APPENDIX 9
Supplementary Memoranda submitted by the
Department of Trade and Industry
REGULATION OF SECURITY ON UKAEA, BNFL AND
URENCO LICENSED SITES
1. The regulation of security in the civil
nuclear industry is the responsibility of Ministers of the Department
of Trade and Industry under the provisions of the Atomic Energy
Acts 1954 and 1971 and the Nuclear Installations Act 1965. The
attached diagram shows the various factors taken into account
in the production of the written requirements (Minimum Standards[3])
which these companies must follow for the physical protection
of their sites.
THE DIRECTORATE
OF CIVIL
NUCLEAR SECURITY
2. The Directorate of Civil Nuclear Security
(DCNSy) advises on the physical security standards with which
each site must comply and audits compliance with these standards.
It is funded by the bodies to which it provides advice and physical
and IT security audit services (UKAEA, BNFL and URENCO), as well
as by the DTI on whose behalf it acts, both in the UK and in a
number of roles overseas. The current Director of Civil Nuclear
Security was appointed six months ago.
3. From 1971 through to the early 1990s,
DCNSy's precursor, the UKAEA Security Directorate, while fully
embedded in the UKAEA, acted on behalf of DTI to help set standards
and audit security on both UKAEA and other civil nuclear licensed
sites (ie those of BNFL and URENCO) which were subject to Ministerial
Direction under the terms of the Atomic Energy Act. As a result
of discussions during 1994 and 1995, in the light of DTI's increasingly
active involvement in the sensitive area of nuclear security,
the Directorate's position was modified by the previous Government
to make more explicit its independence of action in nuclear security
regulation, acting as the technical arm of the DTI, the statutory
regulator. DCNSy remains tenuously linked to the UKAEA, reliant
on UKAEA simply for pay and rations administration. Although the
Director still reports formally to the Chairman of the Board,
DCNSy is outside the Chief Executive's line of responsibility.
In practice, DCNSy works for and to the DTI on a day to day basis.
MINIMUM STANDARDS
4. The Minimum Standards document, issued
under Ministerial Authority, lays down the standards of physical
protection for the different security categories of Special Nuclear
Material (SNM), with which UKAEA, BNFL and URENCO sites must comply.
These standards depend on the sensitivity and quantity of the
particular type(s) of SNM on each site. Operators must notify
DCNSy of any significant changes in SNM type and quantity, in
order that the regular audits conducted by DCNSy are against the
correct standards.
5. The requirements in Minimum Standards,
as the attached diagram shows, stem from international requirements
and guidelines for physical protection, requirements in UK law,
and accepted good practice as laid down by central Government.
DCNSy apply their technical expertise to audit nuclear sites'
standards both against these requirements and against a background
of advice on risks from a range of government sources.
6. DCNSy is responsible for advising DTI
on the need to revise national standards for the physical protection
of nuclear materials in the light of changes in the threat or
in international recommendations or requirements. The last major
revision of Minimum Standards was in 1990. There have been some
very minor revisions since this text. However, much work was carried
out during 1997 on a full scale updating and revision of Minimum
Standards to incorporate a number of minor changes in international
regulations, to reflect DCNSy's experience in audits over the
last few years and the Government's view of future physical protection
needs. One of the major improvements planned for the new version,
details of which have been discussed extensively with industry,
will be an annex which lays down clearly for the first time in
Minimum Standards the formal minimum numbers of police required
on each site at all times, to ensure that the relevant armed response
requirement can be met. The protective marking of Minimum Standards
is "Restricted", but the Annex is marked "Confidential"
since it is particularly sensitive.***[4]
7. The Government places great importance
on the continuous review of the threat and to evaluate the effect
any changes in that threat may have on the required levels and
methods of physical protection. It is because of the potential
hazards that could follow terrorism at a nuclear site, that high
standards of protection are needed even when the threat is low,
in order to deter potential terrorists and guard against an increase
in the threat. Responsibility for assessing the threat lies with
the Security Service whose remit includes the collection and collation
of all intelligence on any terrorism affecting the interests of
the UK. Its recommendations to the DTI on physical protection
measures for reducing the vulnerability of the civil nuclear industry
to those threats are taken into account when laying down the detailed
standards to be met by the industry.
