MEMORANDUM BY THE DEPARTMENT OF HEALTH
(CONT.)
7. A nationally agreed support scheme will
provide assistance to 12 of the PFI schemes prioritised in the
first wave. The early PFI schemes were being progressed on the
assumption that they would be revenue neutral or better, but this
did not happen because the capital cost base of hospitals in the
top prioritised schemes was already depressed because of their
poor state. A nationally agreed mechanism for smoothing out the
payments profile of PFI schemes was put forward. This aimed to
put the cost profile of PFI schemes on to the same footing as
publicly funded schemes.
8. As originally conceived, a proportion
of the concession payments each year were to be capitalised in
recognition of the future economic benefits from the reduced payments
in the secondary concession period. This complex way of providing
support was originally thought necessary in order to be compatible
with PFI schemes, and the sums agreed are shown in the following
table. It has, however, now been concluded that support can be
provided more simply. The support will be added to the HAs revenue
allocations.
9. In common with trusts with publicly funded
schemes, and trusts with short-term financing difficulties, regional
offices sometimes make local financial support available. The
terms of this support are agreed legally and vary from region
to region.
SUPPORT TO PFI SCHEMES
| NHS Trust | Annual Purchaser Benefit £'000s
|
| Carlisle Hospitals NHS Trust | 374
|
| North Durham Health Care NHS Trust | 757
|
| South Durham Healthcare NHS Trust | 308
|
| Calderdale Healthcare NHS Trust | 427
|
| Bromley Healthcare NHS Trust | 1,048
|
| Greenwich Healthcare NHS Trust | 601
|
| Wellhouse NHS Trust | 358 |
| Dartford & Gravesham NHS Trust | 1,059
|
| Swindon & Marlborough NHS Trust | 1,042
|
| Worcester Royal Infirmary NHS Trust | 763
|
| Hereford Hospitals NHS Trust | 562
|
| South Manchester University Hospitals NHS Trust
| 370 |
(iv) Could the Department provide a table showing
the increases to the capital cost of schemes since the last expenditure
questionnaire and provide a commentary on changes of more than
10 per cent? In addition, could the Department provide
the intital costs of PFI schemes at outline business case (baseline
year) for those schemes reported in last year's questionnaire
and comment on increases?
10. The information requested is contained in the following
tables.
Table 4.8.3
INCREASES TO THE CAPITAL COST OF PFI SCHEMES
Northern & Yorkshire
| A | B | C
| D | E | F
|
| Region | Capital cost at OBC stage
| Capital cost reported last year |
Capital value this year | % change since OBC stage
| % change since last year |
| £m | £m
| £m | |
|
| NORTHERN & YORKSHIRE REGION |
| | | |
|
| Leeds Teaching Hospitals NHS Trust |
| | 119.0 | 0.0
| 0.0 |
| Newcastle upon Tyne Hospitals NHS Trust |
| 123.8 | 105.3
| | --14.9 |
| South Tees Acute Hospitals NHS Trust | 51.2
| 96.3 | 121.9 |
138.1 | 26.6 |
| Carlisle Hospitals NHS Trust | 39.0
| 64.7 | 66.7 |
71.0 | 3.1 |
| Calderdale Healthcare NHS Trust | 31.0
| 64.6 | 64.6 |
108.4 | 0.0 |
| North Durham Health Care NHS Trust | 55.2
| 61.0 | 61.0 |
10.5 | 0.0 |
| Leeds Community & Mental Health Services NHS Trust
| 39.0 | 43.0 |
42.2 | 8.2 | --1.9
|
| South Durham Health Care NHS Trust | 20.0
| 41.2 | 48.0 |
140.0 | 16.5 |
| Hull and East Yorkshire Hospitals NHS Trust |
21.7 | 21.7 | 21.7
| 0.0 | 0.0 |
Northumbria Health Care NHS Trust
Hexham GH
| 18.0 | 18.0 |
21.2 | 17.8 | 17.8
|
| Northumbria Health Care NHS Trust | 8.2
| 18.2 | 16.9 |
106.1 | --7.1 |
North Durham Health Care NHS Trust
Chester-Le-Street Comm Hospital
| 10.4 | | 10.4
| 0.0 | |
| Total Northern & Yorkshire | 293.7
| 552.5 | 698.9
| | |
Comment on any increases over 10 per cent
GENERAL COMMENT
ON OBC COSTS
The OBC options were worked up a long time in advance of
eventual agreement of the PFI solution. Differences in cost are
therefore generally attributable to:
(a) Inflationary increase
(b) Changes in the scope of the scheme eventually undertaken
under PFI.
