Select Committee on Environmental Audit Seventh Report



SEVENTH REPORT

The Environmental Audit Committee has agreed to the following Report:—

WATER PRICES AND THE ENVIRONMENT

Summary of recommendations and conclusions[1]

    (a)  The confusing plethora of customer surveys produced throughout the 1999 Periodic Review was not constructive. The Committee recommends that, in future, comprehensive and independent surveys should be commissioned by the DETR. (Paragraph 52)

    (b)  The early statement by the DETR regarding the possible size of the environment programme was helpful and appropriate. However, the Committee recommends that in future, Ministers should respect the role of the independent regulator, Ofwat, to determine price limits and not influence customer and consumer expectations by publicly announcing its own price expectations. (Paragraph 68)

In turn, the Committee recommends that Ofwat seeks to ensure that its own statements do not "demonise" environmental and quality investment by portraying it as the key upward pressure on prices without equally emphasising the customer and public benefits which it delivers. (Paragraph 69)

    (c)  The Environment Agency must develop and strengthen its capacity to assess and demonstrate the benefits of the schemes which it proposes for inclusion in future National Environment Programmes and engage in a more critical examination of their unit costs. (Paragraph 90)

    (d)  The Committee recommends that, in future reviews, the DETR presents a short, overall statement of existing policy to the DETR, Ofwat, Water UK, DWI, Environment Agency and English Nature (the quadripartite members) at the outset. As well as key environmental protection goals this should encompass relevant social and economic policy objectives. (Paragraph 94)

    (e)  The Committee welcomes the Environment Agency's proposal to publish an annual report on the progress of the water companies in implementing the National Environment Programme. The Committee recommends that the Agency also takes steps to monitor and report upon the environmental benefits derived from water company investment. (Paragraph 121)

    (f)  The Committee recommends that a stakeholder forum is held annually to facilitate the presentation and discussion of progress on the delivery of the environmental and quality programme. (Paragraph 122)

    (g)  The Committee believes that roller coaster prices confuse consumers as to whether their valuable water resources are being carefully managed by the industry and how far they themselves should be bothering about water efficiency. As metering becomes more widespread, there will be an increasing price incentive to be water-efficient and clear pricing signals will be needed. (Paragraph 128)

    (h)  The Director should seek to ensure that the Final Determinations document makes clear how far changes in key factors such as the cost of capital (during the review process), have influenced the final outcome. (Paragraph 139)

    (i)  The 1999 Periodic Review provides a satisfactory outcome for the environment but there is no room for complacency as we face new, future quality obligations and uncertain water resource constraints. (Paragraph 142)

    (j)  The Periodic Review is an effective mechanism for dealing with point source environmental problems caused by water companies. However, the Committee is concerned that the DETR and the Environment Agency are disproportionately relying on the Periodic Review mechanism and the water companies as the key means to achieve compliance with water quality and environmental protection objectives and not sufficiently tackling pollution from diffuse sources. (Paragraph 159)

    (k)  The Committee believes that the current Periodic Review Process, operated by Ofwat, provides a fair and open system for determining water price limits and thus provides valuable incentives for water companies to reduce operating costs and to search for innovative ways of designing and operating new schemes. However, the Committee recommends that the DETR, companies and the regulators ensure that the five year investment programmes of the Periodic Review are set in a clear, comprehensive framework of longer-term policies and goals including those relating to water resources and environmental quality and serviceability goals. In turn, these five year periods of investment should contribute to the achievement of these goals. (Paragraph 179)

    (l)  The Committee is not satisfied that Ofwat's "no deterioration" approach to the maintenance and renewal of underground assets (sewers and water mains) is a logical or acceptable means of assessing the amount of investment which water companies need to meet these requirements. The Committee believes that this approach has amounted to intellectual neglect of this important problem. (Paragraph 208)

The Committee therefore very much supports the initiative of the DETR, and the agreement by Ofwat, to develop a new approach. This approach should be forward looking and should enable companies to adequately prepare to renew and repair the cohorts of sewers and mains which will come up for renewal/rehabilitation simultaneously as a result of historical peaks in building activity. (Paragraph 209)

    (m)  The Director General of Ofwat should be directly accountable for ensuring that Ofwat makes a positive contribution to the Government's sustainability agenda. (Paragraph 220)

    (n)  We believe that companies do not have sufficient incentives to promote water efficiency and that there would be merit in investigating the feasibility of setting company-specific targets for domestic water use, once a robust methodology for efficiency measurement has been agreed. (Paragraph 225)

    (o)  The Government should spell out its long term aims for leakage reduction in the context of water resource policy and clarify in particular whether it wants companies to reduce leakage below their own economic levels. (Paragraph 231)

Introduction

1. Water is a necessity of life. It is also a resource which needs to be carefully managed to ensure that we, as consumers, can enjoy a continued supply whilst our environment and health are protected. As consumers we pay for such safeguards, and maximum water prices are set every five years by the Director General of the Office of Water Services (Ofwat)—the industry's economic regulator in England and Wales.[2] This process is known as the Periodic Review. The 1999 Periodic Review (PR 99) made provision for a £5.2 billion environmental improvement programme and means that by 2004-5 the average household customer will pay about 12% less (in real terms) for their water.[3]

2. PR 99 was the second review to be undertaken by Ofwat since the water industry was privatised in 1989. Both Ofwat and the Department for the Environment, Transport and Regions (DETR) have conducted their own reviews of the process over the years. However, the Committee felt that an independent parliamentary review was both necessary and timely, given this year's change of Director General at Ofwat and the prospect of a Water Bill in the next parliamentary session.

3. In the run up to the publication of the water price limits for 2000-2005 (the Final Determinations), the debate on the balance to be struck between price cuts and environmental investment was highly charged. There was an open exchange of claims and counter claims by Ofwat, the DETR, the Environment Agency, water companies and non-governmental organisations (NGOs) about what could and should be achieved in PR 99. The Committee accepts that such open debate is more constructive and transparent than whisperings behind closed doors. However, it left us as parliamentarians, and similarly the wider public, uncertain as to whether the 1999 Review had really been successful. One would expect a cut in bills and the delivery of a sizeable environment programme to silence most critics but the simmering unease which continued after the announcement of the 2000-2005 price limits suggested that there were outstanding issues which needed to be addressed.

4. We focussed our inquiry on the extent to which the process and outcome of PR 99 contributed to environmental protection and sustainable development. In doing so we considered the Review process's mechanisms for: arriving at the final price limits, considering the obligations which they are intended to fund, monitoring the implementation of the water companies' contribution to the Environment Agency's National Environment Programme (NEP), and accommodating new obligations which might arise before the next price review in 2005.

5. We did not seek to challenge the information which formed the basis of Ofwat's final determinations but examined the principles upon which the review process itself was conducted and the outcomes which it sought to deliver.

6. In the interests of time, oral evidence sessions were restricted to the main regulators involved in the periodic review process. Oral evidence was given by: the Minister for the Environment, the Rt Hon Michael Meacher MP, Sir Ian Byatt (then Director General of Ofwat), Mr Michael Rouse (Chief Drinking Water Inspector) and representatives from the Environment Agency and Water UK. However, written evidence was received from a wide spectrum of organisations including those representing consumer, engineering, and environmental interests.[4]

7. We were particularly grateful for the advice and insights of our special advisers for this inquiry—Mr Paul Herrington, Department of Economics, University of Leicester, and Dr Neil Summerton, Oxford Centre for the Environment, Ethics and Society, Mansfield College, Oxford and the Oxford Water Research Centre, University of Oxford. We would also like to thank Three Valleys Water, GU Partnership, and North West Water Ltd for giving us the opportunity

to see their operations at first hand. This greatly enhanced our understanding of the Periodic Review process and its impacts.[5]

The Privatised Water Industry of England and Wales

8. It is important to consider the process and outcome of the 1999 Periodic Review (PR 99) in the context of the previous price reviews which have taken place and the evolution of the water industry following privatisation.

Regulation

9. The current system of regulation of the privatised water industry in England and Wales was established by the Water Act 1989. Since privatisation, the industry's fortunes have largely been dictated by the economic regulation of the industry by Ofwat, which from August 1989 to July 2000 was headed by Director General ("the Director") Sir Ian Byatt. Mr Philip Fletcher took over the post in August 2000 and will no doubt be a key influence on the industry's future fortunes.

10. The Director's duties are set out in Section 2 of the Water Industry Act 1991 and require that the Director acts in a way which he considers is best calculated to ensure that:

11. The Director also has to ensure, in the interests of customers, that no undue preference is shown and there is no undue discrimination in the way in which companies fix and recover charges.[6] This means that a customer's bill should, in general terms, reflect the costs which the customer imposes on the water and sewerage systems for a supply of clean water, the disposal of dirty water and the draining of surface water.[7]

12. Other responsibilities include: promoting economy and efficiency, enforcing the duty placed on water companies by the Environment Act 1995 to promote the efficient use of water by customers, facilitating competition between suppliers and potential suppliers and ensuring that a framework exists in which competition can develop, enforcing company licences and limiting charges for water.

13. The Director also has environmental duties (set out in Section 3 of the Water Industry Act 1991). However, these are rather narrow, referring mainly to the conservation of: flora and fauna, natural features, sites, buildings and the protection of Sites of Special Scientific Interest (SSSIs). Water quality standards in inland, estuarial and coastal waters are regulated and enforced by the Environment Agency of England and Wales. Drinking water quality standards are set by The Secretary of State for the Environment, Transport and Regions which are enforced by the Drinking Water Inspectorate (See paragraph 32).

Periodic Reviews—background

14. Sir Ian Byatt chose to give effect to his Director's duties by setting maximum price limits in the Periodic Review process in the manner described in paragraphs 37-42. Initially, company licences required that a major review of price limits took place after ten years, or after five if the company or the Director so wished. Both the Secretary of State in 1989 and the Director in 1994 set price limits for ten years ahead. However, in practice, Ofwat found that a gap of ten years between reviews was too long despite the long-term nature of the water industry[8] and that all the

factors influencing prices needed to be reviewed every five years in the light of companies' performance.

15. The construction price index is an example of a key factor which can greatly influence the context in which the water companies operate. The Government first set price limits in 1989 when construction prices were at a peak. A later dip meant that water companies found their investment programmes were costing less than expected, and indeed than allowed for, in the price limits. For example, North West Water was estimated to have had its costs cut by £94 million in this way.[9]

16. Ofwat felt that a five-year time-frame preserved adequate incentives whilst allowing a swifter distribution of benefits to customers.[10] Thus, in 1996 Sir Ian announced that he would be re-setting price limits for the second five year period in 1999. Water company licences have since been modified (with effect from April 2000) so that price reviews now take place automatically at five-yearly intervals.[11] Prices for 2000-2005 were set in November 1999, taking effect in April 2000.

17. Ofwat sets price limits which restrict the amount of revenue that water companies can raise according to a formula RPI+K+U. The RPI is the Retail Price Index and accounts for inflation. U is any underspend carried over from previous years. K is the amount (positive or negative) by which charges are allowed to rise each year above inflation (or if negative, must fall below inflation). The K factors are set individually for each company. In the interests of their shareholders, companies therefore have the incentive to reduce costs by providing services to customers more economically than the Director has assumed would be possible for them. If they are successful, savings can be passed to customers at the next price review in the form of lower prices, or a larger quality/environmental programme, or a mixture of the two. In this way, the regulatory system is intended to give the water companies the incentive to be efficient.

18. At privatisation, the then Secretary of State for the Environment, Nicholas Ridley, had to make assumptions about the cost of capital, dividend yields and expected costs and outputs, all based upon the company information made available. In addition, the Government recognised that a large programme of investment would be required to meet environmental and water quality standards, in particular the Urban Waste Water Treatment Directive, and offered a "green dowry" of £1.1 billion for upgrading the industry's assets and a £5 billion debt write-off.[12] With this information, and his own assumptions about future efficiency gains, the Secretary of State fixed each company's K-values for a decade ahead. It soon became apparent that the companies were in better shape than had seemed and, under pressure from Ofwat, the companies raised prices less than the maximum which the K-values permitted.

19. In the 1994 Periodic Review, Ofwat concluded that the companies could increase their efficiency at a faster rate than they had achieved since privatisation and than they had in the pre-privatisation era. However, even with these tougher assumptions, Sir Ian told the Committee that it "turned out that they could do better than that".[13] They quickly showed out-performance on operating and capital costs and there was clearly some extra efficiency which could be passed to customers.

20. After privatisation profits started to soar in real terms[14]—between 1990/91 and 1997/8 the pre-tax profits of the ten water and sewerage companies increased by 147% [15] at a time when customers faced continual price rises. Water and sewerage prices rose respectively by 36% and 42% from 1988-1998 (in real terms)[16] with the bulk of the increase occurring in the period up to 1994-1995.[17] The industry faced a public outcry in relation to high levels of directors' pay and profits, and Sir Ian came in for some criticism for being too soft on the industry. However, Sir Ian told the Committee "I think in the circumstances we made perfectly good estimates and at the time people did not disagree with those. It was only when the numbers started to show that the water companies could do better that I observed then there were some benefits to be had at the next review, and I believe those benefits arose because the full power of the incentive regime started to operate in that period".[18]

21. Sir Ian felt that the figures demonstrated this. In 1990-95, on average across the companies, prices went up by 5% a year above the rate of inflation and 1.5% from 1995-2000 —much slower but still going up.[19] These increases did not escape customers' notice—complaints about charges and billing have dominated and accounted for over half of all complaints received by Ofwat Customer Service Committees (CSCs) in the last decade (1990-2000). Not surprisingly, 1999-2000 was the only year in the last decade when the proportion of charging complaints fell—the year when price cuts were announced.[20]

22. Sir Ian told the Committee that water company efficiencies had been seen in both operating expenditure and on capital expenditure.[21] The main controllable costs for companies are: manpower, energy and chemicals, and these are where the main efficiencies can be made.[22] Sir Ian explained that companies had felt they could operate with less staff and by giving junior staff much more flexibility in carrying out their work many operations could be carried out more cheaply. On the capital side, Sir Ian felt that because of some innovative solutions and increasingly more effective procurement and planning, companies were now able to carry out their obligations with more streamlined methods.[23]

  23. PR 99 has assumed that the companies can continue to increase their efficiency. Ofwat identified past and future efficiency savings which amount to some £60 per year per household customer,[24] allocating £30 towards improvements in drinking water and environmental quality and £30 to lower bills.[25] Sir Ian advised the Committee that the efficiencies had come later in the water industry than the other utilities but that they were now coming.[26] The Environment Minister, Mr Meacher, felt that the determinations of PR 99 were "tight, challenging but realisable".[27] However, Water UK described PR 99 as a "tough settlement" and the one-off price cuts as a "short term fix which put at risk the high level of service which companies currently deliver".[28]

24. Just before the final determinations were published, Water UK warned that one in four jobs in the water industry could go (amounting to some 9,000[29]) as a direct result of the draft price proposals. It warned that companies were being driven towards job losses in order to meet efficiency targets that were neither realistic nor practical.[30] So far significant job cuts have been announced by Severn Trent, Anglian and Yorkshire Water.[31] Both the Chief Drinking Water Inspector, Mr Michael Rouse and the Environment Agency have publicly warned companies that reductions in operational personnel must not result in the "cutting of corners" in relation to maintaining drinking water quality or meeting their statutory duties relating to the environment.[32] The regulators will clearly be watching to ensure that health and safety, and the quality of monitoring arrangements are not compromised.

25. Two water-only companies, Mid Kent Water and Sutton and East Surrey Water, appealed to Ofwat for referral of their determinations to the Competition Commission. The Competition Commission has since revised their price limits, resulting in slightly higher average K-values for 2000-2005 than proposed by Ofwat but still a far cry from those put forward in the companies' business plans.[33] The Commission determined that a number of company-specific factors affected both the costs allowed by Ofwat and the scope for efficiencies. In particular, the Commission took a different approach from Ofwat on: the treatment of depreciation, the scope for efficiencies in capital programmes, and the number of customers opting for a meter.[34] However, the Commission did endorse Ofwat's approach and conclusions on the cost of capital and Ofwat's assessment of the scope to make efficiency savings. Ofwat has undertaken to consider the Competition Commission findings for the 2004 Periodic Review.

