 10. Back
141
Q. 268. Back
142
RI06, para.8. Back
143
See RI20, p.1; see also Q.64. Back
144
See RI20, p.2. Back
145
Q.2. Back
146
RI21, para.10. Back
147
See Q.260, Q.268 and Q.305. Back
148
See Safety chief blames Railtrack for neglect, Independent
on Sunday, 18 February 2001. Back
149
RI06, para. 8. Back
150
RI02. Back
151
Red/green zone working - A report on the progress with maximisation
of green zone working on Railtrack infrastructure, HM Railway
Inspectorate, 12 February 2001, which is at www.hse.gov.uk/railway/rgzwrep1.htm. Back
152
This required Railtrack to achieve a 12.7 per cent improvement
in its passenger train performance (as measured by minutes delay
per passenger train caused by Railtrack) in the ended 31 March
2000. A fine would be imposed if the target was not achieved
(see Railtrack's performance targets: statement by the Rail
Regulator, Office of the Rail Regulator, August 1999). Back
153
RI02. Back
154
Q. 356. Back
155
Information supplied by the RMT: see HC (2000-01) 17, para.11. Back
156
See Recent Events on the Railway (HC (2000-01) 17), para.
11. Back
157
For example, see RI06, paras. 3-5. In 1995-96, the Railway Inspectorate
found that the systems that Railtrack had in place to manage its
contractors needed to be improved. Back
158
See HC (1998-99) 30, paras. 15-24. Back
159
See Train Derailment at Hatfield, 17 October 2000, Second
HSE Interim Report, 23 January 2001. Back
160
See Train Derailment at Hatfield, para.12. Back
161
See Train Derailment at Hatfield, para.5. Back
162
See Train Derailment at Hatfield, para.23. Back
163
See Statement from Railtrack, Railtrack Press Release,
18 October 2000. Back
164
See Railtrack announces interim results, Railtrack Press
Release, 13 November 2000. Back
165
See Prescott calls on industry to work together to produce
a national track recovery plan, DETR Press Release No.670,
26 October 2000. Back
166
See Rail Industry Statistics Published, shadow Strategic
Rail Authority, 15 December 2000. Back
167
See National rail recovery plan delivers real improvements
to train services, Railtrack Press Release, 12 January 2001. Back
168
See, for example, Railtrack Targets Timetables for Significant
Improvements, Railtrack Press Release, 13 December 2000. Back
169
Recent Events on the Railway, HC (2000-01) 17: see http://www.parliament.uk/commons/selcom/etrahome.htm. Back
170
See Recent Events on the Railway, HC (2000-01) 17, para.10. Back
171
See Recent Events on the Railway, HC (2000-01) 17, para.12. Back
172
See Recent Events on the Railway, HC (2000-01) 17, para.15. Back
173
Recent Events on the Railway, HC (2000-01) 17, para.22;
see also Railtrack Response to Select Committee Report,
Railtrack Press Release, 14 December 2000. Back
174
See Train Derailment at Hatfield: 17 October 2000, Second
HSE Interim Report, 23 January 2001. Back
175
Q.608. Back
176
See Q.685. Back
177
See Q.610 ff. Back
178
See Q.614. Back
179
See Railway Safety, First Report, HC (1998-99) 30, para.21
ff. Back
180
Railway Safety, HC (1998-99) 30, para.22. Back
181
Railway Safety, HC (1998-99) 30, para.24. Back
182
See Q.639; see also Q.841. Back
183
See Railtrack announces interim results, Railtrack Press
Release, 13 November 2000. Back
184
See Regulator puts pressure on Railtrack over £15 billion
package, Guardian Unlimited, 13 January 2001; see www.guardian.co.uk/Archive/Article/0,4273,4117118,00.html. Back
185
See HC Deb, 14 February 2001, col.308; see also Rail chaos
'until summer', Sunday Business, 11 February 2001, and Train
delays will continue until summer, Sunday Times, 11 February
2001. Back
186
See Railtrack faces massive cash claims from train firms,
Guardian Unlimited, 13 February 2001; see www.guardian.co.uk/Archive/Article/0,4273,4135500,00.html. Back
187
See Railtrack faces claims bill of £800 million, The
Times, 26 February 2001. Back
188
See Rail chaos drives passengers into BAA's arms, Guardian
