APPENDIX 13
Supplementary Memorandum submitted by
the Department of Trade and Industry
RESPONSE TO WRITTEN QUESTIONS FROM THE COMMITTEE
WALKER REPORT
1a When was (i) the existence of the report
and (ii) the text first brought to the attention (a) DTI officials
and (b) DTI Ministers?
| NII Site Inspector conducts Dounreay visits
| |
| which were subject of observations | Sept 1996-Feb 1997
|
| NII Site Inpsector send record of observations
| |
| to Director, Dounreay | 24 June 1997
|
| DTI Officials received copy of observations direct
| |
| from Inspector | 25 June 1997
|
| Mr Battle told observations exist (but not shown text)
| |
| (John Battle answers Roseanna Cunningham PQ
| |
| official recordcol 120 of 1 June) |
29 May 1998 |
| S of S (Scotland) aware of existence of observations
| |
| (but did not see text) | 11 June 1998
|
| Mr Battle aware of request for observations by TIC
| |
| (but did not see text) | 12 June 1998
|
| Full text of observations published | 15 June 1998
|
1b The Minister referred to legal advice relating to release
of the Report. What legal advice was available on the extent of
his powers to direct UKAEA to lift its refusal to permit its release?
In the first instance it is for the HSE to decide whether
any working document like the Inspector's Observations arising
from a series of inspections in the Fuel Cycle Area (FCA) at Dounreay
should be published. In a recent (2 July) letter, already circulated
to the Committee, the Director General of the HSE has confirmed
that the "inspector's observations" were just thatthey
were not the result of special investigations and were not intended
to be a full report to either HSE management or Ministers. This
letter confirms that it is not HSE's "normal practice to
bring such reports to Ministers' attention . . . [nor] . . . to
put such working documents into the public domain". HSE inspectors
produce tens of thousands of such "reports" each yearwhich
are, as in this case, intended to be working documents which inform
the subsequent dialogue with the bodies regulated (in this case
the UKAEAthe nuclear site licence holder) in order to secure
a continuing improvement in standards. It is worth noting that,
although extremely critical in tone, the inspector's observations
did not give rise to any enforcement action by NII, but rather
to the normal regulatory process of debate and then action by
the UKAEA.
As that letter says "Section 28 of the Health &
Safety at Work Act (1974) makes it a criminal offence to disclose
information that HSE have obtained using [their] powers, except
with the consent of the body giving the information." "At
no time has the question of commercial pressures affected the
action taken by HSE as regulator to secure improvements in safety
at Dounreay". It notes, however, that HSE do have statutory
authority to override the wishes of the body being regulated IF
they consider it necessary to disclose information for the purpose
of HSE's statutory functionie protecting health and safety.
Such a circumstance should and would have been drawn to the relevant
Minister's attention as appropriate.
Clearly HSE did not judge it necessary or desirable to do
so in this case. Indeed, at the Thurso hearing, HSE made it clear
that the consequence had been the expected one of robust debate
between them and the UKAEA in line with normal regulatory practice.
DTI officials, as sponsors of the UKAEA, confined themselves to
their proper role in checking that the UKAEA had sufficient funds
available to them to address any necessary improvements at the
site which were being agreed with the HSE as regulator from the
Summer of 1997.
The question of publication of Dr Walker's memorandum only
arose a considerable time after the observations were writeenby
which time HSE were satisfied that Dounreay management were addressing
the issues raised in the report.
At the time of Mr Battle's 1 June reply to Ms Cunningham
MP, it was clear that while the observations, which were now nearly
18 months old, had been highly critical of UKAEA, much work had
been undertaken by UKAEA in the interim to address the issues
raised in the observations. The HSE were also planning an audit
of safety at Dounreay in the near future, the results of which
were to be published. Consequently it seemed more helpful to point
Ms Cunningham to the results of the forthcoming audit, rather
than to a working document which had already served its purpose
and was becoming out of date.
Our legal advice suggests that Ministers do not have the
statutory authority to direct the UKAEA on operational matters
such as this. It would in any case be an extraordinary use of
Ministerial Direction to over-ride rights which every other regulated
industry has in circumstance where HSE have determined there are
no overriding safety reasons to insist on publication.
1c Since the 5 June announcement apparently removed the
requirement for confidentiality, why was the report not released
in the week of 8 June?
As explained above, the observations had served their purpose
as part of the on-going debate on safety improvements at Dounreay.
It was essentially put into the public domain, even though the
contents had not justified publication by HSE in fulfilment of
their statutory functions, since it was requested by the Trade
and Industry Committee on 5 June. This then became a matter for
decision by the HSE who, together with the Scottish Office, are
accountable to Parliament for safety on nuclear sites in Scotland.
