Letter to the Committee from Ministry
of Defence on the 1998-99 Spring Supplementary Estimates
Thank you for your letter of 12 March requesting
on behalf of the Committee explanations for a number of the significant
changes contained in the Department's 1998-99 Spring Supplementary
Estimates. I am sorry to have been unable to meet your original
deadline.
In broad terms, the purpose of the Department's
Spring Supplementary Estimates was to:
realign provision, both within and
across the three Defence Votes, to reflect (a) changes in the
pattern of anticipated expenditure (principally in respect of
transfers of management responsibility between TLBs and the PE
Business Units); and (b) decisions to aggregate estate disposals
receipts in 2nd PUS's TLB and provision for Telecommunications
Services in VCDS's TLB;
reflect the net additional costs
of the implementation of Strategic Defence Review decisions;
draw onto Vote the Department's entitlement
to End Year Flexibility in respect of its underspend of £225.2
million against the 1997-98 Defence budget cash limit;
draw on to Vote the additional funding
of £85 million from the Reserve agreed by the Treasury as
a contribution towards the unprogrammed costs of ongoing military
operations in the Balkans and over Iraq.
A number of these changes are, of course, linked.
In particular, increases in provision for the PAOs and underspend
in the PE business units reflect the transfer of responsibility,
and hence financial provision, to the PAOs from the PE for particular
items of equipment.
The trend to underspend on the equipment budget
also reflects the Department's determination to protect cash limits,
against the background of previous overspends and related criticism.
As a result, particular care has been taken so as not to incur
additional expenditure to fill the gaps left by slippage in the
equipment programme. Effective end-year expenditure control measures
were also implemented. Thus reducing the risk of overspend inevitably
leads to a degree of underspend. The specific aspects on which
the Committee has requested further explanation are addressed
below, in the order raised in your letter.
SECOND SEA
LORD
The 8 per cent increase in expenditure provision
(some £40 million) in Second Sea Lord's TLB was mainly due
to the following: additonal provision to compensate the TLB for
the aggregation of land disposal receipts into 2nd PUS's TLB (£15
million); the transfer of management responsibility from Commander
in Chief Fleet's TLB in respect of Royal Marines' Training (£7
million); the implementation of SDR measures(£5 million);
and some £14 million for the additional costs of allowances,
training, and the implementation of Resource Accounting and Budgeting.
2ND PUS
The 10 per cent increase (£60 million)
in 2nd PUS's provision for Other Current expenditure was
made to cover the inherent risk in corporate expenditure for which
2nd PUS is responsible, principally in respect of claims against
the Department, the timing and size of which are beyond the Department's
effective control. The 250 per cent increase in Appropriations
in Aid provision (£187 million) reflects the reaggregation
of all land disposal receipts to the DEO Agency within 2nd PUS's
TLB. This follows from the SDR recommendation that the Chief Executive
of the Defence Estate Organisation should assume managerial and
financial responsibility for all property assets after their release
by TLBs.
VCDS
The 12 per cent increase (£185 million)
in expenditure provision within VCDS's TLB had two main components.
The main element related to the aggregation of all funding (£81
million) for Defence Fixed Telecommunications Service provision
into the Defence Communications Service Agency within VCDS's TLB.
This reflects a Public Private Partnership arrangement by which
the return on the capital investment made by the contractor (BT
Inca) is secured through payment by the Department for usage and
service charges. A large element of the funding was transferred
from the Procurement Executive, whose funding for the procurement
of telecommunications equipment was no longer required following
the move to a service only contract. The second component of the
increase, amounting to some £65 million, was additional funding
to cover the unprogrammed costs of overseas operations, £60
million of which related to ongoing military operations in the
Balkans.
THE PRINCIPAL
ADMINISTRATIVE OFFICER
(PAO) TLBS
The respective increases in provision were CFS
9 per cent (£175 million), QMG 11 per cent (£108 million),
and Logistics Command 5 per cent (£76 million). The main
element of these increases was the transfer of some £198
million from the PE Business Units to the PAOs, parallel with
the transfer of responsibility for certain equipments. The further
increases to the PAOs' provision included: provision for the unprogrammed
costs of support to military operations in the Balkans and the
Gulf (£85 million); the implementation of SDR measures (£17
million); and risk in the programme associated with uncertainities
over the performance of industry and the timing of its billing
(£59 million).
COST OF
OVERSEAS OPERATIONS
The £310 million increase in the Defence
budget cash limit (comprising an EYF entitlement of £225
million plus a further £85 million) reflected, inter alia,
the Government's contribution towards the unprogrammed cost of
overseas operations. Although these operations were forecast to
cost some £200 million, at the time of the Supplementary
Estimates it was the Department's judgement that around £115
million of this could be met from funds held centrally against
contingencies. The total forecast of unprogrammed overseas operations
this year, excluding the costs of the current air operations,
breaks down as follows:
|
| £M
|
|
| IFOR | 19
|
| SFOR (including supporting air operation) |
141 |
| OSCE led Kosovo Verification Mission (KVM) |
1 |
| KVM Extraction force | 6
|
| Gulf Operations | 33
|
| Total | 200
|
|
PE EXPENDITURE
The HCDC has commented that despite the fact that Vote 3
was underspent by some £203 million on 1997-98, its 1998-99
cash limit has nevertheless been reduced. There is, however, no
simple correlation between last year's Vote 3 underspend and this
year's PE equipment programme. For example, the relationship is
masked by transfers of responsibility between the PE and the PAOs
and the consequent transfer of funding from Vote 3 to Vote 2.
There was an unusually high level of transfers this year (£198
million). In strategic terms, natural slippages in the PE programme
this year have enabled the Department to protect its overall cash
limit through avoiding backfill. This was also the case in 1997-98.
Another factor contributing to the reduced funding requirement
on Vote 3 in the current year was the very late stage at which
the Department's claim on the Reserve for EYF and funding relief
for overseas operations was approved. The effect of this was to
leave the Department with little opportunity to reverse the deliberate
and prudent management action taken earlier in the year to constrain
Vote 3 expenditure against the prospect of a failure to secure
the full level of additional funding sought in the Supplementary
Estimates. Unlike the slippage from 1997-98 into 1998-99, this
year's anticipated underspend on Vote 3 is not currently expected
to flow through in 2000-01, but to add to FY 1999-2000 expenditure.
In respect of the PE business units specified, the reasons
for the individual underspends cited are consistent with the overall
underspends on the procurement budget described in the preceeding
paragraphs.
1 April 1999
|