Consequences for costs and capability
38. CDP considered that much of the sum so far expended
on the Horizon programme would not be wasted, but readily conceded
the significance of the delays
If we secure our objective of transferring the results
of Horizon Phase I into the national programme, the money will
not have been wasted. What I do accept is that we have caused
a great difficulty for the Royal Navy by being late in the procurement
of the Type 42 replacement. I have to say that is what I feel
most guilty about, that is what is most unsatisfactory. We have
spent ... about £100 million[113]
on [Horizon] ... and I plan to use most of that... [But] it is
difficult for me at this stage, when we have not yet secured the
national programme, to know how much of the investment in Horizon
will translate into a national programme.[114]
39. The unit production costs
of the national ship could be about 8% cheaper than those likely
under the Horizon collaboration.[115]
On the other hand the UK had been destined to contribute only
a share (12/22) of the £900 million (ie about £500 million)
expected to have been needed to develop the Horizon warship,
and the UK will clearly have to bear all of the subsequent development
cost of the less expensive Type 45.[116]
Whether the national warship programme will end up costing
the UK more overall than its Horizon predecessor remains to be
seen. This is a matter which we intend to monitor over the next
few years as the development (and costings) of the Type-45 take
shape.
40. As with any major procurement programme, in delivering
the new warship time and cost will be inextricably linked. At
one level, costs and delays go together. For example, any delay
in the procurement of the warship delays the cost savings from
its cheaper running costsaround £10 million a year
per ship.[117]
At another level, costs and time can often be traded-off. It might
be possible, for example, to save time byas some have suggestedletting
more than one yard build first-of-class vessels, but whether this
increases or reduces costs for the entire 12 ships is not yet
clear. More fundamentally, we remain concerned that there will
be pressures to delay the project for financial expediency. The
National Audit Office's annual report on the MoD's Major Projects
Report analyses the delays in the 25 largest equipment programmes.
The latest Report shows that of the 43 months average delay, 9
months was attributed to the constraints on available MoD funds
in any year.[118]
If the national ship is to cost more overall than the Horizon
frigate, there will be pressure within the MoD to delay the programme
deliberatelyif not for delivering the first-of-class then
for subsequent orders. As one of our MoD witnesses said, "the
incremental delivery of the [national warship] programme will
be one way of containing ourselves within existing provision".[119]
41. As a result of its operational analysis for the
CNGF, the UK's planning assumption had been that it would replace
the current fleet of Type-42s on a one-for-one basis.[120]
The Strategic Defence Review had made no change to the operational
case for the programme and confirmed a requirement for 12 anti-air
warfare ships.[121]
The numbers are not yet finally fixed, with a further assessment
to be made before the end of 2000. That work will look at the
balance required between the Type-45s and the more distant Future
Surface Combatant programme.[122]
Any minor changes to the number of ships in the Type-45 fleet,
however, will not disguise a looming gap in our anti-air warship
capability. Apart from the delay in securing the enhanced
capabilities of the new PAAMS warships, there will be a significant
gap in capability because of the mismatch of the Type 42's departure
and the Type 45's arrival. HMS Birmingham (a Type-42) will leave
service later this year, so for the next eight years the Royal
Navy will have to make do with one less anti-air platform. The
rest of the Type-42 fleet will be decommissioned at six-monthly
intervals beginning in late 2006.[123]
With the Type-45s to be built in batchesas is usually the
casethey are unlikely to be able to be commissioned at
the same rate as the Type-42s will depart.
42. If the Type-45 programme is delayed, the MoD
argued that 'there could be potential implications for the coherency
of the destroyer/frigate programme in terms both of affordability
and industrial loading further downstream',[124]
with knock-on delays for the Future Surface Combatant and the
Type-23 that it will replace perhaps being kept longer in-service.[125]
We do not accept that affordability should be sufficient grounds
for delaying other programmes if the Type-45 is delayed, and we
will be taking further evidence if this arises. While it is sensible
not to run on old ships with expensive running costs and increasingly
obsolescent systems, it makes less sense to decommission them
before their capability is replicated. We recommend that the
MoD re-examine the Type-42s' decomissioning schedule, to avoid
reducing the overall number of hulls available at any one time
for UK anti-air operations.
43. The MoD is already working on the assumption
that capability enhancements will be needed early in the new ship's
life, though not on current plans before 2010.[126]
The MoD's hope is that such upgrades to PAAMS and other systems
need not unduly disrupt the operational readiness of the ships
because new software insertions and some other upgrades could
be prepared ashore and either plugged-in during refits or while
the ship is at sea.[127]
We welcome the emphasis on such a technology insertion approacha
component of the MoD's smart procurement initiative. By aiming
at a more readily achievable capability for the ship's systems
when it is introduced into service, earlier in-service dates and
lower acquisition costs should be possible. This places a premium,
however, on the MoD ensuring that delays are avoided (because
the ship's systems might then be already obsolescent when delivered)
and that the funds needed to maintain operational effectiveness
from early in the ship's life are protected within the Department's
budgets.
113 Excluding MoD staff costs, running currently at
£4.5m pa for CNGF overall (Ev p 55) Back
114 QQ
59, 60 Back
115 Q
62 Back
116 Q
62 Back
117 Q
68 Back
118 HC
519, paras 2.15 and 2.19 Back
119 Q
62 Back
120 Ev
p 20 Back
121 Ev
p 21 Back
122 Ev
p 58 Back
123 Ev
p 21 Back
124 Ev
p 56 Back
125 Ev
p 56 Back
126 Q
72 Back
127 Q
73 Back
|