SITE SECURITY
8. Security on a nuclear site is the responsibility
of the company operating the site. The policing of UKAEA, BNFL
and URENCO nuclear sites is a vital part of the overall site security
arrangements, which include physical protection measures such
as access control, CCTV, intruder detection systems etc. DCNSy
advises these companies on standards and audits their compliance
with these standards on a regular basis.
9. The Department of Trade and Industry,
the regulator in legal terms, steps in if issues cannot be resolved
between DCNSy and the operating company. Ultimately, Ministers
can issue a Ministerial Direction to force the companies to make
any security arrangements deemed appropriate. This reserve power
has not yet had to be used to resolve disagreements.
10. Security audits of both nuclear facilities
and nuclear materials transportation by the State's designated
physical protection authorityin the UK's case this is DCNSyare
recommended in INFCIRC/225/Rev.3 (the international agreed recommendation
on physical protection of nuclear materials[5]),
in order to evaluate the effectiveness of the physical protection
measures and to identify necessary changes in measures so as to
optimise their effectiveness. It is the responsibility of the
operators to implement recommendations from DCNSy's audits, although
DCNSy will monitor closely the progress in implementation, keeping
DTI advised as necessary.
11. Security at all sites is kept under
constant review to ensure that the balance between physical protection
measures such as intruder detection systems, and the number of
police posts, is appropriate to the perceived risk. The key point
in deciding police staffing is to assess the appropriate number
of officers required to provide an effective armed response in
the unlikely event of a terrorist attack. (However unlikely an
event, it is clearly vital to be properly prepared against a very
small risk.) This, together with a control and communications
staffing element, provides the basis for assessing the minimum
number of police who must be on duty at any one time. Officers
are deployed as necessary to meet changing circumstances. Clearly,
more than the minimum number are needed on some occasions.
12. The operators are responsible, in close
consultation with the UKAEA Constabulary and the local Home Office
police force, for preparing and updating contingency plans for
rapid and comprehensive response to hostile action involving nuclear
material, whether at their facilities or in transit, until the
point of transfer of responsibility. These plans are tested in
exercises held from time to time with participation by the police
response forces. The last major exercise at Dounreay was in May
1996.
UKAEA CONSTABULARY
13. The UKAEA Constabulary (UKAEAC) policies
UKAEA, BNFL and URENCO facilities, and provides escorts for movements
of SNM. (Nuclear power stations are not normally guarded by the
UKAEAC, but by guard forces directly employed by Nuclear Electric,
Scottish Nuclear or BNFL/Magnox Generation, and have armed response
arrangements with their local Home Office police force.) In respect
of nuclear material and other property belonging to UKAEA, BNFL
and URENCO, the UKAEAC has jurisdiction within 15 miles of their
facilities and also while nuclear materials are in transit. Its
officers are armed when protecting significant quantities of nuclear
material, in line with the recommendations of INFCIRC/225/Rev.3.
At most sites, depending on local circumstances including site
layout and quanitities of sensitive nuclear material, dog handling
officers are deployed.
DEPLOYMENT OF
UKAEAC ON LICENSED
NUCLEAR SITES
14. In accordance with the provisions of
the Atomic Energy Authority Act 1954, the Nuclear Installations
Act 1965 (as amended by the Atomic Energy Authority Act 1971)
and the Atomic Energy Authority (Special Constables) Act 1976,
the UKAEAC policies the following licensed nuclear sites in the
UK:
UKAEA
Harwell Dounreay Winfrith Windscale
NB: The site at Culham, where the UKAEAC Headquarters
are situated, has never been licensed and is guarded by a commercial
guard force.
BNFL
Sellafield Springfields Chapelcross Capenhurst
NB: At the Risley site (unlicensed) BNFL is
not obliged to have UKAEAC officers to guard its buildings but
has, however, chosen to do so.
URENCO
Capenhurst
(Relations with the UKAEAC force at Capenhurst
falls to BNFL, which also has operations on the site.)
15. On a licensed site, the police are required
to provide policing on a 24 hours a days, 365 days a year basis,
on a shift pattern. In accordance with normal Home Office Standards,
therefore, 5.4 officers are required to cover each post that needs
to be manned on a 24 hour basis. (This includes an extra allowance
for training, sick leave etc for each post needing to be manned.)
