Examination of Witness (Question Numbers
118 - 141)
TUESDAY 15 FEBRUARY 2000
RT HON
STEPHEN BYERS MP
Chairman
118. We will move on to the Ilisu Dam now. Perhaps
we can start with the ECGD aspect of this in relation to the application
by Balfour Beatty. When did the Department, your officials and
indeed your colleagues as Ministers, become involved in the consideration
of the Balfour Beatty application and when were the other departments,
the FCO and the Treasury, brought into the frame?
(Mr Byers) Ministers in my Department
first became aware of this in March of last year and when that
was the case we obviously began to discuss it with colleagues
in other departments.
119. Could you give us an idea of when the decision
was taken or why was it judged necessary to take rather late in
the day the decision to have a desk-top review of the Environmental
Impact Assessment Report? Did they have doubts about the Bonhage
Report or was it just that they felt there should be a DTI version
of it?
(Mr Byers) Given that this was such a significant
development and one that there was a lot of concern about, I wanted
to be in a position where I could publish reports which would
inform the debate, and the problem we had was that many of the
reports had been commissioned by other bodies who whilst they
were prepared to share that information on a confidential basis,
were not prepared to allow us to make public those reports. So
I felt it was important that we could put into the public arena
reports which addressed the main issues and to me the main issues
were the questions of the environmental impact and the question
of re-settlement and the views of the stakeholders, people living
locally, so we commissioned two reports which we then made public
in order to inform the debate, the debate which is now going on,
and I welcome that but the only way we could make those public
was if we had ownership and possession of them which is why we
commissioned those two exercises.
120. Could you explain to us the role of DfID
in some of these matters. We kind of get the impression that matters
of an ethical character are passed into the DfID tray and the
forces of mammon are at work in Victoria Streetat the top
end.
(Mr Byers) DfID is in Victoria Street as well!
121. At the top end of Victoria Street, I hasten
to add. The point being that there does seem to be a wee bit of
confusion here. I do not think it was wholly cleared up by your
colleague, Richard Caborn, when he spoke to the DfID Select Committee.
What is DfID's role in this apart from being concerned about poor
people in countries which are normally designated as being poor,
which Turkey by definition is not?
(Mr Byers) DfID has a role because they have a certain
degree of experience working with particular communities. They
know the position of the Kurdish people well. I think it is true
to say that in relation to Turkey and this particular project,
DFID have not been as closely involved as they would be if it
was in some other parts of the world. Certainly they will express
their views about the project and its desirability. At the end
it will be a government decision that will be taken, but it is
a government department and will be able to express their support
or disagreement or their concerns, so they have a role to play.
Mr Cunningham
122. Can we have a look at transparency and
in particular why was it necessary to have so much secrecy surrounding
the Environmental Impact Assessment Report. Is it the Eximbank
system that creates that?
(Mr Byers) It is. I would have wanted to make public
the report but it was commissioned I think by the Swiss, and they
have decided that although it is to be circulated to the export
credit agencies, it is not to be made public. I regret that decision
but we will make public information that we have. Members may
find it useful to know that there is now a very fundamental
revision of the Environmental Impact Assessment
Report being compiled by Hydro Quebec which we expect to get in
March or April of this year and I intend to make that report public
and it will be more useful, I think, because it will be an updated
report. The problem about the original one is that it is now two
or three years out of date. What we will have in March or April
is an up-to-date report on the environmental impact if the Dam
is to have the go ahead and I intend to make that report public.
123. Looking at other potential reports, and
coming back to the point I was asking, is the Eximbank system
that is used here a contributory factor or would you want to change
the whole system of how this reportor any Eximbank reportwas
made public?
(Mr Byers) There are issues generally about how these
matters are dealt with. I take the view that wherever possible
information should be made public. I regretted the fact that because
we could not make public that particular report that we had to
do our own version effectively. What I am pleased to say is that
there will be an updated Environmental Impact Assessment Report
which will be carried out by Hydro Quebec and we will be able
to make that public. I think that will be helpful in terms of
the debate that we need to have about whether or not export credits
are given to this particular project. I should stress this point:
I have not decided to give export credits to the Ilisu Dam. What
I have said is that I am minded to do it provided four very significant
conditions are met by the developers and by the Turkish authorities.
