AIR TRAFFIC CONTROL
Introduction
1. At its first meeting on 16 July 1997 the Transport
Sub-committee of the Environment, Transport and Regional Affairs
Committee decided to inquire into air traffic control. Our terms
of reference were:
- When National Air Traffic Services (NATS) expected
to begin operations at the new Swanwick air traffic control centre,
and the causes of the delay in its opening
- The terms under which the new Prestwick en route
air traffic control centre would be constructed, and whether delays
at Swanwick would postpone its opening beyond 2001/2
- The new Government's policy as to the ownership
of NATS and the funding of its capital investment programme.
2. Our original intention was to hear evidence only
from NATS and the Department of the Environment, Transport and
the Regions (DETR). However, following our meeting with both organisations
we decided that we needed to hear the views of a number of other
individuals and bodies. NATS was invited back to give further
evidence to us towards the end of the inquiry. In addition to
the oral evidence we heard, we received more than thirty memoranda
and several supplementary papers. We thank all our witnesses for
their assistance, and particularly Mr Douglas Mein and Professor
Peter Ladkin who travelled from Canada and Germany respectively
to give evidence to us. We are also grateful for the help we have
received from our specialist advisers, Mr Laurence Price of SH&E,
and Mr Robert Gifford, Executive Director of the Parliamentary
Advisory Council for Transport Safety.
3. Members of the Sub-committee visited the Swanwick
centre in November 1997. In January 1998 our specialist adviser,
Laurence Price, visited the new Amsterdam air traffic control
centre to obtain information about that project. We wish to thank
the hosts at both facilities for their kind assistance.
Background
4. National Air Traffic Services Ltd is a wholly
owned subsidiary of the Civil Aviation Authority (CAA) which is,
in turn, an independent statutory body for whose performance the
Secretary of State for the Environment, Transport and the Regions
is accountable. The CAA is required by the Civil Aviation Act
1982 to provide air navigation services in the UK and areas outside
the UK for which the country is, by international agreement, responsible.
In addition to providing 'en route' air traffic control (ATC)
from its centres at West Drayton, Manchester and Prestwick for
aircraft passing through the airspace for which it is responsible,
NATS also provides air traffic services at most of the major airports
in the country and co-ordinates civilian and military air traffic
control with the Ministry of Defence through the Joint Air Navigation
Services Council. It has 5000 staff and an annual turnover of
£500m. In 1996/97 it handled over 4 million aircraft movements.[1]
5. In spite of rapidly growing volumes of air traffic,
NATS in recent years has managed to reduce air traffic control
delays from their peak in the late 1980s, although delays have
increased over the last year. The CAA has moved from being a net
borrower from central government (more than £90m in 1994/95)
to repaying £30m this year. At the same time it has reduced
charges to users. These are set at a 'cost recovery' level which
means that although borrowing for investment by NATS counts against
the PSBR there is effectively no risk that the government will
not have the money repaid.[2]
Investment in new air traffic
control centres
6. Following a review last year, NATS reaffirmed
its 'two centre' strategy which is designed to allow it to cope
with rapidly rising traffic levels while allowing adequate contingency
in the event that a centre were put out of action for any reason.
The strategy involves closing West Drayton and Manchester en route
ATC centres, building an entirely new centre at Swanwick in Hampshire
(the New En Route Centre, or NERC) and upgrading the Prestwick
centre (the New Scottish Centre, or NSC). The Prestwick centre
would provide an immediate 60% contingency cover in the event
of NERC failing, rising to 85% over time.[3]
NATS said that airlines believed that this was an acceptable level
of contingency given the cost of providing additional equipment.
The Swanwick centre is being financed through CAA operating profit
and government loans, while in 1993 it was announced by the then
government that the Prestwick project would be financed through
the Private Finance Initiative (PFI), under which the NSC would
be designed, built and financed by a private sector consortium
but would be operated by NATS as a part of its integrated ATC
network. This decision has been reaffirmed by the present government.[4]
The Swanwick centre
History of the project up to January
1997
7. The new facility at Swanwick is required to replace
the present facility at the London Area and Terminal Control Centre
(LATCC) at West Drayton where there is a severe shortage of space
for expansion to meet future demand. Demand on LATCC has grown
from 1 million aircraft movements in 1989 to 1.5 million in 1997.
The decision to proceed with the centre was taken in 1988, with
a projected opening date of 1996. Construction of the building
began at Swanwick in 1991 and was completed in 1994.
