The national Type-45 warship
25. Although the CNGF's latest official in-service
date was 2005, recent submissions from industry had pointed to
a UK first-of-class CNGF vessel being available in 2007.[81]
Now that the UK will not proceed with Horizon, the MoD and UK
industry will have to work hard to deliver a national warshipto
be designated the 'Type-45' destroyer[82]
in such a short time frame.
26. The MoD told us that it was confident that it
could deliver the ship on time,[83]
by making as much use as possible of the results of Horizon's
competitive Project Definition work still underway.[84]
The UK is already bound financially to support this work,[85]
which is due to be completed in October this year[86].
Marconi Electronic Systems' involvement in the Horizon programme
clearly puts it in a good position to take forward the national
warship programme, but the MoD told us that its ability to use
the Horizon 'Phase 1' work was not determined by its choice of
prime contractor.[87]
Nevertheless, the selection of a prime contractor for the Type-45
would be heavily influenced by bidders' willingness to utilise
this Phase 1 work
Until we have appointed a prime contractor for the
national programme we will not know [how much of the Phase 1 work
is usable] ... We have made substantial progress in designing
the ship and we must use that to save time in moving forward with
the national programme. It will be for the prime contractor to
decide, but a great deal of our consideration of who that prime
contractor should be will rest on his ability and willingness
to exploit the results of the work undertaken so far.[88]
To facilitate competition for the prime contractor,
all contenders should be given access to the results of the Project
Definition and Phase 1 work already undertaken.
27. While it remained a possibility that new competitions
would be held [89]
for the ship's 'development programmes' (Figure 2), the MoD would
be looking at the results of the earlier competitions for the
scope for adapting them to a national solution.[90]
The Horizon Joint Project Office is negotiating with the bidders
to make their offers available for the Type-45, and it will also
do so for any French/Italian follow-on ship programme.[91]
Considerable effort and cost has been expended on the 'development
programme' competitions, and the MoD should indeed seek to make
good use of the results to save further cost and time. Potential
prime contractors for the Type-45 will have to weigh up the risk
and cost of utilising the work already done under Horizon, and
it is not clear whether any useful purpose would be served by
the MoD compelling them to re-run these competitions.
28. The design of the new Type-45, like the Horizon
frigate before it, will be influenced and constrained by its primary
role as a platform for deploying PAAMS. In particular, the ship
will need to be able to support an elevated aerial structure for
the heavy Sampson radar in order to maximise the distance at which
threats can be identified, and it will need a beam and depth able
to accommodate the large missile silos of the PAAMS system.[92]
When such requirements are combined, the MoD expects that the
ship would have to be nearer 6,000 tonnes than the 4,000 of, for
example, the Type 23 frigate. The ship cannot therefore be evolved
from the Type-23. The US Aegis destroyer is sufficiently largeat
8,500 tonnes but the MoD considered it unaffordable.[93]
29. As a national programme, however, there is scope
for design flexibility in other areas. Collaborative projects
inevitably involve some compromise in arriving at a common specification
(this is accepted because any additional costs involved should
be outweighed by the savings from economies of scale in development
and production). Accordingly, in turning to a national solution
some elements of the collaborative Horizon warship may now be
cut back, to suit the UK's requirements more closely. A notable
example is the high cost of the Electronic Warfare System (EWS)
for Horizon, which might have cost £180 million to develop
and £14 million to manufacture for each ship. The Common
EWS requirement was unaffordable within the development funds
available, but a reduced requirement was never properly agreed
between the three partner countries.[94]
For the UK's national warship, however, the EWS will be governed
by available funding from the outset, with enhancements coming
later.[95]
By removing non-UK requirements, the MoD expects the costs of
the EWS to be only a third as high.[96]
Savings would also be possible in regard to the Combat Management
System if missile defences could be simplified. CDP told us that
We will probably avoid an inner layer missile system
which was part of Horizon. It was a system designed to defend
the ship against what are called leakers in-coming missiles
which get past the PAAMS system. What is interesting about that
is not that it is just a technicality, it is the complication
of having two missile systems, and the operational handover and
the split-second timing that is necessary to do that makes the
task of the combat management system enormously more difficult.