NORTHMBRIA HEALTHCARE
NHS TRUSTREDEVELOPMENT
OF HEXHAM
GH
The cost has been updated to reflect changes to the content
of the scheme. Revenue affordability has been maintained.
SOUTH TEES
ACUTE HOSPITALSSINGLE
SITE DEVELOPMENT
At OBC there was no PFI option. The cost shown was for a
traditionally financed public sector project the scope of which
was smaller than the PFI scheme eventually undertaken.
The reasons for the increase include:
Design changes to incorporate new services eg, Spinal
Injuries and also to improve clinical functionality, and inflation.
NEWCASTLE UPON
TYNE HOSPITALS
The capital value reported last year equates to the total
capital value of the revised scheme including VAT.
The latest estimate of capital value to private sector is
£105.3 million which excludes planning contingencies (£4.975
million) and VAT.
SOUTH DURHAM
HEALTH CARE
The increase to the capital value reflects changes to the
content of the scheme. Revenue affordability has been maintained.
Table 4.8.3
INCREASES TO THE CAPITAL COST OF PFI SCHEMES
Trent & Eastern
| A | B | C
| D | E | F
|
| Region | Capital cost at OBC stage
| Capital cost reported last year |
Capital value this year | % change since OBC stage
| % change since last year |
| £m | £m
| £m | |
|
| TRENT REGION | |
| | | |
| Southern Derbyshire Acute Hospitals NHS Trust
| | | 177.0 |
| |
| Queens Medical Centre, Nottingham University Hospital NHS Trust
| 10.6 | 16.6 |
16.6 | 56.6 | 0 |
| Nottingham Healthcare NHS Trust | 13.9
| 12.1 | 12.7 | --8.8
| 4.7 |
| Doncaster and South Humber NHS Trust1 | 11.3
| 11.3 | 11.3 | 0.0
| 0.0 |
| Total Trent | | 40.0
| 217.6 | |
|
Notes:
1 Please note that in 1999-2000 this scheme was reported
as two schemes, but it has now been consolidated into one due
to a combined procurement process.
QUEENS MEDICAL
CENTRE, NOTTINGHAM
UNIVERSITY
Earlier cost estimates had been based on the Public Sector
Comparator. The PFI scope is extended in line with the trusts
capital development plans following private sector innovation.
It now includes a private patients unit, relocation of the maxilofacial
services and retain facilities. This figure includes £1.4
million to be funded at the operational phase by non-SPV sources
and the value of land to be disposed.
| A | B | C
| D | E | F
|
| Region | Capital cost at OBC stage
| Capital cost reported last year |
Capital value this year | % change since OBC stage
| % change since last year |
| £m | £m
| £m | |
|
| EASTERN REGION | |
| | | |
Norfolk & Norwich Health Care NHS Trust
Note 1
| 122.9 | 143.5 | 158.0
| 29 | 10 |
| Luton & Dunstable Hospital NHS Trust Note 2
| 6.9 | 14.7 | 14.7
| 113 | 0 |
| Essex & Herts Community NHS Trust | 11.9
| 11.4 | 10.4 | --13
| --9 |
| East Hertfordshire NHS Trust | 10.0
| 10.0 | 10.0 |
| 0 |
| Total Eastern | | 179.6
| 193.1 | |
|
Comments on any increases over 10 per cent
Note 1: OBC based on a bed compliment of 709 and FBC on 809.
An additional 144 beds have been approved in 1999-2000 bringing
the total compliment to 954.
Note 2: The scope of the original project was extended to
include the provision of staff accommodation at an approximate
capital cost of £7 million. The remaining increase is due
to indexation.