For operational security reasons, the total number of police on
each site is not revealed publicly because of the information
any potential terrorist could deduce from that as to the normal
manning level on each shift.
16. Over recent years, there have been frequent
discussions between the UKAEAC, site management, DCNSy and DTI
about the minimum numbers of police required at several nuclear
sites. However, in the case of the UKAEA, at no time was UKAEA
inhibited from implementing necessary security measures through
lack of resources. Specifically, since 1996, the two successive
Chief Constables of the UKAEAC have argued successfully to obtain
the levels of staffing they wanted at Winfrith and Springfields,
as well as the increase in the complement at Dounreay implemented
by 1 April this year.
17. At Dounreay, it took time to assess
the risks and agree solutions to how protection should be enhanced
to meet the perceived threat. Assessment had to be thorough, and
had to take account of the considerable improvements in physical
protection measures at the site, notably the state-of-the-art
security fence round the Fuel Cycle Area. The DTI acted throughout
the assessment and related discussions to ensure that management
took proper account of security concerns.
18. The outcome was agreement at the end
of January this year to the Chief Constable's request that six
extra officers would be allocated to the Dounreay site. At the
Police Authority meeting the following week, the Chief Constable
expressed satisfaction with this agreement. Six extra officers
had all arrived on site by1 April this year. One is an experienced
firearms officer on transfer, while five are newly trained recruits***[6]
19. Agreement to the extra six officers
at Dounreay was reached before the decision to accept the Georgian
uranium, and was independent of that decision. The Georgian material
represents a tiny proportion of the existing inventory at Dounreay
and makes no difference to the security needs of the site.
20. At Springfields, the agreed minimum
numbers of police have been maintained, in line with the then
Chief Constable's wishes and DCNSy advice, despite pressure from
the BNFL site management to reduce them. Similarly, in on-going
discussions between DTI, DCNSy and BNFL about physical protection
improvements to be made at BNFL's Chapelcross site, DTI have told
BNFL that they will not be permitted to reduce policing levels
as a result of enhanced physical security measures being undertaken
at the site.
21. At Capenhurst***[7]
.
22. Police numbers at Winfrith***[8]
.
POLICE AUTHORITY
23. The role of the Police Authority for
the UKAEAC is to agree and monitor the budget for the UKAEAC and
to assist the Chief Constable in achieving operational efficiency.
The approval of minimum numbers of police officers operating at
all times on a site is a matter for DCNSy acting on behalf of
the DTI, not for the Police Authority, although it of course takes
an interest in the budgetary implications.
24. The Police Authority members are drawn
from the companies policed by the UKAEAC (UKAEA, BNFL and URENCO,
who are the equivalent of funding local authorities in a Home
Office force's Police Authority) and DTI (advised by DCNSy). The
Police Authority also benefits from the advice of the Adviser
to the Police Authority (Sir John Woodcock, formerly Her Majesty's
Chief Inspector of Constabulary) who attends Police Authority
meetings. The Chief Constable also routinely attends. DTI has
proposed informally to other members of the Police Authority that
the Director of Civil Nuclear Security should also become a full
member.
11 June 1998
Letter from Mr John Battle, MP, Minister
for Science, Energy and Industry, Department of Trade and Industry
to the Chairman of the Trade and Industry Committee
Following my appearance before the Trade and
Industry Committee on Wednesday, 1 July, it occurred to me that
some people may have misunderstood the scope of my responsibilities
in respect of Dounreay (a suspicion borne out by some of the subsequent
press reports).
As I tried to explain, the Health and Safety
Executive reports to Parliament on the regulation of nuclear safety
in Scotland through the Secretary of State for Scotland. I enclose
a copy of a letter sent to me following Wednesday's hearing by
the Director General of the Health and Safety Executive which
confirms this point and contains other information which may help
your enquiry.
3 July 1998
Letter from The Director General, Health
and Safety Executive to Mr John Battle, MP, Minister for Science,
Energy and Industry, Department of Trade and Industry
DOUNREAYPUBLICATION OF INSPECTOR'S
OBSERVATIONS ON MANAGEMENT OF SAFETY AT THE SITE
I see from reports of your appearance before
the Select Committee yesterday that it is being suggested that
you in some way put pressure on HSE not to publish our inspector's
observations on safety management at Dounreay, in order to safeguard
the commercial interests of Dounreay. I would like to set the
record straight on that point; and more generally on the publication
of such inspectors' reports and of this particular set of observations.
