Memorandum submitted by Mr Huw Vaughan
Thomas, Chief Executive, Denbighshire County Council
1. BACKGROUND
1.1 From appointment in the summer of 1995
by Denbighshire I, as Chief Executive, and subsequently the Director
of Finance and Director of Planning and Economic Development sought
information from Rhuddlan Borough Council on the extent of the
commitments arising from Rhuddlan's Capital Programme which would
need to be met by Denbighshire in 1996-97. It was appreciated
that Rhuddlan Borough Council had a large and ambitious capital
programme principally designed to regenerate the tourist trade
upon which the economy of the Borough depends. The main schemes
were as follows:
The Ffrith Beach Development
Railway Station development.
NB A full list of the schemes pursued in the
period 1993-95 is provided in appendix 1 of the District Auditor's
Public Interest Report. A large part of the funding for these
schemes came by way of external grants including £4.7 million
European money and £4.5 million of WDA money. Additionally,
several schemes were part funded through SDS grants.
1.2 As confirmed subsequently by the District
Auditor, (see DA's PI report p3 point 10) the person with formal
responsibility for the developing the capital programme financing
was the Chief Executive of the former Rhuddlan Borough Council,
Mr E Lake. Based on his advice concerning rollover payments in
February 1996, it was estimated that a sum of some £425k
was needed to meet these commitments. Mr E Lake informed officers
that he would be making available files critical to understanding
the capital programme on 1 April 1996; the date of reorganisation,
and he required the files in the interim for his own work.
1.3 Upon reorganisation a team of officers
comprising staff from: economic development, design services,
legal, accountancy, audit and tourism was established to review
all extant Rhuddlan contracts in order to assess Denbighshire's
liabilities. It was quickly realised that the estimated future
commitments were at least £2 million. It was only later on
in the year (Nov 1996) that the full scale of the funding gap
became clear which by then was identified as £7 million.
This was subsequently reported on to County Council in December
1996.
1.4 The figure of £7 million was confirmed
by the District Auditor in his Public Interest Report of
July 1997 which showed that Rhuddlan had overspent £4m in
1995-96 on its capital works after all available money had been
utilised and in addition there were bills and credit cover of
£3 million falling to be met by Denbighshire. (see DA's PI
report p9).
1.5 The debt placed Denbighshire in the
following dilemma.
(a) The debt was unauthorised and therefore
the authority could not attract the normal standard spending assessment
(SSA) assistance for capital schemes.
(b) It exceeded Denbighshire's basic credit
approval (BCA) allocation.
1.6 To meet these difficulties Denbighshire
sought assistance from Ministers. Additional borrowing power was
provided to regularise the debt, but this assistance fell short
of the full figure. The way in which the debt has been financed
is as follows:
The £4 million deficit
1. For 1995-96 the Welsh Office agreed to
give £2.5 million of additional borrowing power. This additional
borrowing was to be returned to the Welsh Office at the rate of
£500k per annum commencing 1999-2000, but the Secretary of
State has agreed to waive this requirement for 1999-2000 and 2000-01.
He has done this in view of the requirement to repay ERDF grant
in respect to the Ffrith Beach (see 2.5 below). This condition
is to be a deferment not an expunging of the £2.5 million
debt.
2. The Welsh Office permitted Denbighshire
to recycle £1 million of Housing Renovation Grants.
3. Denbighshire's own capital resources.
NB The permission of the District Auditor was
secured to enable the authority to carry over the debt burden.
The £3 million excess capital liabilities
This was met from Denbighshire's own capital
resources and has been achieved by maximising resources and managing
payments to spread the burden over a number of years.
1.7 In consequence Denbighshire has had
to forego pursuing many of its objectives and has been forced
to concentrate largely on servicing its inherited capital commitments.
1.8 As the District Auditor's report makes
clear the largest single financial liability arose from the Ffrith
Beach development which was £4.5 million more than its original
estimate. (See DA's PI Report page 24 appendix 3 (i)). The decision
to proceed on the landscaping contract for the Ffrith was made
in March 1995, two months prior to the formation of the Shadow
Authority, thus predating the requirement under section 51 of
the 1994 Local Government (Wales) Act, whereby former authorities
required the consent of the successor shadow authorities before
proceeding with capital contracts over £1 million. (The cost
of this phase was some £2 million; see DA's PI report p23)
Rhuddlan Borough Council was not therefore required to consult
the new authority on its expenditure plans at this time. The Authority
has not been able to determine from the available records how
the scheme was intended to be financed.
