APPENDIX 8
Memorandum submitted by the Health and
Safety Executive
WASTE MANAGEMENT
STRATEGY: WET
SILO/IN
-CAVE STORAGE
OF FUEL/WASTE
POSTING CELL
9. The unacceptable practice continues of
consigning ILW to the wet silo where it is accumulated in an irretrievable
form.
10. Active handling facilities (D1217, D2001,
D2670) no longer needed for their original purpose are being used
to accumulate and "store" large quantities of waste
including much fuel; uses for which they were never designed for.
All still require POCO, as do the many redundant flasks associated
with their operations. D1217 is being used as a fully operational
fuel "store" but it is under a care and maintenance
regime. Some of the waste has been transferred to "paint
cans" but much has either been accumulated into piles or
simply left where it was found. The waste accumulation is an ever-growing
problem because there has been a two year old problem associated
with the satisfactory refurbishment of one of the two 6021 flasks
that services the waste posting cell.
11. The waste management problem is now
compounded by the fact that the waste posting cell, which is pivotal
to the success of waste management operations, is itself currently
unserviceable. It is not just the problem of the failed waste
counter itself, there is also the fact that the cell is literally
overfilled with waste arisings to the extent that it cannot even
be used for its intended purpose without first having an extensive
clear-out.
12. Even when the waste posting cell is
back in service, it will be unable to cope with the changed needs
of the site and FCA, and it will continue to represent a very
vulnerable bottleneck to waste processing, particular when the
silo "route" is finally closed. Some of the FCA plants
are already awash with waste and more will be arriving as decommissioning
proceeds. If the problem is not satisfactorily resolved now, in
the light of an accurate waste inventory and associated decommissioning-and-waste
management strategy, then that strategy will fail.
13. Waste management in plants such as D1203
is reaching crisis point with more C-bins in the building than
it can reasonably cope with. The overflow of these into ISOs can
only be viewed as a temporary stop-gap. The use of ISOs raises
questions on a number of matters including compliance with licence
conditions 16 and 32, SAMs and emergency arrangements.
14. Given the situation regarding POG's
waste management, it is difficult to see any influence of an effective,
long term strategy that has been formulated taking into account
the problems posed by the very nature of the POG plants. Their
age, physical condition, interrelationships and the apparent conflict
between, on the one hand, a desire for continued operations and
on the other, the clear need for POCO and decommissioning, do
not appear to have been effectively addressed in any clear and
structured strategy for the future.
POCO OUTSTANDING
FOR A
NUMBER OF
FACILITIES, INCLUDING
SOME ALREADY
IN "CARE
AND MAINTENANCE".
15. A number of active handling facilities continue
to hold the materials that were being worked on when the reactor
programme was cancelled (D1200, D1217, D2001, D2670). The staff
who operated the facilities are reportedly no longer employed
and so the operators today have a less than full knowledge of
what they are being asked to deal with. Some facilities have been
"downgraded" to a care and maintenance regime when they
are clearly required to be maintained in a fully operational mode
(eg D1200, D1217) and where this is the case there is a need to
review the situation.
the case there is a need to review the situation.LAB
33: SIMPLY UNACCEPTABLE
16. No notes are necessary to clarify the
issues of concern.
OPERATING PLANT
IN "CARE
AND MAINTENANCE"
17. This relates to the D1217 situation
and those facilities in D1200 where POCO has not occurred.
SAFETY CASES
18. This category of observations is fundamental
to the way forward, not just for new safety cases but perhaps
more importantly for the programme of review/revision and update
of existing ones. Notwithstanding the fact that NII may have played
some part in safety cases in the past, there is an urgent need
to return to the basics of just what a safety case is for, what
it should contain and how its various aspects should be addressed.
In returning to basics before moving forward again, the following
should be included in the matters to be addressed:
plant design and engineering condition,
both in the light of modern standards
Many of the plants are very old
and their condition sometimes uncertain and unpredictable (eg
D1206). In some instances, having inspected a plant, it is extremely
difficult to then identify that plant's true condition from the
description that appears in its safety case. Comparisons of plant
condition with modern standards are consequently unfounded and
complacent. Reliance is placed solely on arguments of reasonable
practicability irrespective of the sheer size of the gap that
exists in some cases between the existing condition and modern
expectations (eg lab 33, D1204, D1206, D1208, D1200 etc.).
operating directives, operating
rules, maintenance schedules (EMITS), safety mechanisms (Key Safety
Related Equipment?)
All these should be derived and then justified
from within the written safety case itself so that each is seen
to be addressed in the proper context to produce a self contained
and complete case. However, in practice:
The operating directives are
significantly influenced by the "advice" proffered by
the SWP, which adopts a quasi-executive role.
Traditionally, operating rules are kept
to a minimum to "raise the level of their importance".
EMIT schedules are constructed by the
ATO-holder in conjunction with the soon-to-be-divested ESG.
Plants are operated according to their
operating directives rather than their safety cases.
Safety mechanisms are not an established
concept.
As a consequence of the above, the plant
operational safety justification becomes a blend of inputs, some
of which are historical, which serve to cloud the issues of justification
and the responsibility of the Head of POG.