If any one of those conditions is not met then I will not approve
an export credit for this project.
Chairman
124. Just for the record, Secretary of State,
you published the reports on 21 December, when did you get them
originally?
(Mr Byers) I think the stakeholder report was a final
revision, it was revised over a couple of months at the end of
November, towards the end of November. I think the ERM report
was earlier than that. I need to refresh my memory on that, Chairman.
We needed to consider them within government. We needed then to
reflect on whether we said anything about the export credit itself.
I took the view that because it was a controversial question,
that rather than just publish the reports without giving an indication
of government thinking on them, that I should indicate how we
were viewing the reports. That meant building in a period of three
or four weeks so around government we could talk about our response
to the reports and that built in that extra delay effectively.
I gave a commitment that I would publish the reports before Christmas.
I was on the record as having given that commitment to a number
of groups including NGOs who knew we had a report and I said,
"It is my intention to publish them before Christmas",
and we just managed to do it. Otherwise it would have been a delay
of three weeks or so before Parliament reassembled and I thought
that would not be helpful in the whole process.
Mr Berry
125. The four conditions you mentioned in your
statement on 21 December and that you have reiterated today do
not include a condition that was in the ERM's review of the original
Environmental Impact Assessment Report that a necessary pre-condition
for ECGD support should be a full Environmental Management Plan
and a review of the institutional capacity of the Turkish authorities
to manage the project. That is two conditions, in fact. Why were
those two conditions not included in your statement and do they
form part of your current set of conditions or not?
(Mr Byers) I think the way to look at it is there
are the four conditions that were stated when we published the
two reports just before Christmasresettlement, water quality,
downstream flow and preservation of cultural heritageand
there are discussions going on at the moment with the Turkish
authorities on each of those four issues. In addition, we will
have an updated Environmental Impact Assessment Report in March
or April. I would expect that report to make recommendations possibly
along those lines and obviously we will need to reflect on that
when we decide what further action to take. Effectively, we have
got the four conditions that I announced just before Christmas.
In addition, we will have the new Environmental Impact Assessment
Report which I would expect to cover the particular aspects which
the honourable gentleman has just mentioned.
126. Why then did you say that you were minded
to say yes, subject to the four conditions when we have a report
being prepared that, quite rightly, you are saying should be in
the public domain and is very important, that will address these
other issues which might suggest to you that therefore there ought
to be other conditions that have to be satisfied? That is what
I do not quite understand.
(Mr Byers) They might do that but they have not reported
yet so until we get to the report in March or AprilWhat
I can say though today, Chairman, if it helps, is if there are
clear indications of environmental damage or worries which are
revealed by that report then that is something we will want to
take into account in arriving at our final decision. Because we
did not have that reportin fact we had rather outdated
reports in December but we knew this environmental assessment
was being conductedthe view was that it was better to wait
for that and then respond accordingly in addition to the four
conditions I mentioned before.
127. But nevertheless you say that you are minded
to say, "Yes, subject to four conditions", as opposed
to, "We will wait and see what the environmental report says"?
(Mr Byers) Because we could identify the four conditions
from the two reports. I want to begin the discussions because
part of this, and I think this is an important point to get over
to the Committee is, if we had said no, the project would have
gone ahead with the other partners. There is no doubt about that.
We do not have a veto on this. If we pull out and Balfour Beatty
do not get the export credit the project will still go ahead because
it is so important to power generation in Turkey. Some people
would like to think if we said that if the £200 million export
credit that we are prepared to underwrite was not there then it
would block the thing, but that is not case; it would go ahead
anyway. It is not going to be a blank cheque for export credit
with me as Secretary of State. What it is going to be is conditions
that will make this a flagship project and if the Turkish authorities
agree to those conditions then I think we will be able to achieve
something that is desirable in terms of energy generation but
also we have got the Turkish authorities to deal with this matter
in a quite different way than they ever have in the past. We will
be breaking new ground. If we can achieve that I think it is worth
giving an early indication of the sorts of conditions that we
expect to be met.