1.9 As a footnote to the Ffrith Development,
it should be noted that the Authority has had to face further
consequences arising from the project. Residents living nearby
have complained to the Ombudsman concerning the use of their road
as an access road for the Bowling Centre at the Ffrith. The Ombudsman's
Report records that in January 1989 the former Rhuddlan Borough
Council granted itself planning permission for the construction
of an indoor bowling centre with two outdoor bowling greens and
that prior to April 1995 visitors to the centre obtained access
from a service road through the Ffrith Beach site. The Ombudsman
found that the planning application for consent for the entertainment
complex now at the Ffrith Beach failed to give a clear and unambiguous
account of the proposal to use the complainants' road as a new
access to the Bowling Centre. He found that failure to amount
to maladministration.
1.10 In his report the Ombudsman stated
that the evidence suggested to him that although reference was
made to a possible car park access from the complainants' road
considerable emphasis was placed on the temporary nature of any
such proposal but there was no condition limiting the period of
use of this access in the eventual permission that the Council
granted itself in December 1993. Having found injustice as well
as maladministration, amongst his recommendations the Ombudsman
proposed that if Denbighshire decided that the complainants' road
was to be used as a permanent access or for a period of longer
than one year from his report made in August 1996 then the Council
should pay the complainants compensation equal to the extent of
any devaluation of their homes arising from the increased use
of their road as an access to the Bowling Centre.
1.11 The authority accepted the Ombudsman's
findings and recommendations but sought an extension of the one
year period to enable other solutions to be explored. Although
the authority remains hopeful that an alternative access can be
provided it has concluded that this will not be achieved in the
short term and has accordingly instructed the District Valuer
to establish the extent if any of such devaluation.
2. OTHER FINANCIAL
LEGACIESEXTERNAL
FUNDING ISSUES
2.1 Following a petition to the European
Union from a local resident regarding the use of its grants on
Ffrith Beach, a Control Mission (Audit Team) visited the Welsh
Office and Denbighshire in June 1998 to check whether the Ffrith
Beach scheme complied with the basic requirements of European
Regional Development Fund (ERDF) grants.
2.2 This was a complicated issue for Denbighshire
for several reasons:
the sheer volume of records covering
the years of the regeneration strategy.
the absence of detailed managerial
knowledge of the various programmes once the former Rhuddlan Borough
Council Chief Executive had left the employment of Rhuddlan Borough
Council at reorganisation. (see section 10 of the District Auditor's
Report).
2.3 This meant that Denbighshire had to
carry out an exhaustive study (estimated as two years of experienced
officer time) of the records on the Ffrith Beach, including both
Welsh Office and WDA files, in order to obtain a coherent interpretation
of the capital programme going back to 1991.
2.4 The European Union was sympathetic to
the problems that Denbighshire faced as a successor authority
but it had to have regard to its responsibility to ensure ERDF
grants were properly applied. In October 1998 the EU control team
wrote to the Welsh Office confirming that the project did not
comply with the original plans approved for European grant aid
in April 1993. The team specifically criticised the following:
the lack of a feasibility study
inadequate enquiry regarding the
expected private sector investment promised by the former Rhuddlan
Borough Council
the failure of both the Welsh Office
and the former Rhuddlan Borough Council to ensure that the work
which went ahead on the site corresponded to the description in
the approved grant submission application. In fact the work carried
out departed significantly from the submission. Changes were undertaken
without the appropriate notification being made and permission
being secured. In particular the introduction of a major new building
(the entertainments complex) constituted a significant departure
from the approved scheme.
Compliance with the time period of
the programme.
2.5 In view of the work which Denbighshire
County Council had commissioned on the Ffrith Beach since it inherited
the site in April 1996, the European Control Mission decided the
following:
Denbighshire be allowed to keep £356.5k
of the original £1.125 million grant if the authority can
meet, by the end of 1999, the original output promised by Rhuddlan
Borough Council, in terms of jobs and visitor numbers: originally
estimated as 80 permanent jobs, 10 indirect jobs, 250k visitors
per year.