26. Both Ofwat and the Environment Agency took the view that as only two out of the 23 water companies had appealed to the Competition Commission the inference was that other companies believed they were adequately financed to discharge their functions.[35] It is interesting to note that when the 1994 price limits were announced one commentator noted that "the meek acceptance of the regulator's decision by all the water companies but one [South West Water] should encourage outsiders to smell a rat".[36]

27. However, Water UK told the Committee that for many companies the decision not to go to the Competition Commission had not been clear cut—a number had taken the view that the alternatives of actually getting on with the job and concentrating on trying to deliver was a better use of their management resources.[37] In addition, companies are required to refer the whole determination, they cannot pick out certain elements of the package which they are unhappy with. Thus, they have to weigh up whether their concerns warrant an investigation of the whole determination especially as industry-wide issues such as the cost of capital can only be looked at on a specific company basis, not as a single issue across the companies. Ofwat fully endorses this approach maintaining that the Competition Commission has to review its entire determination under the same legal duties as the regulator and therefore has to take into account the same range of factors.[38]

28. The industry now finds itself with increased risk, fluctuating share prices and in some cases companies whose value on the Stock Exchange is now less than the sum of their individual assets.[39] In the face of ever more restrictive economic regulation, the industry has been exploring new avenues for restructuring. A recent example was the proposal by Kelda to become a mutual—separating asset ownership from operations. As yet no such scheme has been endorsed by Ofwat which, like the DETR and DWI, remains concerned that such proposals to date have not made clear how statutory responsibilities and liabilities would be distributed between the mutual and the operating company. Ofwat has made it clear that it will be looking

for any restructuring proposal to offer benefits to customers and maintain incentives for efficiency.[40]

The 1999 Periodic Review Process

Roles and responsibilities

Ministers

  29. The role of Ministers is to set the policy framework within which the Periodic Review takes place.[41] This framework is soon to be revised by the forthcoming Water Bill which is expected to implement new measures agreed as part of the Government's Utilities Review.[42] On the advice of the Environment Agency and the DWI, Ministers set the size and range of the environmental and drinking water quality improvement programmes that the industry will have to deliver over the Review's five year period. The National Assembly for Wales (NAW) is responsible for setting the environmental programme for the Welsh water companies, D_r Cymru and Dee Valley Water Ltd, and has an interest in the Welsh operations of Severn Trent plc. The NAW was created towards the end of the PR 99 process in May 1999. During the Review, the DETR operated in close liaison with officials from the Welsh Office and thereafter with the (same) officials serving the National Assembly for Wales.[43]

Ofwat

  30. Once Ministers have determined their policy objectives, it is a matter for the Director of Ofwat to decide the economic conditions, ie the price limits which need to be set in order to achieve them bearing in mind the full range of his own statutory duties (see paras 10-13). Sir Ian told us that in fulfilling his duty to protect customers and to promote economy and efficiency, Ofwat draws Ministers' attention to the implications for customers' bills of the proposed environmental and quality programmes.[44] The process of conducting the Periodic Review is also a matter for the Director.

The Environment Agency for England and Wales

  31. The Environment Agency has a wide range of statutory duties relating to the environment but those most relevant to the periodic review process are to: prevent or minimise or remedy and mitigate the effects of environmental pollution, secure the proper use of water resources (ie to achieve an appropriate balance between the population's needs and the environment[45]) to promote conservation and water-related recreation. The Agency sees its role in the Review as identifying the "environmental problems" caused by water companies and advising Ministers on the relative priority of solving the problems.[46]

The Drinking Water Inspectorate (DWI)

  32. The Drinking Water Inspectorate (DWI) enforces drinking water standards. In administrative and financial terms the DWI is a division within the DETR but it operates as an independent inspectorate. The Secretary of State's and National Assembly for Wales' powers of enforcement and prosecution have been delegated to the Inspectorate.[47]

The Companies

  33. Water companies must properly carry out their functions and deliver the environmental and quality programmes within the price limits set by the Director.

The Quadripartite process

  34. For the 1994 review the DETR set up an informal "quadripartite process" which was used again in the 1999 review. This process seeks to support the Periodic Review process by facilitating the timely flow of information between the various regulators and the industry.[48] Quadripartite meetings are chaired by DETR officials and the participants are: Ofwat, the Environment Agency, Water UK representing the water companies, and the Drinking Water Inspectorate. The DETR admitted that the setting up of such a quadripartite group was "intended to help ensure the inevitable tensions involved were creative and constructive".[49]

35. In 1998, after some pressure, DETR also invited English Nature to join the quadripartite discussions in recognition of English Nature's statutory duties relating to the protection and management of SSSIs. Designated wildlife sites such as SSSIs can be damaged by water company abstractions and sewage discharges and both water companies and the Director have statutory duties relating to nature conservation. English Nature's equivalent in Wales, the Countryside Council for Wales, was established mid-way during the review process and did not directly input to the quadripartite discussions.

36. Michael Meacher told the Committee that he expected that the new independent consumer council for water, which the Government has proposed, would, in the future, join the quadripartite process.[50]

The timetable and inputs

37. Both the 1994 and 1999 Periodic Reviews were conducted over a period of three years. The timetable of key stages for PR 99 is set out in Figure 1 overleaf.

38. The Director consulted on the timetable for the 1999 Periodic Review process in February 1997 by means of a letter to Managing Directors (MD 124). The DETR however, did not put forward proposals on how the quadripartite process should be handled until July 1997, after Ofwat had completed its consultation on the timetable.[51] Water UK was concerned that "Ofwat set the timetable and others had difficulty keeping up".[52] However, the industry body did accept that in principle the timetable seemed reasonable. Sir Ian's view was that as the "water companies did not like the answers [so] perhaps, that is why they say they did not like the process".[53]

39. The Periodic Review is a complex and necessarily iterative process which needs to be efficiently planned and managed. It is therefore important that the Director establishes a clear forward programme with sufficient consultation. The Committee believes that this was achieved in the 1999 Periodic Review, despite Water UK's concerns, and that all relevant parties were given the opportunity to make the case for an alternative timetable if necessary.

40. From early 1997 to late 1998 Ofwat issued consultation papers on a number of topics to establish a framework for the review and to highlight key financial, procedural and technical issues. At the same time Ofwat embarked on a major information collection exercise and companies were required to make a number of submissions on quality costing, supply and demand forecasts, asset condition and unit costs. Ofwat then looked at costed options and published Prospects for Prices in October 1998 which set out in quantitative terms what the options were and identified the key areas where guidance from the DETR and Environment Agency was needed.

41. Ministers set out their decisions on the environment and quality programme in their guidance to the Director in Raising the Quality (September 1998). This guidance was based on advice from the Environment Agency and Drinking Water Inspectorate and in the light of the Director's estimates of the potential impacts on customer's bills.[54] The companies submitted their final business plans to Ofwat in April 1999. Ofwat then consulted on draft price limits in July 1999 and issued the final determinations in November 1999.

42. The process is necessarily iterative because the companies cannot estimate costs nor Ofwat determine the necessary impact on bills until there is some certainty about the environment and quality obligations which need to be delivered. In turn, the Government is not in a position to confirm the scope of this programme until it has an idea of the costs involved, and thus the possible implications for prices.

Assessing customer needs

43. One of the Director's roles is to protect and represent the interests of customers. He therefore needs to have a good idea of what the customer wants. During the course of the review Ofwat and other interested parties carried out a variety of customer surveys. Although these differed widely in their approach they generally sought to investigate customer attitudes and preferences for improvements to drinking water and the water environment, and the extent to which they would be willing to pay more or forgo savings in the annual bills to fund improvements in services.

44. Water UK told the Committee that it had commissioned the largest surveys in its history and had sought to agree individual questions with Ofwat Customer Service Committees and the Environment Agency so that the main parties would accept the findings.[55] The industry's research indicated that customers' priorities for improvements were: reducing leakage beyond current target levels, minimising the risk of foul water flooding and investing to increase supply reliability. Customers were asked to indicate whether they would like varying efficiency savings eg £5, £10, £20 to come to them as a bill reduction or to have it spent on some service improvement. As the amount of money increased people increasingly opted for the 50/50 option which split savings equally between a bill reduction and service improvement.

45. Each survey came up with slightly differing rankings of customers' priorities. The Environment Agency's survey found that 69% of respondents were willing to pay more for cleaner rivers, coastal waters and to ensure an adequate supply of water whilst the DWI's research indicated that ensuring safe, clean drinking water was the greatest priority for customers (79%), compared with improving the reliability of supply (14%) and reducing levels of river pollution (6%). The DETR found that ensuring a reliable supply of water had highest priority for consumers and more than half (53%) of respondents were prepared to pay more for their priority improvements. However this "willingness-to-pay" varied according to income and the level of the current water bill.

46. Overall it can be said that the DETR, DWI, water companies and the Environment Agency all found that customers were not looking exclusively for the maximum possible reduction in water prices if the implication was that important environmental and quality benefits could not be secured. In Raising the Quality, the DETR concluded that in general most customers would probably prefer lower bills in real terms and for water quality and environmental improvements to be funded from efficiency savings by the water companies and a lower rate of return on capital.[56]

Figure 1: Milestones in the 1999 Periodic Review Process

1996

October

Ofwat - announced Review

1997

June/July

Ofwat invited views on its approach to setting price limits, the business planning process and its information requirements.

1998

February

Ofwat set out its decisions on the approach to the review and a detailed specification of its information requirements.


April

The Director - Ofwat - wrote to Ministers indicating the possible costs of the programmes and sought policy guidance


May

The Environment Agency submitted its proposals to Government regarding the National Environment Programme for Water Companies 2000-20005 in A Price Worth Paying.


September

Companies provided submissions to Ofwat setting out their views of the costs of environmental and drinking water obligations.


(Was expected July)

Ministers set out their guidance on the scope and timing of national and regional environmental programmes in Raising the Quality.


October

Ofwat published its approach to the review and set out the Prospects for Prices in April 2000.

1999

March

Minister announced environmental improvement programmes to be included in company business plans for 2000-05.


April

Companies submitted their Business Plans setting out their requirements for future price limits.


July

Ofwat published draft determinations and sought representations from key stakeholders.


November

Ministers issued final guidance on the water quality and environmental programme.


25 November

Ofwat announced final determinations of price limits.

2000

25 January

Ofwat referred appeals to the Competition Commission.


March

Companies provided their Monitoring Plan 2000-2005, to Ofwat, setting out how they would deliver outputs within the price limits set by the Director.


1 April

New price limits came into effect, as published in charges schemes.

47. Ofwat's findings were out of step with the other research. Ofwat's National Customer Council (ONCC) conducted a survey of a sample of people in four regions in early 1999 which found that customers were inclined towards price reductions rather than service improvements. It also carried out research on 48 low income customers. This small sample has been criticised but the ONCC maintains that the survey was designed to fill a gap in the evidence.[57] However, Water UK's evidence to the Committee indicates that its own general national survey had a larger sample of low income customers and the industry body believes that the small sample size in the ONCC study lead to unreliable conclusions.[58] Mr Meacher's view was that it was not satisfactory to have "these tiny unrepresentative samples peddled as though they were an indication of genuine public opinion".[59]

48. From this array of surveys, Sir Ian felt that he had enough material to proceed with his early price estimates in Prospects for Prices. He took the message that customers did not want to see lower bills if it meant lower quality.[60] He also felt that customers had expressed a preference for bills not to rise above levels in 1998 and did not wish to see significant rises after any initial reduction.[61] However, Water UK believed that customers had been "cheated" by the regulator who had "largely ignored their opinions"[62] The industry clearly did not feel that the results of the surveys necessitated the large one off cuts which PR 99 secured for customers. However, its own national survey indicated that on average customers would like to see approximately half of possible efficiency savings used to reduce their bills.[63] This is exactly what PR 99 did.

49. Sir Ian cautioned that it was important to consider how the questions had been asked and he regretted that some surveys had not indicated to customers that they could have both higher quality and lower bills. [64] This attitude has tended to give the impression that Ofwat only rates its own surveys and has led to calls for an independent survey of customers from Surfers Against Sewage (SAS).[65] Ofwat has in the past considered this option however, Sir Ian was keen to see the water companies take the responsibility for asking their customers what they wanted.

50. The Committee agrees that, like any sensible company, water companies should be constantly undertaking the necessary market research to assess their customers' views and needs. However, such work does not obviate the need for a comprehensive and independent survey of public opinion focussed on the particular issues relevant to a given Periodic Review.

51. The DETR seemed to take a 'more the merrier' approach to customer surveys expressing the view that "...it is helpful to have a variety of surveys conducted from different perspectives. Each sheds useful light on the process".[66] Water UK was "not convinced" of the need for an independent customer survey to inform future reviews.[67] It suggested that a framework survey could be developed with accredited questions which companies and regulators could then adapt for their own circumstances.[68] However, it is not evident that this would aid the situation bearing in mind that Ofwat issued guidance to companies during PR 99 on the principles of good practice in surveying customer views and also established a process for Customer Service Committees (CSCs) to assess and advise the Director on companies' customer consultation strategies.[69]

52. The confusing plethora of customer surveys produced throughout the 1999 Periodic Review was not constructive. The Committee recommends that, in future, comprehensive and independent surveys should be commissioned by the DETR. These should seek to establish the public's expectations as water customers and citizens within the five year Periodic Review timescale (including their attitudes to and preferences for environmental improvements). They should also seek views on longer term policies which impinge on the environment. The structure and content of this research should be discussed within the quadripartite group so that there is common ownership of the survey and its findings.

Determining the size and nature of the Environment Programme

53. Water company activities have the potential to impact greatly upon the environment. The basic functions of water abstraction and wastewater treatment influence river, bathing and drinking water. Their activities also impact upon protected habitats and biodiversity, since water companies manage hundreds of Sites of Special Scientific Interest (SSSIs). Thus, the definition of the environment and quality investment programme is a key element of the periodic review process.

54. Mr Meacher told the Committee that the Government's decision on the size of the environmental and water quality improvement programme was made on the basis of the Environment Agency's advice about environmental priorities. It was then prioritised on the basis of advice from Ofwat according to the likely impact on bills.[70]

55. In May 1998, the Environment Agency submitted its proposals to Government regarding the 2000-2005 National Environment Programme for water companies in the document A Price Worth Paying.[71] This set out the actions which it felt were necessary for significant progress to be made towards an environment in 2005 in which: sewage discharges are properly treated, sewages sludges sustainably recycled, no sewage solids foul river banks or beaches, clean rivers and beaches stay unpolluted, the most precious wildlife sites are protected, and rivers are both healthy for wildlife and provide good clean water supplies in a changing climate as well as being able to be used by future generations for sport, leisure and recreation.

56. In June 1998, the DWI issued advice to companies on the information which they needed to provide to the Inspectorate if they wished to seek the Inspectorate's technical support for the inclusion of proposals to Ofwat relating to new works to improve drinking water quality.[72]

57. In the light of the Agency's proposals, the advice of the DWI, and initial data from Ofwat, Ministers issued guidance in September 1998 on the environmental and quality objectives that were to be achieved in the period 2000-05.[73] They highlighted the fact that water companies had achieved larger efficiency gains than Ofwat had allowed for over the period 1995-2000 and that these savings were "available to be reflected in lower prices" for the following 5-year period, 2000-2005. Ministers had therefore sought to define the programme so that there was scope for significant real cuts in average prices in 2000-05 compared to 1999-2000 levels and to allow the quality regulators to implement a major programme of environmental improvement.[74]

58. Ministers felt that the case for investment in quality was exceptionally strong, especially as much of it was mandatory, but equally that water customers had faced very substantial increases in prices since 1989 and that it was neither reasonable or necessary to expect them to face further substantial real increases in the next quinquennium.[75] It was made clear that, depending on the Director's further decisions, the substantial benefits of a lower cost of capital and past and future efficiency improvements would be shared between further quality improvements and lower prices.[76]

59. No estimate of a potential price cut was referred to in the guidance but Ministers estimated that the proposed five-year programme represented investment of £8.0 to £8.5 billion.[77]

Early predictions

60. A number of witnesses expressed concern that it seemed from the outset of PR 99 that Ofwat and DETR were working to a predetermined outcome—significant price cuts for the customer—without any regard at that stage for the potential scale of the environmental protection and quality investment programme which would be needed.[78] They felt that this introduced an unnecessary and unhelpful bias to the start of the process which may have also influenced the customer surveys which were carried out.

61. The Director first indicated that he was considering price reductions in October 1996 when he announced his intention to undertake a price review. He commented that water companies were reporting "substantial efficiency savings" which Ofwat would take full account of at the next Review in order that they could be passed on to customers.[79] Sir Ian reiterated this point in February 1997, in a letter to water company Managing Directors (MD 124), making it clear that the savings would be passed on in "an initial downward adjustment of real prices". The Director provided no figures himself but there was subsequent speculation in the press, often based on City analysts' views. Confirming that a price cut was to be the starting point of the calculations, the Director introduced an adjustment for a permanent percentage reduction in prices from 2000-1 to reflect efficiency gains achieved by the company. This was known as 'P'.