128. One other quick question on this. Another
criticism of the ERM report was the absence of an analysis of
any alternatives to the Dam. Do you expect the new report to address
that?
(Mr Byers) It is certainly something that we are considering
and I would hope it is something that the new report will consider
as well. We do know the options which are being considered by
the Turkish authorities in terms of energy generation. What is
clear is that there is an energy deficit as far as Turkey is concerned
so it is an issue that will need to be addressed. I would have
thought in terms of alternative sources of energy, that is something
that needs to be taken into account.
Mr Hoyle
129. Secretary of State, can I take you onto
the problem of conditionality. Can and will there be anything
in the ECGD contract with the lending bank or the banks' contract
with the Turkish authorities to provide for the withdrawal of
the guarantee in the event of a breach? As a lawyer with expertise
in contract law, can such a contract be terminated for non-performance
by a third party?
(Mr Byers) The way which this will operate, Chairman,
is effectively there will be a loan agreement that will be entered
into between the various parties. This can have written into it
requirements that certain events will have to have occurred or
that the Turkish authorities will have had to have carried out
before the loan agreement itself becomes effective. Undertakings
can be given by the Turkish authorities that they will carry out
certain acts in a certain way. There can be provisions written
into the loan agreement that if undertakings were breached then
the whole amount of the loan then outstanding from the Turkish
authorities will become immediately payable and there can be provisions
that if undertakings were breached then there will be no further
advances to the contractor under the loan. So we can ensure, in
the way in which we construct the agreement and indeed mindful
of any conditions that might be attached which can be included
there, that we can have a watertight set of provisions which will
affect the loan agreement.
130. That is very appropriate with a dam! In
advance of the summer 2000 deal foreseen at present between ECGD
and its bankers, presumably you will come to a judgment on whether
the four conditions have been met so far as they can be at the
time. Monitoring of resettlement apart, which is to be done by
the international panel, will you make an independent UK assessment
or will it be done by the ECAs as a group?
(Mr Byers) What I intend to do, we expect to get the
Environmental Impact Assessment Report in April or May. I want
to publish that report and give people time to look at it and,
indeed, give the Government time to look at it before we arrive
at a decision on whether to extend export credit or not. At the
same time I am going to make public the progress that has been
made in achieving each of the four conditions that I mentioned
in my statement of 21 December. I will make those public as well
and people will be able to judge the extent to which those conditions
have been satisfied. When we have done that and when a period
has been given I will then make a decision on whether export credits
are to be made available. What I can say is that when we have
those details and if we do extend export creditsand, as
I say, no decision has yet been takenthen we will ensure
that those conditions are written into any agreement that might
be entered into.
Mr Chope
131. Will this apply to all potential contracting
parties? You said earlier on that the project will go ahead anyway.
If these conditions are not met, what is the scenario then? Do
you still think the project will go ahead and somebody will break
out of the group and allow the project to go ahead or what?
(Mr Byers) I think what has been very positive is
that as a result of the initiative that the UK Government has
taken in outlining those four conditions we have been able so
far to take other export credit agencies with us in seeing that
these conditions are met. They broadly accept that this is going
in the right direction. I hope that the consortium will manage
to retain this common approach to the issues. I would not want
to prejudge what might happen if we do not get the conditions
signed up to.
132. Progress is being made?
(Mr Byers) Progress is being made. We are reasonably
content. The one area where there is a greater concern is the
issue to do with resettlement where there are probably more fundamental
problems there but I hope they can be overcome. Very good progress
is being made in relation to the other three conditions.
Helen Southworth
133. Can I take you on to the issue of resettlement.
We have had some fairly bleak evidence on issues surrounding that.
We have been told by the KHRP that it is now too late for international
norms to be observed because there was no effective consultation
in the first place; that the past record of resettlement and compensation
was lamentable; that in the political context of south east Turkey
and village destruction, which is where this is taking place,
the idea of independent monitoring is hopeless; and that there
are in effect no domestic legal remedies for people there. That
is not a happy situation. It is extremely difficult for us to
make judgments from here based on the truth of those observations
but we have got a responsibility to make sure that resettlement
does take place and people do have proper and effective remedies
in case of dispute. How is that going to happen?