NB. The Welsh Office, as the responsible authority
for ERDF grants, is seeking clarification of how the European
Control Mission arrived at the particular figure of £768.5k.
2.6 In anticipation of an adverse Control
Mission report, Denbighshire County Council, as soon as it had
completed its examination of the Ffrith Beach papers, sought an
urgent meeting with Welsh Office Ministers to discuss a further
fundamental problem, namely that the situation may be replicated
with other grant funded Rhuddlan Borough Council capital schemes.
2.7 There are several other Rhuddlan schemes
upon which the District Auditor has expressed concern and which
in some cases have not been subjected to detailed audit and in
others no certification has yet been obtained by the District
Auditor. These schemes include the Children's Village and the
Railway Station, but the full list is provided in the Annex.
2.8 Given the issues that have emerged in
the case of Ffrith Beach, neither myself, the Finance Director
or Monitoring Officer of Denbighshire County Council are prepared
to certify any final claims without subjecting the entire schemes
to as thorough an analysis as Ffrith Beach, and this point was
made clear to Welsh Office ministers.
2.9 The Welsh Office was further informed
that due to the fact that those schemes date back to 1991 and
as there are no officers currently in the Authority who were employed
by the former Rhuddlan Council on the capital management of these
schemes, the Authority did not have the requisite resources to
study from scratch all the relevant documents. In consequence
the Welsh Office has recently agreed to give Denbighshire permission
to borrow £100k to finance the necessary work for completion
during this financial year 1998-99, and assistance has been sought
from a firm of Chartered Accountants with experience of public
sector finance and grants to enable it to be undertaken in this
short time scale.
3. QUESTIONS
RAISED BY
THIS ISSUE
3.1 The size of the liabilities inherited
by Denbighshire County Council relative to its resources and the
continuing problems caused has led the Authority several times
to call for the Secretary of State for Wales to hold a public
enquiry. Specifically the Authority believes that the public deserve
an explanation of how the former Rhuddlan Borough Council could
have created the problems outlined in this paper.
3.2 It believes that since so many public
bodies in Wales were involved in scrutinising Rhuddlan's tourism
related capital expenditure, only an independent examination could
be seen to be impartial.
3.3 The District Auditor's report remains
the major study of the Rhuddlan capital debt as regards 1994-96,
but the County Council regards this report as too restricted in
its analysis.
3.4 Denbighshire County Council has two
principal reservations regarding the District Auditor's findings:
Was it reasonable to suppose, as
the tenor of the report suggests, that the whole problem originated
in the last year of Rhuddlan? The District Auditor had made minor
observations on the capital programme and its management in his
1994-95 Management Letter; (see DA's Pi report p4 point 21) but
given the fact that the European Control Mission has identified
substantial difficulties regarding scheme compliance with grant
criteria, should the District Auditor's audit procedures also
have uncovered these problems?
Most of Rhuddlan's Capital Programme
was dependent on grants from elsewhere, especially European Regional
Development Funds. Since the practice was not to audit these funds
until the final grant claim was submitted, there are question
marks about the validity of the accounts certified by the District
Auditor for the final years of Rhuddlan Borough Council. I understand
that the District Auditor is reviewing audit practices in the
light of these difficulties.
3.5 The District Auditor commented on the
weaknesses in Rhuddlan's control procedures for its capital programme,
(see DA's PI report p7, point 30, p8, point 39, p17, point 86-88)
but there are several important questions regarding the external
grant making regime which remain unanswered:
what controls were exercised by the
grant making bodies? The Control Mission's work on Ffrith Beach
shows that had the Welsh Office monitored effectively the ERDF
grant, it would have noticed that what was being built differed
from the grant application.
to what extent did the individual
grant making bodies consult with each other to ensure that there
was no double funding and that the projects were viable?
given the extent of public money
involved it seems surprising that the District Auditor did not
identify the risks earlier; is there perhaps a need to consider
the extent of the District Auditor's scrutiny role?