First, the inspector's observations were just
that: the observations were not the result of a special investigation,
nor were they intended to be a full report to HSE management or
Ministers. HSE inspectors produce tens of thousands of such "reports"
each year: they are working tools which inform subsequent dialogue
with duty-holdersemployers or in this case licenseesabout
what action must be taken to comply with the law and maintain
or improve standards of safety.
For obvious reasons, it is not our normal practice
to bring such reports to Ministers' attention. Nor in most cases
do they come anywhere near senior management levels in HSE. It
is also not our practice to put such working documents into the
public domain. In part this is because they are working
documents. But the more pressing reason is that Section 28 of
the Health and Safety at Work Act 1974 makes it a criminal offence
to disclose information we have obtained using our powers, except
with the consent of the person giving the information. The only
exception to this is where we consider it necessary to disclose
without consent for the purpose of our statutory functionsie
protecting health and safety. We did not feel that such an exception
was justified in this case. Our statutory functions do not include
keeping the public informed or related access to information purposes.
Section 28 is of course being reviewed and amended as part of
action on the Government's freedom of information legislation.
In the case of the inspector's observations
on Dounreay's safety management, the question of publication did
not arise until well after the observations were written and we
were satisfied that Dounreay management were addressing the problems.
When disclosure was first requested, I understand that my inspectors
declined to do so because of the Section 28 constraints. I was
then asked by the Select Committee to provide them with the inspector's
observations. I made clear to the Committee clerk that I wished
to do so, but that I needed UKAEA's consent given that some of
the information gathered by the inspector was commercially confidential.
I agreed with the Clerk thatS.28 and legal advice to me
notwithstandingI would make the observations available
to Committee members; I would also, if UKAEA did not consent to
disclosure, provide a memorandum which could be made public (ie
would exclude commercially sensitive information), and which would
detail the main conclusions and recommendations in the inspector's
observations together with the action subsequently taken to improve
health and safety management at the site. In the event, UKAEA
did, on consideration, agree to release of the document in full,
and we published it on 15 June at the same time as it was given
to the Select Committee members.
As you and I both know, there was no question
of your attempting to pressurise HSE into not disclosing the document.
Your officials had the document butlike HSEwere
constrained by Section 28 from considering its publication; I
understand that it was not shown to you. They too did not suggest
at any time to HSE that the document should not be published.
I should like to make two other points clear.
At no time has the question of commercial pressures affected action
taken by HSE as regulator to secure improvements in safety at
Dounreay. The "commercial sensitivity" issue relates
solely to statutory restrictions on disclosure of information.
Secondly, the Chief Inspector of Nuclear Installations had not
seen the inspector's observations at the time when he advised
your Department on the Georgian fuel. But he assures me that his
advice would not have been so different had he done so.
The report of the audit which HSE is now conducting
into safety management at Dounreay will of course be published
in full. Should I be asked by the Select Committee for further
clarification on the status and publication of our inspector's
observations, I would intend to draw on the contents of this letter.
But I should be very happy for you to pass it to the Select Committee
if you wish.
I am copying this letter to the Secretary of
State for Scotland in view of his responsibility for safety at
Dounreay; and to Angela Eagle at the Department of Environment
Transport and the Regions in view of her responsibilities for
the Health and Safety at Work legislation including S.28 and for
HSE.
2 July 1998
3 The current (1990) version of this document (currently
being revised) is being made available to the Committee on a confidential
basis.
Back
***
4 indicates passages removed
at the witnesses' request and agreed by the Committee.
Back
5
A copy of INFCIRC/225/Rev.3, which is freely obtainable from the
International Atomic Energy Agency, is being made available to
the Committee. DISCUSSIONS ABOUT POLICING NUMBERS
Back
***
6 indicates passages removed
at the witnesses' request and agreed by the Committee.
Back
***
7 indicates passages removed
at the witnesses' request and agreed by the Committee.
Back
***
8 indicates passages removed
at the witnesses' request and agreed by the Committee.
Back
|