SIXTH REPORT
The Welsh Affairs Committee has agreed to the
following Report:
DENBIGHSHIRE COUNTY COUNCIL'S FUNDING
LEGACY
Introduction
1. On 1 April 1996, local government in Wales was
reorganised: the 8 county councils and 37 district councils were
replaced by 22 unitary authorities. The responsibilities of Rhuddlan
Borough Council, which covered an area including the coastal towns
Prestatyn and Rhyl and inland to St Asaph, Rhuddlan, Dyserth and
Bodelwyddan, were taken over by the new Denbighshire County Council.[1]
It gradually emerged that there were serious problems with Rhuddlan's
capital programme. As the accounts for 1995-96 were drawn up,
it became apparent that in its last year of operation Rhuddlan
had overspent by £3.9 million. And the inherited liabilities
which Denbighshire had to meet in 1996-97 turned out to be some
£3 million more than the expected £400,000. In July
1997 the District Auditor published a "Public Interest"
report[2]
drawing attention to the problems that had arisen. Since then
the situation has become worse: it appears that some of Rhuddlan's
grant-aided projects may not have been carried out in accordance
with the terms of the grant, and the grant-givers may claw-back
some of the grant allocated. The European Commission has already
asked for some £0.8 million of European Regional Development
Fund (ERDF) money to be repaid in respect of the Ffrith Beach
development project, and it is feared that a further £300,000
may be at risk. A recent report by independent auditors suggests
that grant for three other projects is similarly at risk: a further
£2.3 million may be clawed back. Thus, Denbighshire has
been burdened with a substantial, and unexpected, legacy of debt
from Rhuddlan, which may amount to over £10 million.
2. The emerging story of Rhuddlan's debt has caused
considerable public anger in Denbighshire. Concern has been heightened
by uncertainty as to the scale of the debt, and by the absence
of any clear account of what happened. We decided that good would
be served by bringing the facts more clearly into the open, and
by publicly questioning some of the key people involved. We therefore
decided to hold an evidence session in Rhyl on Monday 22 March.
The four groups of witnesses comprised the Chief Executive and
officials of Denbighshire County Council; the District Auditor
and colleagues; the Chief Executive and Members of the former
Rhuddlan Borough Council; and Welsh Office officials. The transcript
of this oral evidence and the related written submissions have
been published as House of Commons Paper 340-i. Further written
evidence is printed with this Report.[3]
In this Report, we seek to highlight the seriousness of the problems
which have arisen, to propose how matters may be moved forward,
and to suggest some general lessons which should be learned for
the future.
The "Rhuddlan debt"
RHUDDLAN'S PROGRAMME
3. Rhuddlan Borough Council had for some years
pursued an ambitious capital programme, designed principally to
regenerate tourism in the seaside towns of Rhyl and Prestatyn.
This programme was funded to a large extent by external grants,
from both European and UK sources. Over its last ten years, Rhuddlan
received some £18 million in grant funding: £10 million
from the European Regional Development Fund, £3 million from
the Welsh Development Agency, £3 million from the Welsh Office,
and £2 million from the Wales Tourist Board.[4]
It appears that Rhuddlan's capital programme enjoyed a high level
of public support until the overspend came to light, although
the development schemes were not without their opponents locally.
4. Rhuddlan's Chief Executive Officer and Borough
Treasurer, Mr Edwin Lake, played a key role in the capital programme,
and was apparently given considerable discretion by the Council
in its management.[5]
In the Council's final months, as other staff left, he appears
to have run the programme almost single-handed. When the Finance
Director left in August 1995, to take up a post in a new unitary
authority, it was agreed that Mr Lake as the only officer
qualified to do so would take on the role of Chief Financial
Officer in addition to his own.[6]
RELATIONS WITH DENBIGHSHIRE
5. The new Denbighshire County Council was established
in shadow form in May 1995. Mr Huw Vaughan Thomas was appointed
its Chief Executive in July 1995. Surprisingly, no meeting was
arranged between the incoming Chief Executive and his predecessors.[7]
The District Auditor has suggested that "dialogue and co-operation
between the key players in Rhuddlan and the Denbighshire Shadow
Authority in the final months were not conducive to the efficient
exchange of information".[8]
Denbighshire claim that repeated requests for information were
refused by Mr Lake: Mr Lake, on the other hand, denies this.[9]
Whatever the truth of this, it is clear that there was remarkably
little contact between the two authorities in 1995-96, and what
contact there was, was largely informal.