8. The contract for the definition of the software
for the centre was awarded to IBM and Thomson CSF in 1991. In
1992 the implementation contract was let to IBM, with a delivery
date of late 1995. During 1993 the system was designed and developed
by IBM. In 1994 IBM International Air Traffic Corporation was
acquired by LORAL Corporation, which was in turn acquired by Lockheed
Martin in March 1996.
9. NATS told us that the technology chosen was "more
advanced than anything that is being tried anywhere in the world".
When the project was conceived it was thought that the United
States would be installing similar technology as part of the Federal
Aviation Administration's (FAA) Advanced Automation System, and
that NATS would follow its American counterparts. The FAA subsequently
"ran into considerable difficulties with this project and
in the end abandoned it" in 1995.[5]
After this, in November 1995, NATS' acceptance of the NERC system
was halted. In January 1996, following software integration problems,
NATS and LORAL announced that it was intended to accept the system
in June 1997 and operate from December the same year. In December
1996 delays to the availability of the Training and Development
Unit (TDU) prompted a further revision of the operational date
to March 1998.[6]
10. In November 1996 NATS gave evidence to the then
Transport Committee. The previous Chief Executive, Mr Derek McLauchlan,
explained that the delay of a year had been caused by problems
with the stability of the very complicated software at NERC. When
tested on thirty workstations it had performed well, but when
tested on 160 stations it had not worked. He told us that the
contractors had met all the project milestones they had set since
January that year and that he was confident that the system could
be made to work.[7] In
January 1997 NATS gave evidence to the Transport Committee again.
Mr McLauchlan insisted that NERC was due to be operational by
March 1998.[8]
Further delays and a new timetable
for opening
11. In July 1997 it was announced that the operating
date would be further delayed in order to incorporate additional
functions into the systems and complete the air traffic controller
training programme.[9]
12. In September and October 1997 NATS consulted
the government, users and staff on six options for proceeding
with the project, which would lead to a number of possible new
opening dates.[10] One
of these options was chosen and the resulting revised plan was
for Lockheed Martin to complete the TDU of the new system by December
1997 and complete and deliver the rest of the operational system
by April 1998. This would allow time for training and for the
move from West Drayton so that the new centre could be operational
in the winter 1999/2000 (it was not considered wise to open it
in the busier summer season). NATS told us that during the consultation
process its staff were "understandably cautious" and
preferred the lower risk option of opening NERC in winter 2000/01.
Others preferred moving to Swanwick using the operating methods
presently used at LATCC.[11]
13. In view of the delay to Swanwick NATS decided
that it was necessary in the meantime to increase the capacity
of LATCC, since 10% of flights it handled in summer 1997 were
being delayed by an average of over 9 minutes, and delays had
increased over the last year. The airspace to the north-east of
London, known as the Clacton sector, would therefore be 'resectorised'
by winter 1998/99 to allow more air transport movements.
14. The present Chief Executive of NATS, Mr Bill
Semple, was appointed in July 1997. When he gave evidence to us
in November 1997 he was confident that the TDU would be ready
for simulation training to begin on 1 December 1997. He described
the actions that NATS and its contractors would take by November
1999 in order to bring the centre into operation. He was confident
that he would meet the target date, which remained 1999/2000,
but admitted that there was a risk that the programme might not
be met. He was unwilling to estimate that risk.[12]
15. On 28 January the Guild of Air Traffic Control
Officers (GATCO) told us that it was "concerned that the
simulator does not seem to be working correctly and as a result
training development units have been cancelled".[13]
The union representing air traffic controllers, the Institution
of Professionals, Managers and Specialists (IPMS), confirmed that
training had not started in January and would not do so before
March.[14]
16. The Chairman of the CAA, Sir Malcolm Field, wrote
to the Sub-committee on 28 January 1998 with further information
on the progress of the NERC project. The winter 1999/2000 target
date had not changed, and there was spare simulation capacity
and time built into the programme. He said that "the programme
of simulations on the Training and Development Unit (TDU) is being
re-assessed in the light of a number of change requests and other
observations made by air traffic controllers before and during
the course of the TDU work-up in December. There had been a clear
feeling amongst controllers that their concerns about the system
were not being listened to, and that further changes were necessary".[15]
17. Sir Malcolm admitted that there was risk that
the programme might not be met, and contingency plans had been
drawn up: "the first line of contingency in the programme
is to extend the project timescale by one year".[16]
Software
18. Sir Malcolm said that 95% of the 21,000 defects
that had been found in 1995 had now been eliminated. It was "a
common problem in large software projects that there will be a
significant number of defects found during test and development
and that these take time to eradicate. Moreover, it is also a
fact that new problems will be identified, and that change requests
will add to the scale of the software revision task". He
told us that "There is clear evidence that the stability
