Supplementary memorandum submitted by
Mr Huw Vaughan Thomas, Chief Executive, Denbighshire County Council
The House of Commons Welsh Affairs Select Committee
agreed that I could submit a further memorandum surrounding three
points:
A. The Steps that Denbighshire County Council
took to obtain information from the outgoing Councils
B. Specific Observations from Mr Lloyd Conaway
C. The Mark Lewis memorandum.
The following is my additional response.
A. THE STEPS
THAT DENBIGHSHIRE
COUNTY COUNCIL
TOOK TO
OBTAIN INFORMATION
FROM THE
OUTGOING COUNCILS
INTRODUCTION
Following the Welsh Affairs Committee's fact
finding exercise in Rhyl Town Hall on 22 March, I was invited
to make some additional observations on the liaison arrangements
which prevailed between the former Rhuddlan Borough Council and
the Shadow Authority. Below I provide additional detail showing
that liaison was not superficial but was appropriate and adequate
to the situation which the Authority was being presented with.
I would however like to make some preliminary observations regarding
the context.
CONTEXT
Members of the Committee need to be aware of
the restrictions on liaison between the two authorities arising
from reorganisation.
Officers appointed to this authority
during the shadow year, apart from two employees, were appointed
on a part time basis. They had to carry out their existing duties
as well as prepare for the new authority. In all cases they were
doing so very much on their own as supporting staff had not been
appointed and very often there were depletions in the former authorities'
staff arising from appointments elsewhere.
The handful of officers appointed
to Denbighshire prior to April 1996, therefore, had to be very
economical with their time and deploy their resources rationally.
It would not have been logical to focus on areas where the assurances
given repeatedly by the Chief Executive and Section 151 Officer
of the former Rhuddlan Borough Council described a satisfactory
and problem free situation.
Time had to be spent where problems
had been identified and in this connection I would advise the
Committee that I was appointed to an authority whose transitional
bodies had undertaken no preparation work with regard to the political
or internal management arrangements. As my appointment was also
late in the series of appointments of Chief Executives, subsequent
Director and Heads of Service appointments were also made later.
The Authority started its life therefore with a certain disadvantage
with respect to the preparation time available before reorganisation.
Also with the benefit of hindsight,
decisions regarding the capital programme which had a significant
effect upon the size of the Rhuddlan inheritance all appear to
have been taken prior to the setting up of the Shadow Authority.
The largest single contributory factor to the £3.9 million
of unfinanced debt as my earlier memorandum states was taken in
March 1995.
In consequence the Authority lacked any information
which would have suggested that a greater scrutiny was required
and when it did receive the information, beginning of April 1996,
it was too late to enable other options to be fruitfully explored.
CO -OPERATION
AND LIAISON
WITH THE FORMER
AUTHORITY BY
DENBIGHSHIRE COUNTY
COUNCIL
Chief Executive Level
It has to be remembered that the important liaison
would have been between the relevant officers taking over the
specific responsibilities. This is where the level of detail would
have been discussed enabling a clear picture of the responsibilities
to emerge.
My main concern was in setting up the new authority,
getting the staff in place, designing and producing the service
delivery plan, and liaising with the various authorities on transfer
arrangements as well as in setting the budget for the Authority's
first year. Regular meetings with the former Chief Executives
were not therefore a pressing concern or even a necessity once
an agreement on co-operation on staffing matters had been achieved.
On the issue of the level of commitment I was given to understand
by the former Rhuddlan Chief Executive at a meeting on 12 July
1995 and again on 8 September 1995 that the level of commitment
was in the region of £300,000. As can be seen below and in
my Memorandum, this figure was within a range which was consistently
supplied to officers of this Authority.
Over staffing appointments co-operation was
achieved at my very first meeting with the Denbighshire Shadow
Authority secretariat in 17 July 1995, comprising the Chief Executive
of Rhuddlan Borough Council, Glyndwr District Council and the
Deputy Chief Executive of Clwyd County Council. Mr Lake explicitly
advised that he would give full permission for staff appointed
to Denbighshire from his authority to focus on Denbighshire work,
albeit on a part-time basis. He stated that he saw little point
in meeting of the Secretariat and stated that his responsibility
would be to manage Rhuddlan until reorganisation date. Similar
assurances were received from the other members of the Secretariat.
Overall arrangements with regard to staffing were dealt with on
an inter authority basis and became increasingly the responsibility
of the Head of Personnel once he was appointed in September 1995.
Given that little work appeared to have been
done by the Shadow Authority secretariat up to my appointment
on the financial base of the new authority, sought a secondment
from both Glyndwr and Rhuddlan authorities financial departments
so as to prepare for the new authority's first financial year.
And in the case of Rhuddlan Gail Shaw was nominated by Mark Lewis,
Rhuddlan Borough Council's Director of Finance for this task.
