CNGF
BACKGROUND
4. The CNGF was conceived as a bilateral (later a
tri-national) collaborative programme to provide up to 16 (later
22) anti-air warfare frigates. France sought two vessels, with
the possibility of two more later on. Italy declared a requirement
for six but there have been doubts in some quarters about the
number it really needs and now, post-Horizon, it seeks only two
warships. The UK had the largest requirement, for 12 warships
to replace and upgrade the capability provided by its Type-42
destroyers. The programme included the warship's principal weapon
system, which is to be a new high speed, highly manoeuvrable missile
to intercept attacking aircraft and salvoes of anti-ship missiles.
In the UK's case, the missile system will be the successor to
the much less capable SeaDart missile currently deployed on the
Type-42s, and to a great extent the SeaWolf too.
5. The CNGF programme grew out of a previous collaborative
warship programme the NATO Frigate Replacement for the
'90s (NFR-90) which involved eight countries. After the
UK withdrew from NFR-90 in 1989 the programme came to a halt.
In its place the MoD began developing a national requirement for
an anti-air warfare warship, but also reviewed warship procurement
plans of potential partners with a view to a possible European
collaboration. Only the French Navy was identified as having a
sufficiently similar requirement and procurement timetable, and
in 1991 work started to develop a detailed bilateral Staff Requirement
for the new ship. Italy were already partners with France on the
Famille des Systemes Sol-Air Futur (FSAF), or family of ground-to-air
missiles, and so were given observer status to the discussions
in 1992. Italy accepted the Anglo-French requirement, allowing
all three navies to sign the Tri-national Staff Requirement for
a CNGF in December 1992.
6. The CNGF programme was afflicted by significant
delays to both the ship and the missile system. The MoD's 1998
Major Projects Report[13]
noted that as at 31 March 1998 the CNGF programme was running
some 33 months late, putting back the ship's planned entry into
service from December 2002 to September 2005.[14]
By the time the MoD announced that the collaborative partners
had decided no longer to pursue a common warship, the planned
in-service date for the collaborative PAAMS system and the warship
(now to be procured nationally) had slipped to 2007[15]an
overall delay of five years.
7. In this report we examine the factors behind the
delays in the CNGF programme and the termination of its Horizon
component; and we take a forward look at the MoD's plans for a
UK national warship to provide a platform for the PAAMS system
and the implications of these delays and changes of course for
the Royal Navy.
CNGF DELAYS AND THE CANCELLATION OF THE HORIZON PROGRAMME
8. The MoD's 1998 Major Projects Report[16]
itemised the then expected 33 months of delays to the projected
in-service date of the new frigate, most of which were attributable
to difficulties with the PAAMS system. A delay of 18 months had
ensued while a "realistic and well developed programme for
PAAMS" was achieved. A further 12 months delay was reported
as due to disagreements between the partner countries concerning
the performance required of PAAMS, an acceptable common industry
structure and arrangements for a tri-national contract.[17]
These delays also affected the timing of the Horizon platform
element, with the missile and ship programmes having to be kept
aligned.[18]
Only three months of the delay noted in March 1998 was attributed
to difficulties in negotiating a prime contract for the Horizon
warship itself. That is not to say that progress within the Horizon
part of the programme had proceeded without hitches, and there
had been delays in gearing up Horizon after its deliberately imposed
periods of idleness.[19]
9. Difficulties on the PAAMS element of the programme
were resolved (finally we hope) in October 1998,[20]
allowing it to proceed to the next stage. However, the UK's involvement
in the warship collaboration (the Horizon element) will proceed
no further. The MoD put this down to difficulties with the required
performance of the weapon system and with the contractual approach
being followed
The Horizon International Joint Venture Company[21]
was unable to put forward proposals for an affordable ship that
would deliver the capability and in-service dates required. It
did not demonstrate that it had established itself as a strong
prime contractor with a robust supporting industrial structure
that could manage the development and build of the warship and
its main systems. The UK will now pursue a national prime contract
and seek the maximum benefit from collaboration over equipment
for the ships.[22]
We explore these factors further below.