Table 4.8.3
INCREASES TO THE CAPITAL COST OF PFI SCHEMES
London
| A | B | C
| D | E | F
|
| Region | Capital cost at OBC stage
| Capital cost reported last year |
Capital value this year | % change since OBC stage
| % change since last year |
| £m | £m
| £m | |
|
| LONDON REGION | |
| | | |
| Barts & the London NHS Trust | 620.0
| 250.0 | 620.0 | 0.0
| 148.0 |
| University College London Hospitals NHS Trust
| 115.0 | 160.0 | 347.0
| 201.7 | 116.9 |
| Havering Hospitals NHS Trust | 145.6
| | 146.5 | 0.6
| |
| Bromley Hospitals NHS Trust | 112.1
| 117.9 | 117.9 | 5.2
| 0.0 |
| Greenwich Healthcare NHS Trust | 57.1
| 93.0 | 96.1 | 68.3
| 3.3 |
| King's Healthcare NHS Trust | 77.2
| 64.0 | 75.5 | --2.2
| 18.0 |
| Barnet & Chase Farm Hospitals NHS Trust |
54.0 | 54.0 | 54.0
| 0.0 | 0.0 |
| St. George's Healthcare NHS Trust | 31.4
| 40.0 | 45.7 | 45.5
| 14.3 |
| West Middlesex University NHS Trust | 38.2
| 33.0 | 38.2 | 0.0
| 15.8 |
| The Whittington Hospital NHST Trust | 23.0
| | 23.0 | 0.0
| |
| South West London Community NHS Trust | 20.5
| | 20.5 | 0.0
| |
| Newham Healthcare NHS Trust |
| 20.0 | 20.0 |
| 0.0 |
| Oxleas NHS Trust | 14.3 | 15.0
| 14.5 | 1.4 | --3.3
|
| Newham Community Health Services NHS Trust |
12.7 | 14.5 | 12.1
| --4.7 | --16.6 |
| Parkside Health NHS Trust | 11.0
| 11.0 | 11.9 | 8.2
| 8.2 |
| Redbridge Health Care NHS Trust | 7.6
| 10.4 | 10.4 | 37.4
| 0.0 |
| London Total | 1,339.7
| 882.8 | 1,653.3
| | |
Comment on any increases over 10 per cent
BARTS AND
THE LONDON
The capital cost reported last year relates to the earlier
OBC approval which related to the closuse of Barts and the development
of the Royal London. The scheme has reached preferred PFI partner
staus and was working towards FBC. The Turnberg Review of Health
Services in London set out a very different option for the Trust
which included the retention of Barts and additional beds. The
OBC for the current scheme was approved by the RO in February
2000. The approved capital cost was £462 million which included
IM&T costs of £25 million for which a separate OBC is
being prepared. The capital cost identified above is an estimate
of the capital cost to the private sector of the project which
includes an estimate of building price inflation over the 10 year
implementation period of the project shown in the OBC. This may
well decrease if a private sector partner is able to substantially
decrease the implementation period.
UNIVERSITY COLLEGE
HOSPITALS NHS TRUST
The capital cost reported last year relates to the proposed
scheme based on a 1996 tender. The cost of the scheme has increased
due to a number of factorsinflation, additional facilities
with in the scheme. The capital cost indentifed above is an estimate
of the capital cost to the private sector if the project which
includes debt servicing and professional design costs. The PFI
scheme, which came forward in October 1997, differed radically
from the solution identified in the OBC (March 1995) in that it
proposed a single site solution comprising a high rise ward block
linked to a lower rise podium block, rather than a four site solution.
The service and revenue advantages of a single site, all
new build, hopsital offset the high construction costs. The trust
has undertaken several cost reduction exercises and the consortium
price properly reflects the location and type of scheme.
The scheme has changed significantly in scale and cost. Increases
in cost can be broadly attributed to inflation costs, land acquisition
costs and additonal facilities not within original scheme (as
well as debt service costs).
The increased cost is primarily due to some cost increases
on the part of the consortium which have not been passed through
to the NHS through increases in the unitary tariffa practical
demonstration of risk transfer to the private sector.