THE COMPONENTS OF "THE DEBT"
Overspend
6. It was not until the accounts for 1995-96
were being drawn up that it became apparent that Rhuddlan's capital
programme had been significantly overspent in its final year.
Rhuddlan paid out £10.1 million in capital expenditure, but
had only £6.2 million in available finance, leaving a shortfall
of £3.9 million.[10]
Mr Lake assured us that when the budget was prepared for 1995-96,
he had been satisfied that sufficient funding was available to
meet the capital programme, and that when that programme was monitored
in December 1995 or January 1996, he had still been satisfied
that there was sufficient funding to cover the projected overspend.[11]
Mr Lake was unable to explain what had gone wrong, though he suggested
that the shortfall might have been caused by a reduction in income
as much as by an increase in expenditure. Specifically he mentioned
an unexpected reduction of WDA grant for the Ffrith Beach redevelopment
of some £300,000.[12]
He also suggested that expenditure on contractors' claims and
on contract variations might be greater than originally estimated.
7. The District Auditor has also come to the conclusion
that the shortfall was caused by a combination of factors: contract
costs overran, allied costs were not properly budgeted for, and
expected grant did not come to fruition.[13]
In his view, "assumptions made regarding the costs of some
projects and the availability of funding were over-optimistic".[14]
It has been impossible either to verify or to disprove Mr Lake's
claim that adequate resources were thought to be available, as
proper records have not been found. Rhuddlan did not prepare a
formal capital programme statement for 1995-96, on the ground
that there were no new schemes (apart from the East Parade car
park development, for which Denbighshire's consent was obtained).
It is interesting that, in a memorandum sent to the Chief Executive
Officer in June 1995, the Rhuddlan Director of Finance, Mr Mark
Lewis, said that he was "seriously concerned about the financing
of the 1995/96 Capital Programme", and it is not clear from
his written evidence to us that these concerns as opposed
to concerns that there might be shortfall in 1994-95 were
satisfied.[15]
Inherited liabilities
8. In addition to the unfinanced expenditure
in 1995-96, Rhuddlan left to Denbighshire inherited liabilities
of over £3.3 million.[16]
Mr Lake suggested that it was "inaccurate and misleading"
to describe these capital payments as part of Rhuddlan's overspend.
He pointed out, quite rightly, that there is nothing unusual in
capital expenditure falling in more than one financial year, and
that every new local authority would expect to have to make such
payments. However, Denbighshire's complaint is not that they inherited
capital liabilities but that those liabilities were so much greater
than they had been led to expect. Mr Lake had suggested that they
might have to pay between £300,000 and £425,000. As
it turned out, Denbighshire faced bills of some £3.2 million,
plus additional credit cover of £176,000 in respect of the
Rhyl station Gateway project.[17]
When asked to explain the disparity between what he predicted
and what occurred, Mr Lake told us that some £0.5 million
was for work done in March 1996, which was not certificated till
April and therefore fell to Denbighshire.[18]
Of the remainder, he suggested that most would be due to inflated
contractors' claims; and he maintained that the final figure might
be considerably less than estimated.[19]
Denbighshire witnesses accepted that some part of the liabilities
were claims, but said that most were normal contractual payments
and fees for work done.[20]
We find it hard to believe that contractors routinely overclaim
to the extent that Mr Lake suggests: if they do, it is very worrying.
Nevertheless, the possibility of excess claims still clouds the
issue of how much "Rhuddlan debt" was inherited.