62. At the time of the Director General's initial statements, the Environment Agency issued an open letter to a wide range of organisations. This indicated the Agency's concern that there appeared to be an element of pre-judging the outcome, based upon the assumption that the benefit to the customer/consumer could only be in the form of a price reduction and that they gained no benefit at all from a cleaner environment.[80] In hindsight, the Agency told the Committee that countering these early statements actually furthered its cause because it helped to highlight to Ministers that there was scope for both price cuts and a substantial environment programme.[81]

63. Ofwat has continually cited the environmental investment programme as the variable which pushes up prices rather than seeking to ensure that the customer understands that such investment is vital to the services they expect and for necessary environmental improvement measures. In Prospects for Prices—a consultation paper on strategic issues affecting future water bills—Sir Ian Byatt pointed out that if it had not been for the massive capital cost of implementing quality obligations, primarily the Urban Waste Water Treatment Directive, prices would have been falling since1995.[82] The Director also consistently made the point throughout the review process that if it were not for the continuing investment in protecting the environment, the price cut achieved by 2004-05 could have been significantly greater.[83]

64. In April 1998, Ofwat published a paper on the efficiency of the companies which contained initial estimates of the scope for reducing costs through greater efficiency over the period of the new price limits.[84] In the DETR's supplementary evidence to the Committee, the Department states that on the basis of the information available from Ofwat by September 1998, including the initial costings and efficiency estimates, it estimated that the environmental programme proposed in Raising the Quality could be delivered with an initial average real terms price cut of around 10%.

65. In its written evidence to the Committee, Ofwat concurs that the Government stated this expectation.[85] However, although this figure appeared in the press in September 1998 it did not appear in any DETR documents or press releases until March 1999 when Michael Meacher announced that an £8 billion water quality improvement plan could be delivered with an average price cut of 10%.[86]

66. Ofwat published Prospects for Prices in October 1998, prior to the DETR's March 1999 press release. Here the Director reiterated his belief that the water industry's large capital programme "could now be financed within a framework of falling prices".[87] He also made it clear that he felt that a substantial environment programme would make it difficult to achieve substantial price cuts in the medium term—bills would fall initially but would then have to rise again, although he estimated that the average household bill in 2004-05 could still remain 2% to12% below the expected level in 1999/20 (ie the last year of the previous pricing period).[88] DETR's 10% estimate was therefore at the upper end of this range and represented a challenging target for the regulator to achieve. The Committee voiced its concerns to Mr Meacher that he had effectively "boxed in" the regulator. However, the Minister denied this claiming that Sir Ian would have been perfectly entitled to disagree with Ministers based on the economic facts.[89]

67. We would expect Ministers to provide estimates of the cost of the environmental and quality programme which they propose. It is also reasonable for Ministers to make clear, to the regulator, their political wish to deliver both price cuts and a comprehensive environmental programme and to indicate that their proposed programme had been designed to allow this. However, ultimately, the actual degree of price cuts is a matter for the independent economic regulator, Ofwat. The DETR did not make this clear in its March 1999 press release and neither did it justify its assessment that a 10% price cut was possible.

68. The early statement by the DETR regarding the possible size of the environment programme was helpful and appropriate. However, the Committee recommends that in future Ministers should respect the role of the independent regulator, Ofwat, to determine price limits and not influence customer and public expectations by publicly announcing its own price expectations.

69. In turn, the Committee recommends that Ofwat seeks to ensure that its own statements do not "demonise" environmental and quality investment by portraying it as the key upward pressure on prices without equally emphasising the customer and public benefits which it delivers.

Prioritising the Environment Programme

70. Once DETR Ministers had agreed the overall shape and size of the environment and quality programme it was up to the Environment Agency, the DWI and Ofwat to cost and prioritise a more detailed programme. This would then allow Ministers to take an initial view on the appropriate balance between what the DETR described as the "level of environmental ambition" in each company and the consequent effect on bills.[90]

71. The Agency felt that experience of the previous review had shown the importance of establishing early clear guidance on all the separate and different reasons investment might be required to achieve improved environmental quality. In 1997, guidelines were developed and issued in consultation with Water UK, DETR and Ofwat specifying how each cause of environmental concern should be defined and assessed. Periodically these guidelines were updated, modified and then reissued to all participants.[91] In PR 99, for the first time, the Environment Agency developed a comprehensive list of the existing environmental problems generated by water companies and maintained a rolling spreadsheet of all the main sites with problems to make sure that they were prioritised and identified and could be carried forward in subsequent reviews.[92]

72. In March 1999, the Agency published these detailed, company-specific spreadsheets which had been approved by Ministers and which contained lists of proposed investment schemes for each company. These spreadsheets were drawn up after collaboration amongst the Departments, Ofwat, and the Environment Agency. The Agency had offered advice on the prioritisation of the schemes where there was an element of discretion (EU obligations were already driven by clear commitments and timings), Ofwat advised on the implications for bills in each company and the DWI issued Letters of Support for drinking water quality improvement schemes to be included in water company Business Plans.

73. In the main, those investment schemes where there was an element of discretion were those relating to River Quality Objectives. The Agency sought to prioritise such schemes by using a multi-attribute-technique (MAT) for assessing the relative benefits. A number of different characteristics were given weightings and then a total score could be calculated for each scheme to allow comparison. The Agency developed the weighting factors and the scores using focus groups and statutory advisory committees and published the findings.[93] The Agency did not use this method to indicate what should or should not proceed but to enable it to prioritise.

74. The Agency then sought to take an integrated approach and consider what discretionary elements should be considered at each site bearing in mind the range of non-discretionary works that were required. A residue of discretionary elements, not matched to mandatory works, then remained in a prioritised list. The Agency describes this final prioritisation and timetabling as a balance between "achieving EU timetables, early significant environmental improvement, achieving integrated solutions and the practicality of delivery".[94]

75. The Agency's work was also informed by long term Water Resource Plans which it received during 1998-99 for the first time from every company. Water Resource Plans are intended to secure the reliability of the public water supply for the next 25 years.[95] The Plans detail all aspects of future prediction for the demand for water, the impact of measures to manage demand, the need for improvements to the flexibility of use of existing sources of water and the potential need for, and timing of extra sources of water as well as the impact of measures in the NEP to restore a sustainable balance of abstraction where SSSI's and other sites are adversely affected by abstraction.[96] The Agency has informed the companies that future new licences, and modifications to existing licences will only be agreed if the company is delivering all the elements of their approved Water Resources Plans eg leakage reduction, metering, water efficiency or extra treatment capacity.[97] It is also Government policy that any proposals for new sources should only be developed if projected demand cannot reasonably and reliably be met from existing sources.[98]

Costing the Environment Programme

76. Ministers, with advice from the Environment Agency and the DWI, decide the final form of the five year programme of environmental and quality requirements which will be funded by the Periodic Review. Ofwat then reflects these requirements in the calculations underlying the Final Determinations with any further checks which it considers necessary to ensure value for money.[99]

77. Ministers have made it clear that they expect Ofwat together with the Environment Agency and the DWI to look critically at the costs of the environmental and quality objectives and to challenge them where appropriate with the aim of achieving the Government's objectives in the most cost-effective manner, driving costs down as far as possible.[100] However, Ministers ultimately decide where to strike the balance between reducing costs and increasing benefits.

78. The Environment Agency has a duty to have regard to an assessment of the likely costs and benefits in exercising its powers but only when the exercise of these powers is within its discretion.[101] This does not translate into a statutory requirement to undertake cost benefit analysis for every environmental improvement which the Agency puts forward and nor does the Agency think it should.[102] There is also no requirement for the Agency to generate cost estimates for new schemes and it is expected to use such information as already exists.[103]

79. The Agency argued that, in practice in PR 99, the duty regarding costs and benefits only applied to 10% of the National Environment Programme (NEP) approved by Ministers. The reasoning behind this was that 70% of the NEP (by capital cost) related to EC Directive requirements or SSSI protection, both of which had to be undertaken. A further 20% was a result of Government policy decisions relating to sewage sludge applications to farm land as well as increased volumes of sludge produced. This left 10% which related to Government approved quality objectives for rivers, non-SSSI locations affected by over-abstraction and those combined sewer overflows not required by EU directives. In these cases there was no obligation for Ministers to include schemes in the capital programme.

80. The Agency acknowledged that it did not try to scrutinise in detail the costs of the companies' proposals "site by site" as this was Ofwat's role.[104] However, it did have to provide some assessment of the benefits of schemes for Ofwat to consider against the costs. Ofwat's scrutiny of these benefits was a key element of the PR99 review.

81. Ofwat reviewed the Agency's 700 schemes, looking at their cost-effectiveness in terms of their MAT score (ie their benefit) to cost ratio, and suggested that the most expensive schemes representing the last 5% of aggregate benefit should be reappraised.[105] Ofwat excluded 62 surface water quality schemes and four abstraction schemes from the final determinations on the grounds that at first view they were very expensive per unit of benefit generated, for example per metre of river improved. Ofwat felt that there was a good case for revisiting these schemes to see whether there were more cost effective ways of meeting the same objectives. Sir Ian told the Committee that the average cost of the whole quality programme, excluding the challenged schemes, was £130 per linear metre. However, the average cost of the 62 schemes excluded from the price limits was over £800. One proposed scheme had been costed at up to £10,000 per linear metre improved.[106]

82. Mr Meacher has now asked the Environment Agency to complete a further appraisal of costs and relative benefits and resubmit these to him during the 5 year period. If satisfied, he can then either: (i) include the schemes in the Environmental Programme at the next price review or (ii) trigger an earlier introduction by asking the Environment Agency to propose a revision of a water company's discharge or abstraction licence. Paragraphs 142-150 below consider the problems which could then arise if the new schemes are not large enough to trigger an interim determination which would grant the company a new, larger K-value for the remainder of the quinquennium.

83. Considering the schemes in dispute in PR 99, Sir Ian Byatt said that he hoped that the Environment Agency would press companies for other solutions and think about whether these schemes had been gold-plated.[107] He clearly felt that there was room for improvement in the assessment process. This was certainly indicated by the re-appraisal of one scheme, after the draft determinations, which resulted in an alternative solution (acceptable to the Environment Agency) costing an estimated £10 million less than the original proposal.[108]

84. Ofwat was also concerned that limited consideration appeared to have been given to exploring whether similar environmental benefits could be obtained at lower cost by addressing non-water company discharges. Ultimately however, it is for Ministers to make the final decision and they may decide that there are no other alternatives to an expensive scheme which provides benefits key to achieving important policy objectives. It would then be Ofwat's statutory duty to incorporate such a scheme into the price limits.

85. Sir Ian told the Committee that he believed that more work on the objective analysis of benefits would lead to better decisions. He pointed to the work already undertaken by the Foundation for Water Research to develop a comprehensive approach to monetary cost benefit analysis of surface water quality improvements and claimed that the Environment Agency did not use this in the 1999 Review[109]. However, the Agency itself does claim to have drawn on this work in developing MAT.[110]

86. Ofwat clearly has concerns over certain aspects of the Agency's work to establish cost-effectiveness and has said that "limited attention seems to have been given to establishing that proposed improvements offered value for money for the environment or the customer".[111] Ofwat has argued that there are a number of technical problems with the Agency's MAT methodology which have never been satisfactorily been resolved and is critical of the fact that the technique ranks schemes according to aggregate benefits rather than as part of a cost benefit comparison. Ofwat is also concerned that the Agency did not reject any of the 700 River Quality Objective schemes as not being cost-effective enough. The economic regulator claims that all were submitted to Ministers for confirmation, many with very low MAT benefit values, and three schemes were assessed to offer zero benefit.[112]

87. The Environment Agency told the Committee that there were no generally available accepted methodologies for costing or pricing environmental benefits as opposed to measuring more tangible benefits such as potential monetary impact on tourism or regeneration. Water UK felt that the Agency had made a good start with trying to assess the true costs of achieving environmental benefits but there was further work to be done and the water industry was keen to be part of that work.[113]

88. The Agency made it clear that it would like better access to better cost information.[114] In PR 99 site-specific cost information was only available for a limited number of sites late in the process. In general, the Agency found that the information on costs collected by Ofwat could not be disaggregated to individual location costs. The Agency felt that this made it difficult to judge the balance between cost and benefit when only working with generic costs as the Agency could only contrast the relative cost and benefit of improvements at each location.[115] This also made it difficult for the Agency to comment in an informed way on the benefit of cost-effective solutions through integrated approaches.

89. The Agency is currently exploring how it can capture the outcomes of the 1999 investment programme in economic terms so that the economic benefits which appear in practice can be quantified.[116] That still does not provide a clear costing of the environmental benefits which remains the difficulty and leaves the Agency in a weak position to defend its proposals against Ofwat's cost-orientated scrutiny.

90. The Environment Agency must develop and strengthen its capacity to assess and demonstrate the benefits of the schemes which it proposes for inclusion in future National Environment Programmes and also engage in a more critical examination of their unit costs.

The role of the DETR

91. Many witnesses felt that DETR had handled the review well.[117] Water UK believed that the Department had been more directly involved in this review than the last and would like to see the Department take an even greater lead in the next than it did in PR 99.[118]

92. Water UK would like to see a situation where no policy documents are issued without full sign-up from all appropriate regulators and the DETR to avoid confusion and uncertainty.[119] An example where this was clearly not the case was Appendix E of Ofwat's Final Determination which set out the protocol for changes in companies' obligations and consents after the final determinations. This was issued without consultation with the Environment Agency because Ofwat did not believe that the protocol had any implications for the functions and duties of the Agency.[120] However, the Agency has concerns that it affects their obligations under the Water Resources Act 1991. The DETR is now seeking to clarify these concerns so that definitive guidance can be given to all concerned.[121]

93. Water UK felt that it would help if the quadripartite group discussed the overall long term goals for the sector before the Periodic Review process got underway [122] rather than the current somewhat piecemeal approach which ultimately risked losing sight of the overall vision. The Committee is aware that a number of Government guidance documents, Agency plans and strategies as well as company Water Resources Plans were in place during the quadripartite discussions but the Committee accepts Water UK's point that key elements of policy need to be outlined and discussed with the quadripartite forum at the outset. In this way the parties would be clear on the future framework and key pressure points.[123]

94. The Committee is mindful of Ofwat's lead role in running the Periodic Review process. However it is important that the overall policy objectives are kept in sight throughout the process by all parties. It is the Government which provides the policy framework within which the Review operates and the Committee would like to see the DETR take the lead in bringing the overall policy "vision" to the fore more vigorously within the quadripartite process. The Committee recommends that, in future reviews, the DETR presents a short, overall statement of existing policy to the quadripartite members at the outset. As well as key environmental protection goals this should encompass relevant social and economic policy objectives.

Transparency

95. Ofwat has stated that transparency is fundamental to the way in which it operates but that in conducting a periodic review a balance has to be struck between maintaining commercial confidentiality and operating transparently.[124]

96. UNISON takes the view that "it would help all those involved if there was a greater understanding of the issues involved, and the reasons behind the eventual determinations".[125] The National Consumer Association has also called on Ofwat to be more open about the information and assumptions it has used in order to justify its final proposals and to explain why more generous cuts were not possible.[126]

97. Ofwat has made a number of changes to improve transparency since the 1994 Periodic Review as this was a key issue highlighted in its own review of that process which it undertook in December 1994. A key learning point from this review was that there was a perceived inequity between the volume of information provided to Ofwat by the companies and the explanations provided to the companies by Ofwat of the price limits set for them. In direct response, Ofwat provided each company with a confidential Supplementary Report setting out the specific reasoning behind its individual determination at both draft and final determinations and the differences between these decisions.[127] It should also be noted that in 1999 Ofwat published its draft determinations; in 1994 this information had been kept confidential.

98. Water UK conceded that there had been a shift from the previous review in that more information was available and that level of information was clear.[128] At a strategic level and almost at intermediate level the process had been transparent and the Director General had set out very clearly in a number of documents exactly what he was expecting and what the water companies had to return.[129] However, when companies wanted to explore the reasons behind specific decisions relating to them the information had been missing.[130]

99. It appears that despite the increased efforts by Ofwat, the information of key interest to companies remains somewhat elusive—the financial model. Ofwat published the Financial Model Rule Book in October 1998 and maintains that the calculations and workings of the financial model were exposed at an early stage. Ofwat expects that companies will build their own model from this but the Rule Book, rather cryptically, does not provide all the relevant equations. Thus, company models will always generate different answers to Ofwat's. Sir Ian offered us no reason as to why the equations in the financial model were not open to public discussion and use and the situation seems to be rather like being given a car without an engine. However, Ofwat has since offered to consider the issue of transparency in this respect for the next Periodic Review in 2004 which is a welcome development.[131]

100. The Committee recommends that Ofwat makes the full financial model as used for the Periodic Review, including equations, publicly available.