ST GEORGE'S
HEALTHCARE NHS TRUST
The OBC was produced in 1995 and the capital cost of the
preferred option was £31.4 million.
The capital value this year is the capital cost of the PFI
option at financial close.
The PFI Capital cost does reflect the provision of additonal
clinical accommodation for futre flexibilitytwo shelled
operating theatres and two additional ITU beds over the PSC. The
latter is wholly at the risk of the private sector.
WEST MIDDLESEX
UNIVERSITY HOSPITAL
NHS TRUST
The costs shown above do not include refurbishment of existing
buildings on the site.
REDBRIDGE HEALTHCARE
NHS TRUST
The OBC was approved in February 1997. The scope of the Case
was only for adult acute wards. EMI provision and a PICU. There
have been three key changes in the project scope since OBC approveda
day hospital for older people has been included in agreement with
the (then) North Thames RO in 1998; a change in the clinical model
of care which has meant the inclusion of additional therapy space
and an increase in the floor are of the scheme to ensure that
there will be compliance with Government policy on single sex
segregation. A further driver has been the effect of inflation.
This has increased the cost of the Public Sector Comparator from
£7.4 million at 1997 prices to £11.89 million at 1999
prices.
The capital value reported this year and last year is shown
as being the capital value to the PFI Partner which has stayed
broadly constant at £10.44 million.
Table 4.8.3
INCREASES TO THE CAPITAL COST OF PFI SCHEMES
South East
| A | B | C
| D | E | F
|
| Region | Capital cost at OBC stage
| Capital cost reported last year |
Capital value this year | % change since OBC stage
| % change since last year |
| £m | £m
| £m | £m
| |
| SOUTH EAST REGION | |
| | | |
| Dartford & Gravesham NHS Trust | 96.0
| 94.0 | 94.0 | --2.1
| 0.0 |
| Portsmouth Hospitals NHS Trust1 |
| | 75.0 | |
|
| Oxford Radcliffe Hospitals NHS Trust2 |
| | 71.0 | |
|
| South Buckinghamshire NHS Trust |
| 45.1 | 45.1 |
| 0.0 |
| West Berkshire Priority Care Services NHS Trust (Fairmile Scheme)
| 29.4 | 29.4 | 29.7
| 1.0 | 1.0 |
| Stoke Mandeville Hospital NHS Trust | 23.7
| 23.7 | 23.7 | 0.0
| 0.0 |
| Nutfield Othopaedic Centre NHS Trust | 23.6
| | 23.6 | 0.0
| |
| Sussex Weald & Downs NHS Trust | 17.0
| 17.0 | 19.9 | 17.1
| 17.1 |
| Northampton Community Healthcare NHS Trust |
19.8 | | 19.8 |
0.0 | |
| Southampton Community Health Service NHS Trust
| 16.9 | 18.0 | 18.0
| 6.5 | 0.0 |
| West Berkshire Priority Care Services NHS Trust (Newbury Scheme)
| 18.0 | 18.0 | 18.0
| 0.0 | 0.0 |
| Surrey Hampshire Borders NHS Trust (Farnham Scheme)
| 15.0 | 15.0 | 18.0
| 20.0 | 20.0 |
| Portsmouth Healthcare NHS Trust | 8.3
| 11.0 | 12.0 | 44.6
| 9.1 |
| Thames Gateway (Sheppey Community Hospital)3
| 10.0 | 10.0 | 12.5
| | 25.0 |
| Total South East | |
281.2 | 480.3 |
| |
1 Portsmouth Hospitals have not yet an OBC approved. SOC was approved for £75 million.
2 Oxford Radcliffe Hospitals have not yet had an OBC approved. SOC was approved for £71 million.
|
Comment on any increases over 10 per cent:
Sussex Weald & Downsconstruction cost remains £17
million. £19.9 million includes fees and equipment.
Surrey Hampshire Bordersincrease due to building inflation.
Portsmouth HealthcareChanges since OBC to reflect Patient's
Charter requirements, single sex ward and NSF requirements.