and performance of the system, on the currently specified level
of software, demonstrates that the system will work and will deliver
its capacity".[17]
19. When giving further evidence in February 1998
NATS told us that it was "still working on the programme
to bring the New En Route Centre into operation in the winter
of 1999/2000", and that this was an achievable date, but
that "there are inevitably risks along the road to achieving
that".[18] NATS
would know by April whether the software was viable and able to
do the things for which it was designed, and by October, when
extensive simulation work would have been done, it should know
whether the target operation date was achievable.[19]
20. Mr Burlyn of the Aviation Study Group (ASG),
which was formed in 1992 by aviation specialists with an interest
in studying technological change and its effect on aviation personnel,
told us that although the specification for Swanwick had included
a large number of features to assist controllers, "Progressively
the functionality of the system has been reduced bit by bit in
order to try and bring it into use" and that there was a
danger that this would reduce the amount of additional air traffic
control capacity that the centre would offer. The Director Professional
of GATCO also said that the facilities and support information
offered by the new system were being reduced and was not sure
whether the system that remained would be usable.[20]
21. NATS responded: "We are not reducing the
functionality of the system ... as part of the programme we have
identified a number of functionality changes and functionality
additions which have to be made to the system now that it is being
exposed to use by operational air traffic controllers. That is
what we expected to find." Some additions were being made
and some features surplus to requirements were being removed.
90% of the original system specification from the early 1990s
was still relevant.[21]
22. Professor Ladkin, Professor of Computer Networks
and Distributed Systems at Bielefeld University in Germany, wrote
to us to comment on NATS' software development at NERC. He believed
that the failure to 'scale up' the operating software from 30
to more than 100 workstations was evidence that there were fundamental
system operation problems with the NERC software, and that "There
is no reliable method for estimating how or if such problems can
be safely engineered out of the system." The problem might
also not be as simple as removing a certain number of 'bugs' from
lines of computer code: unwanted behaviour in software systems
was often more complex than that. It was possible that the system
might never work satisfactorily. He stressed the importance of
the users of the system-air traffic controllers-trusting it and
finding it easy to use if they were to operate it safely and efficiently.
He expected that many problems would be found by the users during
the training phase and that therefore as much delay could be expected
at this stage of the project as at previous ones.[22]
23. Professor Ladkin believed that, of the NATS options,
only the final one, to extend the programme further, seemed to
be sensible. The other options were flawed because:
- if a software project was late, it could not
be speeded up much, as resources had to be diverted to train new
personnel
- reducing functionality in mid-development required
careful and considerable re-engineering
- adding tasks not in the original project plan
hindered development work on the basic system.
He noted that NATS had not proposed one further option,
that of abandoning the project and starting afresh: "One
wonders why this was apparently not considered. In the case that
the system will never work effectively, this is clearly the best
option. Experience with other new-generation ATC developments
has shown that a careful evaluation of this option 'helps clear
the air'."[23]
24. The Executive Editor of Computer Weekly
wrote to inform us that in the journal's experience one of the
most common causes of public sector computer failures was the
inability of project teams to pass bad news up and down the chain
of command. Parliament only discovered details of computer disasters
years later. He also said that a common cause of failure was a
lack of direct involvement of the users of the software until
after it was delivered; this had apparently been the case at Swanwick.
Although NATS had told the Sub-committee that only 5% of the computer
bugs remained in the system, independent specialists had estimated
that fixing those 5% could take 95% of the time available to the
project team to resolve all outstanding IT issues. He recommended
an independent audit of progress with the Swanwick project which
could be completed by a single consultant in three weeks.[24]
25. NATS believed that an independent assessment
of the integrity of the systems at Swanwick was unnecessary[25]
and warned that, because of the complexity of the software, it
would probably take more than two or three months.[26]
26. We sought further evidence from our witnesses
about how long such an audit could take. The Editors of Computer
Weekly magazine reiterated their view that a single knowledgeable
consultant who had full access to people and documents could assess
whether the Swanwick project was under control within three weeks
without any delay to the project. They believed that the independent
audit was particularly important because "the Swanwick project
shows some of the classic early warning signs of a public sector
computing disaster", including repeated missing of revised
internal deadlines soon after assurances that the project was
on target, serious problems being treated as teething troubles,
continual modifications to the system to meet the demands of end
users who had not been adequately consulted when the specifications
were drawn up, and strong resistance to an independent audit itself.