101. Water UK also felt that Ofwat had been rather opaque in relation to the independent business advisers which Sir Ian appointed in 1998 to address Ofwat's lack of a business understanding. Their appointment was clearly announced in an Ofwat press release in January 1998[132] and their terms of reference are available from the Ofwat Library. However, the advisers' reports have not been published and although the Director did refer to their advice throughout the Final Determinations this was mainly to reinforce his decisions and it is not clear where the panel may have held different views. The Director recently established a policy committee consisting of four independent advisers and the Ofwat senior management team. The Committee would welcome clarification of the role of the new policy committee, its role and relationship with the Director, and its implications for Ofwat's access to independent business advice.

102. Although Ofwat has made efforts to address its transparency since the last review, as acknowledged by the water industry and the Environment Agency,[133] the Committee believes that the regulator has not yet struck the right balance between commercial confidentiality and operational transparency.

Involving wider stakeholders

103. Surfers Against Sewage made it clear to the Committee that they were not satisfied with Ofwat's efforts to involve the full range stakeholders in the periodic review process.[134] They were critical of the seminars which were held for environmental groups, one of which the Director General was unable to attend, adding to the perception that the events were only cosmetic. However, English Nature "found them a useful way of involving stakeholders in the decision-making framework".[135] Ofwat is aware that these seminars (including those for companies and customers) were not as successful as those which were held for City investors and analysts. In its recently published code of practice on consultations Having Your Say, the regulator has undertaken to consider the merits of future "listening events" and "meetings with interested parties".[136]

104. Ofwat must make further efforts to involve the full range of stakeholders beyond the quadripartite forum during the periodic review process in a more effective way. The Committee recommends that, in considering the merits of various means to achieve this, Ofwat gives effect to best practice in this area such as the Environment Council's stakeholder dialogue methods.[137]

Data provision

105. Water companies were clearly not convinced that the level of detail of data they were required to submit at various times during the review process was necessary. Water UK felt that given the number of companies submitting the substantial level of detail required, it was difficult to perceive how it was analysed to be meaningful.[138] The trade body particularly highlighted the example of the first costing exercise which it claims in retrospect was "clearly a waste of time and effort".[139] Ofwat stated that this exercise would "be used to assess the current best estimate of the scope of the quality issue".[140] The exercise actually generated figures between £2.2bn and £7 bn which the industry felt was too large a range to be guidance on the best estimate. However, Ofwat claimed that the exercise "highlighted major cost drivers" and identified key areas in which guidance from DETR and the Environment Agency was needed".

106. Water UK argued that in reality the objectives subsequently changed as the exercise was undertaken in advance of the May 1997 election and in advance of DETR setting out its proposals on how the quadripartite process was to be handled.[141] The industry was also concerned that the different regulators, involved in the review, seemed to request the same information in different forms.

107. Sir Ian told the Committee that he felt that the water companies' approach to information was "not yet fully mature". He said "...they spend a lot of time explaining that I ask for too much information, it is a tremendous burden, and costs an enormous amount of money to provide. Then whenever I make a decision they bring in (metaphorically) a forklift truckload of more information which disputes the fact that the decision is a right decision".[142] During PR 99 Sir Ian was frequently disparaging about the quality of the information provided to him by the water companies. He felt that at both the 1994 and 1999 Reviews many of the Companies' Business Plans, were more like bids for additional resources. He thought many lacked coherent Board strategies setting out the views of all stakeholders, including customers, and showed little acceptance of the need to make tough business decisions.[143]

108. The burden of information collection is recognised by the Director, particularly for small companies. Ofwat has acknowledged that "it will be important to consult with the industry and others on the data required for the next Periodic Review in a similar manner to the recent consultation on the annual information requirements in the June [Annual] Return".[144] In the latter case, Ofwat maintains that it has always tried to follow a general principle that companies should be asked to provide data which a prudent company would collect for its own managerial purposes.[145]

109. The Committee welcomes Ofwat's continuing work to ensure that the data it requires from companies is proportionate to the regulator's needs. In view of the potential burden (in both time and money) that such data requirements present, the Committee recommends that, as a matter of regulatory best practice, Ofwat accounts for the data which it demands. Companies should be left in no doubt what data and analysis is required from them and why.

The system of Reporters

110. Companies are required by the Director (under a number of licence conditions) to appoint independent professionals, known as Reporters, to certify and report their opinion on the regulatory information which companies submit to Ofwat. Reporters are mainly consultant engineers but companies do employ financial analysts as required. Economic expertise is becoming increasingly necessary especially in areas such as demand forecasting and the development of water efficiency initiatives.

111. The water companies employ and pay for the Reporters. However, the Director approves the Reporters' appointments and can direct the water companies to terminate their contracts on the grounds of poor performance. The Reporters' relationships with Ofwat, the quality regulators and the water companies, and the framework of the approach to the Reporter task are set out in the reporters' protocol of November 1997.

112. Sir Ian explained that Ofwat uses Reporters primarily to make sure that the information which Ofwat receives is properly comparable across the companies and that the uncertainties in the information are properly exposed. Ofwat then draws its own conclusions about the effectiveness and the cost of different companies.[146] However, the industry seems to have a different perception of how Reporters' work is used. Water UK commented that they would be satisfied if Ofwat actually took notice of its own Reporters that they were paying for. They were dissatisfied that Ofwat seemed to override the Reporters and alter figures without giving any reasons.[147]

113. During the 1999 Periodic review Ofwat commissioned a joint team from KPMG (management consultants) and the Babtie Group (engineering consultants) to review the Reporter process. The team's opinion was that the Reporters' process was valuable to the Director in giving him an objective evaluation of the soundness and validity of the information employed by the water companies in the development and presentation of their Business Plans. It concluded that the Director should feel confident in relying upon this evaluation.[148] With such an endorsement it would seem appropriate for the Director to always make it clear why he/she is departing from a Reporter's conclusions.

114. Ofwat clearly feels that there is merit in the close working relationships between the Reporters and the companies.[149] However, if Ofwat directly employed the Reporters it would have more direct control over important aspects such as training, the enforcement of minimum standards and ensuring that existing expertise was relevant to the evolving needs of the industry and its processes.

115. The Committee recommends that Reporters should be engaged and paid directly by Ofwat rather than the water companies and that Ofwat regularly monitors its arrangements with its Reporters to ensure that:

—there is effective scrutiny and audit of the estimated costs of schemes

—water companies identify least cost solutions to meet environmental standards which take into account the whole life costs (capital and operating) and the environmental as well as economic costs of a scheme or programme of schemes.

Monitoring

116. It is vital that there is effective monitoring of the delivery of the environmental programme to ensure that money is spent where it was allowed and that projects are phased as envisaged as far as possible. It is the Environment Agency's responsibility to ensure that the investment programme is implemented through changes in abstraction licences and discharge consents. If the water companies' fail to deliver the role for enforcement in relation to their management performance and economic or financial performance rests with the Director General.

117. The Agency has published its full National Environment Programme listing every site which is going to receive investment with the timetable for that investment.[150] Annually the Agency will produce a statement of progress against that for each individual water company.[151] This process will be in addition and complementary to Ofwat's established process of June return whereby each company is required to submit comprehensive returns on actual progress, service levels delivered, activity, expenditure and financial results. The Drinking Water Inspectorate will also provide a report on its assessment of each company's compliance with quality obligations.

118. At present Ofwat reviews the June return information to assess each company's performance and compliance with statutory and licence requirements, regulatory expectations and how it compares with its peers. Where shortfalls are identified regulatory action follows to require the company to remedy the situation by the earliest possible date, together with more frequent reporting (usually quarterly) to check on progress. Ofwat summarises the position for the sector and each company in its annual series of reports.[152]

119. Surfers Against Sewage (SAS) have applauded the work of the DETR and Environment Agency to set a timetable for the implementation of the National Environment Programme. A comprehensive timetable of this kind did not exist in previous reviews and SAS felt that this had resulted in the tail-ending of the capital investment programme ie leaving construction of schemes until the end of the five year period instead of spreading work and therefore expenditure evenly over the period.

120. English Nature suggested to the Committee that it would be useful for the quadripartite process to continue through the monitoring phase.[153] The Agency rejected this idea saying that it risked "creating a forum for negotiating variation from what is currently a very clear, firm agreement and programme".[154]

121. The Committee welcomes the Environment Agency's proposal to publish an annual report on the progress of the water companies in implementing the National Environment Programme. The Committee recommends that the Agency also takes steps to monitor and report upon the environmental benefits derived from water company investment.

122. The Committee recommends that a stakeholder forum is held annually to facilitate the presentation and discussion of progress on the delivery of the environmental and quality programme.

The Outcome

The price profile

123. The profile of the final determination largely reflects an L-shaped profile with price limits remaining stable following an initial reduction to reflect past efficiency and a lower cost of capital.

124. The water industry has been particularly critical of the final price profile and would have preferred a stable profile over the whole of the five-year period. Water UK criticised the final price profile as being short-term in the light of inevitable future price rises.[155] However, Ofwat argued that this would have left the companies with a lot of profit in the early stages and that customers were not keen on this.[156] Sir Ian cautioned that there had been a more gentle adjustment of prices in the 1994 review (a 'glide path') and the companies had responded by increasing their dividends very substantially. He had warned the companies several times about this and "resolved that it was not a sensible position to repeat".[157]

125. In Raising the Quality, Ministers cautioned Ofwat that 'a large cut in 2000 followed by increases over the rest of the quinquennium would send confusing messages to consumers' and they promoted the idea of an L-shaped profile with stable prices following an initial price cut.[158] In general, the Director has set the PR 99 price limits to achieve the latter. For most companies there is a significant price reduction for 2000-01, price limits are broadly flat for the next two years but then begin to rise slowly.[159] However, in four out of ten of the water and sewerage companies prices are set to rise significantly in the latter part of the quinquennium following the initial price reduction to allow for factors such as accelerated environmental programmes and higher than average rates of take-up of optional meters.

126. Even in the remaining companies, Ofwat acknowledges that prices may well have to increase during 2000-2005 as a result of both anticipated cost pressures and unanticipated new obligations.[160] Ofwat's memorandum to the Committee points out that analysis of four key companies has indicated that if the 2006-2010 quality programme were to be the same size as the 2000-2005 programme, then the average household bill, for those companies, may rise by £20-50 in the period 2005-6 to 2009-10. Ofwat therefore has cautioned against significant investment on "non-statutory" environmental improvements in the current pricing period as this would leave less room for mandatory improvements to be efficiently financed in the period after 2005.[161]

127. Ofwat made it clear in the Final Determinations that there was a potential £900 million of environmental investment which may crystallise during the five years although this figure was not broken down into any useful detail. In addition, there are a number of areas where Ofwat has made provision for companies to claim interim price increases if necessary. For example, if more people than estimated take up the free metering option available as a result of the Water Industry Act 1999 (see paragraph 145).

128. The Committee believes that roller coaster prices confuse consumers as to whether their valuable water resources are being carefully managed by the industry and how far they themselves should be bothering about water efficiency. As metering becomes more widespread, there will be an increasing price incentive to be water-efficient and clear pricing signals will be needed.

129. The Committee sought Sir Ian's assurance that the PR 99 price profile took account of the necessary phasing of the environment and quality investment programme. Sir Ian said that it had. In some cases, the profile has price limits rising at the end of the period to allow the companies sufficient revenue to meet interest payments on the capital they need to borrow to fund the quality and environmental programme.[162] In the Final Determinations, the Director re-phased schemes worth £70 million primarily to ensure that legislative requirements were met.[163] Meanwhile, Ministers made clear in their early guidance to the Director that certain action, such as that to protect SSSIs, must be driven by environmental realities[164] and schemes required within 2000-2005 should go ahead on the "optimal timetable in environmental terms", without deferral to the next price review period.[165]

Size and nature of the environment programme

130. In terms of output, Ofwat claims that the 2000-2005 price limits allow for the biggest ever five year programme to protect and enhance the aquatic environment.[166] The 1994 environmental and water quality programme was worth £8.67 billion but Sir Ian Byatt told the Committee that the £7.4 billion programme for 2000-2005 delivered more improvements for less cost as the companies were now more efficient.[167]

131. The 1995-2000 programme was essentially the implementation of the Urban Waste Water Treatment Directive consisting of large primary and secondary treatment work, often in coastal areas as well as drinking water improvements. The next five years will allow for more discretionary river improvement particularly by dealing with combined sewer overflows. The Agency takes the view that as rivers recover from gross sewage pollution it is easier for them to see other underlying problems perhaps from other sources.[168]

132. The Environment Agency's then Chairman, Lord de Ramsey, responded warmly to Ofwat's final determinations. He said "by 2005 we will have reached a position where the significant environmental damage created over the past 200 years will have been repaired".[169] The Agency told the Committee that the latest spending programme would meant that by the end of 2005 we will have seen the elimination of the discharge of crude sewage into the environment.[170]

133. Just over half of the programme will be directed at improving discharges from sewage treatment works whilst a third will go towards improving the performance of intermittent discharges, principally combined sewer overflows from the sewerage systems. The remainder represents the assumed cost of additional and enhanced sludge treatment and disposal facilities and works addressing the effects of over-abstraction including the alleviation of low flows in rivers.[171]

134. Appendix 2 to Ofwat's written memorandum sets out the environmental programme outputs expected from companies for the period 2000-2005.[172] The Environment Agency told the Committee that all the water courses currently devoid of fish because of sewage pollution would be addressed by the programme and in terms of the quality in inland waters, half the length of water not currently achieving fair quality—ie capable of reliably supporting fish populations—would be improved.[173] The Agency admitted that this left a residual length of river where fish might be absent because of historic mine pollution and also because of diffuse sources such as pollution from sheep dips which would need to be addressed in a different way.[174]

135. The Agency also outlined the types of schemes which had been left out of the investment programme. Low priority combined sewer overflows, ie those with low aesthetic impact, were not being tackled and priority had been given to those with high aesthetic impact and those which were discharging continuously and not just intermittently.[175] This meant that approximately a third of the identified problem of combined sewer overflows would not be addressed by the programme. There were also some sites which would not be dealt with where there was a low probability that there would be a failure in river standards if projected sewage-works loading from population increases were actually realised. Schemes where the UK needed to make further progress on compliance with the guide values in EC Directives, as opposed to the imperative or mandatory standards, were also of low priority. There is no timetable as such for meeting these guide standards but the UK must demonstrate progress.

136. The Agency highlighted the difficulties that would be faced if all the schemes had been approved. For example, in Preston in the North West it would have meant severe disruption with deleterious excavation of the roads bringing the town to a halt. In discussion with the company and in the light of an assessment of the manageability of and scale of rebuilding the sewers the Agency took the view that the work needed to be spread over a long period of time. [176]

137. Clearly, the investment programme which PR 99 aims to deliver is substantial and the Environment Agency has not pointed to any serious omissions although it does have concerns regarding some of the schemes which Ofwat challenged and are therefore being reappraised. However, the RSPB pointed out to the Committee that the environment programme could perhaps have been even larger for no overall increase in cost. Government Ministers publicly endorsed a programme of £8 billion (£500 million less than the Agency's suggested programme) in March 1999 and agreed that the costs and time-frame were reasonable and realistic. Shortly after this decision was made, Ofwat lowered the assumed cost of capital (the minimum return providers of capital require to induce them to lend or invest in a business) from 5.25% to 4.75% —effectively lowering the cost of the programme by £500 million. This means that the Environment Agency's full programme and more could have been delivered with no overall increase in cost.

138. The Committee put this criticism to the Department who addressed the matter in their supplementary memorandum. The DETR maintains that after the draft determinations were published further discussions took place between the Department, Ofwat and the Environment Agency to finalise the environment programme and its phasing in the light of better information on costs, the cost of capital and the full range of other factors.[177] However, the DETR offered no examples of the resulting programme alterations. Ofwat's Final Determinations also referred to changes in the quality programme and additional expenditure included since the draft determinations but again it is not clear how far the environment and quality programme benefited from the large sum generated by the lower assumed cost of capital.

139. The Director should seek to ensure that the Final Determinations document makes clear how far changes in key factors such as the cost of capital have influenced the final outcome during the review process.

