Memorandum by the Electricity Association
(EA 50)
INTRODUCTION
The Electricity Association is the trade association
which represents the major electricity generation, transmission,
distribution and supply companies in the UK. Our members have
dealings with the Environment Agency across a range of its activities
including, in particular, the IPC regime, water abstraction licensing,
regulating radioactive substances and waste management.
The electricity industry supports the principal
aim in establishing the Agency as a one stop shop integrating
a range of regulatory activities, and notes that significant efforts
have been made towards more consultation on the Agency's overall
policies and plans. We recognise that the Agency has succeeded
in making progress, in particular in raising general awareness,
in waste management and in the management of water resources.
We also recognise that there were inevitable difficulties in the
early years establishing a body which was bringing together previously
separate organisations with different cultures, boundaries and
types of duties.
Nevertheless, our members' experiences of the
Agency have raised certain issues relating to the principles of
the way the Agency is operating in practice and which we therefore
consider appropriate to this Inquiry. These relate to:
the Agency effectively seeking to
set, rather than simply implementing, national policy;
regional variations in implementation;
the lack of a more risk based approach
in targeting its efforts, and
the lack of transparency in its charging
regimes.
and these issues are discused in more detail
below.
NATIONAL POLICY
In 1996, HMIP had agreed a programme of emissions
targets with the fossil fuel generators in England and Wales aimed
at reducing the total emissions of sulphur dioxide (SO2) and nitrogen
oxides (NOx) from coal and oil fired power stations. This agreement
introduced a very positive approach from the regulator in that
generators were set limits for individual stations within a company
total limit, which recognised the greater flexibility of station
operation needed for the competitive generating market. The agreement
established targets up to 2005 for SO2 and to 2001 for NOx.
In January 1998, the now Environment Agency,
which had incorporated the former HMIP, proposed a revised series
of targets which would have accelerated the reduction programme
agreed less than two years previously. This raised several concerns
including:
why the Agency had chosen to review
the electricity industry's IPC licences in less than two years
while it was falling behind in its nominal four-year cycle of
reviews for all IPC licences;
how industry is meant to plan long
term investment with such short term regulatory change (electricity
industry projects typically have five year planning horizons,
with installations designed to operate for 25 years and more);
the Agency's justification for the
proposals that there had been a significant change in the generating
market when that change was itself partly in response to the HMIP
targets.
In particular, there was also the issue of whether
the Agency's proposals reflected Government policy at this time.
In December 1996 the Government had published
the UK strategy Reducing National Emissions of Sulphur Dioxide
which considered the UK's likely emissions through to 2010,
relative to its international commitments on reducing emissions
under both EU and UNECE agreements. The electricity industry had
been a key consideration in that strategy and the paper had concluded
that the existing (ie HMIP 1996) target reductions to 2005 meant
that the Government Strategy was well on course, and that no additional
measures were likely to be necessary before then.
At this time, the Government had also already
announced that it was reviewing the electricity generating market
in view of concerns over the future of the UK coal industry; the
review later resulted in the Energy White Paper Conclusions
of the Review of Energy Sources for Power Generation which
led to the current "moratorium" on new gas generation
and the reform of the electricity trading arrangements. At the
time therefore, the Agency's proposals would have predetermined
the direction of the generating mix, pre-empting any decisions
arising from the Government's review.
Eventually the Agency's proposals have been
reconsidered, in particular due to the White Paper, but the exercise
has nevertheless involved both the Environment Agency and the
electricity generators in a significant expenditure of time and
effort. The management decision to initiate these proposals, which
were clearly out of step with the Government's published Sulphur
Strategy and pre-empting its review of policy for the UK coal
sector, was ill-considered and a questionable deployment of the
Agency's already stretched resources.
REGIONAL IMPLEMENTATION
Another issue where the electricity industry
has reservations about the functioning of the Environment Agency
is that implementation can vary between regions, arising particularly
from its responsibilities on Waste Management. When our members
covering different regions have asked local inspectors for advice
on certain activities, that advice has not always been consistent
making it difficult to implement actions on a company wide or
national basis. This has tended to occur due to the wording of
certain legislation where the interpretation of the relevant requirements
is unclear in relation to particular operations, materials or
plant. Our experience has also been that such issues have centred
on fulfilling the appropriate administrative procedures rather
than on the actual activities and their risks for the environment.
In these instances, additional guidance from
the Agency on a national basis, or from the DETR, would be needed.