Are there lessons to be learnt when
an Authority has an unexpected and crushing burden placed upon
it by the actions of a former public body?
Finally, and this point goes beyond
the District Auditor's brief: are there lessons related to the
management of capital schemes by authorities, taking into account
the possible imminence of Objective 1?
3.6 The Secretary of State has provided
two responses to the Authority's request for a public enquiry.
With regard to its initial request made following
the District Auditor's Public Interest Report the Secretary of
State responded by seeking a review of the District Auditor's
early work by the Audit Commission. The review confirmed the adequacy
of the District Auditor's findings, and on that basis the Secretary
of State declined the request for a public inquiry.
3.7 The subsequent request related to the
European Grant situation. The Secretary of State, whilst agreeing
to offer further assistance to help Denbighshire repay the European
Union grant has, however, reserved his position on whether a public
inquiry is necessary.
3.8 My Authority believes this to be an
entirely unsatisfactory situation and therefore welcomes the House
of Commons Welsh Affairs Committee's intervention in this matter.
4. EFFECTS ON
DENBIGHSHIRE
4.1 In assessing the impacts of this legacy
it has to be borne in mind that there are positive benefits to
the people of Denbighshire arising from the legacy, although not
all of them are fully realised and much work remains to be done
to deliver the promised outputs.
the sea front at Rhyl has been transformed
in part
there are new capital assets.
4.2 It must also be stressed that there
is a difficult climate for developing a traditional tourist resort;
a fact which has hampered efforts to find a solution to the Ffrith
Beach complex.
4.3 In assessing detrimental impact it is
necessary to examine three aspects:
Annual Revenue Charges
The capital costs are now covered by credit
approvals and the resulting capital financing charges are, therefore,
built into SSA and are within the RSG settlement and expenditure
guidelines. However, in the first two years of Denbighshire the
SSA did not fully allow for these costs with a resulting loss
of RSG and a reduced expenditure cap. Further, the reserve funds
of the former authority were utilised and were thus not available
to the new authority.
The impact on the County Council's Capital Programme
An estimated £3.4 million has been diverted
away from other potential new schemes. Some of this funding could
have been used as match funding for ERDF and other grant aided
schemes which may have brought the total to as much as £5
million. Examples of projects include: routine highways improvements
and much needed school building repairs. The impact on BCA funds
has also meant that Denbighshire was deprived of much needed flexibility
in setting budgets and this will continue until the £2.5
million arrangement (see para 1.6 above) with the Welsh Office
has expired. With reference to 2.9 concerning the external consultant's
work on other grant funded schemes, there may be further grant
claw back implications which cannot be estimated at this time.
The amount of officer time spent resolving an
issue which could have been more profitably spent elsewhere
Denbighshire has been diverted from pursuing
positive programmes for its community into investigating the Rhuddlan
legacy with the resulting pressure of work leading to an unfulfilled
mission statement and corporate strategy.
4.4 OTHER DETRIMENTAL
IMPACTS
Denbighshire's public image has suffered from
poor publicity over a long period undermining the reputation of
a new authority with the community it serves.
Staff motivation has been inevitably affected
by the negative publicity resulting from the revelations. This
has been made especially bad as the facts continue to unfold and
attempts to draw a line under the issue have therefore proved
impossible.
Divisivenessthe issue has exacerbated
sub-County differences between ex-Rhuddlan and ex-Glyndwr/Colwyn
areas of the County.
5. CONCLUSIONS
5.1 The size of the capital debt problem
for this authority goes beyond what is reasonable for an Authority
by itself to manage, especially as it is itself not responsible
for its inheritance.
5.2 The former Rhuddlan Borough Council
had an unusually large capital programme, larger for example than
many County Councils. In the circumstances it is unfortunate that
the auditing and external grant monitoring regimes were insufficiently
robust to detect the possible problems.
5.3 It is fortunate that Denbighshire as
the successor authority to Rhuddlan inherited a range of officers
with the requisite skills to unravel the debt issue. Without their
experience the identification of this serious legacy would have
been delayed and the management of its consequences made much
harder. As it is, realising the potential of the inherited Rhuddlan
schemes remains challenging and the continuing consequences for
other Council services remain substantial.
March 1999
|