So by deciding that PAAMS is good enough, why do we need an inner
layer missile system on introduction into service? We have saved
money on the production cost of the ship and, just as important,
we have hugely simplified the combat management system. That is
the type of trade-off we are looking at.[97]
The MoD must of course avoid gold-plating for
the Type-45, and it is sensible to throw overboard the top-heavy
and expensive non-UK elements of Horizon that helped to capsize
that project. It may be possible to make savings by carefully
trading off cost and capability, but we trust that this does not
jeopardise the enhancements in naval air defence capability, which
we will still need to have early in the next century.
30. Not all of the benefits offered by pursuing a
national warship programme involve cost savings and trimming back
capabilities. It will be easier, for example, to adapt the requirement
to provide additional evolving capabilities sought by the UK.
When we visited the US in October 1999 we were briefed on the
flexibility afforded by the Lockheed-Martin VLS-41 missile launcher.
While the French/Italian 'Sylver' PAAMS launcher is tailored for
the anti-air 'Aster' missile, the VLS-41 (already in service on
many US Navy ships) can accommodate missiles fulfilling a number
of rolestactical ballistic missile defence, land-attack,
anti-surface ship and anti-submarine, as well as anti-air warfare.
We were told that the UK has already ordered the Sylver launcher
for its first-of-class Type-45. Lockheed-Martin were concerned
however that should the MoD wish to extend the role of the ship
beyond simply an anti-air warfare capability, a ship design focussed
exclusively on the space and weight requirements of the Sylver
launcher might preclude the use of the larger and heavier VLS-41
system in follow-on batches of the warship.
31. The MoD should take full advantage of the
opportunities afforded by the national Type-45 programme to explore
the potential for using alternative sub-systems, looking beyond
the equipment available from the three former partner countries.
The Future Surface Combatant will no doubt seek to address
the evolving requirements for capabilities currently provided
on the Type-23s, which it will succeed. More immediately, however,
we recommend that the MoD should explore the opportunities
for designing the Type-45 to allow maximum flexibility for potential
capability enhancements. In the particular case of the missile
launcher for the Type-45, we expect the MoD to examine carefully
the scope for designing-in the ability to fit a wider range of
missile types including the sort of Tomahawk land-attack missiles
(TLAM) that the Royal Navy used in Operation Allied Force. It
may be possible to adapt the Sylver launcher at some future point
for use with more types of missile, but a more flexible option
would be to provide enough space in the ship to accommodate a
VLS-41 launcher. This would also have the advantage of ensuring
that there was potential for competition for the rest of the class.
32. As regards competition for supplying the new
warship, CDP was careful not to restrict options for integrating
the warship systems to only UK prime contractors,[98]
although Government policy is that UK warship hull construction
should only be undertaken in UK yards. National hull construction
is the approach also adopted by other countries with an indigenous
shipbuilding industry. It seems that such an approach by each
of the Horizon partners precluded some of the potential savings,
as the design of each country's ship was to have differed, to
reflect incompatible computer-aided design tools and cranage capacity
in each country's shipyards.[99]
CDP was clear however about the advantages of constructing the
UK ships in British yards
I do not see any reason to move away from our policy
of constructing our warships in this country. In my view to do
so without securing reciprocal arrangements with other countries
would be a type of suicide note. I also think that, not just in
commercial terms, but also [because of] the extreme complexity
of building a warship and integrating all its systems, keeping
control of security issues and the many other technical features
of warship construction. When it comes to the systems, to insist
on those being developed in companies operating in Britain would
not be sensible. I think that would be penalising the Royal Navy.
You only have to look at the armament of a ship with Harpoon missiles,
or Exocet in the past, and many other pieces of equipment which
have come from overseas,
to realise that if you insist on having all the systems
developed in this country we will pay both a financial price and
one of military capability.[100]
33. To build the warship, the MoD has three "obvious
shipyards" in the UK: Yarrow on the Clyde, GEC Marine (VSEL)
at Barrow-in-Furness and Vosper Thorneycroft at Southampton.[101]
With Yarrow and Barrow under the same ultimate ownership of BAe/GEC
Marconi, the MoD is keen that Vosper Thorneycroft also can be
a credible competitor, not least because competition will be needed
for follow-on production batches of the class in order to retain
incentives for the shipyards to improve their performance.[102]
The firm would have to enlarge its facilities to build the ship
at its Woolston yard.[103]
The MoD's strategy to secure this competition means that while
Marconi Electronic Systems has been given start-up work and a
subsequently appointed prime contractor will undertake 'Preparation
for Demonstration' work, the subsequent 'Demonstration and First-of-class
Manufacture' contract will stipulate a warship design that lends
itself to building the ships in the yards both of Vosper Thorneycroft
and Yarrow Shipbuilders.[104]
34. Now unfettered by the incompatibilities of
the equipment selections and competition policies of Horizon's
partners, the MoD acting alone can now make sensible procurement
choices for the Type-45's key systems. But that must mean keeping
an open mind on potential bids from the existing tri-national
Horizon consortia and other foreign systems-integration firms,
as well as from UK suppliers. Warship building itself, however,
remains a closely protected industry by all countries with an
indigenous capability, and in that light, like CDP, we see no
reason to review unilaterally the policy not to allow warship
building to go overseas.