DIFFERENCES IN THE CAPABILITIES REQUIRED BY THE PARTNERS
10. For the PAAMS weapon system, there were differences
from the outset of the collaboration between the UK and the other
partner countries concerning the extent to which different systems
would satisfy the missions envisaged in the common capability
requirement. For the Royal Navy, PAAMS was intended to provide
a local area defence against modern anti-ship missiles, protecting
lightly armed and unarmed vessels operating alongside itamphibious
assault ships and Roll-on-Roll-off shipsas well as aircraft
carriers.[23]
For the French, the initial focus was on protecting key naval
assets like aircraft carriers, rather than the whole naval task
force. The system performance sought by the UK, in terms of such
factors as the likely number of incoming missiles to be defeated
and their stealthiness, was more stringent than the others.[24]
Although the Tri-national Staff Requirement was to be able
to counter threats envisaged for 2010-15, because of underestimated
difficulties in tailoring an essentially land-based missile system
for maritime use, the capability sought was later eased to be
able to counter only the threat level envisaged at the date that
the system would enter service.[25]
This was the principal cost/capability trade-off in the PAAMS
programme.[26]
Nevertheless, the PAAMS development contract
will include provisions for individual nations to commission the
study work for subsequent enhancements, and such an upgrade might
be commissioned by the UK for 2010.[27]
11. Greater compromises would have been needed, however,
with the PAAMS' multi-function radar. Rather than a completely
common PAAMS system, the partner countries agreed to create a
twin-track approach in which separate prime contractors would
provide two separate PAAMS packages. Consequently, while the three
partner countries have agreed to procure a mainly common PAAMS
system, they will buy different multi-function radars (Figure
1). France and Italy will use the European Maritime Passive-Array
Radar ('Empar') already being developed as part of their bilateral
FSAF programme. The FSAF programme predates the PAAMS project,
and France and Italy had already invested heavily in its Empar
radar. The UK, on the other hand, will procure the Sampson radar,[28]
developed by UK industry and based on research by the UK's Defence
Evaluation and Research Agency (DERA) for a Multi-function Electronically-Scanned
Adaptive Radar ('Mesar').[29]
Empar involved less technical risk and would be in-service earlier,
but it would have less capability than Mesar. The UK Sampson radar
would involve more technical risk but have a superior performance
which CDP described for us in some detail, in particular the future
development potential that is possible with its 'active array'.[30]
| Figure 1: Main elements of the Principal Anti-Air Missile System (PAAMS) |
- The missile
- Multi-function radar
- Fire control system
- Launcher
- Long range radar
|
12. Differences between the CNGF partners concerning
the operational capability acceptable for the missile system hampered
the PAAMS programme. But questions of military capability are
closely bound up with industrial strategy. The UK's requirement
for a more sophisticated multi-function radar would allow UK industry
to take forward work done with DERA. France sought a system available
early for the escorts for its Charles de Gaulle carrier,
but along with Italy they also favoured the lower level of capability
that their industries were working to deliver. While such flexibility
can be seen as a positive element of collaborative procurement,
to the extent that it is driven by non-defence factors it must
also be recognised as an impediment to good procurement practice.
NATIONAL DIFFERENCES IN APPROACH TO COMPETITION AND
CONTRACTUAL MATTERS
13. The PAAMS and Horizon elements of the CNGF programme
were each managed by a Joint Project Office on behalf of the three
governments, each of which in turn reported to a tri-national
steering committee. Each project office was intended to contract
work from its relevant prime contractorthe Horizon International
Joint Venture Company (IJVC) for the warship, and 'Europaams'
for the PAAMS system.[31]
While these prime contractors would be tasked with developing
and manufacturing the ship and missile system respectively, there
were tri-national memoranda-of-understanding that required them
to hold competitions for as many sub-systems as possible.[32]
To handle the separate national requirements for the missile system,
subsidiary organisations were set up within Europaams'Eurosam'
for the French and Italian requirements, and 'UKAMS Ltd' for the
UK requirement.