(Mr Byers) I agree with all of that and I think it
is important that we do have appropriate mechanisms in place that
will ensure that if a resettlement programme is agreed it is one
which covers all of the affected people and not just a few, and
it is one that may need to cover those people who are not there
at the moment but have already been displaced because, as you
rightly say, changes have already taken place in the village structure
in that particular area so we need to be mindful of that. We need
to have effective independent monitoring of the resettlement programme.
There does need to be compensation which is adequate. All of those
measures will need to be put in place. Because it is difficult
and complex it is probably one of the reasons why this is the
area that we probably have most concern about in terms of the
progress which is being made. The Turkish authorities, though,
have just recently appointed an independent group to try and look
at the resettlement process. I think they are genuine in doing
that but we do need to ensure that we get the resettlement package
together in a way which we feel comfortable with, that is going
to be the test at the end. I think we need to ensure that it is
a resettlement which, as I say, covers all of the affected people
and not just a minority or even the majority.
134. You are confident there is a political
will to see that happen on the ground?
(Mr Byers) I hope there is. Can I be clear on this,
if we do not have a resettlement plan in place which satisfies
the UK Government we will not extend an export credit to this
project.
135. Can I ask about the downstream issues.
There has been a considerable amount of anxiety expressed by downstream
nations. It may or may not be misplaced but there is certainly
the possibility to reduce water flow and to enable Turkey to "turn
off" the Tigris. What are you making of that?
(Mr Byers) Two things really. First of all, over half
of the flow of the Tigris is actually downstream from the Dam.
Secondly, we are seeking assurances from the Turkish authorities
that they will consult neighbouring states about the whole issues
which are involved and also that we have now got an agreement
with the Turkish authorities that there will be a minimum downstream
flow regime operating during the filling of the reservoir. That
is the time when potential difficulties of downstream flow will
arise. Once the Dam is built then the issue is not one of blocking,
because the way in which the Dam works, to create hydro-electricity,
of course is to have a flow of water going through, the destruction
to the flow of the Tigris actually comes from the period during
which the reservoir is being filled up with the flow of the Tigris.
We have now got an agreement that there will still be a flow,
even during the time when the reservoir is being filled up. There
will still be a downstream flow to add to the 50 per cent of the
Tigris which is already flowing the other side of the Dam.
136. You are expecting consultation to take
place, will you be pursuing rigorously that it will actually take
place?
(Mr Byers) Yes, there is a requirement that the Turkish
authorities should consult neighbouring states.
137. Can I ask you about Hansankeyf. What kind
of international monitoring, decision making process is there
going to be amongst experts within the archaeological profession
to ensure that as much as possible is actually being saved rather
than some lip service being paid?
(Mr Byers) There has been a detailed technical survey
on the cultural heritage and in particular the impact that it
will have locally. There has been, I understand, a recent presentation
which has been given in Ankara about the steps which will be taken.
We have not seen details of that yet but we will be studying that
obviously very carefully.
138. You will be expecting international experts
to be involved in the process throughout?
(Mr Byers) I think that will be helpful.
Chairman
139. I think we are just about at the end. Can
I just check up one point, when you spoke about the documents
and the press release being published on 21st December, you mentioned
this was done in order to get it out before Christmas and the
three week recess. Actually the recess started on the 20th.
(Mr Byers) Did it?
140. Perhaps, Secretary of State, you could
talk to the people in your Press Office and say that an awful
lot of irritation could be avoided if the Parliamentary timetable
is taken account of rather more than the convenience of the Department,
to which at the end of the day you are answerable. Perhaps, if
you could convey that to your colleagues, it would be helpful.
(Mr Byers) Yes.
141. Can we say, also, you have given us a lot
of your time this morning. We are just over the edge as far as
timing is concerned. I think we have covered everything and you
have been extremely frank with us, perhaps franker on some issues
than you probably feel you ought to have been . We are very grateful
for the time and we look forward to having you at our mutual convenience
in the future.
(Mr Byers) Thank you very much.