35. The MoD intends to procure the Type-45 warships
in more than one batch. It considered that making a first-of-class
prime contractor responsible for running the competitions for
follow-on production would involve too much risk and possible
conflicts of interest.[105]
The MoD told us that
Competing for follow-on ships in batches increases
the pressure on tenderers to reduce prices. Savings of around
30% were achieved between the first-of-class vessel of the Type-23
and the 14th hull of that class and we do not believe that these
savings would have been as large without the pressure of competition.
We anticipate achieving a similar level of savings in the Type-45
programme.[106]
We welcome the MoD's intended approach of overseeing
the competition for the follow-on vessels, rather than giving
this responsibility to the first-of-class prime contractor.
36. A batch approach would also facilitate future
capability enhancements. The MoD told us that although the basic
ship design should remain the same, changes in some aspects of
the design are inevitable in the time it would take to produce
all 12 vessels.[107]
As CDP put it, "it is virtually inconceivable that some systems
will not be capable of improvement, even if it is only by modifying
the software".[108]
37. CDP outlined the timetable now envisaged for
procuring the Type-45, with an in-service date of 2007
The first bottleneck is to make sure we place the
PAAMS contract this summer.[109]
... The second bottleneck is to order the ship next year, the
first of class ship. [A 'Preparation for Demonstration' contract
will be completed by late 2000, when approval will be sought for
placing a 'Demonstration and First-of-class Manufacture' contract.[110]]
... It is important that we make use, where appropriate, of the
work that has already been accomplished in Horizon Phase 1, because
otherwise that sort of timetable would be far too optimistic.
We then have about a five year ship design and construction programme.
There is usually about a year and a half of design work before
we start cutting steel and building the first module. We are satisfied
that that is rational because that is what it takes on similar
programmes. If all that comes to pass, contractors' sea trials
will take place before the end of 2005. Then there will be a very
demanding work-up of the systems, particularly the PAAMS system,
in extensive trials on the first of class ... Then there will
be operational work-up for the crew, and the ship will enter useful
military service with the Royal Navy before the end of 2007. That
is not an optimistic timetable. That is a timetable that is absolutely
founded on our own experience of how long it takes to bring ships
into service.[111]
CDP also told us of his determination to keep the
programme on track
I hope I have made clear the determination to make
sure PAAMS remains the critical path. We must not allow the ship
to somehow delay the introduction into service of PAAMS. ...It
was the fact we settled the PAAMS terms and conditions last autumn
which has really brought the ship programme to a head because
of a determination to keep them alive. ...We are not going to
be blown off-course on the national programme, [and this is] because
we have a timetable set by PAAMS.[112]
We welcome the CDP's determination to keep momentum
behind the Type-45 programme.
81 Ev p 21 Back
82 Q
58 Back
83 Ev
p 21 Back
84 Ev
p 21, Q5 Back
85 Q
5 Back
86 Ev
p 23 Back
87 Ev
p 57 Back
88 Q
7 Back
89 Q
43 Back
90 Q
40 Back
91 Ev
p 55 Back
92 Q
63 Back
93 QQ
63-65 Back
94 Ev
p 55 Back
95 ibid Back
96 Q
8 Back
97 Q
74 Back
98 Q
15 Back
99 Q
17 Back
100 Q
53 Back
101 Q
45 Back
102 QQ
45, 49 Back
103 Q
45 Back
104 Ev
p 57 Back
105 Q
54 Back
106 Ev
p 56 Back
107 ibid Back
108 Q
58 Back
109 This
contract was subsequently placed on 11 August 1999. Back
110 Ev
p 57 Back
111 Q
42 Back
112 Q
74 Back
|