New obligations

140. Forthcoming European and national legislation will undoubtably bring new quality and environmental obligations which Ofwat believes will, like PR99, be a very significant influence on water bills in the next pricing period.[178] In addition, there are uncertainties regarding water resource policy if customer water use patterns alter or global warming trends continue and the UK is subject to a climate change which results in greater demands for water and changes in rainfall patterns.

141. The European legislation which is expected to impact on the water industry includes: the Water Framework Directive, Sludge to Agricultural Land Directive, and revisions of the Bathing Water Directive and Shellfish Waters Directive. The Government has also recently announced an increase in the potential designations for nature conservation purposes under the Habitats Directive.[179] A recent UK review of Special Areas of Conservation (SACs) has identified 81 new sites in England, covering 300,000 hectares, which are to be added to the list of 495 UK SACs which have already been submitted to the European Commission. These further designations of sensitive areas, like new quality standards, are very likely to trigger the need for improvements in sewerage treatment works which will need to be accommodated in the next periodic review.

142. The 1999 Periodic Review provides a satisfactory outcome for the environment but there is no room for complacency as we face new, future quality obligations and uncertain water resource constraints.

Accommodating new obligations

143. If companies find that during the price period 2000-2005 they face additional obligations or circumstances which were not factored in to their price limits they can, in certain situations, request that Ofwat adjusts the price limits. This is called an interim determination.

144. However, provisions in a company's operating licence (Condition B) only allow for an interim determination if the net additional cost of the new obligations or circumstances (actual or forecast) which the company is subject to between periodic reviews exceeds, in total, 10% of the company's annual turnover. If new obligations are not large enough to trigger an interim determination the costs associated with delivering additional outputs are "logged-up" by the companies and taken into account at the next review.

145. The Final Determinations for PR 99 identified three areas where there was a risk that cost pressures would arise for the companies but they had not been taken into account in the price limits. One of these was a faster than expected take up of the free meter option by customers as provided by the Water Industry Act 1999. In PR 99, Ofwat allowed for rates of take-up between 5-15% for each company but acknowledged that if take-up was faster there could be a significant loss of revenue without hitting the 10% threshold required for an interim determination. Ofwat therefore modified company licences so that a more practical threshold applied specifically to the three key areas identified in the Final Determinations.[180]

146. Three companies have already requested interim determinations as a result of PR99: Tendring Hundred (water-only), Anglian Water, and Welsh Water. All three applications were triggered as a result of more customers moving to meters than was allowed for in the price limits which has resulted in lower revenues than forecast to pay other work such as water quality monitoring and waste treatment.[181]

147. Previous to this recent application, the last company to apply for an interim determination was Northumbrian Water in 1998. The Environment Agency had confirmed that secondary treatment at several coastal sewage outfalls was required to meet the requirements of the Urban Waste Water Treatment Directive. Ofwat agreed that this was a new legal obligation which had not been accommodated in the companies' 1994 price limits and allowed the company to increase its prices for 1999-2000, by a maximum of 0.7 % (on average) above inflation. The original price limits allowed for -2.1%.[182]

148. These examples illustrate how the review process has tried to accommodate the uncertainties which the companies face within a review period. However, in PR 99 £320m worth of environmental improvement schemes were not financed on the grounds that the costs were either not known or agreed, and there were £700m of other new obligations which Ofwat thought might arise during 2000-05.[183] These will be dealt with by the usual logging-up/interim determination process if it transpires that work is required within 2000-05. However, there is no set protocol for the re-appraisal of schemes and it may be a lengthy procedure. Ofwat has also made it clear that companies must have exhausted all appropriate means of challenging the imposition of a requirement and/or its timetable where this is in advance of a just-in-time date set down in regulations or directives. Ofwat will therefore assume that a company's choice not to challenge a new requirement is indicative that it can absorb the implications of the change without increasing price limits.[184]

149. A number of witnesses, including English Nature, the RSPB and the utility expert Dr Dieter Helm, remain uneasy that, in practice, all these factors will just spell delay. Customers are likely to react badly to surprise increases to their bills towards the end of the pricing period and this may generate pressure on the regulator to defer schemes to the next review.[185] Companies will add to this pressure if they adopt the confrontational approach required by Ofwat to resist the imposition of new requirements.

150. Water UK confirmed that there was very little financial headroom within the companies to cope with logging-up and that there was a likelihood that companies would indeed have to resist/appeal new obligations because they didn't have the capacity to fund them.[186] Surfers Against Sewage (SAS) were concerned that if the companies had to log-up significant costs, but could not trigger an interim determination, this could have adverse knock on effects for maintenance and operating costs and the delivery of environmental obligations.[187] However, Ofwat has acknowledged that companies may face difficulties in relation to metering costs only. Overall, the RSPB is pessimistic that interim price determinations and the logging-up process will deliver the works necessary within the period 2000-2005.[188]

151. The Committee is concerned that there is an apparent lack of clarity in the present arrangements for dealing with the timely introduction of those environmental schemes which were approved within the National Environment Programme for 2000-05 but which are currently subject to re-evaluation and not included in the price limits. The Committee recommends that Ofwat reviews this process before the next periodic review.

Tackling diffuse sources of pollution and ensuring the polluter pays[189]

152. The Periodic Review considers the funding necessary to deal with the environmental problems caused by discharges from waste water treatment works which are generated by the water companies and their infrastructure. That is, it essentially generates funding to deal with an important part of point source pollution. However, another key area of water pollution is that from diffuse sources such as run-off containing nitrates, pesticides and herbicides from agricultural land and run-off from roads containing hydrocarbons. In 1997, the Environment Agency reported that the sewage and water industry accounted for the largest proportion of water pollution incidents (27%) and the industrial sector 19% (of which the construction industry was the most frequently identified source). Pollution from other sources only accounted for 17% of all incidents—agriculture (10%) and domestic and residential sources (7%).[190] However, this is still a sizeable contribution to the pollution problem considering the smaller scale of most of the contributing operations in comparison to the extensive operations of the water companies and large chemical companies. In addition, the sources of more diffuse pollution tend to be less likely to be tied into comprehensive regulatory frameworks.

153. Water UK expressed its concerns to the Committee that the water industry was receiving an undue proportion of the attention devoted to the overall management of pollution because there happened to be a neat mechanism, in the form of the Periodic Review, for the generation of funding whereas no such system existed to facilitate the management and financing of diffuse pollution.[191] In effect the industry felt that it was picking up the pollution tab for everyone else.

154. Ofwat too has expressed its concerns that the Environment Agency has expended much effort in identifying "every single" water company discharge which may cause or contribute to current failures of river quality objectives and EU bathing water standards but has not yet addressed or evaluated, to the same degree, the impact of other sources of pollution on water quality, most significantly diffuse sources. The Environment Agency estimates that only about one percent of the current shortfall in meeting river quality objectives can be attributed to the impact of water and sewerage company discharges. Ofwat has therefore observed that it is "not clear whether the amount being paid for by water customers for improvements is disproportionate" and therefore out of line with the polluter pays principle.[192]

155. In some cases water companies have taken action themselves to tackle diffuse pollution. In April 1998 Wessex Water announced that it was offering farmers a financial incentive of up to £40 per hectare to use fewer pesticides and fertilisers by switching to organic farming.[193] The amount of nitrate from artificial fertilisers which had been percolating through to groundwater sources was heading towards levels where treatment would be needed to avoid breaching drinking water standards if the process was not halted. This would require additional investment by the company. In November 1999, Wessex Water estimated that the annual operating cost of pre-treatment to remove nitrates was on average £6,800 per Ml and the removal of pesticides £7,000 per Ml.[194] Although such an innovative scheme is to be welcomed the real polluter is clearly not paying.

156. The Agency told the Committee that it would continue to have regard to both diffuse sources and those that were the direct responsibility of the water companies to make sure that the environment programme was implemented by the former, and also to focus on agricultural issues and coal mine discharges.[195] At the other end of the scale, the Agency admitted that dealing with the pollution generated from a series of small hotels or septic tanks was very labour-intensive and legislation was difficult to handle in that area—some of the work was through persuasion rather than statutory means. The Agency was however, changing the shape of its regulatory departments to focus rather more on the diffuse source issues.[196] It should be able to count on some support from the DETR in this area. In written evidence to the Committee, the DETR stated its intention to encourage the Environment Agency to focus more regulatory effort on diffuse sources, particularly where bathing waters or river water quality objectives were threatened.[197]

157. The Agency detailed a number of measures that it has already taken to tackle diffuse sources: it has published a strategy for dealing with eutrophication from all sources and a strategy for investigating and starting to deal with endocrine disrupters wherever they originate. It has also introduced a minimum standard with the Coal Authority for mine water discharge which accounts for a third of current damaged lengths of river. The Agency thought that Integrated Pollution Control (IPC) and the implementation of the Integrated Pollution Prevention Control Directive (IPPC) would be picking up industry in the wider sense and the associated discharges—the new IPPC regime has an automatic programme to progressively tighten not just the emissions to air but also releases to water based on best available technology. The Agency was also in discussion with the DETR about the possibility of an overall approach to water quality in surface waters to address those issues.[198]

158. Under the Ground Water Directive, the Agency is currently grappling with the issue of sheep dip—one spill can negate millions of pounds worth of investment in sewage treatment.[199] The Agency told the Committee that 700-800kms of river had been affected because the sheep dips which were now being used were safe for humans and mammals but not for aquatic life—both insects and fish. The Agency had observed that farmers now seemed to be less careful in their disposal because there was less danger to their own health.

159. The Periodic Review is an effective mechanism for dealing with point source environmental problems caused by water companies. However, the Committee is concerned that the DETR and the Environment Agency are disproportionately relying on the Periodic Review mechanism and the water companies as the key means to achieve compliance with water quality and environmental protection objectives and not sufficiently tackling pollution from diffuse sources.

160. The Committee welcomes the DETR's intention to encourage the Environment Agency to focus more regulatory effort on diffuse sources. The Committee recommends that the Department acts swiftly to ensure that the Agency can demonstrate an overarching enforcement strategy for dealing with diffuse sources of pollution.

Water Quality Programme

161. In its evidence to the Committee Water UK claimed it was "alarmed" at the under-resourcing evident in the DWI for the Periodic Review and that the DWI appeared unable to get its agenda included properly, contributing to extensive under-funding for water supply improvements.[200] The DWI refuted that there was any evidence to support this statement[201] and maintained that it had been advised by Ofwat that the Final Determinations made provision for all of the programmes supported by the DWI for PR99.[202]

162. However, in 1999 a DWI commissioned survey, intended to obtain feedback from companies on its performance, highlighted company concerns that the DWI did not have the resources to carry out its duties.[203] The DWI acts as an independent Inspectorate but for finance purposes it is dealt with as a division within the DETR and is therefore bound by the DETR's budgetary constraints. In response to industry concerns, the DWI stated that it intended "to carry out a full review of its procedures for the next Periodic Review and its relationships with other organisations with a view to learning lessons for the handling of a future Periodic Review".[204]

163. The Committee would welcome a report on the progress of the DWI's review of its procedures and on the adequacy of its resources.

164. The DWI's Chief Inspector Michael Rouse told the Committee that the DWI was content with both the outcome and the phasing of the drinking water programme for the 1999 Review.[205] All the Inspectorate's requirements had been included in the final scheme because they were all required by regulations. Most of the requirements had set dates for implementation set out in Directives—most had to be met by December 2003.[206] For cryptosporidium (a protozoan parasite which can be transmitted in water) there was not a fixed timetable but the DWI regarded it as the highest priority in relation to public health and had therefore worked with water companies to ensure that this was reflected in their programme.[207]

New obligations

165. The DETR is currently consulting on proposals for new regulations to implement recent revisions to the Drinking Water Directive. The Directive has both mandatory standards and indicator parameter values which the DWI does not interpret as being mandatory. However, as Government proposals stand, the UK is exercising its prerogative to go further than the Directive requires and proposes to make some of these indicator parameter values mandatory to maintain existing UK standards for aesthetic water quality. There are also two or three parameters which are not included in the Directive and for which the Government is proposing standards because they are important either in public health terms or for the aesthetic quality of drinking water. For example, it is proposed that the current UK standard for the chlorinated solvent tetrachloromethane is maintained and that there is a mandatory standard for sodium to address concerns about the level of sodium in our diet.[208]

166. The DWI did not think that maintaining existing standards would have an impact on the companies' existing investment programmes up to 2005. In addition, Michael Rouse told the Committee that PR 99 had taken account of the likely impact of accommodating some of the proposed indicator parameter values on mandatory standards, eg with respect to iron, manganese, aluminium and turbidity which would have to be dealt with by improving the distribution system and re-lining and replacing pipes.[209] The DWI explained that there had been an ongoing 20-year quality programme which was now going in to its third phase of four five year programmes.[210] The DWI estimated that one third of the system (80,000km) would have been replaced or renovated for water quality reasons over the 20 year period—a major catching- up programme.[211]

Interface with planning process

167. Planning permission will be required for many of the new investment projects which have been allowed for in the Final Determinations. Thus, the planning system has the potential to greatly influence the timetable of projects and the compliance with statutory obligations especially if applications are delayed or refused. The Environment Agency was aware of several instances where companies had really struggled to get the necessary approval for sewage works sites. In one case, a company had identified over 30 potential sites and none had been accepted by the local planning authority. The development was required to comply with Urban Waste Water Treatment Directive standards and yet there seemed to be an unwillingness to accept the need for the site at all.[212] The Agency also pointed out that there was no requirement on local planning authorities to take account of the Government's international commitments.[213]

168. The Environment Agency itself recognises the potential impact of the planning process on its National Environment Programme which can cause delays outside a company's control and takes a pragmatic approach. Where a scheme is delayed the Agency will accept a compensating acceleration in another programme. No one-way adjustment however will be accepted if a project has to be delayed. Overall Water UK in particular did not feel that water issues or the interface with the periodic review were adequately addressed by the planning system. The industry body has raised this issue with DETR and Ministers both independently and in partnership with the RSPB and the CPRE.[214]

169. Most of the key issues relating to this interface are related to completely new development. Developments or alterations on existing sites for example to a waste water treatment works (WWTW) which is already in operation, are likely to benefit from permitted development rights.[215] If such rights are not available, schemes are subject to the Government's general guidance and advice to local planning authorities and may require an Environmental Impact Assessment (EIA).

170. The Government's planning policy guidance on development plans (PPG12) emphasises the need for local planning authorities to consider the requirements of the utilities for land both in their own and other authorities' areas to enable them to meet the demands that are likely to be placed on them. It also comments specifically on the likelihood of there being additional needs for infrastructure such as WWTW. It advises local planning authorities to consult water companies and the Environment Agency to enable such needs to be met and to consider the possible implications for the environment both from such land use and from the additional water abstraction and discharge that may be associated.[216] In some cases the Environment Agency is a statutory consultee—Water UK believes that water companies should also become statutory consultees in the planning process.[217]

171. As well as the attitude of local planning authorities, the Committee was made aware of concerns regarding Ofwat's interference with planning matters as expressed in Appendix E [218] of the Final Determinations document. The Director suggested that decisions on whether to impose stringent planning requirements on works necessary to meet quality improvements "should rest with government rather than local planning authorities and water companies" (only the costs of reasonable requirements had been allowed for in PR 99). Local planning authorities are already subject to Government advice regarding the application of conditions and CIWEM (the Chartered Institution of Water and Environmental Management)[219] in particular, felt that this sought to undermine the role of local planning authorities. [220] However, the DETR confirmed that it remained the Government's policy not to interfere with the jurisdiction of local planning authorities unless it was necessary to do so.[221] The Committee believes that the Director's statement in Appendix E was inappropriate and his remit in this area, or lack of it, should have been made clear.

172. Overall, the Committee is satisfied that there is a suitable framework in place which should provide the necessary interface between the planning system and the required outcomes provided for by the Periodic Review. However, this framework is not being utilised as it should be in all cases.

173. The Committee is concerned that evidence indicates that local planning authorities (LPAs) do not always seem to recognise the importance of the statutory obligations faced by the water companies and the extent of the National Environmental Programme which needs to be delivered with their co-operation. The Committee recommends that the Government provides the LPAs with clearer guidance which is also relevant to the Government's international commitments.

Long term planning

Economic cycles versus sustainability

174. The five yearly periodic review process does not currently sit comfortably with the long term planning which is necessary in an industry where the assets are long-lasting and which has to look 20 years ahead to assess what water resources it will have—it can take 5 to 15 years to plan, design and build new supply schemes. Five year price limits are clearly sensible from an economic regulator's viewpoint but it is important that longer term environmental targets and programmes are also accommodated. These must not be compromised by short term political decisions designed to please the customer over a five-year time horizon.