14. While France and Italy could base their selection
of contractors for the various PAAMS systems to favour their state-owned
enterprises, the UK selected for UKAMS the companies possessing
the relevant technologiesnot just the UK supplier of the
Sampson radar, Siemens Plessey Systems (now BAe Defence Systems
Ltd), but also French and Italian firms involved in the FSAF missile
system.[33]
Furthermore, although originally a consortium, UKAMS was subsequently
restructured as a wholly-owned subsidiary of Matra BAe Dynamics,[34]
providing a stronger leadership on the industrial side of the
project.[35]
With a single contractor for the UK PAAMS requirement, the MoD
considered that a price reduction of around 10% became possible
as the management of risks was grasped by a single responsible
body. A consortium of firms from each country risked a "tablecloth
tugging exercise where everybody is frightened to let go, in case
all the work-share lands in the lap of the person sitting opposite".[36]
We see evidence here of the inhibiting effects on efficient
procurement of the unresolved turbulence in the European defence
manufacturing industry. The hodge-podge of interlocking
companies and project teams for the programme, with different
reporting lines, also illustrates the complexities of trying to
bring off a collaborative project. It does not, we judge, provide
a very positive pattern to be followed in the future. However,
despite these institutional impediments to swift and effective
decision-making, the PAAMS project appears now to be on reasonably
firm ground.[37]
In April 1999 the three governments agreed to proceed as quickly
as possible to begin the missile systems' full-scale development
and initial production,[38]
and the contract for this work was placed on 11 August 1999.[39]
Though adding to the complexity of the organisation of the
CNGF programme, and eroding the benefits of collaboration, it
seems clear that its twin track approach is part of what makes
the PAAMS project workable, allowing different priorities for
trading-off costs, capabilities and time, as well as differences
in contract strategies of the partners, to be accommodated.
15. The Horizon programme fared less well. In suggesting
that its termination was a joint decision,[40]
we judge that the MoD is putting a rather favourable gloss on
the programme's failure. CDP told us that "the UK did not
withdraw from Horizonthe three countries involved agreed
not to proceed to the next phase".[41]
That may be formally correct, but from comments we have received
from France and Italy[42]
it is quite clear that this was the initiative primarily of the
UK,[43]
which withdrew from the project after losing patience with the
programme's unfocussed management and the high price of the warship.
The Horizon IJVC was based in London and would have operated to
UK law and UK Government contracting standards.[44]
The MoD had sought for it to be restructured as a genuine prime
contractor,[45]
but the firms involved in the Horizon IJVC could not agree amongst
themselves on how such a prime contractor should be established,[46]
nor which one of them should become the leader.[47]
The governments of France and Italy, however, also clearly played
their part. Their Horizon contractors, which they nominated to
the IJVC, were state-owned monopoly shipbuilders[48]
and under the strong influence, and in some cases the direction,
of their respective governments.[49]
Direction des Constructionnes Navales (DCN), for example, is also
part of the French Defence Ministry. The UK, on the other hand,
ran a competition for its member of the tri-national industry
body, which was won by a GEC Marconi-led consortium.[50]
GEC Marconi recognised the need for a strong leadership on the
industrial side,[51]
and sought to lead the Horizon IJVC in April 1999, though without
success.[52]
The Italian defence attaché reported that having GEC Marconi
(currently the subject of a takeover bid by British Aerospace
which is before the European competition authorities) as a prime
contractor would not have been acceptable to France or Italy.[53]
16. The competition for the ship's Combat Management
System (CMS) exemplified this fatal lack of separation of 'customer'
and 'supplier' on the part of France and Italy. The CMS was
one of three sub-systems being developed for the warship (Figure
2), for each of which two consortia were given contracts to develop
competing proposals[54].
The two consortia competing for the CMS sub-contract'HEPICS'
and 'EuroCombat'each comprised UK, French and Italian firms.
