CLARIFICATION
ON THE
QUANTITIES OF
SNM RECEIVED FROM
GEORGIA
18. Discussion about the SNM in Georgia
prior to the Government's decision being taken had focused on
the need to remove all material of proliferation concern from
Georgia and the quantities of HEU were specifically mentioned.
After the decision had been reached, a technical document from
the Georgian authorities was passed by the US authorities to UK
officials, who passed it on to technical specialists at Dounreay
who were having to make the necessary arrangements for the receipt
of the Georgian material. This document, which included for the
first time details of all of the nuclear material at the Tbilisi
site, indicated that in all probability there would be LEU in
the consignment which was due to arrive some weeks later. A breakdown
of communication between technical specialists and policy officials
meant that, neither at this time nor for some weeks after the
material's arrival, did policy officials realise that there would
be, and then was, LEU in the shipment. Nor, since the Transfer
Agreement had been negotiated in terms of an itemised inventory
of rods and pellets, did this Agreement serve to alert officials
briefing Ministers that there was LEU either expected or arrived.
19. The shipment arrived safely. The unirradiated
material, both HEU and LEU, was subsequently verified by the on-site
Euratom inspector and the results passed back to their Luxembourg
headquarters via the Safeguards Office in the DTI. On 19 May all
the irradiated material was unloaded from its transport flask
and the inventory check could finally be completed. (The irradiated
material has not been verified by Euratomthey rarely do
verify such material and for such small quantities it would be
particularly exceptional.) A few days earlier a query from the
Euratom Supply Agency about a seeming difference between the verified
figures and what officials had explained to them of the shipment
at the time of its arrival, led policy officials to check and
then double-check the figures of what had arrived and the waste
arising from any reprocessing. Once officials were certain in
the last week of May that the new figures were accurateand
there were some minor downward adjustments to all four categories
of material on the original technical Georgian lista draft
written Parliamentary Statement was prepared. It was not put up
immediately for Ministerial approval. Ministers were first told
on 5 June that the information they had given was incomplete in
respect of the quantities of material that had arrived. Ministers
made clear that steps should be taken to ensure that an addendum
containing the additional information was put in the public domain
as soon as possible. This was done on 10 June.
SECURITY
AT THE
DOUNREAY SITE
20. Security at the site consists of a combination
of: (a) physical, technical and personnel security measures such
as fences, CCTV, passes, document security, vetting etc in accordance
with Government requirements and (b) policing by the United Kingdom
Atomic Energy Constabulary (UKAEAC) whose statutory remit is to
guard the SNM on UKAEA's, BNFL's and URENCO's licensed nuclear
sites and in transit. This guarding is 24 hours a day, 365 days
a year with an agreed minimum number of police on the site's complement.
This is kept under constant review depending on:
(i) recommendations from the Directorate
of Civil Nuclear Security (DCNSy), often as part of their regular
security audits;
(ii) the approximately four yearly inspections
by Her Majesty's Inspectorate of Constabularies;
(iii) specialist risk assessments at varying
intervals; and
(iv) changes to and improvements in the physical
protection of the site. The most recent improvement at Dounreay
was security fence costing well over £1 million installed
last year round the Fuel Cycle Area.
21. The former Chief Constable of the UKAEAC
had recommended an increase of six in police numbers at Dounreay
and detailed discussions on this with the UKAEA were nearing completion
when he resigned in late January. The UKAEA agreed to six extra
staff shortly thereafteran agreement reported to the Police
Authority's scheduled early February meeting. All six extra police
have been at Dounreay since the beginning of April. The last physical
protection audit of Dounreay was undertaken in April 1997 by DCNSy.
The UKAEA's implementation of their recommendations was reviewed
on site in October 1997 by the Deputy Director of DCNSy and a
senior official of the DTI. All recommendations except one had
already been implemented and the outstanding one was completed
by the end of 1997. The Director of Civil Nuclear Security has
declared himself satisfied with the standard of security on site.
However, as for all nuclear sites, security is kept under constant
review.
11 June 1998