Claw-back of grant
9. Following a petition from a local resident
in March 1997, the European Commission sent a "Control Mission"
to Wales to check whether the Ffrith Beach project complied with
the ERDF requirements.[21]
The visit took place in June 1998, and the Commission notified
the Welsh Office in November 1998 of its conclusion that the project
did not comply with the original plans approved, and that £768,500
of the £1.125 million grant should be repaid. (The balance
of £356,500 could be retained as long the intended output
in terms of jobs and visitors was achieved a condition
which looks increasingly uncertain.) The Welsh Office appealed
against this decision in December 1998, and were still awaiting
a response from the European Commission when they gave evidence
to us in March.[22]
We understand that the negotiations are still continuing.[23]
While we appreciate that the Welsh Office does not "want
to push the Commission into a situation where we are forced to
recover the grant from Denbighshire"[24],
it seems most unsatisfactory that these matters take so long to
resolve.
10. Meanwhile, concern has grown about other capital
projects. Denbighshire commissioned Deloitte & Touche to study
four projects (the Rhyl Town Centre Pedestrianisation Phase II;
the Children's Village, Rhyl; the Events Arena and Rhyl Promenade;
and the Rhyl station "Gateway") to establish the extent
of any shortfall in financing and the potential for claw-back
of grant. Their report, published in May 1999, is unable to predict
the total likely amount of claw-back, since eligibility criteria
are still uncertain and final claims are yet to be agreed. The
report makes the general observations that Rhuddlan's claim forms
and applications contain "the bare minimum of information"
and "tend not to identify other matched funding", and
some claims have been based on expenditure projections rather
than actual costs.[25]
In the case of the Rhyl Town Centre Pedestrianisation Phase II,
it appears that there was an element of "double funding"
with 100% funding from the WDA (in Town Improvement Grant) and
50% funding from the ERDF. In other words, both grants were claimed
against the same expenditure which should not have occurred.[26]
This is likely to result in claw-back by the WDA.[27]
Denbighshire estimates that £300,000 may be at risk of claw-back.[28]
In the case of the Children's Village, there is uncertainty whether
the costs of constructing a cinema are eligible for ERDF funding:
this factor and the failure to secure private sector involvement
may lead to claw-back. Denbighshire suggest that £1.4 million
may be at risk. In the case of the Events Arena and Rhyl Promenade,
while the scheme diverges from the original specification, there
is thought to be no risk to grant entitlement. In respect of the
Gateway, it appears that the contract for Phase II of the scheme
was let after the expiry date for the award. Denbighshire suggest
that £600,000 may be at risk. The potential claw-back
from the three projects where grant is in doubt may amount to
some £2.3 million.[29]
THE MISSING FILES
11. Efforts to get to the bottom of what happened
have been hampered by the apparent loss of the former Chief Executive
Officer's working file or files on Rhuddlan's capital projects.
Mr Lake told us that there were around 100 files, contained in
four filing cabinets in the room next to his office in Russell
House in Rhyl, and that he handed these over to the Borough Secretary
on 30 March.[30]
Denbighshire confirm that they have received 94 files relating
to Rhuddlan projects: what is said to be missing is the file or
files in which Mr Lake maintained his own working papers.[31]
Mr Lake denied that any files were shredded by the outgoing administration,
as has been rumoured locally.[32]
It seems strange to us that Mr Lake sought signatures for Waterford
crystal glass and other valuables, but attached less importance
to files explaining where Rhuddlan's money had been spent.[33]
The procedures for handover were woefully inadequate. It is unlikely
that the working files will turn up at this late stage: conclusions
will have to rely on the information currently available.