It is the safety case itselfthe written
justification of continued safe operation, where the technical
arguments for all of the above should be found. It should include
the identification/derivation/justification of all the above,
to demonstrate their adequacy, suitability and sufficiency. Licence
condition 23 includes an absolute requirement for such a case
and adequate arrangements made under licence conditions including
14, 15, 19-22 and 35 should then enable its maintenance as a "living"
document.
nuclear safety assessments (criticality
assessments), conditions and limits
Nuclear safety assessments (criticality
assessments) should all be an integral part of the plant's safety
case so that it is complete in all its aspects, thereby ensuring
the assessments are all subject to the same careful control as
is the safety case itself.
The SAM system and the system for nuclear
safety (criticality control) appear to be working as two parallel,
separate systems where it comes to both so-called "minor
assessments" and modifications to plants that already hold
a criticality clearance certificate. It is also not being applied
correctly to new plants where the operational dose is less than
5 mSv, even though the plant's operations involve fissile material,
eg D1231 store, which was categorised as a SAM D: no effect on
safety.
The criteria for "minor assessments"
are less than comprehensive and are open to beneficial interpretation
for the sake of operational convenience.
The UKAEA at Dounreay is now very close
to losing its expertise in nuclear safety assessments, having
chosen to include this function in the divestment of AEAT. The
site still possesses a UKAEA post of Criticality Safety Officer
(CSO) but this is seen as being, at best, a tenuous claim to its
maintaining control of work with fissile material. Major peer
review is undertaken by AEAT at Risley and, with the exception
of the contribution of the CSO, the SWP criticality sub group's
subject-specific expertise resides almost wholly with AEAT staff.
The role of the CSO post does not include any critical scrutiny
or monitoring of the activities of the divested AEAT criticality
section. Under the above circumstances it is difficult to see,
with regard to criticality assessments, how the UKAEA is still
meeting its licensee's duty of maintaining control.
The SWP should really provide advice
to the Head of POG to assist him in his executive decisions relating
to POG's plants. However, where operating rules and operating
directives are concerned, the SWP appears to act with quasi-executive
authority itself, thereby clouding the issue of responsibility.
It has no clear terms of reference relative to POG operations,
the head of POG or indeed, the DNSC itself. Also, the SWP has
a very large membership which raises questions about both membership
criteria and its ability to effectively and efficiently discharge
its duties.
PROJECT CATEGORISATION
AND SUB-DIVISION
19. Projects are being under-categorised,
eg remediation of temporary D1208 ventilation system, D1206 effluent
monitoring system replacement, turnstile replacement in D1209,
D1231 store, C-bin storage in D1203 intended office space, D1206
RRP ventilation system, D2670 AgII rig, D1211, etc replacement.
20. Projects are being sub-divided into
a number of components that will each then be considered as a
project in its own right, thereby attracting lower SAM categories
than the project as a whole rightfully deserves, eg the temporary
D1208 ventilation system, D1211, etc replacement, the replacement
D1208 ventilation system.
21. The hazard of criticality is not being
afforded the respect it deserves and projects associated with
fissile material that do not breach a 5 mSv operational limit
are being categorised as a SAM D: no effect on safety, eg D1231
store.
22. So-called "minor assessments"
for nuclear safety (criticality) have few guidelines or control
and seem to be outside the SAM system completely.
23. There are examples of "liberal"
interpretation of minor assessments to suit operational convenience,
eg the storage of arrays of sample bottles on the floor in several
areas of D1203 because storage racks are full.
MAINTENANCE PROCEDURES
AND EQUIPMENT
LISTS
24. Plant maintenance procedures (planned
maintenance instructions) still do not exist for many of the items
on MITS and PIMS A; equipment lists are likewise incomplete. The
need for their completion does not appear to have been a consideration
in the ESG divestment proposals.
SQEPS, DAPS
AND TRAINING
25. This category of observations includes
several observations that do not easily fit into any of the other
categories but taken together, they raise concern regarding fundamental
aspects of the management of safety. The observations relate to:
"reading across" a criticality
clearance/letter of comfort from one particular situation to another
(D1203)
in a supervisors instruction: the
absence of any means of complying with a recently changed operating
rule (D1208)
out of date training records (D1206)
poorly defined training requirements/standards,
as exemplified by:
the currency of a plant or maintenance
supervisor's knowledge in relation to their particular duty is
not routinely revalidated as it would be if they were duly authorised.
a supervisor's need for assistance in
his efforts to demonstrate compliance with an operating rule.
a supervisor's incomplete training and
consequent inability to recount the plant operating rules or to
describe what an operating directive is (both subjects are mandatory
training requirements for supervisors).
a supervisor's inability to explain the
contents of a "routines" sheet.
recently introduced standing instructions
that conflicted with the plant instructions, thereby causing some
confusion on the part of the supervisor.
ATOS, ATO-HOLDERS,
BUREAUCRACY AND
SWPS
26. Above the ATO-holders, there is a vacuum
instead of a shared responsibility for safety. The vacuum is filled
only when the post of Site Director is reached. In between the
two, nobody shares the burden of the ATO-holder and the Site Director
is too remote to do so himself. The head of POG and the POG Departmental
Heads all have responsibilities that are declared in the POG organisational
chart to be solely associated with commercial and production considerations.