175. The RSPB believes that "the current system of water regulation stifles creative thinking and imposes a 'boom/ bust' mentality within the water companies. It also believes that it does little to reward efficient and creative uses of water, acting against the sustainable management of the water cycle".[222] Surfers Against Sewage has similar concerns and feels that short-term decisions are being taken which may be less cost effective than those which take account of the possible future development of standards and obligations.[223]

176. The Committee put these criticisms to the Environment Agency which accepted that the current legislation tended to drive them towards "end-of-pipe solutions" for pollution control [224] ie those which focus on addressing the pollution at the point at which it is being discharged rather than looking at the whole process and ways of minimising the production of the pollution in the first place. The Agency told the Committee that it went to great lengths to structure the programme so that decisions could be based on the engineering work that may eventually have to be carried out at one particular sewage works. For example, if secondary treatment is going to be needed to meet the Urban Waste Water Treatment Directive, it would be a good time to perhaps add ultra-violet disinfection or meet a river quality objective for ammonia standards.[225] However, the Agency also had to bear in mind that during construction work on a sewage works, for example, there was a risk of unacceptable discharge. It was therefore sensible to keep the number of construction phases on a sewage works to a minimum which also encouraged the company to devise more cost-effective solutions.[226]

177. The industry sees merit in reviews being more of a continuous process.[227] The Environment Agency has already adopted this kind of approach by compiling its rolling spreadsheet of programmes for the environment. However, Water UK told the Committee that it did not feel that the Environment Agency did enough in terms of "the big picture, big goals and looking forward".[228] The Agency has since published a draft vision for a sustainable future[229] which looks ahead five to ten years. For water, the Agency has proposed long term objectives which include aiming to fully control all sources of water pollution, eutrophication and acidification and to ensure that water is acknowledged to be a scarce resource.[230]

178. In general, the management of water quality and water resources need to be considered and planned over much longer timescales than five years ahead. Thus, it is important that periodic review outcomes are made consistent with the pursuit of longer-term objectives, targets and strategies as they impinge on the water environment. For example, the Environment Agency's national water resources strategy should be seen as part of the "environmental future" which provides the context for the periodic review.

179. The Committee believes that the current Periodic Review Process, operated by Ofwat, provides a fair and open system for determining water price limits and thus provides valuable incentives for water companies to reduce operating costs and to search for innovative ways of designing and operating new schemes. However, we recommend that the DETR, companies and the regulators ensure that the five year investment programmes of the Periodic Review are set in a comprehensive, clear framework of longer term, policies and goals including those relating to water resources and environmental quality and serviceability goals. In turn, these five year programmes should be seen as contributing to the achievement of these goals.

180. The Committee believes that the DETR should take the lead in setting out the policy framework and environmental future at the outset of the periodic review process as recommended in paragraph 93.

Maintaining the infrastructure

181. Water and sewerage companies have extensive networks of water mains and sewers which they are required to maintain to ensure that they can provide service to current and future customers. Network assets (ie pipes) make up a very large proportion of capital and companies also have considerable above-ground assets such as treatment works or pumping stations.

182. These assets have been built up gradually over the last 200 years and many were built in the mid-twentieth century, particularly in rural areas and new settlements. Urban assets tend to be older and many date from Victorian times. Three Valleys Water and North West Water explained to the Committee the importance of maintaining their records of the age of these assets (see paras 239 and 258). Historic periods of peak building activity will mean that cohorts of sewers and mains will be due for renewal or rehabilitation around the same time, requiring large peaks of investment. The adequate maintenance of assets is essential to ensure that drinking water presents no harm to human health and is not contaminated by sewerage. In addition, it is important that insufficient maintenance in the future does not obviate substantial environmental and water quality gains which have been derived from recent investment in the infrastructure.[231]

Levels of funding

183. The Director is required to ensure that the price limits are set at a level which provides for sufficient maintenance of the networks. Capital maintenance constitutes planned work carried out by the companies to replace and refurbish water and sewerage assets to provide continuing services to customers. It also includes meter renewals, management and general expenditure on vehicles and plant, IT systems, telecommunications and plant monitoring and control.[232]

184. Much of the evidence which the Committee received highlighted concerns that the 1999 Periodic Review (PR 99) did not deliver enough funding for asset maintenance. The Campaign for the Renewal of Sewerage Systems (CROSS) even went as far to say that the importance of the sewerage structure and its condition was ignored.[233] In 1991, the House of Lords Select Committee on the European Communities also identified an "out of sight out of mind" attitude in relation to dealing with sewage waste in its report on Municipal Waste Water Treatment.[234]

  185. Mr Meacher told the Committee that he did not believe that "the provision made by the regulator in the 1999 Review was inadequate and that the evidence was that it was probably adequate".[235] He felt that all the evidence from recent surveys showed that there were not significant or major problems with the network and that the level of money which was going into maintenance at the moment was sufficient. Neither did he believe that the network was in a seriously detrimental state but he stressed that the Government was not complacent.[236]

186. For the period 1993-1998 water mains in poor condition (grades 4 and 5) increased from 9% to 11%, equating to £0.78bn worth of pipes moving into these categories. As of March 1998 (the latest assessments) 10% of critical sewers were also in a poor condition.[237] However, Ofwat maintains that there has not been a measurable increase in the amount of assets in poor condition over the last five years.[238] Sir Ian told the Committee that he did not believe that there was any evidence that serviceability was about to decline dramatically and if anything it was on the whole improving overall.[239] He explained that if deterioration took place it usually did so slowly and Ofwat was measuring this happening.[240] The Agency however told the Committee that if there was substantial under-investment in infrastructure renewal the risk of failure and environmental damage would escalate quite rapidly.[241]

187. Historically, spending on infrastructure has not been consistent. In 1974-1989, under central Government control, capital spending was cut heavily to fight inflation and keep water prices down. The actual expenditure by the industry doubled in the five years from privatisation in 1989 to over £1.2 billion per annum.[242] This level of spending was maintained during 1994-99 and Ofwat resisted the company's proposals to increase spending in this area.

.

188. PR 99 allows for £6.4 billion capital maintenance expenditure in the period 2000-05. Ofwat has chosen to cut the previous level of expenditure of £7.1bn by 10% or more because of efficiency improvements. In practice, Ofwat figures show that companies have historically spent less than is allowed for and often significantly less than the amount of money which they claimed to be necessary.[243] In PR 99, the companies indicated to Ofwat through their business plans that they wanted to spend £8.3 billion and were concerned that they have not been given adequate finding to maintain serviceability. The issue of funding is key to the water companies as they have a statutory duty to maintain their assets and this maintenance has to be demonstrated in line with their licence conditions. The companies also risk prosecution from the Environment Agency if asset maintenance is not adequate and leads to environmental pollution. The Agency believes that it has generated a comprehensive list of all the historic pollution problems of the companies and it has made it clear to the companies that any new failures of environmental standards will be treated as a failure of asset maintenance. Thus, the Agency will be seeking enforcement action straight away—not waiting for the next price review—just as they would with any other industry.[244]

189. Water UK commissioned a report by Professor Chris Binnie[245] to consider the present arrangements for assessing funding for capital maintenance. This concluded that Ofwat's decision to provide less funding than requested was likely to cause deferment of important capital maintenance.[246] The report also argued that the available funding did little more than allow for the repair of sewer collapses. A key customer concern, especially in the North West, is the flooding of homes from sewers.[247] However, Ofwat considers work to reduce this risk to be discretionary spend.[248] In the Final Determinations, Sir Ian Byatt concluded that allowance should be made in price limits for further reductions in the risk of sewer flooding for all companies. However, he commented that the "scale of the other environmental obligations has limited the level of investment which can be allowed for in price limits". The Director felt that "significant progress" would be possible where the problem was most acute (for example, D_r Cymru, Severn Trent, North West and Yorkshire Water) and the remaining companies would be able to achieve some limited improvement.[249]

190. In order to help the Director decide the appropriate level of funding, for capital maintenance companies are required to prepare Asset Management Plans. These assess the condition of the assets according to classification—grades 1 to 5. They also incorporate forward-looking assessments of the assets, with risk analysis to identify the capital maintenance funding required to meet serviceability criteria. These assessments are verified by Reporters and Ofwat assesses these plans as well as the company's outputs in recent years. In PR 99, companies were also required by Ofwat to submit an asset inventory in August 1998 as part of their business plan including changes in the number, age, profile, condition and performance of their assets since 1992/3.

Ofwat's "no deterioration" approach

191. The large discrepancies between Ofwat and industry estimates of necessary levels of funding for capital maintenance seem to arise mainly from Ofwat's "no deterioration" policy. In the 1999 Periodic Review, Ofwat took the view that if there was no evidence of a deteriorating trend in serviceability (ie service generated by the infrastructure) over the most recent 5 year period (1992-3 to 1998-9), the Director would assume that the average level of maintenance expenditure in that period would be sufficient, on a company wide basis, to avoid deterioration in the period covered by PR99 (2000-05). In other words, Ofwat presently assumes that what has been satisfactory in the past will be satisfactory in the future.[250]

192. Ofwat uses serviceability indicators to determine whether there is a deteriorating trend in serviceability. These are set out in Ofwat information notes 35A[251] and 35B.[252] For the above ground assets (primarily treatment works) the indicators look at the trends in compliance with coliform standards and other numeric consents. For underground water main assets (mainly the pipelines but also incorporating service reservoirs) there are four indicators: number of burst mains, scale of interruptions to supply, low pressure problems, and water quality compliance. For the sewer networks the indicators are: sewer flooding of properties, sewer collapses and pollution incidents.

193. Progress against the indicators is published annually and has been since 1990-91. Ofwat told the Committee that this represented a "longish" run of information upon which to base its assumptions.[253] Ofwat also carries out asset stock surveys every five years and Sir Ian felt that the most recent survey in 1998 confirmed Ofwat's view that serviceability was being adequately maintained.

194. In Ofwat's view serviceability for most companies has not deteriorated over the last seven years. Thus Ofwat concluded in the Final Determinations that there was no need to increase capital maintenance activity. In PR 99 only three water companies were funded for increases in capital maintenance activity to restore serviceability to customers.

195. A clear advantage to Ofwat's indicator approach is that it emphasises the "output" of the network and the actual service which customers receive. However, the evidence put to the Committee throughout its inquiry has suggested that the disadvantages to this method are overwhelming and that it has a number of inherent flaws. These relate to the particular indicators which are used, the reliance on historical data, lack of economic appraisals and forward-looking assessments of asset condition.

196. In his critique of Ofwat's methodology, Professor Binnie argues that the present serviceability criteria do not reflect the need for future maintenance very well because they can be distorted by so many other factors. For example, the frequency of pipe bursts is an indicator which can be influenced by the weather and operational tactics. Recent mild winters have lowered the burst rates as have low pressure management schemes introduced in recent years to reduce leakage. Thus, the indicator can mask the real, underlying condition of the assets and may lead to corrective action being taken too late because the indicator has been too "optimistic".

197. Even if Ofwat could select indicators free of distortion, the present method takes no account of the future condition of the asset stock. Instead it bases 2000-2005 capital maintenance expenditure allowances on changing circumstances over 1994-98. This means that there is no provision for the fact that as assets get older they may need more maintenance. Neither does this approach acknowledge that some new assets may have a shorter life than those that they replace and assets corresponding to historic peaks of building activity will be due for attention at the same time. This backward looking approach appeared completely illogical to a number of witnesses who felt that a more forward-looking approach was required. Professor Binnie concluded that most of Ofwat's serviceability criteria had little relevance to assessing future serviceability, future risk of failure or future capital maintenance requirements. He suggested that forward looking assessments of asset condition along with the capital maintenance needed to meet serviceability criteria provided a more robust way of assessing future capital maintenance requirements.[254]

198. It is this "failure" based approach which concerned our witnesses most. Water UK believed that, if Ofwat's method was followed, only recent failure would allow a company to spend more money than had been spent previously. However, companies were anxious not to fall short of the serviceability criteria and incur the resulting penalties of breaching licence conditions. They therefore wanted to secure funds for precautionary spending. Ofwat, however, argues that companies can choose to spend more if they think it is necessary—by allocating additional spending out of their profits. The Committee accepts that ultimately this option is open to the companies to avoid licence breaches. However, efforts should be made to ensure that Ofwat's methodologies for determining funding levels incorporate more forward-looking elements.

199. The Chief Drinking Water Inspector, Michael Rouse, told the Committee that he would like to see serviceability criteria which do not wait for failures but actually predict and pre-empt those failures so that the DWI can carry on its work on water quality beyond 2005 and 2010.[255] The Environment Agency held similar views and thought Ofwat's approach just measured the rate of failure and whether that rate of failure was low enough to be acceptable. The Agency wanted to see pre-emptive maintenance, preventing sewer collapse for example. If a large new housing estate was being connected to a sewer the Agency wanted to see evidence that the company was considering whether the design capacity of that sewer was going to be exceeded or not and whether the downstream storm overflows were going to operate more frequently than intended and may therefore develop into new problem overflows. However, the Agency felt that the present serviceability criteria seemed to follow, rather than lead, performance.[256]

200. Another key flaw in Ofwat's present approach is that it has not been related to the economic prioritisation of capital maintenance expenditure, ie it offers no framework for directing expenditure to where the largest benefits will be generated. Ofwat has acknowledged that a better understanding is needed of the economic case for the levels of capital maintenance expenditure that are to be financed by customers.[257] Sir Ian admitted to us that there was a gap in Ofwat's information here which he attributed to the water companies not assessing the economics of capital maintenance in the way he would like them to. He said that Ofwat had indicated in its early methodology papers for the review that it would look at both past and future serviceability and had challenged the companies to provide information which would show how future expenditure would relate to future serviceability. He had been disappointed in the plans which the companies had submitted because they did not link the condition of the assets to future serviceability very clearly.[258]

201. The Director explained how he would like the information presented in a letter to water company Managing Directors in April this year (MD 161). Ofwat wants to see each company demonstrate how the flow of services to customers can be maintained at least cost in terms of both capital maintenance and operating expenditure, recognising the trade off between cost and risk whilst ensuring compliance with statutory duties.

202. Ofwat has indicated a number of areas where it would have been helpful if companies had provided further information in the economic appraisals they provided for PR99 in their Business Plans. For example, the impact on operating costs of capital maintenance activity, before and after assets are renewed and the cost of any potential loss of serviceability to customers, including consideration of risk scenarios and their probabilities as well as illustrations of how serviceability to customers would decline, if the activity was not undertaken. Ofwat hoped that such information would help to indicate the extent to which levels of capital maintenance should change, up or down, for future capital maintenance to be economic.

Developing a new approach

203. In Raising the Quality, Ministers endorsed Ofwat's approach to asset maintenance but noted that it would be appropriate in the longer term to develop absolute standards for serviceability and to develop a strategic approach to maintenance.[259] Ofwat and the DETR are now working together to develop a new approach[260] which is clearly needed. Further impetus has been added by the Competition Commission which has recommended, in the course of reviewing the final determinations for Mid Kent Water and Sutton and East Surrey Water, "that more work be done in the industry to broaden the understanding of the relationship between serviceability and asset condition".[261] The Competition Commission was "not persuaded" that the methods adopted by either the Director or the water companies for assessing the level of funding required for infrastructure maintenance were satisfactory.[262]

204. The Committee is concerned that it seems that even some of the most basic information relating to asset maintenance is not collected in any consistent manner across the network. CROSS felt that there was no publically available, reliable or comprehensive information about the underground network from which to monitor maintenance expenditure systematically.[263] Hepworth Building Products, who manufacture drainage and water supply products for the construction industry, warned that "without a clear process for the collection of information, identification of investment needs and regulation of activity, including the age, state and materials of sewers, the asset management plans of water companies are inadequate".[264]

205. The Committee was particularly concerned to hear from both Ofwat and the Environment Agency that although the water companies claimed a range of implied life estimates for sewers and pipes there was no clear information in the public domain which enabled them as regulators to establish the facts. Companies arrive at implied asset lives by looking at their rates of investment. North West Water told us that their renewal rate was 426 years,[265] whilst CROSS found at best 280 years and on one calculation nearly one thousand years.[266] Sir Ian told the Committee that such calculations were illegitimate because they did not allow for the fact that the stock of assets was growing. He felt that the implied life calculations were "frankly nonsense".[267]

206. However, despite the steer provided by MD161 companies remain unclear why the information which they submitted for AMP 3 was not deemed to be adequate by Ofwat and what exactly Ofwat would like them to provide.