RESPONSIBILITY
Rhuddlan officers
12. Responsibility for the Rhuddlan debt
must lie principally with the officers of the former Rhuddlan
Borough Council. In the view of the District Auditor, "Errors
of judgement were made by certain officers of Rhuddlan Borough
Council ... compounded by a failure to follow all the proper procedures".[34]
He concluded that officers were remiss, even negligent, but not
guilty of wilful misconduct, and thus there were no grounds for
a surcharge.[35]
He found no evidence of fraud or corruption. Given that the Chief
Executive Officer took such a leading role in the capital programme,
he must bear the major part of the responsibility. Mr Lake accepted
somewhat grudgingly that the overspend amounted
to mismanagement, though he demonstrated little evidence of contrition
or even regret.[36]
The Deloitte & Touche report observed that "there appears
to have been a lack of understanding by Rhuddlan BC of the rules
surrounding the various grant regimes".[37]
Given Mr Lake's long experience and success in obtaining grant
support, we wonder whether it was not so much a lack of understanding
as a lack of care. The District Auditor suggested that the Chief
Executive Officer's failure to keep Council members sufficiently
informed of costs, contract variation and funding would have provided
grounds for disciplinary proceedings, had he not left local government
service.[38]
Council officers have been found by the District Auditor to
have been negligent in their management of very large amounts
of public money: we empathise with the anger felt locally that
those involved have got away without so much as a reprimand. It
is time that the former Chief Executive Officer, who has admitted
mismanagement, should now apologise to the community for what
took place.
Rhuddlan Councillors
13. While the mismanagement of Rhuddlan's capital
programme is primarily the responsibility of the Council's officers,
it does not reflect well on the members of the Council. The Councillors
from whom we took evidence (the Leader of the majority Independent
Group, and the Secretary to the Labour Group) were keen to distance
themselves from what had occurred, stressing that they relied
on the advice of officers and trusted that the District Auditor
would inform them if anything was amiss.[39]
Indeed, as every former Councillor we contacted was at pains to
deny that they had been Leader of the Council, we can only assume
that it was left to the Chief Executive Officer to take on this
role. Councils should be led by Councillors, not by Council Officers,
however experienced. Rhuddlan Councillors appear to have been
dominated by their Chief Executive to a degree that is most unhealthy.
The way in which the Council operated was worryingly informal:
full Minutes were not kept for meetings of the Council Committees,
and Councillors accepted oral reports from officers on even major
issues.[40]
The District Auditor criticised members of the Tourism and Amenities
Committee, in particular, on the grounds that they "should
have been more thorough in obtaining financial reports from officers
and more diligent in complying with the Prudential Code by gaining
confirmation that suitable funding was in place to meet both planned
and unplanned expenditure".[41]
Rhuddlan Councillors cannot abdicate responsibility for their
Council's financial mismanagement: they do not appear to have
taken sufficiently seriously their duty to their electorate to
ensure the proper management of public funds.
Denbighshire
14. Nor can Denbighshire escape some share
of the responsibility for the problems which have landed upon
it. They failed to take advantage of the shadow period to
get a full understanding of Rhuddlan's financial position. Given
the size and importance of Rhuddlan's capital programme, it is
surprising that Denbighshire's Chief Executive did not initiate
direct contact with Rhuddlan's Chief Executive Officer. There
clearly was, and is, a lack of personal warmth between key players
on the two sides, and we fear that this has impeded their professional
co-operation. It is surprising that greater pressure was not placed
on Rhuddlan to provide a formal capital programme statement for
1995-96. Too much was left to trust and unsubstantiated assurances.
It is remarkable that no effort was made by Denbighshire to contact
former Rhuddlan officers when the problems with Rhuddlan's finances
became apparent, or to enlist their support in resisting claw-back
by the European Commission.
The District Auditor
15. The District Auditor too has come in for
some criticism for failing to draw attention to Rhuddlan's problems
sooner. The current District Auditor, Mr Ceri Stradling, took
up his post in November 1996, so cannot be held responsible for
what happened previously; but there has been some question over
whether his predecessor should have identified problems during
1995-96, or indeed in previous years. At the request of the Welsh
Office, the Audit Commission commissioned a private sector auditor
to conduct an independent investigation of the work of the District
Auditor in respect of Rhuddlan's financial standing.[42]
They concluded that the District Auditor's performance had not
been remiss, that the audit investigations carried out were appropriate,
and that there was no evidence that Rhuddlan's capital programme
was unfinanced prior to 1995-96.[43]
While it beggars belief that Rhuddlan's capital programme went
so spectacularly wrong only in the last few months, there is no
clear evidence to the contrary.