The difficulty stemmed from a close involvement in one consortiaHEPICSby
DCN, because DCN was also part of the Horizon IJVC.[55]
This blurred the contractual boundaries considerably, with DCN
putting itself in the awkward position of being part of the team
of one of the bidders while it would also be involved in awarding
the CMS contract. CDP tried to place a charitable interpretation
on the situation, stating that DCN behaved "impeccably".[56]
The pressures on DCN to favour HEPICS must have been considerable,
however, because its SENIT family of combat management systems
(on which the HEPICS solution was based) was already fitted in
other French navy vessels, including the Charles de Gaulle
aircraft carrier which the French Horizon frigates were intended
to protect.[57]
When the Horizon programme was ended, the CMS competition had
not been decided.[58]
In May 1999, the French Ministry of Defence belatedly announced
a restructuring of the DCN state-owned shipyard, to put it into
a more commercial framework with a contractualised relationship
with the French government.[59]
This necessary first step has however come too late to meet the
UK's concerns about the competition arrangements for Horizon.
| Figure 2: The main components of the Horizon programme |
| Items developed specifically for the warship: |
- Combat Management System
- Fully Integrated Communication System
- Electronic Warfare System
|
| Main items not requiring development as part of the Horizon programme: |
- Data transfer system
- 'Identification Friend or Foe' system
- Inner-layer missile system
- Target indication system
- Medium calibre gun
- Medium frequency sonar
- Infra-red alerting system
- Navigation radar
- Small calibre gun system
- Torpedo launch system
- Meteorology and oceanography system
- Quick pointing device
- Surface-to-surface guided weapon
- Underwater telephone
|
17. The 1994 Horizon Memorandum of Understanding
made value for money the primary consideration in awarding contracts,
and no formal work-share was defined (although work-share was
intended broadly to reflect cost-share).[60]
The disciplines of competition and value for money, however, proved
difficult to apply. Firms involved in the EuroCombat bid told
us of their frustration over the inability of both the Horizon
IJVC and the Horizon Joint Project Office to deal with the CMS
competition in a sound manner.[61]
BAe Defence Systems, for example, told us that
Both French and Italian Government defence procurement
methodologies were closer to the pre-Levene[62]
era of UK procurement than current UK practices ... As a result,
the attempt to run a competition on the basis of a level playing
field was probably unrealistic. The French and Italian industrial
organisations involved in Horizon had different approaches to
competition, and were not faced with a "winner takes all"
situation but an environment where a national workshare deal was
inevitable. The enforcement of a best value for money UK-style
equipment selection decision was always going to be difficult
in such a situation ... In the Horizon procurement, the position
of the DCNpart of the French Ministry of Defencemeant
that it was the customer (working with the DGA [French procurement
agency]), a shareholder in the prime contractor organisation (the
IJVC) and a subcontractor bidding ... its HEPICS combat management
system . This, combined with the French Government's support for
its national champion, had a significant impact on the prospects
for a level playing-field competition.[63]
18. And GEC-Marconi, part of the Horizon IJVC, was
particularly scathing about the arrangements for managing the
Horizon programme more generally
The structure of the Horizon IJVC was sub-optimal.
Shareholders in the IJVC, taking shared liability on a high risk
programme, inevitably required the protection of unanimous agreement.
This led to a lack of clear leadership and the shareholders tended
to be more concerned with protecting their domestic interest,
particularly in terms of work share, than managing the project
on an objective basis. Further there was lack of agreement until
very late in the programme on the extent to which responsibility
should be delegated to the chief executive of the IJVC, and this
resulted in too many decisions being referred to the shareholders
...This resulted in the IJVC being micro-managed by the customer
... Industry initiatives were frustrated ... by the Joint Project
Office, who were concerned with preserving technical performance
instead of balancing risk and value for money ...[it sought
to] refine the project in greater and greater detail rather than
allowing the IJVC to ... define an overall warship with balanced
and affordable capabilities ... The introduction of Smart Procurement
in the UK has emphasised the different approaches to contracting.