207. Sir Ian told the Committee that he accepted that further work was needed regarding the exact relationship between future spending and future serviceability and accepted that he would like to see more analytical work in this area.[268] He wanted universities and other research establishments to look at this issue more systematically.[269] Water UK took the initiative in July this year and organised a "Think Tank" event to share and develop strategies for creating an agenda for action on capital maintenance. The resulting report[270]recommends that new standards of serviceability need to be developed which are more relevant to capital maintenance needs. In its evidence to the Committee, OXERA recommended a number of new factors and methodologies which should be built into a new approach to ensure that the serviceability of assets is maintained at an acceptable level into the long-term future.[271] These requirements would include:

    (a)  Data on asset failure and design to provide failure patterns for each type of asset and help to determine the optimal maintenance programme.

    (b)  Models to link the impact of asset failure on customer levels of service

    (c)  Consideration of the cost and benefit (levels of service) trade-off of expenditure options eg replacement versus renovation and reactive versus proactive maintenance.

    (d)  Preparation of whole life maintenance profiles for an asset in a particular operating role.

208. Water companies need to manage and renew their sewers and water mains in order to develop appropriate levels of service to their customers on a sustainable basis. The Committee is not satisfied that Ofwat's "no deterioration" approach to the maintenance and renewal of underground assets (sewers and water mains) is a logical or acceptable means of assessing the amount of investment which water companies need to meet these requirements. The Committee believes that this approach has amounted to intellectual neglect of this important problem.

209. The Committee therefore very much supports the initiative of the DETR, and the agreement by Ofwat, to develop a new approach. This approach should be forward-looking and should enable companies to adequately prepare to renew and repair the cohorts of sewers and mains which will come up for renewal/rehabilitation simultaneously as a result of historical peaks in building activity.

210. It is imperative that the new approach is in place in time for the next Periodic Review, with water industry support and assistance. The Committee acknowledges Water UK's recent initiative to develop an agenda for assessing capital maintenance needs. This is a key area of responsibility for water companies and the Committee hopes that the industry will now continue to make a pro-active and positive contribution to developing new methodologies.

211. The Committee recommends that the DETR moves rapidly to commission work in this area and examines the suggestions put forward by Water UK and OXERA regarding the necessary elements of new methodologies. It is imperative that water companies and Reporters are fully engaged in the processes of developing and implementing any new approach and that the latter receive appropriate training.

212. In future Ofwat must make clear exactly what data and analysis it expects the companies to provide with respect to their capital maintenance needs.

Wider issues

213. There are a number of environmental and water policy issues which need to be considered in the context of the periodic review process.

Setting the right framework

214. As discussed above it is Ministers who determine the overall policy framework within which the periodic review, and indeed Ofwat and its Director General (the "Director"), all operate. It is therefore important that this framework encourages Ofwat to promote a sustainable approach in its economic regulation of the water industry. Michael Meacher told the Committee that all "Ministers, officials and key representatives of the governing process have got to take account of the sustainability process. We do not live in narrow silos and over there are the sustainability people and the rest of us just go on as if it does not exist".[272]

215. The Director of Ofwat does not have a specific duty to promote sustainable development. Indeed Ofwat believes that such a duty better rests with Government rather than the economic regulator and that Government can further the cause of sustainable development through the use of economic instruments for pollution control.[273] Ofwat's view is that it contributes to, but is not the main party responsible for, promoting sustainable development.[274] The Environment Agency does have a specific duty to promote sustainable development[275] and Ofwat has pointed out that as 96% of the Agency's preferred schemes were included in the 2000-2005 programme the outcome of PR 99 makes a considerable contribution to sustainable development.[276]

216. This attitude that sustainability is not a direct matter for Ofwat is evident in much of Ofwat's work. English Nature pointed out that during PR99 the Director General had acknowledged his duties to further conservation but had "deferred to the Secretary of State and to the Environment Agency, giving his priority to the interests of customers". English Nature also felt that Ofwat's interpretation of the relative priority of duties towards the water companies, the environment and customers was not borne out by what Parliament enacted in the Water Industry Act 1991.[277] This tendency was also picked up by the Environment Sub-Committee of the House of Commons Environment, Transport and Regional Affairs Committee in its 1998 report on sewage treatment and disposal. The Committee noted that the Director General of Ofwat had "seen his role in terms only of protecting the consumer from rising bills". The Committee went on to recommend that although this was an important role, his duties towards the customer should extend—as was originally intended—to protecting the water supply and the environment".[278]

217. Sir Ian has constantly proclaimed the principle of customer affordability, making it clear that it is Ofwat's view that environmentally driven projects should only be financed by the price-cap mechanism if the costs can be properly demonstrated to be less than the measured benefits. This goes further than a sensible cost-effectiveness approach and is contrary to the precautionary principle. It is for the Government to ensure that the Director works within a framework which accommodates this principle in line with Government policy.

218. In its response to the Committee's first report on the Greening Government initiative,[279] the Government agreed that sustainable development should be central to all Government policies and machinery. Departments are now required to consider whether to incorporate sustainable development into the aims and objectives of all new bodies when they are set up.[280] This requirement post-dates the establishment of Ofwat. However, the Government is already committed, as a result of its utilities review, to amend and update the general duties of the Director General to take better account of socio-economic factors and to take on a broader sustainability agenda.[281] The Government has also confirmed that it intends to give Ministers power to give guidance to the Director General about environmental matters and sustainability. The vehicle for these changes is expected to be the forthcoming Water Bill. Originally these measures were to be included in the Utilities Act 2000 but the water provisions were dropped to be considered in a separate bill. The proposal in the original Utilities Bill enabled Ministers to issue guidance to the Director "about the making by the Director of a contribution towards the attainment of any social or environmental policies" which it set out or referred to.[282]

219. Existing provisions in the Water Industry Acts of 1991 and 1999 already provide for environmental guidance and for both regulations and guidance on social matters so the DETR does not expect this to have a profound impact on the interactions between Ofwat and the Department.[283] According to the DETR this move does not reduce any of the Environment Agency's responsibilities but acknowledges the major contribution that the Periodic Review can make to the sustainable development agenda as it encompasses the need to protect the environment, meet consumer needs, and consider the financial stability of the water companies.

220. The Director General of Ofwat should be directly accountable for ensuring that Ofwat makes a positive contribution to the Government's sustainability agenda. The Committee recommends that, in line with the Government's own commitment, the Director General should have a specific duty to have regard to sustainable development.

Water efficiency

  221. Water efficiency is a key part of the companies' Water Resource Plans and water companies have a statutory duty to promote the efficient use of water by their customers.[284] Ofwat is responsible for ensuring that the companies fulfil this duty and requires them to set out a water efficiency strategy and monitors their activities. The Environment Agency and DETR also seek to promote water efficiency.

222. The Agency told the Committee that this efficiency duty was difficult to enforce and for the water companies to fulfill[285] because it is difficult to interpret the impact that a particular efficiency measure has on the use of water. The Agency has been working with Ofwat, DETR and Water UK to improve the information in this area. A three-year UKWIR (UK Water Industry Research Ltd) research project has just begun which seeks to define best practice in water efficiency measurement. The Agency envisaged that this work would possibly move towards developing some sort of water efficiency targets for the water companies which it felt was the right way to go.[286] Mr Meacher was also receptive to the idea of such targets, if effective baselines could be established to measure improvement, and accepted that companies may want to set water efficiency targets for customers in arid areas.[287]

223. However, Water UK did not agree that such targets would be a helpful step at this stage as the companies have already developed strategies for promoting water efficiency over the next five years and submitted these to Ofwat thus demonstrating sufficient commitment in this area.[288] Water UK has also been discussing issues such as product design and labelling with white goods manufacturers, researchers, regulators and the retail industry.[289] Ofwat too believes that it is not necessary to set performance targets for water efficiency as the 1998-99 report on Leakage and Water Efficiency already sets out the water efficiency activities Ofwat expects water companies to undertake.[290]

224. The Agency told the Committee that at present the water companies were undertaking ad hoc investigations and initiatives on water efficiency but this was patchy and some of the incentives on companies did not seem to encourage them to put more effort and money into this area because it would not always yield "short-term savings".[291] The crux of the matter is that the water companies do not directly benefit from any longer term savings to the whole community from additional water efficiency measures, for example avoiding the need for new water supply schemes. Companies only see small savings, largely in chemicals and energy, in the costs of operating the existing supply system. Thus, they have no significant financial incentive to search for successful water efficiency measures. Whilst this system prevails, the regulators, Ofwat and the Environment Agency will always be seeking to cajole and persuade the companies to go further than they may want to.

225. The Committee acknowledges and welcomes the number of water efficiency initiatives being undertaken by the water industry. We believe that companies do not have significant incentives to promote water efficiency and that there would be merit in investigating the feasibility of setting company-specific targets for domestic water use, once a robust methodology for efficiency measurement has been agreed. This would help to focus efficiency efforts and drive the markets for water efficiency and innovation.

Leakage

226. Companies are required to meet mandatory leakage targets which have been set annually by Ofwat since Autumn 1997. Previous to this, water companies were monitored against their own leakage targets. These targets were the result of a ten point plan, presented by the Deputy Prime Minister John Prescott, at the 1997 Water Summit. They were prompted by earlier droughts and water shortages in 1995 which had coincided with peak levels of leakage. The total leakage in 1994-5 was 5,112 Ml/d, equivalent to the daily needs of over 33 million people.[292] Leakage levels have since fallen by 35% to 3,306 Ml/d.[293]

227. The annual leakage targets aim to move the companies towards meeting their economic levels of leakage (ELL) by 2005. Ofwat defines the ELL as the level of leakage at which it would cost more to make further reductions in leakage than to produce the water from another source. This suggests that leakage reduction should be pursued to the point where the long run marginal cost of leakage control is equal to the long run marginal benefit of the water saved.[294] The latter takes account of the operating costs of additional water plus any capital expenditure associated with future resource developments or reinforcements of the network.[295] This should include an assessment of the environmental benefits/disbenefits.[296]

228. In PR 99 the Director set leakage targets for 2000-01 based on the economic levels suggested by the companies if he felt that there was robust analysis to support these. If this was not the case a proxy was set on a "pragmatic" basis but within the framework of economic levels.[297] This year 16 companies will now be monitored against their own leakage targets as recognition that they are showing consistent progress towards robust economic levels of leakage. Ofwat recently reported that water companies' leakage levels have fallen by almost 35% since 1994 and the 2000/1 leakage target is set to reduce net leakage by a further 6%.[298]

229. As with water efficiency measures overall (see paragraph 221), companies have little financial incentive over the next five years to reach their own economic levels of leakage. The benefits which companies see from reducing their leakage are often very small, largely savings in power and chemicals only. They do not receive any immediate benefits themselves from deferring the construction of a new reservoir etc and thus in effect there is market failure. However, politically they do need to be seen to be reducing leakage, otherwise no other resource options will be sanctioned by the Government. How far the companies need to go before the Government is satisfied that they have taken sufficient action is unclear. It is also not clear whether this is below the economic level of leakage. However, Mr Meacher did agree that "one could drive down the level of leakage even below the economic level in the interests of conservation at times of potential drought".[299]

230. The DETR has set up a tripartite group looking at leakage and water efficiency to facilitate the exchange of information between itself, Ofwat and the Environment Agency. The water companies are concerned that they have not been consulted on this tripartite work.[300] However, the DETR confirmed that the companies would be involved in the Tripartite Leakage Study which has been commissioned and funded by the group. This study is investigating the environmental and economic justification for further, long-term reductions in leakage (amongst other topics). The DETR is keen that this study retains its independence from commercial interests as it will inform future policy on leakage reduction.[301] The Committee looks to this new study to clarify how water companies are to investigate the ELL taking account of both economic and environmental costs and exactly what information in this regard needs to be provided to Ofwat.

231. The Government should spell out its long term aims for leakage reduction in the context of water resource policy and clarify in particular whether it wants companies to reduce leakage below their economic levels. If it does, it should explain its reasons.

232. Ofwat should make clear what information it requires to assess where each company stands at present in relation to its economic level of leakage.

The Future

233. In 1997, the Government made it clear that its aim was for the UK to approach the 21st century with a world-class, water-efficient and environmentally sustainable water industry.[302] PR 99 presented a key means of achieving this and looks set to deliver a vast environmental programme and welcome price cuts for customers. However, there are certainly likely to be some important after-shocks which need to be kept in mind as we prepare to embark on the next Periodic Review.

234. The last regulatory price review has left some water companies, already with high debt levels, with serious financial difficulties. They are finding it increasingly difficult to raise the billions of pounds necessary for investment over the next five years and water share prices have been significantly downgraded since the price review. They are now looking for ways to restructure to create greater shareholder value, reduce their debts and avoid becoming takeover targets like Hyder which has now been taken over by the American joint venture group, Western Power Distribution. Companies are also increasingly developing activities which are not regulated in the UK and have branched into areas such as waste management as well as looking for water acquisitions overseas in order to avoid the regulator. Where they are managed well, it is these interests that are providing growth.[303]

235. Kelda's idea of separating asset ownership from operations, selling the assets to pay off debt and return some cash to shareholders is not dead in the water. Kelda's original plan was blocked by Ofwat because it was not demonstrably in the interests of all stakeholders. However, the principle still seems to have widespread support and may well surface again. The new regulator, Mr Philip Fletcher, has said that proposals similar to Kelda's which addressed Ofwat's concerns might "nevertheless be developed" and he is not tied to one "right" model for water company structure.[304] City analysts have already forecast that the specialist (vertically integrated) water companies could soon become a thing of the past.[305] However, Ofwat is clearly cautioning that it is not sufficient for the pressure for change to come solely from shareholders and those with financial interests.

236. The structure of regulation of the water industry and the periodic review itself may well need to change to accommodate new company structures. As the regulatory structure evolves to meet the needs of a maturing, privatised industry so it should also ensure that the long-term interests of the environment are safeguarded.


1  NB: This is a summary only and does not replicate all of the recommendations and conclusions or their full text which are contained in the main body of the report. Back

2  The three Scottish water authorities are regulated by the Water Industry Commissioner for Scotland. Back

3  Ofwat, Final Determinations: Future water and sewerage charges 2000-2005, November 1999, p17 Back

4  The oral and written evidence taken by the Committee is set out in Volume II (HC597-II). Back

5  A note of discussions held on these visits is annexed to this Report. Back

6  Water Industry Act 1991, s2 (1) (a) (ii) Back

7  The role of the regulator as described at http://www.ofwat.gov.uk/rolereg.htm in October 2000 Back

8  Ofwat Press Notice PN 41/96, Ofwat announces review of water company price limits, 15 October 1996 Back

9  Graham Sargent, North West Water balks at watchdog plan to cut price rise, Times, 16 October 1992 Back

10  MD 120 (Letter from the Director General of Ofwat to Managing Directors), Periodic Review in 1999, 15 October 1996 Back

11  Ofwat Press Notice 34/98, Ofwat announces changes to water company licences and the way ahead for changing the tariff basket, 1 September 1998 Back

12  John Hassan, The European water environment in a period of transformation, 1996, p115 Back

13  Q198 Back

14  In the 1997 Budget, Chancellor Gordon Brown announced that introduction of a windfall tax on the "excess profits of the privatised utilities". See Budget Press Releases, Inland Revenue 1, Windfall Tax, 2 July 1997 Back

15  House of Commons Library Research Paper 98/117, Water Industry Bill, 10 December 1998, p51 Back

16  DETR, Raising the quality: Guidance to the Director General of Water Services of the Environmental and Quality Objectives to be achieved by the Water Industry in England and Wales 2000-2005, September 1998, pp 2&4 Back

17  Prospects for Prices: A consultation paper on strategic issues affecting future water bills, October 1998, p23  Back

18  Q199 Back

19  Q195 Back

20  Representing water customers 1999-2000: Annual report of the Ofwat National Customer Council and the ten Regional Service Committees June 2000, p23 Back

21  Q197 Back

22  Q55 Back

23  Q197 Back

24  The average reduction in expected household bills in the period 1999-00 to 2004-05. See Ofwat's Final Determinations, November 1999, Table 5, p23 Back

25  Q192 Back

26  Q199 Back

27  Q324 Back

28  Water UK Press Release, Water UK response to Ofwat's price determinations, 25 November 1999 Back

29  Ofwat ignores pleas on job losses, Water, 15 October 1999 at

http://www.water.org.uk/magazine/bulletins/waternews/23.html Back

30  Water UK Press Release, One in four jobs could go in water industry, 11 October 1999 Back

31  Major job losses follow harsh regulatory review, Water, 10 December 1999

at http://www.water.org.uk/magazine/bulletins/waternews/49.html Back

32  Michael Rouse, Drinking Water Quality Regulation over the next few years, Wti Conference on Regulation, 26 January 2000 Back