16. Denbighshire are of the view that there was something
wrong, not with the performance of the District Auditor, but with
the process of audit at that time. The practice until recently
was not to audit grants on capital projects until the final grant
claim was submitted. Denbighshire's Chief Executive has suggested
that this practice meant that there were "question marks
about the validity of the accounts certified by the District Auditor
for the final years of Rhuddlan Borough Council".[44]
The District Auditor explained that the annual accounts process
would involve checking capital grant income, receipts and accruals,
but that it would not be until final certification of grant claims
that eligibility and double-funding issues would be addressed.[45]
Thus, problems occurring several years ago are only now coming
to light. The introduction of annual grant audit and certification
from March 1999 was, in our view, long overdue.[46]
17. It seems that the role of the district auditor
is more limited than is commonly thought. Mr Stradling emphasised
that it is "the responsibility of management to operate in
such a way that the body's financial standing is sound; the role
of the auditor is to review the arrangements in place and carry
out an independent assessment".[47]
As he told us, "having proper arrangements in themselves
is not a cast-iron guarantee that things may not go wrong ...
it is dependent on officers and members applying those ... arrangements
properly at all times". This fact was evidently not clear
to Rhuddlan Councillors.
Grant-giving bodies
18. Some responsibility for the Rhuddlan
debt must lie with the Welsh Office, and with the Welsh Development
Agency and Wales Tourist Board, who grant-funded Rhuddlan's capital
programme. It is clear that their monitoring of the £8
million in grants they dispensed was inadequate. Deloitte
& Touche's report shows that Rhuddlan was allowed for years
to get away with grant applications and claims which lacked rigour
and detail, with very little being done to challenge them by the
grant-giving bodies. When problems were identified, there seems
to have been little follow-up. They placed, and continue to place,
considerable reliance on the word of local authority officers
and on the work of the District Auditor. Public money should
be better looked after. As Denbighshire's Chief Executive
suggested, grant-making bodies cannot "disown responsibility
for the use of the grants".[48]
THE IMPLICATIONS FOR DENBIGHSHIRE
19. The burden of debt inherited from Rhuddlan
has had a considerable impact on Denbighshire.[49]
It impacted on Denbighshire's revenue position in the first two
years. It has affected, and continues to affect, Denbighshire's
capital programme. An estimated £3.4 million has been diverted
from planned schemes across the county (for example, much-needed
road improvement and school building repairs). As some of this
could have been used as match funding to secure grant funding,
the total loss may be as much as £5 million. The threatened
claw-back of grant will make the situation worse. Denbighshire,
as part of the West Wales and the Valleys area, is soon to be
eligible for Objective 1 funding: there is real concern that the
county will not be able to benefit fully from this great opportunity,
if it has no money to provide match funding. The Rhuddlan
debt has taken a large amount of officers' time, diverting them
from other, more positive, work. It has had a negative effect
on the public image of the county and its local government, discouraging
further investment by the private sector. And it continues to
divide the local community, with resentment against the Rhuddlan
area from other parts of the county.
20. As soon as the Rhuddlan problems became apparent,
Denbighshire contacted the Welsh Office to inform them of potential
financial difficulties.[50]
In February 1997 the Welsh Office agreed to a financial assistance
package, allowing Denbighshire to finance Rhuddlan's unfinanced
expenditure by transferring £1 million originally intended
for Home Renovation Grants, and by a loan of a further £1.5
million, to be paid back over three years from 1998-99.[51]
In August 1997, following publication of the District Auditor's
Public Interest report, the Welsh Office extended this package
to allow a transfer of £1.27 million housing money and a
further loan of £2.5 million, to be repaid over five years
from 1999-2000. The package has since been extended to provide
£100,000 to fund a review of Rhuddlan's capital programme
and to dispense with the agreed repayment of £0.5 million
in 1999-2000 and 2000-01, if the Council is required to pay grant
back to the European Commission.