Thus the plant managers, as ATO-holders, appear to be required
to shoulder a burden of safety responsibility that they cannot
reasonably be expected to discharge, given their position in the
organisation and its corresponding command of capital, resources,
priorities and attention. Some have multi-plant responsibilities
which merely serve to compound their particular problems.
27. The ATO-holders appear to be particularly
pressed for time, given the expansion of their duties and responsibilities,
and the reduction in support staff that is reported to have taken
place in the last few years. This reduction has been taken to
the point where the expertise to both operate and support the
plant is no longer available in-house, eg contractors have had
to be brought in to remedy the widespread and significant deficiencies
in D1203 operating instructions and bring them all up to date.
As noted above, some ATO-holders have multi-plant responsibilities
which seem excessive given their position in the organisation.
The situation of undermanning is not just restricted to operations
however and plant maintenance instructions for safety related
equipment on MITS and PIMS A remain incomplete, as do equipment
lists.
28. The CSIs address the safety responsibilities
of the ATO-holder but the ATO itself does not mention the word
"safety" once in its requirements. Its renewal is a
bureaucratic process that is founded on the SWP sitting in judgement
of the plant's recent operational history. The decision itself
should not rest with the SWP but with the Head of POG, after taking
the advice of the SWP about the adequacy of the safety case to
support a plant's continued operation into the future, following
a review of the case in the light of recent operational experience.
NUCLEAR SITE
LICENCE CONDITIONS
AND CSIS
29. Licence condition arrangement requirements
are embodied in the CSIs but these are written more to hold together
a collection of separate business centres spread across a number
of sites than to accurately reflect the needs of Dounreay's particular
operations and problems. Rather than being a set of policies and
general principles written for local interpretation and implementation,
that could then be tailored to best suit the needs of a particular
site, their detail and requirements are such that any scope for
interpretation is limited. While the approach may have been appropriate
in the past, it no longer represents the situation at Dounreay
where a site director is in overall charge of a unitary DMT.
30. Because the CSIs are detailed documents
that are centrally driven, it is not possible for the Dounreay
Director to quickly or easily change arrangements to suit the
particular needs of what is now "his" site, if the post
is to have any real meaning. The recent "disappearance"
from the CSIs of the post of Criticality Safety Officer is a very
good example: the continued existence of the post is essential
to the case for UKAEA at Dounreay remaining an "intelligent
customer", and yet it is no longer seen as being a formal
requirement by the corporate centre. Also, there are a number
of licence condition issues at Dounreay that cannot be resolved
by the site itself, even though their early resolution there would
be of benefit to its drive to improve the management of safety
(eg DAPs, safety cases, maintenance service support by contractors).
31. The way in which the CSIs are constructed
veils the licence conditions and their requirements from the view
of most managers. Their understanding of both is consequently
less than might reasonably be expected from a licensee.
CONFLICT BETWEEN
POG OPERATIONS AND
DMT/LOSS OF
CONTROL/TIMESCALES:
"US AND
THEM" ATTITUDES
AND INTERFACE
MANAGEMENT
32. The introduction of contractors to support
the management of the site has been done in such a way that UKAEA
staff in POG feel alienated towards DMT. This has led to a number
of "us and them" issues developing where the staff of
POG, who are all UKAEA employees, have seen their control diminished
in relation to the safety-related projects, priorities and timescales
associated with their plants. Certainly, they do not see themselves
as being an integral part of DMT and they report that DMT sets
priorities, even though POG is meant to be part of that organisation.
A strong management control of such interfaces is vital both to
the continued well-being of the plants affected by them and to
help engender a stronger feeling that everyone is working for
the same organisation: UKAEA itself.
CONCLUSIONS
33. It is important to bear in mind that
the deficiencies reported here arise as a result of the legacy
to the site from both its past and recent histories. Each of these
histories is very different but nevertheless, each has played
its particular part in the legacy: very old plants, intended initially
for demonstration and support purposes only, and which had been
left behind by the march of modern standards, were overnight turned
into production plants and fuel or waste stores. The shielded,
active handling facilities that once supported the fast reactor
programme were no longer needed, as indeed were the staff who
operated them. Consequently many of those facilities are still
awaiting POCO today. Staff numbers in the mean time have been
replenished by both managing, and decommissioning, contractors.
In its quest to satisfy government's requirements then, the overall
effect of such significant changes, in the absence of an adequate
strategy for the management of change, has been for the corporate
UKAEA to lose sight of its duties as a licensee at Dounreay.
34. The attached observations clearly contain
some matters that will require urgent, short term action by UKAEA
and others that will demand a sustained effort over a longer period.
It also remains for UKAEA to take the necessary steps to satisfy
itself that others of a similar nature do not remain hidden from
consideration elsewhere. Over and above the remedying of the identified
matters however, is the need for UKAEA to address the issue at
Dounreay of its ability to discharge its duties as a licensee.
This is not to say that NII, as UKAEA's regulator, is wholly free
of some of the burden of responsibility.
June 1997
|