33  The Competition Commission allowed 5-year, average K-values (%/yr) of -2.8 (Mid Kent Water) and -2.5 ( Sutton and East Surrey Water). These compare with Ofwat's determinations of -4.0 and -5.1. See Ofwat press notice 40/00, Ofwat announces Competition Commission decisions following companies' appeals against price limits, 8 August 2000. Back

34  Ibid Back

35  Q144 (Environment Agency) and Q195 (Ofwat) Back

36  Water price rises just won't wash, Independent, 29 July 1994 Back

37  Q67 Back

38  Ev, p102, para 16 Back

39  Q97 Back

40  Competition in water, Speech by Philip Fletcher, Director General of Water Services to The Economist, 11th Annual Water Industry Conference, 10 October 2000 Back

41  Ev, p146, para 2  Back

42  As this report was being prepared the Government published its draft Water Bill for consultation (Cm 4908, November 2000) Back

43  Ev, p148, para 13 Back

44  Ev, p94 Back

45  http://www.environment­agency.gov.uk/aboutus/who_we_are/who_we_are_our_aims.htm Back

46  Ev, p62, para 2.2  Back

47  Q161 Back

48  Ev, p147 para 4 Back

49  Ev, p146, para 3 Back

50  Q405 Back

51  Ev, p27 Back

52  Ev, p3, para 3c Back

53  Q282 Back


55  54  QQ 62 & 63 Back

 Back

56  DETR, Raising the quality: Guidance to the Director General of Water Services of the Environmental and Quality Objectives to be achieved by the Water Industry in England and Wales 2000-2005, September 1998, para 11 Back

57  Ev, p214, para 19 Back

58  Ev, p28 Back

59  Q360 Back

60  Q212 Back

61  Ev, p101, para 12 Back

62  Water UK memo p7 para e) Back

63  Prospects for Prices, p 27 Back

64  Q212 Back

65  Ev, p199, para a) Back

66  Ev, p147, para 6  Back

67  Ev, p4, para 3e Back

68  Ev, p4, para 3e Back

69  Ev, p101, para 11 Back

70  Q343 Back

71  Environment Agency, A price worth paying: The Environment Agency's proposals for the National Environment Programme for Water Companies 2000-2005, May 1998  Back

72  DWI Information Letter 7/98, The Periodic Review of Prices and AMP 3 Back

73  DETR, Raising the quality: Guidance to the Director General of Water Services of the Environmental and Quality Objectives to be achieved by the Water Industry in England and Wales 2000-2005, September 1998 Back

74  Ibid p4 Back

75  Ibid p4 Back

76  Ibid p4 Back

77  Ibid p8 Back

78  QQ56 & 113 Back

79  Ofwat Press Notice, PN 41/96, Ofwat announces review of water company price limits, 15 October 1996 Back

80  Q113 Back

81  Q113 Back

82  Prospects for Prices: A consultation paper on strategic issues affecting future water bills, October 1998, p4 Back

83  For example Ev, p95 Back

84  Ofwat, Assessing the scope for future improvements in water company efficiency: a technical paper, April 1998 Back

85  Ev, p101, para 13 Back

86  DETR Press Notice 179, Meacher tells water companies they can improve environment and cut bills, 1 March 1999 Back

87  Ofwat, Prospects for Prices: A consultation paper on the strategic issues affecting future water bills, October 1998, p4 Back

88  Ibid p7 Back

89  Q352 Back

90  Ev, p168, para 2 Back

91  Ev, p63, para 31 Back

92  Q105 Back

93  MAT Scoring and Weighting System, Environment Agency, section 1.1, available at: www.environment-agency.gov.uk/ourservices/consultations/mult_attrib.htm Back

94  Ev, p64, para 3.18 Back

95  Ev, p65, para 6.6 Back

96  Ev, p65 Back

97  Ev, p65 Back

98  Cm 4345, DETR, A better quality of life: A strategy for sustainable development for the UK, May 1999, p76 para 8.30  Back

99  Ev, p146, para 3 Back

100  DETR, Raising the quality: Guidance to the Director General of Water Services of the Environmental and Quality Objectives to be achieved by the Water Industry in England and Wales 2000-2005, September 1998, p8 Back

101  Environment Act 1995, S39 Back

102  Q131 Back

103  Ev, p63, para 3.8 Back

104  Q131 Back

105  Ev, p105, para 20 iii)  Back

106  Q264 Back

107  Q267 Back

108  Final Determination p112, Section 8.1.1 Back

109  Q263, Ev, p105, para 20 iii) Back

110  MAT Scoring and Weighting System, section 1.1, Environment Agency, available at www.environment-agency.gov.uk//ourservices/consultations/mult_attrib.htm Back

111  Ev, p104, para 20 Back

112  Ev, p105, para 20 iii) Back

113  Q39 Back

114  Q147 Back

115  Ev, p64, para 3.13 Back

116  Q133 Back

117  Ev, p188, para 15, Ev, p199, para b) Back

118  Ev, p2, para 3a) Back

119  Ev, p2, para 3a) Back

120  Ev, p103, para 17 Back

121  Ev, p171, para 17 Back

122  QQ9 & 10 Back

123  Q6 Back

124  Ev, p98, para 3 Back

125  Ev, p174, para 1 Back

126  NCC Press Notice, NCC calls for steeper falls in household bills, 21 November 1999 Back

127  Ev, p100, para 8 Back

128  Q85 Back

129  Q85 Back

130  Q85 Back

131  Ofwat, MD164, 31 July 2000, p2 Back

132  Ofwat press notice 1/98, Senior industrialists to advise water regulator, 21 January 1998 Back

133  Ev, p66, para 9.1 Back

134  Ev, p199, para a) Back

135  Ofwat, Having your say, 3 October 2000, p9 Back

136  Ibid p6 Back

137  See Fifth Report, 1998-99, Volume II, HC 384 II, Ev, p88 Back

138  Q87 Back

139  Ev, p27 Back

140  Ofwat, MD 124, February 1997, p9 Back

141  Ev, p27 Back

142  Q294 Back

143  Ev, p100, para 7 Back

144  MD 164, Ofwat, 31 July 2000, p4 Back

145  Ofwat Letter to Regulatory Directors (RD 17/00), 31 July 2000, p4 Back

146  Q296 Back

147  Q92 Back

148  Ev, p99, para 6 Back

149  Q300 Back

150  Environment Agency, Achieving the quality: The Environment Agency's view of the benefits to the environment of water company investment over the next five years, June 2000 Back

151  Q105 Back

152  Ev, p103, para 19 Back

153  Ev, p190, para 34 Back

154  Q139 Back

155  Ev, p5, para 5a) Back

156  Q210 Back

157  Q211 Back

158  DETR, Raising the quality: Guidance to the Director General of Water Services of the Environmental and Quality Objectives to be achieved by the Water Industry in England and Wales 2000-2005, September 1998, p5 Back

159  Ofwat, Final Determinations: Future water and sewerage charges 2000-2005, November 1999, p9 Back

160  Ibid p16 Back

161  Ev, p102, para 15 Back

162  Ev, p101, para 12 Back

163  Ofwat, Final Determinations: Future water and sewerage charges 2000-2005, November 1999, p101 Back

164  DETR, Raising the quality: Guidance to the Director General of Water Services of the Environmental and Quality Objectives to be achieved by the Water Industry in England and Wales 2000-2005, September 1998, para 109 Back

165  Ibid para 110 Back

166  Ev, p96 Back

167  Q224 Back

168  Q188 Back

169  Ev, p95 Back

170  Q106 Back

171  Ev, p96 Back

172  Ev, p108 Back

173  Q110 Back

174  In 1999 95% of the UK river network was assessed as being of good or fair chemical quality compared with 94% (1988) and 92% (1990). See DETR News Release RW-10, River. Water quality headline indicator for sustainable development: 1999, 21 September 2000 Back

175  Q125 Back

176  Q128 Back

177  Ev, p169 Back

178  Ev, p102, para 15 Back

179  DETR News Release 562, Major steps to protect England's wildlife-Prescott, 25 August 2000 Back

180  See Ofwat letter to Managing Directors, MD 149, July 1999 Back

181  Ofwat press notice 49/00, Three companies ask Ofwat to re-examine their price limits because of special changes to their financial position, 16 October 2000. Back

182  PN 35/98, Water regulator confirms increase in water bills in North East to finance higher environmental standards,14 September 1998 Back

183  Figures provided in Ofwat, Final Determinations: Future water and sewerage charges 2000-2005, Table 20, p110, November 1999  Back

184  Ibid p162 Back

185  Ev, p182, para 14 Back

186  Ev, p6, para 5d) Back

187  Ev, p202 Back

188  Ev, p218, paras 3.1-3.2 Back

189  The House of Commons Environmental Audit Committee's Sixth Report (July 2000): Budget 2000 and the Environment (Summary (d)) highlighted that major, environmental tax reform must play a more effective role in relation to water. The Committee noted that a failure to implement the polluter pays principle through a pesticides tax, was resulting in substantial hidden subsidies for intensive farming as against organic farming for example, as well as extra costs borne by householders and business through water prices Back

190  Snapshots of the Environment: Integrated River Basin Management, Environment Agency, 1998, para 5.6  Back

191  Q42, Ev, p4, para 4b) Back

192  Ev, p96 Back

193  Wessex Water Press Release, Wessex Water to pay farmers to protect water sources, 7 April 1998 Back

194  Letter from Andrea Husband (Compliance Scientist) Wessex Water to Eric Lewis (EAC Committee Specialist), 19 November 1999 Back

195  Q116 Back

196  Q116 Back

197  Ev, p170 Back

198  Q117 Back

199  Q117 Back

200  Ev, p3, para 3c) Back

201  Ev, p88 Back

202  Ev, p36, para 6 Back

203  Ev, pp29 & 42 Back

204  Ibid Back

205  QQ165 & 166 Back

206  Q166 Back

207  Q166 Back

208  Q169 Back

209  Q170 Back

210  Q171 Back

211  Q172 Back

212  Q141 Back

213  Q140 Back

214  Ev, p61 Back

215  Part 16, Section 2 to the General Permitted Development Order, 1995 Back

216  Ev, p169 Back

217  Ev, p30 Back

218  Ofwat, Final Determinations: Future water and sewerage charges 2000-05, Ofwat, p164 (5) Appendix E, November 1999 Back

219  Ev, p196 Back

220  Q262 Back

221  Ev, p170, para 12 Back

222  Ev, p216, para 1.1 Back

223  Ev, p201 Back

224  Q111 Back

225  Q112 Back

226  Q131 Back

227  Q10 Back

228  Q39 Back

229  Creating a sustainable vision: Progressing the Environment Agency's contribution to sustainable development by way of a better environment in England and Wales, Environment Agency, Consultation Draft June 2000 Back

230  Ibid p27 Back

231  Drinking water quality has risen each year since privatisation and the quality of rivers and bathing waters is improving Back

232  Professor Chris Binnie, Future Water and Sewerage Charges 2000-2005: Draft determinations-The implications for capital maintenance expenditure, October 1999, p7, para 1 Back

233  Ev, p174, para 1 Back

234  HL 50-I (Session 1990-91), Tenth report of the House of Lords Select Committee on the European Communities, Municipal Waste Water Treatment, 14 May 1991 Back

235  Q366 Back

236  Q366 Back

237  Ev, p138 Back

238  Final Determinations: Future water and sewerage charges 2000-05, Ofwat, November 1999, p106, para 7.3.4 Back

239  Q218 Back

240  Q217 Back

241  Q115 Back

242  Ofwat,Final Determinations: Future water and sewerage charges 2000-05, November 1999, p105 Back

243  Ofwat, Final Determinations: Future water and sewerage charges 2000-05, Ofwat, November 1999, Figure 19 showing total capital maintenance expenditure, p102 Back

244  Ev, p66, para 7.7 Back

245  Professor Chris Binnie, Future Water and Sewerage Charges 2000-2005: Draft determinations-The implications for capital maintenance expenditure, October 1999 Back

246  Ev, p10 Back

247  The North West Customer Service Committee has recently highlighted this problem and written to the Environment Minister, Michael Meacher, to request that some of the company's funding for environmental and water quality improvements are diverted to tackle sewer flooding of homes. See CSC Press Notice 09/00NW, Local watchdog demands end to sewer flooding misery, 19 October 2000 Back

248  Q12 Back

249  Ofwat, Final Determinations: Future water and sewerage charges 2000-05, p73, November 1999, para 4.6 Back

250  Q218 Back

251  Ev, p134, Ofwat Information Note 35A, Serviceability of the water main and sewer networks in England and Wales up to March 1999, March 2000 Back

252  Ev, p140, Ofwat information note 35B, Serviceability of water treatment works, water storage, water pumping stations, sewage treatment works, sewage pumping stations and sludge treatment facilities in England and Wales up to March 1999, March 2000. Back

253  Q217 Back

254  Professor Chris Binnie, Future Water and Sewerage Charges 2000-2005: Draft determinations - The implications for capital maintenance expenditure, October 1999, p52 Back

255  Q172 Back

256  Q145 Back

257  Ofwat, MD 16, April 2000 Back

258  Q217 Back

259  DETR, Raising the quality: Guidance to the Director General of Water Services of the Environmental and Quality Objectives to be achieved by the Water Industry in England and Wales 2000-2005, September 1998 Back

260  Q172 Back

261  Ofwat Press Notice 40/00, Ofwat announces Competition Commission decisions following companies' appeals against price limits, 8 August 2000 Back

262  Mid Kent Water plc: A report on the references under sections 12 and 14 of the Water Industry Act 1991, Competition Commission, September 2000, pp 24-5; and Sutton and East Surrey Water plc: A report on the references under sections 12 and 14 of the Water Industry Act 1991, Competition Commission, September 2000, p25 Back

263  Ev, p148 Back

264  Ev, p212 Back

265  Ev, p258 Back

266  Ev, p177, para 7 Back

267  Q229 Back

268  Q218 Back

269  Q235 Back

270  Ev, pp33-42 Back

271  Ev, p184, para 4 Back

272  Q402 Back

273  Ev, p96 Back

274  Ibid Back

275  Environment Act 1995 Back

276  Ev, p96 Back

277  Ev, p188, paras 16 & 17 Back

278  HC 266 -I (Session 1997-98) Second Report of the Environment, Transport and Regional Affairs Committee, Sewage Treatment and Disposal, February 1998, para 259 Back

279  The Government's response to the Environmental Audit Committee's Report on the Greening Government Initiative, November 1998 Back

280  Greening Government: First annual report of the Green Ministers Committee 1998/99, July 1999, p41 Back

281  Q402 Back

282  Utilities Bill, s110 2A, 20 January 2000 Back

283  Ev, p150, para 18 Back

284  Reference to Act Back

285  Q119, Q330 Back

286  Q119 Back

287  Q133 Back

288  Ev, p29 Back

289  Ibid Back

290  Ev, p106, para 21 Back

291  Q119 Back

292  Based on Ofwat's assumption that 2,000Ml/d is enough to meet the daily needs of 13 million people stated in Ofwat Press Notice 46/00, Ofwat report shows water leakage continues to fall, 28 September 2000 Back

293  Ofwat, Leakage and the efficient use of water: 1999-2000 Report, September 2000, p6 Back

294  Ev, p126a) Back

295  Q242 Back

296  Ev, p126(a) Back

297  Ofwat, Final Determinations: Future water and sewerage charges 2000-05, November 1999, 127, para 9.5 Back

298  Ofwat Press Notice, PN 46/00, Ofwat report shows water leakage continues to fall, 28 September 2000 Back

299  Q373 Back

300  Ev, p27 Back

301  Ev, p170 Back

302  Environment Agency, A price worth paying: The Environment Agency's proposals for the National Environment. Programme for Water Companies 2000-2005-A submission to Government, May 1998 Back

303  Oliver Ralph, Privatisations: Time to Sell your Favourite Shares-Beginning with the High-Financial Times Business Limited, Investors Chronicle, 6 October 2000, pp24-27 Back

304  Competition in water, Speech by Philip Fletcher, Director General of Water Services to The Economist, 11th Annual Water Industry Conference, 10 October 2000 Back

305  For example, E-Water, Issue 34, UK Water companies could become a thing of the past, UBS Warburg report, 18 September 2000 Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2000
Prepared 14 November 2000