21. The Parliamentary Under-Secretary of State for
Wales told the House on 25 June that "we have done all that
is possible and reasonable to assist the authority ... the Welsh
Office has to be seen to act fairly with Denbighshire, but also
to other local authorities".[52]
Of course, Denbighshire should not receive preferential treatment,
and we recognise that all unitary authorities inherited some outstanding
debt. The Minister's statement that Denbighshire is in the lowest
third of Welsh authorities in terms of outstanding loan debt is
a little misleading. Welsh Office figures show that, at 31 March
1998, Denbighshire's outstanding debt stood at £921 per head,
which is the highest figure in Wales.[53]
As ever, statistics can be found to support whatever view you
wish. While the assistance package has allowed Denbighshire to
cover the Rhuddlan overspend, it has been left to absorb its inherited
liability of £3.3 million. As far as we are aware, Denbighshire
is uniquely positioned among Welsh local authorities in view of
the unexpected nature of its debt and its size in comparison to
the authority's overall budget.
FURTHER INQUIRY?
22. There have been many calls in Denbighshire
for a full public inquiry into the Rhuddlan debt. We can fully
appreciate the frustration felt locally that all the facts are
still not known. We readily acknowledge that our own inquiry has
thrown little new light on the exact causes of the overspend or
the increased inherited liabilities. As the District Auditor has
suggested, it is unlikely given the lack of papers
that the full facts will ever be known. But we believe that there
needs to be further study of what went wrong in Rhuddlan, in order
to ensure that it does not happen again. We suggest below that
the National Audit Office and the Audit Commission together initiate
a review of audit practice and grant-monitoring, using Rhuddlan
as their starting point. We believe there are important lessons
which should be learned from Rhuddlan for wider application in
Wales and across the UK.
Lessons to be learned
LOCAL GOVERNMENT
23. Rhuddlan offers many lessons for the future
operation of local government. Councillors must take responsibility
for ensuring the good financial management of their Councils.
While officers will always play the major part in day-to-day management,
it must be clear that Councils are run by Councillors. Councillors
must be of sufficient calibre to be able to challenge experienced
officers, and understand the many complex financial matters which
are put before them. There ought to be much clearer guidance as
to the degree of discretion which can properly be delegated to
officers, and there ought to be safeguards to ensure that too
much power is not vested in individual officers. It should
be made plain, in our view, that it is not acceptable for the
posts of Chief Executive Officer and Chief Financial Officer to
be combined, even for short periods. We welcome the Government's
proposals to strengthen and reinvigorate local government, as
set out in the White Paper "Local Voices Modernising
Local Government in Wales"[54],
and we note that the draft Local Government (Organisation and
Standards) Bill, currently under scrutiny by a Joint Committee
of the two Houses of Parliament, will apply to Wales. We suggest
that Rhuddlan should be borne in mind as a useful object lesson,
when reform of local government is being considered.
24. One clear lesson from Rhuddlan is that satisfactory
auditors' reports in themselves do not guarantee that a local
authority is in good financial health. This simple fact, though
obvious to an auditor, is not always understood by Council members
or the public. The limitations of the District Auditor's role
should be spelt out more clearly in guidance to local authority
members.
25. It is likely that local government in Wales will
be not be subject to further reorganisation for a good many years.
Nevertheless, it may be useful to learn lessons for the future
from the handover from Rhuddlan to Denbighshire. There should,
in our view, be much clearer guidance as to roles and responsibilities
in the shadow period. It is clear that the effectiveness of the
old authority was greatly reduced by staff losses, and the effectiveness
of the new by the fact that many of its officers were working
in dual roles. Though it may be hard to avoid some disruption,
when officers are naturally eager to secure posts with new authorities,
it might be possible to offset the increased workload of remaining
officers by the short-term employment of support staff, for example.