However, particularly where UK legislation was transposed from
European directives, the possibility of legal challenge to the
interpretation has led both the Department and the Agency to avoid
developing clarifying guidance. Without a test case, the situation
is left to continue. Clearly in such circumstances, industry does
not wish to impose excess costs on itself by assuming the most
onerous interpretation, but equally it wishes to avoid risking
prosecution arising from failings in the regulatory structure.
There needs to be greater liaison between the Agency and the DETR
when the need for better guidance becomes apparent.
RISK BASED
REGULATION
We consider that the Environment Agency should
adopt a more risk based approach to environmental regulation,
in order to target its resources most efficiently. For some time,
the Agency has been developing its OPRA (Operator Performance
Risk Appraisal) system but this is not yet up and running. This
aims to assess which operations present a higher risk to the environment,
rather than simply those with the highest emissions, based on
the nature of the process and whether the operator uses an environmental
management system such as ISO 14001 and EMAS. The Agency could
then adjust the level of regulatory effort to the level of environmental
risk.
We consider that this should be taken further
to reflect the actual performance of the operator. For example,
power stations clearly produce significant levels of emissions,
including SO2 and NOx. However, the electricity generators have
consistently achieved reductions in these well ahead of the targets
set in their authorisations and a risk based approach should also
reflect this accordingly. The 1998 proposals by the Agency described
earlier would have sent inappropriate messages to other sectors
of industry, ie that investing early under an agreed programme
of environmental improvement results in the Agency seeking to
take those savings and tighten targets further, discouraging responsible
early action.
FEES AND
CHARGES
One of the aims of a unitary regulator was to
generate greater efficiency. For example, the Agency's plan for
1997-98 referred to the Agency restructuring, improving efficiency
and reducing staff in order to reduce Agency costs. However, its
1998-99 plan showed actual staff numbers to have grown and proposed
charges for IPC and Radioactive Substances to increase by inflation
plus 5 per cent and for Discharges and Water Abstraction by inflation
plus 2 per cent. For 1998-99, Agency charges for regulating IPC
increased by 14.5 per cent and for 1999-2000 by 14.8 per cent.
Recently the Agency has issued a consultation
paper on an interim charging scheme for the introductory period
of the new Pollution Prevention and Control regime, which implements
the European IPPC Directive. The proposed charges to industry
are based on an Agency cost of £1,215 per man-day. This compares
to charges of around £600 per day by the Scottish Environment
Protection Agency (SEPA) and around £750 by the Health and
Safety Executive (HSE) and is significantly higher than industry
would pay for most consultancy services.
This failure to deliver greater efficiency and
cost reduction is particularly resonant for an electricity industry
whose other regulator (OFGEM) restricts increases in the industry's
own charges to less than inflation, the well-known RPI minus
X formula.
While the Agency does publish accounts in its
annual corporate plan, these are not sufficiently detailed to
understand how costs are attributed to IPC or other activities
relating to the industrial sector and to justify the charges that
are set. The Electricity Association considers that there should
be greater transparency in the Agency's funding and in the charges
made to industry for regulating environmental licences.
CONCLUSION
In its published strategies and plans, the Environment
Agency cites the four values it has adopted for itself, as follows.
"being open and consulting others about
our work"
The Agency has consulted on its plans and on
many issues and been open in communicating the results, but the
mechanisms and criteria by which the decisions were made have
been less apparent. A way forward would be a system where it is
clear where accountability lies and which ensures the decision
process is transparent and seen to be robust and fair.
"basing our decisions on sound science
and research"
While sound science has been one of the factors
taken into account, other factors such as local or national interests
also appear to play a significant part, for example the refusal
for a power station to burn petroleum coke where local interests
appeared to take precedence. The Agency should, of course, consider
the views of all parties and require the necessary measures which
address genuine local concerns but the science should be the basis
for the decision.
"valuing and developing our employees"
We have no comment on this.
"being efficient and business like in
all we do"
The submission has already indicated our concerns
about the need for avoiding bureaucracy, movng to a risk-based
approach and the delivery of cost-effective regulation. The Agency
should be committed to a process of internal rationalisation and
integration, to improve internal communications and provide consistency
of approach and internal standards. In order to achieve the business
efficiency which the Agency desires, it should look at improving
commercial understanding of "excessive cost" and consider
recruitment of people experienced in industry and commerce to
positions of influence to support its technical capability.
October 1999
|