HSE had to consider whether to refuse the request, make it privately
available to the TIC or, subject to the necessary consent from
UKAEA publish fully. The decision was to do the latter, but since
it had been written for a technical audience, had never been intended
for publication, and had been overtaken to some extent by events,
it was supported by an explanatory note from the HSE which sought
to put it into its proper regulatory context. UKAEA agreed on
Friday 12 June to its publication, which it had become possible
for them to do, following the removal of the commercial confidentiality
impediment by the announcement that UKAEA would accept no new
contracts for commercial reprocessing on 5 June. The report was
then given to the TIC on the next working dayMonday 15
Juneand published simultaneously.
1d What part did DTI play in the decision to release the
document between 11 and 15 June?
The DTI was supportive. But the decision was for the Scottish
Office, HSE and UKAEA. Once the UKAEA's agreement had been received
on 12 June, it was for HSE to make the necessary arrangements
for publication, which occurred on the next working day.
MONEY
2. It would be helpful to have a note of the financial
arrangements, including the sums paid to the Georgian government
(Para 10 of the DTI memo), the value to the UKAEA of the material,
and the UKAEA's additional attributable costs.
We understand the United States government paid the Georgian
government the approximate world market value of the unirradiated
HEUapproximately £27,000 per kgso around £110,000.
The UK made no payments to the Georgian government, but paid the
US government a single US dollar for the total consignment under
the terms of the Transfer Agreement (Article IV) negotiated with
them. On the advice of our lawyers, a token sum was deemed advisable
to buttress the liability clause in the unlikely event of an accident
en route from Georgia since the US and UK governments are signatories
of different nuclear liability conventions. This sum was paid
over in cash to the senior US government representative on Kinloss
air field and will be met by a DTI budget for physical protection
assistance in Eastern Europe and the FSU.
Both the value of the unirradiated and irradiated High Enriched
uranium and low enriched uranium and the UKAEA's additional attributable
costs are subject to a range of assumptions about world market
prices, amounts recoverable through reprocessing, storage times
at Dounreay prior to processing or reprocessing and the price
the UKAEA will get for the targets and the civil research reactor
fuel which should be the end products. So figures are very approximate
only. Unirradiated HEU currently has a world market price of around
£27,000 a kg and LEU, which is more widely available, a maximum
of £4,000 per kg. There is no real market in irradiated fuel
so no value has been assumed for this. Thus the very approximate
gross value of the Georgian consignment to the UKAEA is around
£147,000.
BUT against this need to be set: the costs of transport from
Kinloss to Dounreay and unloading (estimated by UKAEA at £56,000),
the costs of storage for what is at present an uncertain length
of timethough hopefully the unirradiated HEU will be processed
fairly swiftly if and when the current ban on operations in the
FCA is lifted; and the costs of processing and reprocessing currently
estimated by the UKAEA as around £150,000. At present therefore
the net loss to the UKAEA, and therefore to the DTI and the taxpayer
looks to be around £60,000. This is clearly a UK financial
contribution to nuclear safety and security in Eastern Europe
and the FSU. Arrangements have already been made for the DTI to
monitor regularly the UKAEA's specific costs relating to the Georgian
material until all the consignment is dealt with.
5 JUNE DECISION
3. Exactly when and how were DTI officials and Ministers
told of the UKAEA's view that it would not be economic to continue
to seek new commercial reprocessing contracts?
On 17 March 1998, the UKAEA Board considered the future of
reprocessing at Dounreay and recommended that no new commercial
work be accepted as part of a phased rundown to a complete cessation
of reprocessing. The Chief Executive of UKAEA advised DTI officials
of the Board's proposed course of action by letter dated 19 March
1998. Officials then sought clarification from UKAEA on their
proposal and a situation report was submitted to Mr Battle on
30 April. This was for information only, as at that stage officials
were seeking further information from the UKAEA. Mr Battle arranged
a meeting with the Chairman and Chief Executive of UKAEA on 20
May to discuss these issues fully. The President of the Board
of Trade consulted colleagues by letter on 29 May before the Government
made the announcement on 5 June to endorse UKAEA's decision to
accept no new commercial reprocessing contracts at Dounreay.
SECURITY
4. Is there anything in the 27 April answer to the PNQ
and subsequent answers that in Ministers' view should be corrected
in the light of Mr Pointer's memorandum.
No. The DTI is content for the restricted memorandum on security
which we submitted to the Committee to be published, subject to
a small number of excisions of the most security sensitive passages,
which we have agreed with the Clerk. This memorandum we believe
deals fully with the issues raised by Mr Pointer in his memorandum
to the Committee. It is important that a reasoned reply should
be in the public domain. Frank debate about operational and budget
issues will continue to be a fact of life in the UKAEAC, as in
all Home Office police forces.
|