Consideration should be given to retaining key staff from the
old council to prepare the final accounts of their last year in
operation.
EUROPEAN STRUCTURAL FUNDS
26. We believe that Rhuddlan provides very
significant lessons for the future operation of the European grants
process. The imminence of Objective 1 funding in large parts
of Wales, Denbighshire included, gives these issues particular
urgency. It is vital that those applying for grant-funding appreciate
the importance of keeping to specification and of fulfilling the
terms of the grant. Risk of future claw-back must be avoided.
We urge the National Assembly, perhaps through the Wales European
Task Force, to develop new guidance for grant applicants which
is thorough, yet readily understandable. We suggest that this
should be supplemented by a series of seminars or local workshops
on the application process, and perhaps regional advice centres.
This will require resources, but we believe this would be cost-effective
in the longer term.
27. The Deloitte & Touche report has shown that
the monitoring of Structural Fund money has not been adequate.
It is quite bizarre that the problems with the Rhuddlan projects
only came to light because of a complaint by a member of the public.
Monitoring of Structural Fund grants must be much more effective.
While there is no evidence of fraud in Rhuddlan, the potential
for fraud must be great. We suggest that the National Assembly
should increase the number of staff involved in this area considerably.
28. What we have learnt in this inquiry of the performance
of the European Commission has been less than impressive. Welsh
Office witnesses appeared to find it unsurprising that they were
still awaiting in March a response to a letter of December.[55]
Less used to the ways of the Commission, we were surprised by
its slowness in responding to our own inquiries: indeed getting
a response at all required considerable chivvying.[56]
We accept the assurance of the Director of the Commission's Regional
Policy and Cohesion Directorate that their delay in responding
was simply error, "not a sign of a low priority given to
requests for information from Committees of national Parliaments".[57]
As European integration proceeds, it is increasingly important
that the Commission be open and accessible to inquiry from Select
Committees of national Parliaments, and indeed from the National
Assembly. We see no reason why we should accept lower standards
in terms of quality and speed of information from
the European civil service than we would from our own. We urge
the European Commission to review its procedures for dealing with
inquiries from national Parliaments and to establish clearer lines
of responsibility and communication. We understand that our experience
is by no means unique among Select Committees of this House, and
ask the Government to raise the matter through the Council of
Ministers.
GRANT-MONITORING AND AUDIT PRACTICE
29. The Rhuddlan events also hold lessons, we
suggest, for the way in which UK grant-funding is monitored and
audited. At present, the grant-giving bodies rely to a very great
extent on the probity of the recipients of grant, and on District
Audit. There appears to be little attempt to verify claims for
themselves. Each grant-giving body appears to operate a different
regime: greater consistency would make things much easier for
applicants and auditors. One problem area may be the division
of responsibility for audit between the National Audit Office
(central government) and the Audit Commission (local government).
We note that the National Audit Office currently has no power
to follow grant down to the point of spending. We suggest that
there would be merit in giving the National Audit Office the right
of access to the accounts of local authorities, in order to follow
through their audit of grant-giving bodies. We believe that
there is need for a fundamental review of audit practice and grant-monitoring,
and suggest that it would be appropriate for the National Audit
Office and the Audit Commission to carry this out jointly.
Conclusion
30. Responsibility for funding local government
in Wales passed on 1 July to the National Assembly of Wales. We
hope that Assembly Members will recognise the severity of the
financial problems facing Denbighshire and will provide further
financial assistance to the county if it is required to pay back
grant to the extent that is feared. We urge the Assembly to support
our proposal of a review of audit mechanisms to ensure that problems
of this kind do not escape attention for so long again,
and that the expenditure of public money is better monitored in
future. The imminence of Objective 1 funding requires that the
system for monitoring Structural Fund moneys be reviewed with
particular urgency. For its part, we hope that Denbighshire will
begin to put the Rhuddlan legacy behind it and move on. Rhuddlan
did not just leave a legacy of debt, but a legacy of extensive
capital investment and innovative developments. It is now up to
Denbighshire County Council to promote these projects positively.