Unlimited, 3 February 2001; see www.guardian.co.uk/transport/Story/0,2763,432851,00.html. Back
189
Fifteenth Report of the Environment, Transport and Regional Affairs
Committee, The Road Haulage Industry, HC (1999-2000) 296. Back
190
See Eight weeks after Hatfield - real and continuing chaos
for rail freight, Rail Freight Group Press Release, 12 December
2000. Back
191
See Regulator puts pressure on Railtrack over £15 billion
package, Guardian Unlimited, 15 January 2001; see also Railtrack
'nearly bankrupt', The Guardian, 19 February 2001, Railtrack's
SOS for £2bn, The Observer, 18 February 200, and Embattled
Railtrack will slash investment, Sunday Times, 18 February
2001. Back
192
Railtrack 'nearly bankrupt', The Guardian, 19 February
2001. Back
193
See Prescott bails out Railtrack with £1 bn, The Sunday
Times, 25 February 2001, and Railtrack seeks early £1
bn aid, Daily Telegraph, 26 February 2001. Back
194
RI17. See National Rail Trends, shadow Strategic Rail
Authority, 15 December 2000. Back
195
Transport 2010: the background analysis, para. 9. Back
196
Transport 2010: the background analysis, para. 17. Back
197
Transport 2010: the ten-year plan, para. 3.5. Back
198
Transport 2010: the ten-year plan, para. 6.16. Back
199
Transport 2010: the background analysis, para. 22. Back
200
RI20. Forecasts produced for Railtrack in conjunction with the
Association of Train Operating Companies suggested that growth
in passenger traffic could range from 23 per cent to 64 per cent
over the next ten years. It was subsequently reported that Railtrack
had adopted a lower central forecast of 37 per cent following
the Government's decision to end the fuel duty escalator, which
had previously increased petrol and diesel prices above the rate
of inflation (Railtrack cuts passenger growth forecast,
Financial Times, 29 December 2000). Back
201
2000 Network Management Statement, March 2000, Railtrack. Back
202
RI20. Back
203
RI20. Back
204
Under the revised financing arrangements announced in 1998, Railtrack
has committed to acquiring the assets of and to assuming construction
risk for the first phase (the Channel Tunnel to Fawkham Junction,
Kent) of the project. It also has the option (exercisable until
July 2003) to commit to acquire the assets of phase 2 (Southfleet,
Kent to St Pancras station in London) (The Channel Tunnel Rail
Link, DETR see www.railways.detr.gov.uk/ctrl). Back
205
RI20. Back
206
RI20. Back
207
RI20. Back
208
Maintenance and renewal of the West Coast Main Line,
Office of the Rail Regulator Press Notice, 20 June 2000. Back
209
RI21, para. 14. Back
210
See More rail chaos mars station reopening, Guardian Unlimited,
16 January 2001, which can be viewed on the internet at www.guardian.co.uk/Archive/Article/0,4273,4117758,00.html. Back
211
Information provided in a letter to the Chairman of the Transport
Sub-committee from the Director, London North Eastern, Railtrack,
which has not been published. Back
212
RI20C. Back
213
RI16. Back
214
RI02A. Back
215
RI30, para. 3.8. Back
216
See Leeds station plans run off the rails, Guardian Unlimited,
15 January 2001, and Rail repairs close delivery centre,
Guardian Unlimited, 10 January 2001. Back
217
Railtrack misses new deadline as Leeds suffers,
The Times, 16 January 2001. Back
218
Modern Railways, February
2001, p. 6. Back
219
Quoted in Regulator gets tough with Railtrack after operator
anger, Financial Times, 3 January 2001. Back
220
RI21B, para. 36(c). Back
221
Railtrack seeks more State help for Channel link, The Daily
Telegraph, 11 November 2000. Back
222
The Channel Tunnel Rail Link,
www.railways.detr.gov.uk/ctrl. Back
223
QQ. 623 and 624. Back
224
See Prescott bails out Railtrack with £1 bn, The Sunday
Times, 25 February 2001. Back
225
Railtrack in £1 billion threat to new lines, The Times,
16 January 2001. Back
226
Quotation from a letter to the Chairman of the Transport Sub-committee
from the Director, London North Eastern, Railtrack, which has
not been published. Back
|