The small effort of an independent audit would confirm whether
the project was on target, whether the timetable for testing was
too short, or whether the system no longer met its requirements.
They told us that "It is a common facet in failures of large
projects that they are not abandoned early enough because of the
lack of an independent auditor asking the fundamental question:
is the project ever likely to be completed satisfactorily or should
we pull the plug now?"[27]
27. Professor Ladkin believed that assessing the
functionality of the system was a task with two steps: identifying
the problem areas, and then assessing their nature and how long
it would take to solve them. He estimated that the first stage
might take three or four experts about 60-100 hours, but could
not estimate how long the second stage would take since it would
depend on the nature of the suspected problems.[28]
It would not take longer than a year.[29]
He believed that a two-stage technical audit was the only way
to discover whether the software at NERC could ever be made to
work, and that if nothing were done the problem might persist
for a further two years.[30]
Cost of the project and the impact
of delays
28. Of the total £339m cost of Swanwick, £163m
is the cost of the system; most of the rest is the capital cost
of the land and buildings.[31]
NATS told us in November that all but about £20m of the cost
of the system had already been paid to Lockheed Martin.[32]
However, it was a fixed price contract, and therefore the cost
of solving the problem lay with the contractor. That, NATS said,
had cost Lockheed Martin a lot of money.[33]
In February NATS said that £11m of the capital cost had still
not been paid.[34]
29. The delay to Swanwick has, however, increased
the cost of the project. NATS estimated this extra cost to be
a net £2.7m, made up of a total of £18.6m of operational,
project and other costs, including the cost of resectorising airspace
at LATCC and the 58 extra air traffic controllers who were needed
for the changeover to the new centre. This cost was offset by
'savings' of £15.9m. However £14.2m of these savings
were attributed to deferred depreciation.[35]
NATS agreed that this money would still have to be paid at some
time in the future.[36]
30. The Swanwick project contrasts with the with
the experience of the Netherlands in introducing its new ATC centre
at Amsterdam, which will be only 6km from the existing centre.
This will open in June1998, having been ordered in 1993 in order
to cope with projected demand. It uses as its basis the previous
ATC system with modernised hardware and new function enhancements.
Some of the features, for instance vertical view stacks and visual
display of the approach system, are considered extremely positive
and capacity-enhancing developments. The centre's successful completion
in this time is attributed to the fact that the organisation had
a clear idea from the beginning of what it wanted and that the
project manager and the contractor put great efforts into removing
software bugs at the development stage rather than on site. Air
traffic controllers and engineers were involved in the project
from the start, and had constant discussions with the contractors,
Raytheon. Within a week of delivery in Amsterdam, 70% of the system
was functioning properly.[37]
1
ATC 03, para 2.2. Back
2
ATC 03, para 2.7. Back
3
Some of this eventual capacity would be provided by other facilities
(ATC 03A). Back
4
Q82. Back
5
Q14. Back
6
ATC 03; ATC 28A. Back
7
Minutes of Evidence taken before the Transport Committee, 30 October
1996, HC (1996-97) 55-i, QQ57-60. Back
8
Ibid, QQ456-7. Back
9
ATC 01, para 9. Back
10
These options are set out in ATC 03, para 4.8. Back
11
ATC 03, para 4.9. Back
12
QQ8-9. Back
13
QQ336-7. Back
14
Q338. Back
15
ATC 28A, section 2. Back
16
Ibid. Back
17
Ibid. Back
18
QQ414-6. Back
19
QQ438-9. Back
20
QQ339-40. Back
21
QQ417-8. Back
22
ATC 20. Back
23
Ibid. Back
24
ATC 32. Back
25
Q421. Back
26
Q467. Back
27
ATC 32A. Back
28
ATC 20A; Q675. Back
29
Q673. Back
30
QQ712-4. Back
31
ATC 28A, Annex C. Back
32
Q62. Back
33
Q56. Back
34
Q513. Back
35
ATC 03A; Q32. Back
36
Q501. Back
37
Information from visit. Back
|