1 Denbighshire County Council also took over the major
part of the district of Glyndwr and a small part of the district
of Colwyn. Back
2
Section 15(3) of the Local Government Finance Act 1982 requires
the District Auditor to consider whether, in the public interest,
he should make an immediate report on any matter coming to his
notice in the course of an audit. Back
3
References to "Q" are to the question numbers in the
oral evidence, and references to "Evidence, p" are to
the pages in the written evidence published with the oral evidence,
in HC 340-i. References to "Appendix, p" are to the
pages of the additional written evidence published as Appendices
to this Report. Back
4
District Auditor's report to Denbighshire County Council as
the Authority designated to replace the former Rhuddlan District
Council, 25 July 1997 ["Public Interest report"],
page 3. Back
5
Public Interest report, paragraphs 7, 10-11. Back
6
Evidence, p 36. See Public Interest report, paragraphs 63-69. Back
7
Qq 44-45. Back
8
Public Interest report, paragraph 40. Back
9
Evidence, pp 34-35, 78-79; Qq 43-56, 211-215, 222-225. Back
10
Public Interest report, paragraph 41; Q 22. Back
11
Evidence, pp 36-37; Q 281. Back
12
Evidence, p 37; Qq 227-230. See also Appendix, p 9, paragraph
2. Back
13
Q 143. Back
14
Public Interest report, paragraph 39. Back
15
Evidence, pp 79-80; Appendix, pp 17-18, paragraph 3. Back
16
Figures supplied July 1999: Appendix, p 18. In oral evidence
Denbighshire had suggested £3 million in total: Qq 5-6.
See too Public Interest report, p 9. Back
17
Appendix, p 18. Back
18
Q 242. Back
19
Q 232-242. Back
20
Q 7. Back
21
Appendix, p 10. Back
22
Evidence, p 61, paragraph 78; Qq 361-365, 368-370. Back
23
See Official Report, 25 June 1999, col 1492. Back
24
Q 368. Back
25
Denbighshire County Council: Review of EU Grant Claims - Final
Report, Deloitte & Touche, May 1999: paragraph 2.5. Back
26
See Qq 79-85, 294-297. Back
27
Appendix, pp 9-10, paragraph 3. Back
28
Appendix, p 18. Back
29
Appendix, p 18. Back
30
Qq 207-231. Back
31
Qq 57, 66. Back
32
Q 232. Back
33
Q 217. Back
34
Evidence, p 20, paragraph 26. Back
35
Qq 195-199. Back
36
Qq 266-268. Back
37
Deloitte & Touche, paragraph 2.5. Back
38
Public Interest report, paragraph 88. Back
39
Evidence, pp 40-41; Qq 325, 331. Back
40
Evidence, p 41, paragraph 4. Back
41
Public Interest report, paragraph 80. Back
42
Qq 108, 113, 124-126. Back
43
Evidence, p 64-66. Back
44
Evidence, p 4, paragraph 3.4; Qq 94-95. Back
45
Q 165; Evidence, p 19, paragraph 22. Back
46
Qq 171-172, 358-360. Back
47
Evidence, p 18, paragraph 6. Back
48
Q 91. Back
49
Evidence, p 5. Back
50
Evidence, pp 57-62, especially paragraphs 39 and 51. Back
51
Funding is provided to local authorities in the form of credit
approvals (borrowing approvals). The additional financial support
provided to Denbighshire has been in the form of Supplementary
Credit Approvals (SCAs). Back
52
Official Report, 25 June 1999, col 1492. Back
53
Evidence, p 63, paragraph 3. Back
54
Cm 4028. Back
55
Qq 362-364, 369-370. Back
56
See Appendix, pp 10-11. Back
57
Appendix, p 11. Back
|