The UK places more emphasis on cost targets and performance than
specification and schedule. Although the French and Italian Defence
Ministries are moving towards similar disciplines they still place
a greater emphasis on political and industrial considerations
and work-share.[64]
19. CDP himself told us that the compromises needed
to keep Horizon afloat were substantial, and would have involved
moving away from a performance based contract. The twin track
approach for PAAMS allowed the UK to place its contract ultimately
through a single-entity prime contractorUKAMS Ltd.[65]
The Horizon IJVC, on the other hand, was in CDP's words "almost
unimaginably complex", with its membership comprising DCN
(the French state-owned shipyard and defence manufacturer) and
Italian state-owned firms as well as a consortium of three UK
private-sector firms. CDP told us that
Getting all these people to agree a fixed price performance
based contract looked to me to be a possibility three years ago,
but by the middle of last year it was beginning to look increasingly
unlikely. We gave industry three chances to do that: a last chance
in December [1998], another last chance in February [1999], and
an absolutely final last chance in April, and we did not get it.
We would not compromise on that principle.[66]
20. Differences in procurement procedures between
the UK and the other partners were clearly at the very heart of
the difficulties encountered with Horizon, and the other partner
countries highlighted for us the difficulty of reconciling the
UK's market approach with their own focus on work-shares.[67]
Such differences in approach were ultimately dictated by whether
the relevant defence industries in each country were privately
or publicly owned. With hindsight, it seems clear that the Italian
and (in particular) the French governments were never going to
be prepared to embrace the MoD's focus on competition, value for
money and contracting for system performance. Indeed, France's
DCN appears to have had every intention of buying certain equipment
from sources close to home, whatever the requirement or the equipment
competitions might have otherwise suggested. Looking to the
future, the constraints of work-share, or juste retour,
may be eased if managed by the 'Organisation for Collaboration
and Cooperation in Armaments' (OCCAR).[68]
OCCAR is charged with seeking to achieve a global workshare balance
over several years and over several equipment programmes, rather
than the balance within each programme more usually sought by
collaborative partners.[69]
We are separately examining the treaty to establish this five-nation[70]
organisation, ahead of its ratification by the UK.
LESSONS IDENTIFIED
21. As part of the arrangements for its winding-up
in October 1999, the Horizon Joint Project Office has been charged
with providing the three partner countries with an audit of the
work done, a project history and views on lessons to be learnt.[71]
For its part, the MoD intend to undertake a comprehensive national
evaluation which will draw on the work by the Joint Project Office.[72]
The Department meanwhile has set out a tentative view of the lessons
from the collapse of the Horizon programme
At this stage, it seems that four of the major lessons
to be drawn from this experience are that:
- The operational requirement should be agreed
in detail,[73]
be affordable against agreed budgets and be nationally achievable
in the timescales required by the service customer. Where national
requirements diverge[74]
a handling strategy must be specified from the outset.
- Early in the programme, an industrial organisation
must be established which meets the requirements of industry and
of all participant governments. For the UK, this means the appointment
of an effective prime contractor.
- Databases should be established very early on
in a project's life to collect Integrated Logistic Support data,
particularly that required to conduct the comparative analysis
of through-life costs for the competitions for individual weapon
and ship equipments.
- There should be a common view of the risks and
how to manage them, and technical obstacles to collaboration,
such as differing national shipbuilding and safety standards,
must be harmonised early in the programme.[75]
22. CDP also elaborated some other areas where he
considered that future collaborations might usefully be conducted
differently. Governments need to be readier, he told us, to share
information on budgets and equipment requirements to help reduce
over-ambitious proposals, and then to communicate this information
to potential contractors. Although this would be a break from
traditional methods, CDP was convinced that without such budget
disclosure years may be wasted while "you bring people's
feet back down to earth".[76]
23. On the CNGF programme some of the firms involved
complained to us that the defence departments themselves had initially
sought attractive but over-complex and unaffordable technical
solutions.[77]
Without visibility of the indicative costs, industry said it had
had difficulty in establishing clearly with the customer governments
the relative priorities, and trade-offs opportunities, for meeting
cost targets and technical specifications.[78]
The earlier NFR-90 programme had involved over-ambitious and irreconcilable
requirements, with the net cast too widely in trying to encompass
the needs of eight nations each requiring a fundamentally different
type of frigate,[79]
and although the subsequent CNGF programme involved cost/capability
trade-offs to produce a common solution there were still differences
in the technical specifications that proved difficult to reconcile.