FinanceStatement by the Director of Finance
Following my appointment in October 1995, in
accordance with standard practice, I approached Gail Shaw, the
Capital Accountant with Rhuddlan Borough Council to obtain the
usual information regarding carry over to validate the £300,000
figure in general circulation. I was surprised that she explained
that she would have to seek detailed information from the Chief
Executive Officer. Although not concerned about the prima facia
extent of the carry over being approximately 10 per cent of anticipated
capital programme.
By mid January I was concerned at the lack of
progress by Ms Shaw and requested Mr C Taylor (Clwyd County Council)
to pursue the matter on my behalf. This led directly to the fax
of 24 January 1996, indicating £425,000 rollover.
As Mr Lake was the Senior Officer in Rhuddlan
Borough Council and was a qualified accountant and the Section
151 Officer, I felt entitled to rely on his information.
In early March it is normal practice to review
the capital programme with a view to fine tuning the matching
of expenditure and resources and finalised estimated impact on
the following year. Mr Taylor again approached Mr Lake but was
informed that all the information was in the files which would
be available on 1 April and not before. As there was no indication
of any significant change and there was only a short time until
1 April, further argument seemed a waste of scarce time.
On a separate matter, the debt analysis of the
Welsh Office more accurately reflects the impact on the County's
finances as it excludes Housing Revenue Account. By statute the
HRA must be kept totally separate from County fund and it is the
impact on the latter that is critical; Inclusion of the HRA figures
serves only to cloud the issue of the impact of the Rhuddlan Borough
Council programme.
Planning and Economic Development
The Director of Planning and Economic Development
and The Head of Economic Development met with Mr Lake on 25 January
1996. Efforts by both Denbighshire officers to arrange an earlier
meeting had been unsuccessful. A presentation on the background
to Rhuddlan's strategy was given together with an indication of
the immediate challenges.
Both officers began work on the immediate matters
acquainting themselves with the detail of projects and arranging
reports, where appropriate, to Denbighshire.
Mr Lake invited both officers to attend the
Rhuddlan Working Parties and while both indicated their willingness
to attend they pointed out that they were already working for
two Councils and the task of preparing for the transfer of functions
was becoming more demanding. Both attended meetings on College
expansion proposals and on an urban regeneration scheme but the
pressure of commitments elsewhere made further attendances impossible.
Mr Lake also indicated a rollover commitment
of £320,000 for Denbighshire arising from existing commitments.
He indicated that the cost of schemes had been given to Denbighshire's
Head of Finance and that a further provision of £80,000 should
be set aside to cover future equipment costs at Ffrith Beach.
This provision was never made nor was the equipment ever provided
as the reality of the final Rhuddlan became clear.
B. SPECIFIC OBSERVATIONS
FROM MR
LLOYD CONAWAY
With regard to Mr Lakes' Tourism remarks regarding
liaison arrangements with Mr Lloyd Conaway, Head of Tourism and
Leisure he had provided the following detailed note.
CONTEXT/BACKGROUND
My name is Lloyd Conaway, I am Head of Tourism
and Leisure with Denbighshire County Council. Prior to Reorganisation
I was Assistant Chief Executive at Colwyn Borough Council, with
special responsibilities for Leisure, Tourism and Economic Development.
I was appointed in October 1995 and for the period November 1995
to March 1996 I worked approximately 50 per cent of my time with
Colwyn Borough Council and 50 per cent of my time on Denbighshire
County Council issues, there were large work load demands during
this time.
I was present at the Welsh Affairs Select Committee
on Monday, 22 March 1999 and am able to chronologically set out
my recollection of the issues surrounding my involvement. Fortunately,
I keep my diary and record books and they have helped with my
recollections.
DETAILS
I did not meet with Mr Lake in the Autumn of
1995 as stated in his written submission. We met on Monday, 22
January 1996. The meeting was arranged over the telephone. It
was a useful meeting when Mr Lake gave a brief resume of the nature
of the projects and the background to the issues surrounding Rhuddlan's
strategic approach. At my meeting with Mr Lake he told me that
there would be about £330,000 capital required to complete
the schemes from Denbighshire.
During this meeting I felt that there was not
a great deal to be gained from me spending a lot of time on the
financial issues and grants partnerships. My view was that this
had already been done and I was more interested in what Denbighshire
was going to inherit and how this was to be managed, in particular
finding tenants.
Mr Lake agreed with this sentiment and explained
to me that within Rhuddlan he regarded his job as providing the
policy, visionary leadership role, securing the finance, liaising
with consultants, quantity surveyors and architects and driving
the projects forward. When they were finished within Rhuddlan,
he would then pass them on, completed, to the Director of Tourism
for him to manage. Due to the imminence of reorganisation I agreed
to focus on management issues. Bearing in mind, the short time
scale and work load demands, presented by having to manage Colwyn
Borough Council's service and develop the new Denbighshire, this
appeared to both of us a sensible way forward.