Thames Gateway NHS trustthe increase is due to building
inflation and changes to the output specification from clinical
practice.
Table 4.8.3
INCREASES TO THE CAPITAL COST OF PFI SCHEMES
South West
| A | B | C
| D | E | F
|
| Region | Capital cost at OBC stage
| Capital cost reported last year |
Capital value this year | % change since OBC stage
| % change since last year |
| £m | £m
| £m | |
|
| SOUTH WEST REGION | |
| | | |
| Swindon & Marlborough NHS Trust |
| 96.3 | 96.3 |
| 0.0 |
| Gloucestershire Royal NHS Trust |
| | 32.0 | |
|
| Exeter & District Community Health Service NHS Trust
| | | 10.5 |
| |
| Cornwall Healthcare NHS Trust |
| | 10.2 | |
|
| Total South West | |
96.3 | 149.0 |
| |
West Midlands |
| | | |
|
| B | C
| D | E | F
|
| Region | Capital cost at OBC stage
| Capital cost reported last year |
Capital value this year | % change since OBC stage
| % change since last year |
| £m | £m
| £m | |
|
| WEST MIDLANDS REGION | |
| | | |
| Walsgrave Hospitals NHS Trust | 178.0
| 180.9 | 178.0 | 0.0
| --1.6 |
| Worcester Royal Infirmary NHS Trust | 64.3
| 86.6 | 86.6 | 34.8
| 0.0 |
| Dudley Group of Hospitals NHS Trust | 67.7
| 67.7 | 67.7 | 0.0
| 0.0 |
| Hereford Hospitals NHS Trust | 44.1
| 64.1 | 64.1 | 45.4
| 0.0 |
| City Hospital NHS Trust | 19.1
| | 22.1 | 15.7
| |
| North Staffordshire Combined Healthcare NHS Trust
| 19.1 | 19.2 | 19.2
| 0.5 | 0.0 |
| The Royal Wolverhampton Hospitals NHS Trust |
10.9 | 12.5 | 10.9
| 0.0 | --12.8 |
| Northern Birmingham Mental Health NHS Trust |
15.9 | 12.3 | 12.3
| --22.6 | 0.0 |
| Total West Midlands |
| 443.3 | 460.9 |
| |
Comment on any increases over 10 per cent:
Both Worcester and Hereford's preferred solutions at OBC
included a large amount of refurbishment.
The decrease to the scheme value at Royal Wolverhampton is
because the value given in the last Health Committee report.
Table 4.8.3
INCREASES TO THE CAPITAL COST OF PFI SCHEMES
North West
| A | B | C
| D | E | F
|
| Region | Capital cost at OBC stage
| Capital cost reported last year |
Capital value this year | % change since OBC stage
| % change since last year |
| £m | £m
| £m | £m
| |
| NORTH WEST REGION | |
| | | |
| Central Manchester Healthcare & Manchester Children's NHS Trusts
| | 127.0 | 199.0
| 36.2 | 56.7 |
| South Manchester University Hospitals NHS Trust
| | 65.6 | 65.6
| 0.0 | 0.0 |
| New Schemes | |
| | | |
| Blackburn Hyndburn & Ribble Valley |
| | 70.3 | |
|
| Burnley Health Care NHS Trust |
| | 13.7 | 100.0
| |
| Total North West | |
192.6 | 348.6 |
| |
Comment on any increase over 10 per cent:
Central Manchester/Manchester Childrens Trusts
The scheme costs have increased for the following reasons:
(a) Health Authorities requirements in terms of the finctional
content of the scheme have increased, principally around a 30
per cent increase in children's activity and renal and cardiac
services being brought into the scheme.
(b) There have been unforseen infrastructure and site
problems;
(c) The new costings take into account building inflation,
post SOC.
4.8 LONG TERM
CAPITAL PROJECTS
AND PFI
(v) Could the Department provide data on the revenue
consequences of schemes which have reached financial close and
represent long term contractual commitment over the next 25 hears?
Could the Department provide an update of the Departmental Report
table showing the source and applications of HCHS capital, giving
the outturn position for 1999-2000?
11. The information requested is contained in the following
tables.
|