As a result of those cost/capability trade-offs, the PAAMS requirement
will only be fully satisfied once it is upgraded in-service,[80]
but they have allowed sufficient commonality for that project
to proceed.
24. We welcome the steps being taken to assess
thoroughly the lessons of the CNGF programme. Such lessons-learning
exercises are not new, however, and conclusions have sometimes
not been fully followed up. This time, we look to the MoD to disseminate
the lessons identified to all project teams, and to apply the
lessons with more conviction.
13 The MPR is produced by the MoD and submitted to both
the Defence Committee and the Committee of Public Accounts, and
is usually published as an annex in an annual report by the National
Audit Office. Back
14 'Major
Projects Report' National Audit Office, HC 519, Session 1998-99,
page 65 Back
15 Ev
p 21 Back
16 Published
as an annex to HC 519 Back
17 MPR
98, page 66 Back
18 Ev
p 54 Back
19 ibid Back
20 ibid Back
21 The
putative prime contractor for the collaborative warship Back
22 Ev
p 22 Back
23 Ev
p 21 Back
24 Q
31 Back
25 Ev
p 20 Back
26 ibid Back
27 Q
31 Back
28 Ev
p 21 Back
29 Q
23 Back
30 QQ
23-26 Back
31 Ev
p 21 Back
32 ibid Back
33 Ev
p 22 Back
34 ibid Back
35 Ev
p 62 Back
36 Q
34 Back
37 Q
31 Back
38 MoD
Press Notice 141/99 Back
39 MoD
Press Notice 312/99 Back
40 Ev
p 54 Back
41 Q
3 Back
42 The
defence attachés of the French and Italian embassies in
London kindly provided their countries' views. These are reproduced
at Ev p 59 and 63 Back
43 Ev
p 59 Back
44 Ev
p 22 Back
45 Ev
p 54 Back
46 Q
4 Back
47 Ev
p 54 Back
48 Ev
p 22 Back
49 Ev
p 62 Back
50 Ev
p 21 and 24 and Annex Back
51 Ev
p 60 Back
52 Ev
p 54 Back
53 Ev
p 59 Back
54 These
competitions were set-up by the Joint Project Office, pending
the establishment of the Horizon IJVC to decide the results of
the competitions Back
55 Q
21 Back
56 Q
21 Back
57 Q
21 Back
58 Ev
p 55 Back
59 Q
11 Back
60 Ev
p 22 Back
61 Ev
p 59 and 62 Back
62 For
a history of the MoD's procurement initiatives, including the
Levene reforms, see the Defence Committee's Eighth Report, Session
1997-98, The Strategic Defence Review, HC 138; paragraphs
305-319 Back
63 Ev
p 62 Back
64 Ev
p 60 Back
65 Q
10 Back
66 Q
10, Ev p 54 Back
67 Ev
p 59 Back
68 Q
34 Back
69 Q
34 Back
70 UK,
France, Germany and Italy are already members of OCCAR, and the
Netherlands' accession is currently being processed Back
71 Ev
p 57 Back
72 ibid Back
73 Although
in the case of the CNGF there was an agreed common operational
requirement, the partners could not agree on how to implement
it. Back
74 The
CNGF had a common requirement, but different national variants
were put forward to meet it. Back
75 Ev
p 57 Back
76 Q
34 Back
77 Ev
p 60 and 62 Back
78 Ev
p 66 Back
79 Q
35 Back
80 On
the Horizon programme, when it was terminated the capability to
be acquired had not yet been fixed. Back
|