I do not recall a discussion about my getting
involved in working groups, I do not recall receiving any advice
or formal notice verbally or in writing as to when these working
groups were taking place. With hindsight, I would not see any
great benefit attending such groups in any case. As I have already
highlighted above, I felt the important issue as far as I was
concerned, was to look at the future management of these properties.
There was no benefit in me getting involved in debates with contractors,
architects or consultants on these issues, that was clearly a
matter for Rhuddlan.
Mr Lake was pleasant and helpful during the
meeting and did offer his continued assistance during the lead
up to reorganisation. We agreed that I should continue to discuss
these issues with Rhuddlan's Director of Tourism and his Team
in order for me to get a feel to understand how the existing facilities
were being operated.
From this meeting with Mr Lake up until reorganisation,
(1 April 1996), I visited Russell House on many occasions speaking
with various staff. There was no requirement until the end of
March 1996 for me to have any office space, I simply took advantage
of meeting rooms and met people in their own offices. I do not
recall Mr Lake offering me secretarial support and in any case
this was not required as I already had my own secretary at Colwyn.
During the January to March period of early
1996 I met with various individuals who I believed were important
to talk to, bearing in mind the imminence of taking up responsibility
for managing these new facilities. During these times I had discussions
and meetings with the Director of TourismRhuddlan Borough
Council, Leisure Services OfficerRhuddlan Borough Council,
Legal DepartmentRhuddlan Borough Council, Commercial Agent
(retained by Rhuddlan Borough Council) and various Council Members.
I do not recall a verbal reminder from Mr Lake
with regard to meeting him, although as I have already explained,
by this time I had developed a well established network in order
for me to be kept up to speed on the issues which I felt to be
important. I was involved in management arrangements, for example,
tenancies, advertising and promotion, lease arrangements with
tenants, securing further tenants, meeting prospective tenants,
that was what I concentrated upon.
During this period, I began to meet with potential
investors in the Ffrith development and the Children's Village.
Discussions began to take place which involved lease arrangements,
rental levels and during this period we began to make arrangements
to market and advertise the sites more fully.
I felt my single biggest responsibility was
to try and drive and move these projects forward and secure tenants
and make them economically viable.
I do not believe therefore, that a valuable
opportunity was lost. In fact, Mr Lake's co-operation was helpful
and I took every advantage of every opportunity that was available
to me to move the projects forward from a management point of
view. My initial enthusiasm therefore did not evaporate, in fact,
quite the contrary.
CONCLUSION
In conclusion therefore, I strongly believe
that I established, with the assistance of Mr Lake and other officers
and Members within Rhuddlan, a proper and appropriate formal liaison
mechanism during the January, February, March period of 1996.
As I have previously stated I particularly concentrated on the
future management issues as required by Denbighshire and left
Rhuddlan to manage their responsibilities. My enthusiasm did not
wane, I took advantage of offers made to me for assistance and
on 1 April 1996 was in a reasonable position to be able to commence
my duties with Denbighshire on a full-time basis.
C. THE MARK
LEWIS MEMORANDUM
The Mark Lewis Memoranda regarding financing of
Rhuddlan's 1994-95 Capital Programme
Memorandum dated 7 June 1995 from Mark Lewis,
Rhuddlan's Director of Finance to the Chief Executive.
This memo raised concern regarding the funding
of Rhuddlan's capital programme and identified an estimated shortfall
of £2.5 million.
It went on to express serious concerns about
the financing position for the 1995-96 programme.
Memorandum dated 21 August 1995 to Mark Lewis,
Rhuddlan's Director of Finance from the Chief Executive.
Mr Lake's response to the 7 June memo advising
accruals be made totalling £1.046 million. This left a balance
of £1.5 million unaccounted for.
The memo is silent regarding the concerns
expressed about the 1995-96 programme.
It should be noted that of the accruals made,
£0.3 million related to landscaping work at the Ffrith. Expenditure
on this contract was not incurred until 1995-96 and accordingly
the accrual should not have been made in 1994-95.
An accrual of £0.5 million was also made
in respect of the Events Arena. The WDA approved grant for this
project of £1.6 million and this sum had been taken into
account in balancing the 1993-94.
The District Auditor identified that WDA grants
had been over accrued by Rhuddlan and took account of the necessity
to adjust for these over-accruals in arriving at the unfinanced
balance of £3.9 million at the end of 1995-96.
Memorandum dated 31 August 1995 from Mark
Lewis, Rhuddlan's Director of Finance to the Chief Executive
This memo refers to outstanding issues concerning
the capital programme for 1994-95 "to ensure that no problems
occur during the Final Account Audit". In its first paragraph
it indicates that ERDF grant also formed part of the means of
balancing the 1994-95 programme.
24 March 1999
|